Vendor & Supplier Management

Chapter 12
Supplier Risk, Resilience and Business Continuity

Advance Diploma in Purchase Management
Vendor & Supplier Management   •   Advance Diploma

Supplier Risk, Resilience and Business Continuity

Introduction

Modern organisations rarely operate through a simple buyer–seller relationship. Products, services, data, finance, technology and logistics frequently cross several supplier tiers and national borders before reaching the customer. This interdependence creates value, but it also creates exposure. A supplier’s insolvency, cyberattack, factory fire, labour dispute, export restriction, quality failure or transport interruption may become the buying organisation’s operational crisis.

Supplier risk management is therefore a strategic purchasing responsibility. It involves identifying uncertainty, assessing its consequences, selecting proportionate controls, monitoring changing conditions and preparing credible responses when preventive controls fail. Resilience is the capability to absorb disruption, maintain essential performance and recover or adapt. Business continuity is the organised capability to continue critical activities at an acceptable level during and after disruption.

The objective of this chapter is to explain how purchasing professionals can identify and prioritise financial, operational, geopolitical, logistics, cyber, concentration and disruption risks, and then convert the assessment into mitigation, contingency and continuity plans.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Distinguish supplier risk, resilience, contingency and business continuity.
  2. Classify major categories of supplier risk and recognise their interdependencies.
  3. Construct and maintain a supplier risk register and heat map.
  4. Apply scoring, scenario analysis and failure-mode approaches appropriately.
  5. Design preventive controls, contingency arrangements and continuity plans.
  6. Evaluate supplier resilience using evidence, indicators and contractual mechanisms.
  7. Explain governance, ethical, regulatory and technology-related implications.

1. The Strategic Nature of Supplier Risk

Risk is not simply the probability that a supplier will fail. It is the effect of uncertainty on organisational objectives. In purchasing, those objectives may include cost, quality, delivery, compliance, innovation, safety, sustainability and reputation.

A useful distinction is:

  • Supplier risk: exposure created by a supplier’s possible failure, weakness or adverse event.
  • Supply risk: exposure arising anywhere in the supply network, including logistics providers, subcontractors, raw-material sources and infrastructure.
  • Resilience: the ability to absorb, adapt to and recover from disruption.
  • Contingency: a prepared alternative action used when a specified event occurs.
  • Business continuity: the capability and arrangements that maintain priority products and services during disruption.
  • Recovery: restoration of normal or agreed performance after the immediate crisis.

Risk management should not seek to eliminate every risk. Complete elimination is usually impossible and may be uneconomic. The professional task is to make risk visible, compare it with organisational tolerance and reduce exposure to a level that is justified by value, criticality and cost.

A supplier may be low risk in one dimension and high risk in another. A financially strong global supplier may present high concentration and geopolitical risk. A small local supplier may be operationally agile but financially fragile. Risk assessment must therefore be multidimensional.

2. Categories and Interdependencies of Supplier Risk

Financial risk

Financial risk concerns the supplier’s ability to remain solvent and perform its obligations. Indicators include declining liquidity, excessive debt, delayed payments to subcontractors, covenant breaches, dependence on one customer and adverse credit information. Financial failure may cause immediate supply interruption, loss of tooling or intellectual property, and difficulty obtaining replacement capacity.

Useful evidence includes audited accounts, management accounts, credit reports, payment behaviour, insurance information, ownership changes and discussions with the supplier’s finance team. Financial information must be interpreted in context: a low-margin business may be healthy if cash generation is strong, while a profitable business may still face liquidity pressure.

Operational and quality risk

Operational risk includes inadequate capacity, poor maintenance, weak process control, labour shortages, quality failures, obsolete equipment and dependence on key individuals. Relevant evidence includes capacity plans, defect data, on-time delivery, corrective-action records, business continuity tests and audit findings.

Quality risk has both direct and indirect effects. A defective component may cause rework, warranty claims, regulatory action or harm to users. Critical suppliers should be assessed not only on average performance but also on process capability, traceability and response speed.

Geopolitical and regulatory risk

Geopolitical risk arises from conflict, sanctions, export controls, political instability, nationalisation, tariffs, regulatory changes and restrictions on foreign exchange or data transfer. A supplier may be compliant today but become inaccessible after a sudden policy change. Purchasing teams should map the countries of incorporation, production, ownership, banking, transport and critical sub-tier supply.

