Curves, Alignments and Route SurveyingIntroduction and contextRoute surveying is the systematic process of selecting, investigating, locating, designing and setting out the alignment of a road, railway, canal, pipeline, transmission line or similar elongated facility. Unlike a local building survey, a route survey must coordinate geometry, terrain, drainage, land use, construction economy, safety and environmental constraints over a considerable distance. A satisfactory route normally consists of three-dimensional geometry: - Horizontal alignment controls the plan position of the centreline through tangents and curves.
- Vertical alignment controls the elevation through gradients and vertical curves.
- Cross-sectional geometry defines widths, slopes, drainage, earthwork and clearances.
Curves are introduced because a sudden change in direction or gradient is unsafe, uncomfortable, difficult to construct and potentially damaging to vehicles or infrastructure. The surveyor therefore converts a designed alignment into field points, reference marks, coordinates, levels and construction information. Learning objectivesOn completing this chapter, a student should be able to: - Explain the purpose and elements of horizontal, transition and vertical curves.
- Calculate and set out simple circular, compound and reverse curves.
- Explain the function of transition curves and apply standard approximate setting-out methods.
- Design and set out summit and sag vertical curves.
- Plan route reconnaissance and alignment surveys.
- Prepare longitudinal sections, cross-sections and earthwork information.
- Select suitable instruments, field procedures and quality-control checks.
- Evaluate practical, safety, environmental and professional issues in route work.
1. Route surveying and alignment principles1.1 Stages of a route surveyA route project commonly proceeds through the following stages: - Desk study: Existing maps, cadastral information, aerial imagery, geology, hydrology, utilities, planning controls and environmental records are examined.
- Reconnaissance: Alternative corridors are inspected on the ground; major obstacles, access conditions, drainage patterns, settlements and sensitive areas are recorded.
- Preliminary survey: Candidate alignments are surveyed sufficiently to compare gradients, curves, quantities, structures, land acquisition and cost.
- Final location survey: The selected centreline and control network are established accurately.
- Detailed design survey: Longitudinal and cross-sectional levels, drainage features, utilities, property boundaries and structures are measured.
- Construction setting out: Centreline, offsets, grade points, curve points, batter stakes and structure locations are transferred to the ground.
- As-built survey: Completed works are measured and compared with the approved design.
The best alignment is not necessarily the shortest. A longer route may be preferable if it reduces steep gradients, unstable ground, bridge length, environmental damage, land acquisition or operating risk. 1.2 Geometric controlsA route alignment is governed by design speed, terrain, vehicle performance, sight distance, drainage, construction methods and applicable standards. Local standards should always be used for minimum radii, maximum gradients, superelevation, transition lengths, stopping sight distance and vertical-curve criteria. The equations in this chapter describe surveying geometry; they do not replace statutory design standards. The direction of a tangent may be expressed as a bearing or azimuth. A bearing is measured clockwise from a stated reference, usually north. The intersection angle between two tangents is the deflection angle, Δ. The sign convention must be stated: for example, right-hand deflections may be positive and left-hand deflections negative. 2. Horizontal circular curves2.1 Purpose and geometryA simple circular curve has constant radius and connects two tangents. Its principal points are: - PI: point of intersection of the tangents;
- PC: point of curvature, where the first tangent meets the curve;
- PT: point of tangency, where the curve meets the second tangent;
- O: centre of the circle;
- Δ: central angle, numerically equal to the tangent intersection angle when expressed in radians or degrees consistently;
- T: tangent length from PI to PC or PT;
- L: arc length from PC to PT;
- E: external distance from PI to the curve;
- M: middle ordinate from the curve to the long chord.
