Procurement and Supplier ManagementIntroductionProcurement is the organised process through which an organisation identifies a need, obtains goods or services, receives them, pays for them and manages the associated supplier relationship. It is broader than purchasing. Purchasing normally refers to the transactional act of ordering and paying, whereas procurement includes planning, specification, market research, sourcing, tendering, negotiation, contracting, supplier development and performance evaluation. In supply chain management, procurement connects internal demand with external supply. Its decisions influence cost, quality, delivery reliability, working capital, operational continuity, innovation, sustainability and organisational reputation. A low purchase price may be outweighed by poor quality, late delivery, excessive inventory, warranty claims or ethical and legal exposure. Effective procurement therefore evaluates total value and total risk rather than price alone. The procure-to-pay cycle, commonly abbreviated P2P, provides the operational backbone of procurement. Strategic sourcing and supplier management provide the analytical and relationship-management dimensions. Together they enable an organisation to obtain the right specification, in the right quantity, at the right time, from an appropriate source, under suitable commercial and ethical conditions. Learning ObjectivesBy the end of this chapter, the learner should be able to: - Explain the purpose and stages of procurement and the procure-to-pay cycle.
- Distinguish direct, indirect, services and capital expenditure procurement.
- Analyse organisational spend and make-or-buy decisions.
- Conduct sourcing, tendering and supplier selection using transparent criteria.
- Apply basic negotiation principles and explain essential contract provisions.
- Evaluate suppliers using cost, quality, delivery, risk, sustainability and ethical criteria.
- Identify procurement controls, technology applications and common implementation risks.
1. Procurement in the Supply ChainProcurement begins with an internal requirement but is affected by the entire supply network. A production stoppage caused by a supplier shortage can affect customer service, revenue and reputation. Conversely, excessive purchasing can create obsolete inventory and tie up cash. 1.1 Types of procurement| Category | Meaning | Typical examples | Main management concern |
|---|
| Direct materials | Inputs incorporated into a product or service sold to customers | Steel, chemicals, components | Continuity, quality and specification conformity | | Indirect materials | Items supporting operations but not incorporated into the product | Stationery, cleaning supplies, personal protective equipment | Demand consolidation and transaction efficiency | | Services | Purchased activities or expertise | Transport, maintenance, consultancy | Scope clarity, service levels and performance evidence | | Capital goods | Long-life assets used in operations | Machinery, vehicles, production equipment | Whole-life cost, technical fitness and investment approval |
Procurement may also be classified by value and risk. A low-value standard item can often be purchased through an approved catalogue. A high-value, technically complex or strategically important item requires formal sourcing, due diligence, contract review and continuing supplier management. 1.2 Procurement principlesProfessional procurement is guided by: - Value for money: balancing price, quality, service, risk and life-cycle cost.
- Competition: obtaining credible market alternatives where feasible.
- Transparency: using documented criteria and an auditable decision process.
- Fairness: giving qualified suppliers equal access to information and opportunity.
- Accountability: assigning authority and retaining evidence of decisions.
- Proportionality: matching procurement controls to value, risk and complexity.
- Integrity: preventing conflicts of interest, bribery, fraud and misuse of confidential information.
- Sustainability: considering environmental, social and governance effects.
2. The Procure-to-Pay CycleThe P2P cycle converts an internal need into a controlled supplier transaction. Although organisations use different names, the typical sequence is: - Need identification and requisition.
- Specification and budget confirmation.
- Supplier or contract selection.
- Purchase order creation and approval.
- Order acknowledgement and fulfilment.
- Receipt and inspection.
- Invoice verification.
- Payment and record closure.
- Supplier performance review and lessons learned.