Due diligence must include sanctions screening, modern-slavery considerations, trade compliance, forced-labour exposure, human-rights risks and relevant environmental obligations. Contractual compliance statements are not substitutes for verification.

Logistics and infrastructure risk

Logistics risk includes port congestion, carrier failure, route closure, customs delays, fuel disruption, warehouse failure and inadequate packaging. Infrastructure risks include electricity, water, telecommunications and critical transport corridors. Long physical lead times amplify the effect of even short disruptions.

The buyer should distinguish lead time from recovery time. Lead time is the normal time from order to receipt. Recovery time is the time required to restore an acceptable supply position after a disruption. A supplier with a short normal lead time may still have a long recovery time if no alternative capacity exists.

Cyber and information risk

Suppliers may hold personal data, design files, payment information, credentials or access to operational systems. Cyber risk includes ransomware, data theft, fraud, software compromise, weak access controls and insecure subcontractors. A supplier can become the entry point into the buyer’s network.

Assessment should cover identity and access management, multifactor authentication, patching, backup and restoration, incident reporting, vulnerability management, segregation of environments and cyber insurance. The assessment should be proportional to the sensitivity and criticality of the service.

Concentration and dependency risk

Concentration risk exists when too much demand, spend, capability or knowledge is placed with one supplier, site, country, route or technology. It is often hidden because multiple purchase orders may ultimately depend on one manufacturing plant or raw-material source.

A basic spend concentration measure is the share of total relevant spend placed with supplier i:

si = \frac{\text{Spend with supplier } i}{\text{Total relevant supplier spend}} × 100

Here, si is the percentage share. The measure is useful for screening, but it does not capture criticality. A supplier representing 5% of spend may provide a unique safety-critical component and therefore deserve more attention than a supplier representing 30% of easily replaceable goods.

Demand, market and disruption risk

Demand volatility, commodity-price movements, strikes, pandemics, natural hazards and sudden changes in customer requirements can create disruption even when the supplier is well managed. Risk assessment should examine both the likelihood of an event and the organisation’s ability to withstand its consequences.

These categories interact. A cyberattack may stop production, damage cash flow and breach regulatory obligations. A geopolitical event may close a route, increase prices and create a quality problem when sourcing is hurriedly transferred. Risk registers should therefore record dependencies rather than treating categories as isolated checkboxes.

3. Risk Identification and Assessment Framework

Establishing scope and criticality

Assessment begins by defining the population to be reviewed. It should include direct suppliers and, where material, logistics providers, contract manufacturers, cloud providers, agents and known sub-tier suppliers.

Supplier criticality can be assessed through questions such as:

  • Does failure threaten life, safety, legal compliance or essential customer service?
  • Is the item technically unique or difficult to qualify?
  • How long would replacement take?
  • Are approved alternatives available?
  • Does the supplier control important data, tooling or intellectual property?
  • Would failure cause significant financial or reputational loss?

Criticality should be agreed by procurement, operations, quality, finance, information security, legal and relevant business owners.

The supplier risk register

A risk register is a controlled record of identified risks, causes, consequences, controls, owners and actions. A practical register may contain the following fields:

FieldPurpose
Supplier and serviceDefines the exposure
Risk eventDescribes what may happen
Cause and dependencyExplains why it may happen
ConsequenceRecords operational, financial, legal or reputational effects
Existing controlsShows current protection
Likelihood and impactSupports prioritisation
Risk ownerAssigns accountability
Treatment actionDefines further mitigation
Trigger and review dateSupports monitoring
Residual riskRecords exposure after controls

A risk event should be written clearly. “Supplier issue” is too vague. “Tier-two resin producer is unable to supply for six weeks after a regional power disruption” is assessable and can be linked to a response plan.

Scoring and heat maps

A common screening method assigns likelihood and impact scores, each often ranging from 1 to 5. A simple risk score is:

R = L × I

where R is the risk score, L is the likelihood score and I is the impact score. This multiplication is a prioritisation convention, not a probability law. It assumes that the organisation has defined comparable scales and accepts that a high-impact, low-likelihood risk may receive the same score as a moderate risk.

For example, if a disruption is rated likelihood 3 and impact 5, its score is 15. If the organisation classifies scores of 15 or above as high, the risk requires senior review. The scale must be documented: likelihood 3 might mean an event occurring between 10% and 30% in a defined period, while impact 5 might mean prolonged interruption of a legally or safety-critical service.

The heat map is useful for communication, but it has limitations. Scores can create false precision, encourage subjective debate and conceal uncertainty. A risk with poor-quality evidence should not be treated as equally reliable as a risk supported by tested data. Record confidence separately where necessary.