For a curve of radius R and deflection angle Δ in degrees: T = R tan(Δ/2) L = πRΔ/180 E = R[sec(Δ/2) − 1] M = R[1 − cos(Δ/2)] Here R and T, E and M have units of length; L is a length; Δ is in degrees in the arc-length equation and must be used consistently in the trigonometric functions. These equations assume a circular arc joining two intersecting tangents. If Δ is expressed in radians, L = RΔ. The long chord is: C = 2R sin(Δ/2) The relationships are useful both for design checks and for locating inaccessible points. A common error is to use degrees in an equation requiring radians, or to confuse arc length with chord length. 2.2 Chainages of curve pointsIf the chainage of PI is known, and chainage increases in the direction of survey: Ch(PC) = Ch(PI) − T Ch(PT) = Ch(PC) + L The chainage of PT must not be calculated by adding the long chord; chainage follows the route length, which is the arc length for a circular curve. 2.3 Setting out methods#### Deflection-angle method In the tangential-angle method, a theodolite or total station is set at PC. The initial line is directed along the tangent. For a chord c from the current point to the next point, the deflection angle δ to that chord is: δ = c/(2R) when δ is in radians and c and R use the same length units. In degrees: δ° = 180c/(2πR) For a sequence of equal chords, the cumulative deflection increases by the same amount for each chord. The final chord is usually a subchord and must be calculated separately. The total deflection from the initial tangent to the PT is Δ/2. The field procedure is to set the instrument at PC, sight the tangent or an accurately established backsight, turn the required cumulative deflection, and measure each chord. The instrument is periodically checked by occupying an established point or by verifying the final tangent direction. #### Rankine or coordinate method A total station can set out points by polar coordinates, using computed distances and directions from a control station. Alternatively, rectangular offsets from a tangent or long chord may be used. Coordinate methods are efficient where a digital terrain model and reliable control network are available, but they remain dependent on correct coordinate systems, prism constants, orientation and data files. Worked example 1: simple circular curveA road curve has R = 300 m and Δ = 40°. The chainage of PI is 12+500 m. Determine T, L, E, PC and PT chainages. T = 300 tan(20°) = 109.19 m L = π(300)(40)/180 = 209.44 m E = 300[sec(20°) − 1] = 19.27 m Therefore: - Ch(PC) = 12,500.00 − 109.19 = 12,390.81 m, or 12+390.81.
- Ch(PT) = 12,390.81 + 209.44 = 12,600.25 m, or 12+600.25.
The result is dimensionally consistent: T, L and E are lengths. A field book should also record the curve direction, radius, tangent bearings, point coordinates and setting-out method. 3. Compound and reverse curves3.1 Compound curvesA compound curve consists of two or more circular arcs of different radii turning in the same direction, joined tangentially at a common point. They may be required where terrain or property boundaries constrain the alignment. They should be used cautiously because the rate of curvature changes abruptly at the common tangent point. For each component i: Li = πRiΔi/180 The total curve length is Ltotal = ∑Li, and the total change in direction is Δtotal = ∑Δi for arcs turning in the same direction. The tangent and intersection geometry must be solved from the known tangent directions, radii and point constraints; the individual arcs cannot be treated as one curve with an average radius. A practical design procedure is: - Establish the incoming and outgoing tangent directions.
- Select radii consistent with the design standard and terrain.
- Determine the common tangent direction and component deflection angles from the geometric constraints.
- Compute tangent points, arc lengths and chainages.
- Check that the common point is tangent to both arcs and that the total deflection equals the change between the external tangents.
- Set out each component separately, clearly marking the common point.
At the common point, the tangent direction is continuous, but curvature changes. A transition curve may be preferable where operating speed is high or comfort is important. 3.2 Reverse curvesA reverse curve consists of two arcs with opposite curvature and a common tangent point. It changes direction first one way and then the other. Such curves are sometimes unavoidable in constrained corridors, but a short tangent between the arcs is generally preferred for roads because it allows superelevation to be reversed safely and gives drivers a clearer path. For a reverse curve, signed deflections should be used. If right-hand deflection is positive and left-hand deflection negative: Δtotal = Δ1 + Δ2 where Δ₂ has the opposite sign to Δ₁. The component arc lengths use the magnitude of each deflection. The key checks are tangency, correct sign convention, adequate sight distance and sufficient length for drainage and crossfall transition. A reverse curve must not be set out by simply adding unsigned deflection angles. 4. Transition curves4.1 Need for transitionAt the beginning of a simple circular curve, curvature changes theoretically from zero on the tangent to 1/R instantly. This produces a sudden lateral-acceleration change, complicates steering and causes abrupt superelevation development. A transition curve provides a gradual change. A commonly used transition is the clothoid or Euler spiral, for which curvature increases linearly with distance s: 1/ρ = s/A² where ρ is the instantaneous radius, s is distance measured from the start of the transition, and A is the spiral parameter. At the end of a transition of length L_s joining a circular curve of radius R: A² = RLs These equations assume a true clothoid and consistent length units. The curvature relation is geometric; selection of L_s must also satisfy the governing road standard for comfort, superelevation and appearance. For small coordinates near the origin, approximate spiral coordinates are: x ≈ s − s⁵/(40A⁴) y ≈ s³/(6A²) − s⁷/(336A⁶) where x is the tangent-direction coordinate and y is the offset toward the curve. These truncated series are suitable only when the omitted terms are negligible for the selected s/A ratio. For production setting out, approved tables, software or a rigorous coordinate computation should be used. 4.2 Transition-curve setting outA standard sequence is: - Determine the circular radius and required transition length.