A purchase requisition is an internal request. A purchase order is the organisation’s formal commercial instruction to a supplier. A goods-received note or service-entry record confirms what was received. The invoice requests payment. These documents should be linked so that the organisation can establish what was requested, authorised, ordered, delivered and charged. 2.1 The three-way matchA basic control compares the purchase order, receipt record and invoice. Payment is normally approved only when the three documents agree within authorised tolerances. This is called a three-way match. For example, if an order specifies 100 units at $20 per unit, the expected value before tax is: Order value = Quantity × Unit price = 100 × $20 = $2,000 If only 90 units are received, an invoice for 100 units should be investigated unless the organisation permits an approved partial-delivery or back-order arrangement. The three-way match reduces duplicate payment, payment for undelivered goods and price or quantity errors. 2.2 Segregation of dutiesA sound P2P system separates incompatible duties. One person should not normally be able to create a supplier, approve a requisition, confirm receipt and release payment without independent review. Typical separation is as follows: | Activity | Responsible role |
|---|
| Define operational need | User department | | Confirm budget | Budget holder or finance | | Select source and issue order | Procurement | | Confirm receipt or service completion | Receiving department or contract manager | | Validate invoice and pay | Accounts payable | | Monitor supplier performance | Procurement and user department |
Emergency procurement may require modified procedures, but the reason, authority and post-event review should be documented. 3. Spend Analysis and Procurement PlanningSpend analysis is the systematic examination of purchasing data by supplier, category, location, department, item, quantity, price and time. It helps an organisation understand where money is being spent and where improvement opportunities exist. A practical spend-analysis process is: - Extract data from enterprise resource planning, finance and purchasing systems.
- Clean supplier names, item descriptions, units of measure and currencies.
- Classify transactions into meaningful categories.
- Examine total spend, supplier concentration, price variation, maverick spend and contract coverage.
- Prioritise categories according to value, risk, complexity and improvement potential.
- Develop sourcing and supplier-management actions.
3.1 Useful spend measuresTotal spend for a category can be represented as: S = ∑(qᵢ × pᵢ) where S is total spend in monetary units, qᵢ is the quantity of item or transaction i, and pᵢ is its unit price. The calculation assumes that quantities and prices are expressed in compatible units and currencies. The percentage of spend with a supplier is: Supplier share = (Supplier spend ÷ Category spend) × 100 These measures can reveal fragmented buying, dependence on one supplier, inconsistent prices and purchases made outside approved contracts. Spend analysis is only as reliable as the data. Missing purchase orders, inconsistent descriptions and unrecorded credit notes can lead to incorrect conclusions. 3.2 The Pareto principle and category prioritisationA Pareto analysis ranks categories or suppliers from highest to lowest spend and calculates cumulative spend. Frequently, a relatively small number of categories account for a large share of expenditure, although the exact pattern must be established from actual data rather than assumed. High-spend categories deserve attention, but low-spend categories may still be critical if their failure stops production or creates safety risk. The Kraljic purchasing portfolio model is a useful conceptual framework. It considers two dimensions: profit impact and supply risk. Categories may be viewed as: - Routine: low impact and low risk; simplify transactions and use catalogues.
- Leverage: high impact and low risk; use competition and volume aggregation.
- Bottleneck: low financial impact but high supply risk; secure continuity and alternatives.
- Strategic: high impact and high risk; develop collaborative relationships, executive oversight and contingency plans.
The model supports discussion; it does not replace professional judgement or detailed risk assessment. 4. Make-or-Buy AnalysisA make-or-buy decision compares internal production with external purchasing. It should consider relevant costs, capacity, quality, risk, technology, intellectual property, flexibility, lead time and strategic capability. For a simple decision, the relevant cost of making a quantity is: Cₘ = Fₘ + (vₘ × Q) The relevant cost of buying is: Cᵦ = Fᵦ + (vᵦ × Q) where Cₘ and Cᵦ are total relevant make and buy costs, Fₘ and Fᵦ are avoidable fixed or setup costs, vₘ and vᵦ are relevant variable costs per unit, and Q is the required quantity. Costs must relate to the same period, quantity, currency and quality specification. Sunk costs are excluded unless they change as a result of the decision. Opportunity cost of capacity must be included where internal resources could be used for another profitable activity. The indifference quantity, when the two alternatives have different fixed and variable costs, is: Q* = (Fᵦ − Fₘ) ÷ (vₘ − vᵦ) This equation applies only when the denominator is non-zero and the cost relationships remain valid over the relevant volume range. It is a cost comparison, not a complete strategic decision. Illustrative example. A firm can make 10,000 units with avoidable fixed cost of $30,000 and variable cost of $8 per unit. A supplier charges $11 per unit and requires no avoidable fixed cost. Therefore: Make: Cₘ = $30,000 + ($8 × 10,000) = $110,000 Buy: Cᵦ = $11 × 10,000 = $110,000 At 10,000 units the relevant costs are equal. At quantities above the indifference point, making becomes less costly under these assumptions; below it, buying may be less costly. The final decision should also consider supplier reliability, internal capacity, quality capability, confidentiality, resilience and long-term strategy. 5. Sourcing and Market ResearchSourcing identifies potential suppliers and determines how the market should be approached. The process begins with a clear requirement. A poor specification creates ambiguous bids, disputes and poor supplier performance. A good specification states, where relevant: - function and performance requirements;
- technical standards, dimensions and tolerances;
- quantities, delivery locations and required dates;
- quality-assurance and inspection requirements;
- packaging, labelling and documentation;
- service levels, support and warranty;
- environmental, labour and ethical expectations;
- acceptance criteria and consequences of non-conformance.