Expected loss and scenario analysis

Where credible numerical data exist, expected loss can support economic decisions:

EL = p × C

where EL is expected loss over a stated period, p is the probability of the event in that period, and C is the monetary consequence if it occurs. The units of EL are monetary units per period. This model assumes a defined event, a meaningful probability estimate and a sufficiently stable consequence estimate. It is not appropriate as the sole basis for low-frequency catastrophic risks, ethical harms or situations where probabilities are highly uncertain.

Suppose a disruption has an estimated annual probability of 0.10 and a consequence of £400,000. The expected annual loss is:

EL = 0.10 × £400,000 = £40,000

A £25,000 control may appear economically justified, but the decision must also consider implementation risk, liquidity, safety, regulatory duties and whether the control reduces probability, consequence or both.

Scenario analysis is particularly valuable when probabilities are unreliable. Develop plausible scenarios such as a 30-day port closure, supplier insolvency, ransomware attack or export restriction. For each scenario, identify affected products, dependencies, decision points, minimum service levels, available capacity and recovery actions. Scenarios should be tested through workshops, simulations or exercises rather than left as documents.

Failure-mode analysis

Failure Mode and Effects Analysis (FMEA) examines how a process, product or supplier arrangement can fail. Typical fields are failure mode, effect, cause, existing controls, severity, occurrence and detectability. Traditional FMEA may calculate a risk priority number:

RPN = S × O × D

where S, O and D are ordinal ratings for severity, occurrence and detectability. The result is a ranking aid, not a probability or monetary value. Ratings must be defined consistently, and a low RPN must not override a severe failure that has unacceptable safety or legal consequences. Many organisations therefore use action thresholds for severity in addition to the RPN.

FMEA is especially useful for critical components, supplier onboarding, logistics processes and cyber-enabled workflows. It forces teams to ask how a failure will be detected and whether controls prevent the cause or merely identify the consequence.

4. Designing Risk Treatments

Risk treatment should be selected according to the source of exposure, criticality and cost. Common strategies are:

  1. Avoidance: discontinue a product, route, technology or supplier arrangement when exposure is unacceptable.
  2. Reduction: improve controls, qualify alternatives, increase visibility or change specifications.
  3. Transfer or sharing: use insurance, contractual allocation, warranties or collaborative investment. Transfer does not remove the underlying operational risk.
  4. Acceptance: retain the risk with an explicit owner, rationale, monitoring plan and approval.
  5. Exploitation or opportunity management: use resilience investments to create flexibility, innovation or competitive advantage.

Preventive mitigation

Preventive measures reduce the likelihood or severity of disruption before it occurs. Examples include dual sourcing, regional diversification, approved substitute materials, supplier development, preventive maintenance, financial monitoring, cyber controls, inventory buffers and formal change control.

Dual sourcing is not automatically resilient. If both suppliers use the same sub-tier producer, port or software platform, the apparent diversification is illusory. The buyer should test independence at the relevant tier.

Inventory can provide time, but it has costs and limits. A buffer should be linked to service requirements, replenishment uncertainty, shelf life and financial constraints. For a continuously consumed item, a simple coverage estimate is:

\text{Days of cover} = \frac{\text{Usable inventory units}}{\text{Average daily demand units}}

This assumes demand is measured over a representative period and that all inventory is usable and available. It does not account for demand variability, safety stock policy, quality holds or replenishment during disruption. Therefore, days of cover is an indicator rather than a complete continuity calculation.

Contingency planning

A contingency plan describes what will be done when a defined trigger occurs. It should specify:

  • the trigger and escalation threshold;
  • the accountable decision-maker;
  • immediate safety and containment actions;
  • internal and external communication;
  • alternative suppliers, routes, materials or processes;
  • approvals and quality requalification requirements;
  • allocation of scarce supply;
  • financial and contractual authorities;
  • records, review and closure criteria.

A plan that merely states “use an alternative supplier” is incomplete. It should identify the supplier, capacity, lead time, tooling, quality status, regulatory approvals, price basis and activation procedure.

Business continuity and recovery

Business continuity planning focuses on maintaining priority activities at an acceptable level. A business impact analysis identifies critical processes, dependencies, maximum tolerable period of disruption, minimum service level and recovery requirements.