- Compute the shift and tangent corrections using the adopted design convention.
- Establish the tangent, transition start and circular-curve points from the final design geometry.
- Set out transition points by coordinates, deflection angles or offsets.
- Verify that curvature increases smoothly and that the transition joins the circular arc tangentially.
Surveyors must distinguish the geometric transition length from the length required to develop pavement superelevation. The controlling value is normally the greater of the applicable requirements. 5. Vertical alignment and vertical curves5.1 Gradients and gradesA gradient is the rate of change of elevation with horizontal distance. If elevations are in metres and horizontal distance is in metres, gradient as a decimal is: g = Δz/L Percentage grade is 100g%. A rising grade may be positive and a falling grade negative, but the convention must be maintained throughout calculations. A vertical curve connects two grades smoothly. The parabolic curve is widely used because it gives a constant rate of change of grade with horizontal distance and provides a practical approximation for highway design. Let g₁ and g₂ be the grades as decimals, L be the horizontal length of the vertical curve, and x be distance from the beginning of curve (BVC). The algebraic grade difference is: A = g₂ − g₁ The grade at distance x is: gx = g₁ + Ax/L The elevation equation is: zx = zBVC + g₁x + Ax²/(2L) At x = L, the equation gives the elevation of the end of vertical curve (EVC), and the grade is g₂. The equation assumes x and L are horizontal distances and g₁, g₂ are decimal ratios, not percentages. If grades are entered as percentages, divide them by 100 first. The point of maximum or minimum elevation occurs where g_x = 0: x₀ = −g₁L/A provided 0 ≤ x₀ ≤ L and A ≠ 0. If x₀ lies outside the curve, the maximum or minimum within the curve occurs at an endpoint. The curve is a summit curve when a rising grade changes to a falling grade, so A is negative. It is a sag curve when a falling grade changes to a rising grade, so A is positive. Worked example 2: vertical curveA summit curve of length 160 m joins a +3% grade to a −2% grade. The elevation at BVC is 250.000 m. Find the elevation at the midpoint and the location and elevation of the summit. Convert grades to decimals: g₁ = 0.03, g₂ = −0.02. Thus A = −0.05. At x = 80 m: z80 = 250.000 + (0.03)(80) + [(-0.05)(80²)/(2×160)] z80 = 250.000 + 2.400 − 1.000 = 251.400 m The summit occurs at: x₀ = −(0.03)(160)/(−0.05) = 96.0 m Its elevation is: z96 = 250.000 + (0.03)(96) + [(-0.05)(96²)/(2×160)] z96 = 250.000 + 2.880 − 1.440 = 251.440 m Thus the summit is 96.0 m from BVC and has elevation 251.440 m. The calculation uses horizontal distance and decimal grades; using percentages without conversion would produce an error by a factor of 100. 5.2 Sight distance and drainageVertical-curve length cannot be selected from geometry alone. Summit curves must provide the required stopping or overtaking sight distance. Sag curves must provide adequate headlight sight distance where relevant, acceptable comfort and drainage. At a sag low point, water must not pond; longitudinal drainage, kerbs, inlets and crossfall transitions require explicit checking. 6. Route reconnaissance and alignment surveys6.1 Reconnaissance planningReconnaissance begins before detailed measurements. The team should define the route function, design speed, traffic or service demand, required connections, survey datum, coordinate reference system, access permissions, safety plan and deliverables. A corridor appraisal should record: - topography and terrain breaks;
- rivers, floodplains, wetlands and drainage paths;
- geological hazards, erosion and landslide evidence;
- existing roads, railways, bridges and utility crossings;
- buildings, cemeteries, protected sites and property boundaries;
- vegetation, habitats and community facilities;
- likely borrow areas, disposal areas and construction access;
- visibility, security, traffic exposure and occupational hazards.