A specification may be performance-based, describing the required outcome, or prescriptive, describing exactly how the supplier must provide it. Performance specifications can encourage innovation, while prescriptive specifications may be appropriate where safety, interoperability or regulatory compliance requires precise control. 5.1 Sourcing methods- Request for information (RFI): gathers market and capability information before a formal solicitation.
- Request for quotation (RFQ): suitable when requirements are clear and price comparison is meaningful.
- Request for proposal (RFP): invites a technical and commercial solution where suppliers may propose different approaches.
- Invitation to tender: requests formal offers under stated rules and evaluation criteria.
- Single-source or negotiated procurement: may be justified by compatibility, intellectual property, emergency, legal exclusivity or lack of credible alternatives; the justification must be documented.
Prequalification may assess financial capacity, technical capability, references, certifications, safety performance and ethical conduct before suppliers receive the full tender. 5.2 Tender evaluationTender documents should state the timetable, submission rules, specification, contract terms, evaluation criteria, weighting, clarification procedure and award method. Criteria should be set before bids are opened. Undisclosed criteria undermine fairness. A weighted scoring model can support evaluation. If criterion j has weight wⱼ and a supplier receives score sⱼ, the weighted total is: T = ∑(wⱼ × sⱼ) Weights should sum to 1, or to 100% if percentage weights are used. Scores must use a defined scale, such as 0 to 5, and evaluators should record evidence. A high score cannot compensate for a mandatory failure such as non-compliance with a safety requirement unless the tender rules explicitly allow such treatment. Example. Suppose cost has a weight of 40%, quality 35% and delivery 25%. Supplier A scores 4, 5 and 3 respectively on a five-point scale. Its weighted score is: T = (0.40 × 4) + (0.35 × 5) + (0.25 × 3) = 1.60 + 1.75 + 0.75 = 4.10 The score is meaningful only when the scoring definitions and evidence are consistent across suppliers. 6. Total Cost of OwnershipThe purchase price is only one part of cost. Total cost of ownership (TCO) considers costs incurred throughout acquisition, use and disposal. A simplified model is: TCO = P + Cₐ + Cₜ + Cᵢ + Cₘ + Cd − R where P is purchase price, Cₐ acquisition and administration cost, Cₜ transport and duties, Cᵢ installation and commissioning, Cₘ operating and maintenance cost, Cd disposal cost, and R residual or recovery value. All terms must be measured over the same life-cycle period and in comparable monetary terms. If costs occur at substantially different times, discounting may be required for a capital-investment analysis. TCO may include energy use, consumables, downtime, training, spare parts, inspection, warranty administration, failure costs and environmental compliance. It is especially valuable for equipment, vehicles, information systems and high-maintenance products. 7. Negotiation and Contract AdministrationNegotiation is a structured process for reaching an acceptable agreement while protecting organisational interests and maintaining a workable relationship. Preparation is more important than improvisation. Before negotiation, the buyer should establish: - objectives and minimum acceptable outcomes;
- priorities and tradeable issues;
- market information and supplier alternatives;
- cost and risk analysis;
- authority limits and approval requirements;
- questions about capacity, quality and continuity;
- a planned agenda and evidence requirements.