Important terms include:

  • Maximum tolerable period of disruption (MTPD): longest period an activity can be unavailable before unacceptable harm occurs.
  • Recovery time objective (RTO): target time to restore an activity or service after disruption.
  • Recovery point objective (RPO): maximum tolerable period of data loss, relevant mainly to information systems.
  • Minimum business continuity objective: minimum acceptable output or service during disruption.

The RTO must not exceed the MTPD. For example, if a critical service has an MTPD of 48 hours, an RTO of 72 hours is not credible. Continuity plans should be exercised and updated after organisational, supplier, technology or regulatory changes.

5. Governance, Contracts and Performance Management

Supplier resilience requires cross-functional governance. Procurement owns commercial relationships, but operational, quality, finance, legal, information security, risk and sustainability functions contribute essential expertise. A senior risk committee may approve risk appetite, exceptions and investments for strategic suppliers.

Contracts can support resilience through:

  • business continuity and disaster-recovery obligations;
  • notification of incidents, ownership changes and material subcontracting;
  • audit and information rights;
  • service levels and measurable recovery obligations;
  • data-security and breach-notification requirements;
  • rights to access tooling, designs or transition assistance;
  • step-in, termination and orderly exit provisions;
  • inventory, capacity or allocation commitments;
  • sanctions, human-rights and environmental compliance;
  • insurance and indemnity requirements.

Contractual rights are effective only when the buyer has the capability and resources to exercise them. A supplier may technically promise 24-hour recovery, but the promise is not credible without tested systems, people, capacity and evidence.

Performance indicators should combine leading and lagging measures. Lagging indicators include late deliveries, defects, incidents and claims. Leading indicators include audit closure, liquidity warnings, overdue maintenance, cyber-test results, staff turnover, capacity utilisation, subcontractor changes and continuity-exercise performance.

Monitoring intensity should be risk-based. Critical suppliers may require quarterly reviews and scenario exercises, while low-risk suppliers may be reviewed annually or through automated exception reporting.

6. Illustrative Case: Meridian Medical Devices

Background

Meridian Medical Devices is an illustrative manufacturer of diagnostic equipment. It purchases a specialised sensor from Supplier A, located in one country, and a protective resin from a sub-tier producer in the same region. The sensor represents only 6% of annual purchasing spend but is incorporated into a legally regulated product. Qualification of a replacement source normally takes nine months.

Problem

A regional earthquake damages transport infrastructure and interrupts electricity to the resin producer. Supplier A reports that it has four weeks of finished-goods inventory. Meridian’s existing risk register classified Supplier A as medium risk because of its modest spend share. No alternative sensor had been approved.

Analysis

A cross-functional team revises the assessment. The event has high impact because the sensor is safety-relevant and difficult to replace. Concentration exists at both supplier and sub-tier level. The team maps the supply chain, reviews inventory, checks regulatory requirements and models a six-week interruption. The risk register records:

ElementFinding
EventSub-tier resin interruption
Immediate effectSensor production stops after four weeks
Root dependencySingle regional resin source and route
ImpactPotential plant stoppage and customer delays
Existing controlFour weeks of finished inventory
WeaknessNo approved substitute or independent second source
OwnerCategory director with operations and quality
TriggerSupplier inventory below six weeks or regional infrastructure alert

The heat-map score is high, but the team does not rely on the score alone. FMEA identifies severe effects, limited detectability of sub-tier changes and inadequate recovery options. Scenario analysis shows that emergency purchasing cannot solve the problem because regulatory requalification is required.

Approach and solution

Immediate actions include securing available inventory, prioritising safety-critical customer orders, communicating transparently with customers and requesting the supplier’s allocation plan. Meridian also audits the supplier’s continuity arrangements and verifies the condition of the sub-tier producer.

Longer-term actions include qualifying a geographically independent sensor supplier, approving an alternative resin, holding a strategically justified buffer, requiring notification of sub-tier changes, and conducting an annual disruption exercise. The contract is amended to require continuity evidence, incident reporting and access to transition information.

Outcome

The initial disruption is managed without an unsafe product substitution. Meridian later qualifies a second source and reduces dependence on the original region. The cost of qualification and inventory is higher than the former arrangement, but the organisation gains improved continuity, regulatory confidence and negotiating visibility.

Learning points

  1. Spend percentage is not the same as business criticality.
  2. Tier-two and tier-three dependencies can dominate risk.
  3. Regulatory qualification time may exceed physical replacement time.
  4. Inventory buys time but does not create a substitute.
  5. A continuity plan must be tested, owned and connected to operational decisions.