Alternative corridors should be compared using transparent criteria rather than informal preference. A multi-criteria matrix may include length, earthwork, structures, land acquisition, environmental sensitivity, utility conflict, operating safety and lifecycle cost. Weighting should be agreed with the client and documented. 6.2 Control and field proceduresA reliable route survey uses a control framework tied to a recognized horizontal and vertical datum. Control points should be intervisible where practical, stable, protected and independently checkable. Typical equipment includes GNSS receivers, total stations, digital levels, automatic levels, data collectors, prisms, staffs, measuring tapes and metal detectors for locating buried services where appropriate. Good practice includes: - checking instrument collimation, compensator, circular and plate levels, prism constant and battery status;
- using backsight and foresight observations with balanced sights for levelling;
- closing traverses and level runs on known or independently observed control;
- recording raw observations, not only computed coordinates;
- applying correct atmospheric, projection and instrument settings;
- maintaining a clear point naming convention and metadata;
- independently checking critical curve points and benchmarks.
For differential levelling, the height of instrument method is: HI = RLBM + BS RLpoint = HI − FS where RL is reduced level, BS is backsight and FS is foresight. For a complete run, the arithmetic check is: ΣBS − ΣFS = RLlast − RLfirst This check detects arithmetic or booking errors but does not guarantee that an observation is free from systematic error. 6.3 Longitudinal sectionA longitudinal section (profile) plots chainage horizontally and reduced level vertically along the proposed centreline. It should show existing ground, design grade line, BVC, EVC, vertical-curve elevations, drainage crossings, utilities, property access, structures and benchmarks. Vertical scales are often exaggerated for readability, but the scales must be stated and interpretation must not confuse plotted appearance with actual slope. The profile supports decisions about: - cut and fill;
- minimum cover over utilities;
- drainage outfalls and culverts;
- driveway and intersection grades;
- bridge approaches;
- vertical clearances;
- construction staging.
6.4 Cross-sectionsCross-sections are taken at regular intervals and at all significant breaks: curve points, intersections, drainage lines, culvert sites, property accesses, retaining structures, changes in ground slope and limits of earthwork. They normally show centreline chainage, offsets, existing levels, proposed formation, pavement layers, side slopes, ditches, berms, utilities and right-of-way limits. For a simple prismoidal estimate of earthwork volume between two sections: V ≈ L(A₁ + A₂)/2 where A₁ and A₂ are end areas and L is the spacing. This is the average-end-area method. It assumes a linear change in area and can be inaccurate where terrain or side slopes vary sharply. The prismoidal formula is: V = L(A₁ + 4Am + A₂)/6 where A_m is the area at the midpoint. It is more appropriate when the section variation is approximately parabolic and a reliable midpoint section exists. Digital terrain models may use triangular irregular networks, but the surveyor must still inspect breaklines and data density. 7. Applied case: illustrative rural access roadBackgroundA local authority proposes a 2.4 km two-lane access road linking a village to an industrial site. The corridor crosses rolling terrain, a seasonal stream and cultivated land. This is an illustrative case, not a statutory design. ProblemThe preliminary straight route has a steep 7% approach, passes close to a flood-prone stream bank and creates a reverse curve near the village entrance. The client requires safe operation, reasonable earthwork and protection of agricultural drainage. AnalysisThe survey team conducts a desk study and reconnaissance, then establishes GNSS control tied to the project datum. A total station traverse and digital levelling survey provide centreline and cross-section data. Three corridor options are compared. The shortest option has the greatest cut volume and requires a long retaining wall. A slightly longer option shifts the stream crossing to a narrower location and reduces the maximum grade. The selected plan uses tangent–transition–circular–transition geometry for the main bend. A short reverse curve at the village entrance is replaced by a longer compound arrangement with a connecting tangent, providing more space to develop crossfall. A summit vertical curve is placed where two grades meet, and a sag curve is lengthened near the stream to improve drainage and comfort. Approach and solutionThe surveyors compute PI, PC, PT, transition points, radii, deflection angles and chainages. They set permanent reference marks outside the construction zone and provide offset stakes because centreline stakes may be removed during earthworks. Cross-sections are collected at 20 m intervals and at all terrain breaks. A longitudinal profile identifies a low point requiring a culvert and inlet protection. The design file is checked by an independent surveyor. Curve points are set out from two separate control stations, and the final tangent bearing is compared with the theoretical bearing. Level runs close on independent benchmarks. The environmental plan includes sediment control, restricted working limits and protection of the stream buffer. Outcome and learning pointsThe selected alignment is longer but reduces major earthworks and avoids a sensitive bank. Construction receives coordinated plan, profile and cross-section information rather than isolated coordinates. The case demonstrates that alignment surveying is an integrated decision process: geometric elegance alone cannot outweigh drainage, safety, constructability, land and environmental constraints. 