Negotiation should address the whole commercial package, not only unit price. Relevant issues include lead time, minimum order quantity, payment terms, price-adjustment mechanisms, warranties, service levels, data ownership, confidentiality, liability, insurance, intellectual property, change control, termination, dispute resolution and exit assistance. 7.1 Contract essentialsA contract should clearly identify the parties, scope, specifications, price, quantity, delivery terms, acceptance process, payment conditions, performance obligations, remedies, term, renewal, termination and governing law. It should also identify who may approve changes and how changes are documented. A service-level agreement may define measurable standards such as response time, resolution time, availability, accuracy or delivery reliability. A service credit or other remedy may apply when performance falls below the agreed level, but remedies should be enforceable, proportionate and consistent with applicable law. Contract administration ensures that the agreement becomes operational reality. The contract manager monitors deliverables, milestones, invoices, variations, risks, claims, insurance, compliance and records. Procurement should not assume that signing the contract completes its work. 8. Supplier Evaluation and Relationship ManagementSupplier evaluation should combine objective performance evidence with forward-looking risk assessment. Common dimensions include: | Dimension | Possible indicators |
|---|
| Cost | Price variance, TCO, cost reduction, invoice accuracy | | Quality | Defect rate, returns, corrective-action closure, audit findings | | Delivery | On-time-in-full delivery, lead-time adherence, fill rate | | Service | Responsiveness, technical support, communication | | Risk | Financial health, capacity, cyber exposure, geographic concentration | | Sustainability and ethics | Labour standards, emissions, waste, anti-bribery controls | | Innovation | Improvement proposals, process capability, new solutions |
A delivery reliability measure can be defined as: OTIF = (Orders delivered on time and in full ÷ Total orders) × 100 The organisation must define “on time,” “in full,” the measurement period and treatment of approved changes. For example, if 92 of 100 orders meet both conditions, OTIF is 92%. A defect rate may be expressed as: Defect rate = (Defective units ÷ Total units received) × 100 The numerator and denominator must use the same inspection basis. Sampling plans can produce estimates rather than a complete count of all defects. Supplier scorecards should show targets, actual results, trend, responsible owner and corrective action. Scores should not hide serious failures: a supplier with an attractive price but unacceptable safety or ethical performance may require suspension rather than an average score. 8.1 Supplier segmentation and developmentNot every supplier needs the same relationship. Routine suppliers may be managed through standard contracts and automated ordering. Strategic suppliers may require joint planning, executive reviews, shared forecasts, improvement projects and business-continuity planning. Supplier development can include technical assistance, process audits, training, joint root-cause analysis and collaborative innovation. Supplier concentration is not automatically undesirable. Multiple suppliers can reduce dependence but may increase qualification, transaction and quality costs. The appropriate structure depends on demand criticality, switching cost, market capacity, geographic risk and the organisation’s resilience objectives. 9. Risk, Ethics and GovernanceProcurement risks include fraud, bribery, conflicts of interest, collusion, bid leakage, counterfeit products, poor labour conditions, cyberattack, supplier insolvency, sanctions exposure, environmental harm and supply interruption. Important controls include: - conflict-of-interest declarations;
- supplier due diligence and beneficial-ownership checks;
- competitive bidding and documented exceptions;
- controlled access to tender information;
- approval thresholds and delegated authority;
- segregation of duties;
- audit trails and record retention;
- contract clauses on anti-bribery, labour standards, data protection and audit rights;
- whistleblowing and investigation procedures;
- continuity plans, alternate sources and safety stock where justified.