7. Technology, Data and Artificial Intelligence

Digital tools can improve supplier-risk management by integrating spend, performance, financial, logistics, cyber and external-event data. Dashboards can identify changes in delivery performance, credit status, port conditions or sanctions exposure. Artificial intelligence may assist with document review, anomaly detection, news classification and relationship mapping.

However, automated risk scores are not objective facts. They may reproduce biased data, confuse correlation with causation, generate false alerts or miss risks in opaque sub-tier networks. AI outputs should therefore be explainable, subject to human review and linked to source evidence. Sensitive supplier data must be protected, and procurement teams should understand data ownership, model security, confidentiality and applicable privacy requirements.

A sound principle is “automation for detection, accountability for decisions.” A system may flag a supplier for review, but authorised professionals should validate the evidence, engage the supplier and approve treatment.

8. Challenges and Limitations

Supplier-risk management faces several persistent challenges:

  • incomplete visibility beyond tier one;
  • poor comparability of supplier financial information;
  • inaccurate or outdated risk registers;
  • subjective scoring and false precision;
  • conflicting commercial incentives to minimise inventory or supplier count;
  • supplier fatigue caused by repetitive questionnaires;
  • uncertain probabilities for rare events;
  • rapid changes in geopolitical, cyber and environmental conditions;
  • overreliance on contractual promises;
  • tension between resilience, cost, sustainability and speed.

Resilience investments should be evaluated as strategic capabilities rather than merely additional cost. Nevertheless, not every risk justifies dual sourcing, extra inventory or expensive technology. The appropriate response depends on criticality, uncertainty, recovery options, stakeholder harm and organisational risk appetite.

Ethically, buyers must avoid transferring unreasonable risk to smaller suppliers through oppressive payment terms, unrealistic service requirements or unilateral contract changes. Responsible supplier management includes fair communication, respect for human rights, privacy, worker safety and environmental obligations. Resilience achieved through exploitation is not professionally sustainable.

Best-Practice Implementation Sequence

An organisation introducing or improving supplier resilience can follow this sequence:

  1. Map critical products, services, suppliers and important sub-tier dependencies.
  2. Define risk appetite, impact scales, ownership and escalation rules.
  3. Assess supplier criticality using operational, legal, safety and customer criteria.
  4. Build a risk register using evidence rather than general impressions.
  5. Apply heat maps, scenario analysis and FMEA as complementary methods.
  6. Select treatments that address causes, dependencies and recovery constraints.
  7. Embed requirements in contracts, specifications and supplier-development plans.
  8. Establish leading and lagging indicators with defined thresholds.
  9. Test contingency and continuity plans through exercises.
  10. Review risks after incidents, market changes, supplier changes and exercises.

Chapter Summary

Supplier risk is a strategic exposure affecting continuity, quality, cost, compliance and reputation. Important categories include financial, operational, quality, geopolitical, logistics, cyber, concentration and disruption risk. These categories interact across multiple supplier tiers, so assessment must examine dependencies rather than rely solely on first-tier supplier status or spend percentages.

Risk registers provide ownership and traceability. Heat maps support prioritisation, while scenario analysis is valuable when probabilities are uncertain. FMEA examines failure modes, effects, causes and controls, but ordinal scores must not override severe safety or legal consequences. Preventive mitigation reduces exposure before disruption; contingency plans specify actions after a trigger; business continuity arrangements maintain priority services and support recovery.

Effective resilience depends on evidence, cross-functional governance, credible contracts, leading indicators, supplier collaboration and tested plans. Technology and AI can improve visibility, but automated outputs require human judgement and strong data governance. The best purchasing decisions balance cost with criticality, ethical responsibility, recovery capability and long-term organisational resilience.

Key Terms

Supplier risk: Exposure arising from possible supplier failure or adverse supplier conditions.

Supply risk: Exposure arising anywhere in the supply network.

Resilience: Ability to absorb, adapt to and recover from disruption.

Business continuity: Capability to maintain priority activities during disruption.

Contingency: A prepared alternative action activated by a defined event.

Recovery: Restoration of agreed performance after disruption.

Risk register: Controlled record of risks, controls, owners and actions.

Heat map: Visual display of risks by likelihood and impact.

Scenario analysis: Examination of plausible future disruption conditions.

FMEA: Structured analysis of failure modes, effects, causes and controls.

Concentration risk: Exposure created by dependence on one supplier, site, route or technology.

Sub-tier supplier: A supplier that provides goods or services to another supplier in the chain.

