Supplier Evaluation, Selection and QualificationIntroduction and ContextSupplier evaluation is the disciplined process of determining whether a potential or existing supplier can consistently satisfy an organisation’s requirements for quality, delivery, cost, technology, compliance, resilience and responsible business conduct. Supplier selection is the decision to appoint one or more suppliers from the evaluated set. Supplier qualification is the evidence-based confirmation that the selected supplier, process and product are capable of meeting specified requirements under actual or representative operating conditions. These activities are strategically important because supplier performance is often embedded in the customer’s product and service quality. A supplier may provide raw material, a critical component, software, calibration, outsourced processing, logistics or a contract-manufacturing service. In each case, inadequate selection can create latent defects, regulatory exposure, production interruption and reputational damage. Conversely, a rigorous qualification process reduces uncertainty before volume commitment and establishes the foundation for continual improvement. The central managerial challenge is to avoid treating supplier choice as a price quotation exercise. A low purchase price may be outweighed by inspection, rework, warranty, disruption, expedited freight and failure costs. Supplier decisions therefore require a cross-functional, risk-based and auditable method. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Distinguish supplier screening, evaluation, selection, approval and qualification.
- Design evidence-based due diligence and supplier capability assessments.
- Construct and use weighted scorecards and multicriteria decision models.
- Plan sample approval, trial production and process qualification.
- Establish cross-functional governance, escalation rules and decision records.
- Critically evaluate limitations, ethical risks and emerging digital practices.
1. A Risk-Based Architecture for Supplier DecisionsA robust supplier decision normally proceeds through linked gates: - Requirement definition: Translate customer, regulatory, technical and operational needs into measurable supplier requirements.
- Market screening: Identify suppliers that meet essential eligibility conditions.
- Due diligence: Verify ownership, financial health, legal standing, ethics, information security, capacity and operational history.
- Capability evaluation: Examine the supplier’s management system, process controls, people, equipment, measurement systems and improvement capability.
- Commercial and multicriteria assessment: Compare feasible suppliers using transparent criteria and risk-adjusted economics.
- Sample approval: Confirm that submitted samples meet specifications and intended-use requirements.
- Trial production: Test the supplier’s process under representative volume, tooling, materials and controls.
- Qualification and approval: Review objective evidence, close nonconformities and authorise production use with defined conditions.
- Post-qualification monitoring: Verify that performance remains stable and trigger reassessment when risk changes.
These gates should not be confused. A sample can conform while the supplier’s process is incapable of producing consistently. Similarly, an excellent audit cannot compensate for an unsuitable product design or an unverified measurement system. Qualification is therefore a body of converging evidence rather than a single certificate or visit. Critical-to-quality requirementsBefore contacting suppliers, the buying organisation should classify requirements. Typical categories are: - Critical: Failure could cause injury, legal noncompliance, major system failure or loss of essential function.
- Significant: Failure could cause customer dissatisfaction, rework, functional degradation or material disruption.
- Routine: Requirements that affect convenience, appearance or administrative performance but have lower direct risk.