8. Quality, safety, ethics and technology8.1 Quality assuranceBefore fieldwork, prepare a method statement, control diagram, equipment checklist, observation tolerances and independent-check plan. During work, protect benchmarks, document changes and retain raw data. During processing, inspect residuals, traverse closure, level misclosure, point codes, units, coordinate systems and surface breaklines. Before issue, compare drawings, models, schedules and setting-out lists. A surveyor must never adjust observations merely to force agreement with a desired design. Suspect data should be flagged, reobserved or reported with its uncertainty. Professional responsibility includes communicating limitations, datum assumptions, inaccessible areas and possible utility uncertainty. 8.2 Safety and governanceRoute work exposes personnel to traffic, unstable slopes, water, vegetation, construction plant, electrical lines and remote locations. Controls include traffic management, high-visibility clothing, communication plans, safe approach distances, lone-worker procedures, weather monitoring and pre-entry inspections. Utility records must not be treated as proof of exact underground position; approved detection and excavation procedures are required. Land access, privacy, indigenous or community rights, environmental permits and data protection must be respected. Survey marks should not be moved without authorization. Deliverables should identify the responsible professional, survey date, datum, coordinate system, equipment and accuracy class where required by regulation. 8.3 Digital and AI-supported surveyingGNSS network corrections, robotic total stations, mobile mapping, LiDAR, UAV photogrammetry and building or civil information models can improve coverage and reduce repetitive measurement. Machine-learning tools may assist point-cloud classification, feature extraction and anomaly detection. They do not remove the need for field control, legal boundary evidence, quality checks or professional judgement. AI-generated alignment alternatives must be tested against design standards, constructability, environmental constraints and actual ground evidence. A defensible workflow preserves raw observations, software versions, transformations and human approvals. Best-practice checklist- State the datum, units, bearing convention and chainage direction.
- Use design-standard criteria for radii, grades, transitions, sight distance and drainage.
- Check every curve independently by geometry and by field orientation.
- Use decimal grades in vertical-curve equations.
- Distinguish arc length from chord length.
- Establish redundant control and protect reference marks.
- Survey cross-sections at both regular spacing and critical terrain changes.
- Coordinate plan, profile, cross-sections, drainage and utilities.
- Preserve raw data and document transformations and assumptions.
- Treat safety, land access, environmental protection and data integrity as part of technical quality.
Chapter SummaryRoute surveying integrates horizontal geometry, vertical geometry, terrain measurement and construction control. Simple circular curves connect tangents with constant radius and can be defined by tangent length, arc length, offsets, chord and deflection relationships. Compound curves use same-direction arcs of different radii; reverse curves use opposite curvature and require careful sign conventions and superelevation planning. Transition curves progressively introduce curvature, commonly through a clothoid relationship. Vertical curves, normally parabolic for practical road design, connect grades and permit calculation of grade and elevation at any chainage. Reconnaissance and alignment surveys extend beyond measurement: they compare corridors using terrain, drainage, safety, land, environmental and construction criteria. Longitudinal sections communicate profile decisions, while cross-sections support earthwork, drainage and formation design. Reliable results depend on datum control, independent checks, accurate field records, appropriate technology and ethical professional judgement. Key TermsAlignment: The three-dimensional geometric path of a route. Azimuth: A horizontal direction measured clockwise from a reference north. BVC: Beginning of a vertical curve. Chainage: Distance measured along the route alignment from a defined origin. Compound curve: A curve made of two or more circular arcs turning in the same direction. Cross-section: A section taken transverse to the route showing ground and proposed works. Deflection angle: The change in direction between two tangents or a tangent and chord. EVC: End of a vertical curve. Longitudinal section: A profile of ground and design levels along the route centreline. Parabolic vertical curve: A vertical curve with a constant rate of change of grade. PC: Point of curvature, where a circular curve begins. PI: Point of intersection of two tangents. PT: Point of tangency, where a circular curve ends. Reverse curve: Two arcs with opposite curvature joined at a common tangent point. RL: Reduced level or elevation relative to a datum. Sag curve: A vertical curve joining a falling grade to a rising grade. Simple circular curve: A constant-radius curve joining two tangents. Summit curve: A vertical curve joining a rising grade to a falling grade. Transition curve: A curve whose curvature changes progressively between a tangent and a circular curve. Traverse: A connected sequence of measured lines and angles used to establish horizontal control. Review QuestionsShort Answer Questions- Define PC, PI and PT in a simple circular curve.