Ethical procurement extends beyond compliance. Buyers should consider whether specifications unfairly exclude capable suppliers, whether payment terms impose unreasonable pressure on small firms, and whether purchasing decisions shift environmental or labour harm to less visible parts of the supply chain. Sustainable procurement may evaluate life-cycle emissions, recycled content, energy efficiency, repairability, responsible minerals and worker welfare. 10. Technology and Contemporary PracticeProcurement technologies include e-catalogues, electronic tendering, contract-lifecycle management, supplier portals, automated approval workflows, spend analytics and invoice-matching systems. These tools can improve visibility, speed and control, but they do not correct poor master data or badly designed processes. Artificial intelligence can assist with spend classification, anomaly detection, demand forecasting, contract searching and supplier-risk monitoring. Human oversight remains necessary because automated systems may reproduce biased classifications, miss context, use incomplete information or generate unsupported recommendations. Confidential commercial information must be protected, and users should understand how important recommendations were produced. Contemporary procurement is also shaped by supply disruption, geopolitical risk, climate events, cyber risk, nearshoring, circular-economy principles and increased scrutiny of human rights in supply chains. Resilience does not mean holding unlimited inventory or using many suppliers indiscriminately. It means understanding vulnerabilities and choosing proportionate responses such as dual sourcing, capacity reservations, strategic inventory, substitution design, supplier collaboration and scenario planning. 11. Illustrative Case: Meridian Foods Packaging ProcurementBackgroundMeridian Foods, a fictional medium-sized food manufacturer, purchases printed cartons from three suppliers. Annual spend is $1.2 million. Production has experienced late deliveries, inconsistent print quality and emergency freight charges. ProblemThe purchasing department selected suppliers primarily on quoted unit price. No common specification existed for colour tolerance, board strength, delivery windows or corrective action. Spend data also showed that departments placed small orders outside the main contracts. AnalysisThe procurement team first cleaned twelve months of purchase data. It found that the largest supplier represented 72% of spend, although two qualified alternatives existed. The apparent cheapest supplier had higher defect rates and frequently delivered late. When emergency freight and line stoppage costs were included, its TCO was not lowest. The team created a specification covering board grade, dimensions, print approval, food-contact compliance, packaging, delivery schedule and rejection procedures. It issued an RFP to three qualified suppliers. Evaluation weights were cost 35%, quality 25%, delivery 20%, risk and continuity 10%, and sustainability 10%. Approach and solutionMeridian negotiated a two-year framework agreement with a primary supplier and a qualified secondary supplier. The contract included forecast-sharing, agreed capacity, an OTIF target, defect limits, price-review rules tied to documented material changes, audit rights and a corrective-action process. A catalogue and approval workflow reduced off-contract buying. Monthly scorecards were reviewed by procurement, production and quality assurance. OutcomeAfter six months, emergency freight declined, quality complaints fell and delivery performance improved. The organisation did not choose the lowest quoted unit price; it selected the strongest overall value and reduced excessive dependence on one source. Learning points- Spend visibility is a prerequisite for category strategy.
- Specification quality affects both competition and performance.
- TCO can produce a different decision from unit-price comparison.
- Supplier segmentation and a secondary source can improve resilience.
- Contract administration and cross-functional review are necessary after award.
12. Challenges and LimitationsProcurement models simplify reality. Weighted scores can create false precision when criteria are subjective. Cost models may omit disruption, learning or reputational effects. Supplier audits provide only a point-in-time view and may not reveal conditions at lower-tier suppliers. Competition may be impossible in a concentrated market. Dual sourcing may reduce dependence but increase cost and reduce volume leverage. Automation improves processing but can amplify inaccurate data and poorly designed rules. Managers should therefore combine quantitative analysis with professional judgement, operational consultation, supplier evidence and periodic review. Decisions should be proportionate, documented and revisable when assumptions change. Chapter SummaryProcurement integrates requirement definition, sourcing, purchasing, contracting, receipt, payment and supplier management. The procure-to-pay cycle provides transaction control through requisitions, purchase orders, receipts, invoices and payment, supported by segregation of duties and three-way matching. Spend analysis identifies value, fragmentation and risk, while portfolio thinking helps distinguish routine, leverage, bottleneck and strategic categories. Make-or-buy analysis compares relevant internal and external costs but must also consider capacity, quality, flexibility, risk and strategic capability. Sourcing requires clear specifications, appropriate market methods, fair tendering and evidence-based evaluation. Total cost of ownership broadens analysis beyond quoted price. Negotiation and contract administration establish and monitor the commercial conditions under which value is delivered. Supplier management uses scorecards covering cost, quality, delivery, service, risk, sustainability and ethics. Governance controls address fraud, conflicts, bribery, data protection and continuity. Technology and AI can improve visibility and analysis but require good data, human oversight and responsible governance. Effective procurement is therefore both a control process and a strategic supply-chain capability. Key TermsProcurement: The end-to-end process of obtaining goods, services or works and managing their supply. Purchasing: The transactional activity of ordering and paying for goods or services. Procure-to-pay: The process from internal requisition through ordering, receipt, invoice verification and payment. Purchase requisition: An internal request to obtain a good or service. Purchase order: An authorised commercial instruction issued to a supplier. Three-way match: Comparison of purchase order, receipt record and invoice before payment. Spend analysis: Examination and classification of purchasing expenditure. Make-or-buy analysis: Comparison of internal production and external acquisition alternatives. Total cost of ownership: Life-cycle cost of acquiring, using and disposing of an item or service. Request for quotation: A solicitation used mainly for clearly specified requirements and price comparison. Request for proposal: A solicitation inviting technical and commercial solutions. Tender: A formal supplier offer submitted under stated procurement rules. Weighted scoring: Evaluation method that combines criterion scores with assigned weights. Supplier due diligence: Investigation of supplier capability, ownership, financial condition and compliance. Supplier scorecard: A structured record of supplier performance against agreed measures. OTIF: On-time-in-full delivery performance measure. Contract administration: Ongoing management of obligations, performance, changes and records after contract award. Segregation of duties: Division of responsibilities to reduce error, fraud and unauthorised action. Supplier development: Activities that improve a supplier’s capability or performance. Maverick spend: Purchasing outside approved suppliers, contracts or processes. Review QuestionsShort Answer Questions- Distinguish procurement from purchasing.