Critical requirements require stronger evidence, such as validated processes, traceability, special-process approval, measurement-system evidence, change control and documented contingency arrangements. The classification should be based on consequence and likelihood, not on purchasing value alone. 2. Supplier Screening and Evidence-Based Due DiligenceScreening is a rapid elimination stage. It should use objective knockout criteria before detailed evaluation consumes time. Examples include inability to meet a mandatory regulation, absence of required technology, unacceptable conflict of interest, inadequate capacity, sanctions exposure, refusal to permit reasonable verification, or inability to provide required traceability. Due diligence extends beyond the supplier’s marketing claims. Evidence may include: | Area | Evidence to request or verify | Typical warning sign |
|---|
| Legal and ethical standing | Registration, ownership, sanctions screening, anti-bribery policy | Opaque ownership or unexplained intermediaries | | Financial resilience | Audited accounts, credit information, liquidity indicators | Persistent losses or dependence on one customer | | Quality capability | Certifications, audit results, defect history, corrective-action records | Certificates without process evidence | | Technical capability | Equipment list, process maps, engineering competence, validation records | Reliance on unsupported verbal assurance | | Capacity and continuity | Capacity model, maintenance plan, disaster recovery, alternate sources | Capacity based only on theoretical machine hours | | Supply-chain transparency | Sub-tier mapping, origin records, traceability | Inability to identify critical sub-suppliers | | Information security | Access controls, incident history, recovery arrangements | Uncontrolled sharing of customer data | | Labour and environmental conduct | Legal compliance records, worker protections, emissions and waste data | Retaliation against workers or unexplained incidents |
Evidence should be proportionate to risk. A low-risk office-supply vendor does not require the same investigation as a supplier of a safety-critical component. However, proportionality is not an excuse for ignoring basic legality, safety or integrity. Screening questions and verificationA supplier questionnaire is useful for consistency but is not proof. Responses should be tested through certificates, records, interviews, site observation, independent databases, reference checks and, where justified, financial or technical audits. Evidence should be dated, attributable and linked to a specific requirement. An effective due-diligence record identifies: the requirement, evidence reviewed, reviewer, date, conclusion, residual risk and required action. This creates an audit trail and makes later reassessment possible. 3. Weighted Scorecards and Multicriteria Decision-MakingSupplier selection typically involves conflicting criteria. Cost, quality, delivery, innovation, resilience and sustainability may not be maximised by the same supplier. A weighted scorecard makes the trade-offs visible and reduces arbitrary judgement. Let supplier i receive a normalised score sij from 0 to 100 on criterion j. Let wj be the weight of criterion j, where weights are non-negative and sum to 1. The weighted total score is: Si = ∑j=1m wj sij, with ∑j=1m wj = 1 Here, Si is the overall score for supplier i, m is the number of criteria, wj is dimensionless, and sij is the supplier’s score on criterion j. The formula assumes that scores are comparable, weights reflect decision priorities, and criteria are sufficiently independent to avoid double counting. For example, suppose four criteria have the following weights: quality 0.35, delivery 0.25, total cost 0.20 and resilience 0.20. Supplier A scores 90, 80, 70 and 60 respectively. Then: SA = (0.35 × 90) + (0.25 × 80) + (0.20 × 70) + (0.20 × 60) = 77.5 The result is 77.5 out of 100. It is not a probability, percentage of conformity or guarantee of future performance. It is a decision aid. Normalising different types of dataRaw data may have different units. A delivery measure may be days, cost may be currency, and quality may be defects per million opportunities. They must be converted to a common scale before aggregation. One possible benefit criterion is: sij = 100 × (xij − xj,min) ÷ (xj,max − xj,min) For a cost or loss criterion, where lower is better: sij = 100 × (xj,max − xij) ÷ (xj,max − xj,min) In these equations, xij is the observed value for supplier i, xj,min and xj,max are agreed reference bounds, and the resulting score ranges from 0 to 100 when the observation lies within those bounds. The bounds must be defined in advance; using only the current suppliers’ minimum and maximum can make the score unstable when a new supplier is added. If the bounds are equal, the criterion cannot be normalised this way and must be redesigned or treated qualitatively. Thresholds and veto criteriaA weighted total can conceal a dangerous weakness. A supplier scoring highly on cost but failing a safety requirement should not remain eligible. Therefore, the scorecard should include minimum thresholds and veto conditions. For example: - quality score must be at least 75;
- no unresolved critical legal or safety nonconformity;
- validated special process required for a safety-critical operation;
- financial and continuity risk must be acceptable;
- total score must exceed the approval threshold.
A supplier may be ranked first yet rejected if it fails a mandatory condition. This is a constrained decision, not merely a ranking exercise. Sensitivity and robustness analysisWeights involve judgement. The team should test whether the decision changes when reasonable weights or scores are varied. If Supplier A wins only when cost has a 35% weight rather than 20%, the decision is sensitive and should receive management review. Sensitivity analysis does not remove judgement; it reveals where judgement matters. A further safeguard is to require independent scoring by quality, engineering, operations, procurement, finance and, where relevant, legal or sustainability specialists. Differences should be discussed using evidence rather than averaged automatically. 4. Capability Assessment and Audit DesignCapability assessment asks whether the supplier can produce conforming output repeatedly, not merely whether it possesses equipment. A useful assessment examines five connected elements: - Process definition: documented specifications, process maps, work instructions and control plans.