MTPD: Maximum tolerable period before disruption causes unacceptable harm.

RTO: Target time for restoring an activity or service.

RPO: Maximum tolerable period of data loss.

Risk appetite: Amount and type of risk an organisation is willing to accept.

Residual risk: Risk remaining after controls and treatments are applied.

Business impact analysis: Assessment of the consequences of disruption to activities and dependencies.

Supplier development: Planned assistance or collaboration to improve supplier capability and performance.

Risk trigger: A measurable condition that initiates escalation or response.

Review Questions

Short Answer Questions

  1. Distinguish supplier risk from supplier resilience.
  2. What information should be recorded in a supplier risk register?
  3. Why can a low-spend supplier still be business-critical?
  4. State two limitations of a risk heat map.
  5. What is the purpose of a contingency plan?

Long Answer Questions

  1. Explain the main categories of supplier risk and show how they may interact.
  2. Describe how a purchasing team should design and maintain a supplier risk register.
  3. Compare heat maps, expected-loss analysis, scenario analysis and FMEA.
  4. Explain how contracts and performance indicators can support supplier resilience.
  5. Discuss the relationship between business continuity, contingency planning and recovery.

Analytical / Application Questions

  1. A sole-source supplier provides a safety-critical component, has strong financial results and represents only 4% of spend. Analyse its risk profile and recommend treatments.
  2. A supplier reports a ransomware attack but claims that production is unaffected. Design an immediate procurement response and a longer-term assurance plan.
  3. A company must choose between dual sourcing, six weeks of inventory or qualifying a substitute material. Develop a decision framework using criticality, recovery time, cost, quality and regulatory constraints.

Multiple Choice Questions with Answers

Question 1

Which statement best describes supplier resilience?

A. The elimination of every possible supplier risk

B. The ability to absorb, adapt to and recover from disruption

C. The percentage of spend placed with approved suppliers

D. The contractual transfer of all supplier liabilities

Correct Answer: B. The ability to absorb, adapt to and recover from disruption

Question 2

A supplier risk has a likelihood score of 4 and an impact score of 5. Using R = L × I, what is the screening score?

A. 9

B. 16

C. 20

D. 25

Correct Answer: C. 20

Question 3

Which item is most characteristic of concentration risk?

A. A supplier has a documented corrective-action process

B. Several suppliers depend on the same sub-tier producer

C. A buyer conducts an annual performance review

D. A supplier has multifactor authentication

Correct Answer: B. Several suppliers depend on the same sub-tier producer

Question 4

What is the main purpose of scenario analysis in supplier-risk management?

A. To guarantee the probability of every disruption

B. To replace all supplier audits

C. To examine plausible disruption conditions and responses

D. To calculate supplier profit margins

Correct Answer: C. To examine plausible disruption conditions and responses

Question 5

In FMEA, detectability refers primarily to:

A. The financial size of the supplier

B. How easily a failure will be detected before causing harm

C. The number of approved suppliers

D. The duration of a purchase contract

Correct Answer: B. How easily a failure will be detected before causing harm

Question 6

A disruption has an estimated annual probability of 0.2 and a consequence of £50,000. What is the expected annual loss?

A. £2,500

B. £10,000

C. £25,000

D. £250,000

Correct Answer: B. £10,000

Question 7

Which statement about contractual risk transfer is correct?

A. It removes the underlying operational risk

B. It makes continuity testing unnecessary

C. It allocates responsibilities but may not remove the operational exposure

D. It guarantees supplier solvency

Correct Answer: C. It allocates responsibilities but may not remove the operational exposure

Question 8

What does the recovery time objective specify?

A. The maximum amount of data that may be lost

B. The target time to restore an activity or service

C. The annual probability of supplier failure

D. The supplier’s maximum payment period

Correct Answer: B. The target time to restore an activity or service

Question 9

Why should automated supplier-risk scores receive human review?

A. Automated systems never process quantitative data

B. Risk scores may contain bias, false alerts or incomplete evidence

C. Human review eliminates the need for source evidence

D. Human review guarantees that no disruption will occur

Correct Answer: B. Risk scores may contain bias, false alerts or incomplete evidence

Question 10

Which is a preventive mitigation measure?

A. Activating an emergency allocation plan after a port closure

B. Communicating with customers after a factory fire

C. Qualifying an independent alternative supplier before disruption

D. Declaring an incident closed after recovery

Correct Answer: C. Qualifying an independent alternative supplier before disruption