- What documents are compared in a three-way match?
- State two purposes of spend analysis.
- Define total cost of ownership.
- What does OTIF measure?
Long Answer Questions- Explain the stages of the procure-to-pay cycle and the controls required at each major stage.
- Discuss how the Kraljic portfolio model can support procurement strategy.
- Explain the difference between an RFQ and an RFP, including when each is appropriate.
- Describe the main provisions that should be addressed in a supply contract.
- Discuss how ethical, sustainability and governance considerations affect supplier selection.
Analytical / Application Questions- A supplier offers a low unit price but has frequent defects and late deliveries. Explain how you would compare the supplier with a higher-priced alternative using TCO and supplier-performance evidence.
- An organisation relies on one supplier for a production-critical component. Analyse the risks and recommend a proportionate continuity strategy.
- Design a weighted supplier-evaluation model for a logistics service provider. Select criteria, assign justifiable weights and explain how you would prevent the model from concealing a critical compliance failure.
Multiple Choice Questions with AnswersQuestion 1Which document normally initiates an internal request to purchase goods or services? A. Purchase requisition B. Supplier invoice C. Goods-received note D. Credit note Correct Answer: A. Purchase requisition Question 2What is the primary purpose of a three-way match? A. To compare supplier market shares B. To verify that the order, receipt and invoice agree before payment C. To calculate a supplier’s carbon emissions D. To select a negotiation team Correct Answer: B. To verify that the order, receipt and invoice agree before payment Question 3A category with high profit impact and high supply risk is classified in the Kraljic model as: A. Routine B. Leverage C. Bottleneck D. Strategic Correct Answer: D. Strategic Question 4A firm has make costs of $30,000 fixed plus $8 per unit and buy costs of $11 per unit with no fixed cost. At 10,000 units, what is the relevant-cost result? A. Making costs $80,000 less than buying B. Buying costs $30,000 less than making C. The two alternatives cost the same D. Making costs $11,000 more than buying Correct Answer: C. The two alternatives cost the same Question 5Which solicitation is generally most suitable when the requirement is clear and comparable prices are required? A. Request for information B. Request for quotation C. Request for proposal D. Supplier development plan Correct Answer: B. Request for quotation Question 6If cost has a weight of 40% and a supplier scores 4 out of 5, what is its weighted contribution to the total score? A. 0.40 B. 1.60 C. 2.00 D. 4.40 Correct Answer: B. 1.60 Question 7Which cost is normally included in total cost of ownership? A. Only the supplier’s quoted unit price B. Only the organisation’s historical sunk cost C. Acquisition, operating, maintenance and disposal costs D. Only the cost of issuing a purchase order Correct Answer: C. Acquisition, operating, maintenance and disposal costs Question 8If 92 of 100 orders are delivered on time and in full, the OTIF performance is: A. 8% B. 50% C. 92% D. 108% Correct Answer: C. 92% Question 9Which control most directly reduces the risk that one person can create a supplier and release payment without review? A. Single sourcing B. Segregation of duties C. Longer payment terms D. Higher order quantities Correct Answer: B. Segregation of duties Question 10Why should a mandatory safety requirement normally be treated separately from a weighted score? A. Safety requirements are always more expensive B. A high score should not compensate for failure of a fundamental compliance condition C. Weighted scoring cannot include quality criteria D. Safety is unrelated to procurement Correct Answer: B. A high score should not compensate for failure of a fundamental compliance condition
|