- Why is a transition curve used between a tangent and a circular curve?
- State the difference between a compound curve and a reverse curve.
- What information is normally shown on a longitudinal section?
- Why are independent checks necessary in route surveying?
Long Answer Questions- Explain the stages of a route survey from desk study to as-built survey, including the principal outputs of each stage.
- Derive or explain the principal elements of a simple circular curve and describe a deflection-angle setting-out procedure.
- Explain the parabolic vertical-curve equation, define all variables and discuss summit, sag, sight-distance and drainage considerations.
- Describe how reconnaissance data, terrain, land, environmental and construction constraints influence alignment selection.
- Discuss quality assurance, safety, ethics and governance requirements for a modern route-surveying project.
Analytical / Application Questions- A curve has radius 250 m and deflection angle 36°. Calculate tangent length, arc length and long chord. State the units and assumptions used.
- A vertical curve 120 m long joins grades of −1.5% and +2.5%, with BVC elevation 180.000 m. Determine the grade difference, the location of the low point if it lies within the curve, and its elevation.
- Two proposed corridors have different lengths, earthwork quantities, stream impacts, land requirements and construction access. Develop a justified multi-criteria comparison and explain how you would verify the selected option through field surveying.
Multiple Choice Questions with AnswersQuestion 1For a simple circular curve with radius R and deflection angle Δ in degrees, which expression gives the tangent length? A. T = R sin Δ B. T = R tan(Δ/2) C. T = πRΔ/180 D. T = 2R sin(Δ/2) Correct Answer: B. T = R tan(Δ/2) Question 2A curve has R = 300 m and Δ = 40°. Its arc length is approximately: A. 104.72 m B. 200.00 m C. 209.44 m D. 218.38 m Correct Answer: C. 209.44 m Question 3Which point is the intersection of the two tangents of a simple circular curve? A. PC B. PT C. PI D. BVC Correct Answer: C. PI Question 4In a clothoid transition curve, which relationship applies at the end of a transition of length L_s joining a circular curve of radius R? A. A = R + L_s B. A² = RL_s C. A² = R/L_s D. A = RL_s² Correct Answer: B. A² = RL_s Question 5A vertical curve joins grades g₁ and g₂. The algebraic grade difference is: A. A = g₁g₂ B. A = g₁ + g₂ only when both grades are positive C. A = g₂ − g₁ D. A = L/(g₂ − g₁) Correct Answer: C. A = g₂ − g₁ Question 6A 160 m vertical curve joins +3% and −2% grades. The distance from BVC to the summit is: A. 32 m B. 64 m C. 96 m D. 128 m Correct Answer: C. 96 m Question 7Which statement correctly distinguishes arc length from chord length? A. Chainage along a circular curve uses the chord length B. Arc length is always shorter than the chord C. Arc length follows the curve, while chord length is the straight-line distance between its endpoints D. They are equal for every circular curve Correct Answer: C. Arc length follows the curve, while chord length is the straight-line distance between its endpoints Question 8Which observation provides the standard arithmetic check for a differential levelling run? A. ΣBS + ΣFS = RL_first + RL_last B. ΣBS − ΣFS = RL_last − RL_first C. ΣBS × ΣFS = RL_last − RL_first D. ΣBS/ΣFS = RL_last/RL_first Correct Answer: B. ΣBS − ΣFS = RL_last − RL_first Question 9A reverse curve consists of arcs that: A. Have equal radii and turn in the same direction B. Have opposite curvature C. Always have zero deflection D. Cannot share a tangent point Correct Answer: B. Have opposite curvature Question 10Which is a principal purpose of cross-sections in route surveying? A. To replace all horizontal control observations B. To define terrain, formation, side slopes and earthwork transverse to the route C. To determine only the magnetic declination D. To eliminate the need for drainage design Correct Answer: B. To define terrain, formation, side slopes and earthwork transverse to the route
|