- Process control: prevention controls, parameter monitoring, reaction plans and error-proofing.
- Measurement credibility: calibrated instruments, suitable methods, competent inspectors and traceable records.
- People and infrastructure: skills, maintenance, utilities, software, tooling and supervision.
- Learning system: nonconformity management, root-cause analysis, corrective action and continual improvement.
The audit should be risk-based. It should trace a real or representative order from contract review through purchasing, receiving, production, inspection, release, packaging and shipment. This “process audit” often reveals weaknesses that a document-only audit misses. Measurement-system credibilityA supplier’s capability claim is only as credible as its measurement system. The assessor should verify that the measurement method is suitable for the tolerance, resolution and environment. For variable measurements, a measurement-system study may estimate repeatability and reproducibility. The precise method depends on the industry and governing standard; the important principle is that observed process variation should not be confused with measurement error. Process capability indicesWhen data are approximately stable and reasonably modelled by a normal distribution, process capability may be summarised using specification limits and process variation. For a two-sided specification: Cp = (USL − LSL) ÷ (6σ) Cpk = min[(USL − μ) ÷ (3σ), (μ − LSL) ÷ (3σ)] Here, USL and LSL are upper and lower specification limits in the same units as the measured characteristic, μ is the process mean, and σ is the within-process standard deviation. Cp reflects potential capability if centred; Cpk also reflects off-centre performance. These indices are meaningful only when the process is statistically stable, the measurement system is adequate, the data represent the intended process and the distributional assumptions are reasonable. They are not defect rates and should not be reported without context. For a process with USL = 10.10 mm, LSL = 9.90 mm, μ = 10.03 mm and σ = 0.02 mm: Cp = (10.10 − 9.90) ÷ (6 × 0.02) = 1.67 Cpk = min[(10.10 − 10.03) ÷ (3 × 0.02), (10.03 − 9.90) ÷ (3 × 0.02)] = min(1.17, 2.17) = 1.17 The process has reasonable spread relative to the specification, but its mean is closer to the upper limit. The appropriate response is not to celebrate the Cp value; it is to investigate centring and confirm stability. Acceptance thresholds must be defined by the organisation, customer and sector requirements rather than assumed universally. 5. Sample Approval, Trial Production and QualificationSample approvalSample approval verifies design intent and initial conformity. The approval package should identify revision status, material or formulation, dimensions, special characteristics, inspection results, deviations and test conditions. Samples should be made using intended production tooling, materials and process where feasible. A prototype made by an engineering laboratory may demonstrate design feasibility but may not represent production capability. Approval should distinguish: - Conformance: the sample meets specified requirements.
- Fitness for use: the sample performs adequately in the intended application.
- Process evidence: the supplier can repeat the result under production conditions.
A conditional approval may be appropriate for a controlled, low-risk gap, but it must specify the limitation, owner, due date, containment and expiry. Uncontrolled verbal concessions create ambiguity and weaken traceability. Trial productionTrial production is a planned experiment under representative conditions. It should define quantity, equipment, tooling, operators, shift pattern, material lot, inspection plan, packaging, traceability and acceptance criteria. The trial should include normal production pressures, not an unusually hand-selected demonstration run. The team should evaluate first-pass yield, downtime, changeovers, scrap, rework, dimensional stability, test results, delivery discipline, documentation and reaction to abnormalities. A trial is not necessarily a statistical proof of long-term capability; it is evidence that must be combined with process knowledge and ongoing monitoring. Qualification decisionA qualification dossier normally contains: - approved specification and contract requirements;
- due-diligence outcome and risk assessment;
- audit report and closure of findings;
- sample and test results;
- measurement-system evidence where relevant;
- trial-production report;
- capacity and continuity assessment;
- control plan, inspection and traceability arrangements;
- agreed change-notification process;
- open risks, conditions and approval expiry, if any.
The approval authority should be explicit. Procurement may negotiate commercial terms, but quality or engineering should not be bypassed when technical or safety requirements are involved. For critical suppliers, approval may require a cross-functional committee or designated executive authority. 6. Cross-Functional GovernanceSupplier qualification is vulnerable to functional bias. Procurement may prioritise price and continuity of supply; engineering may prioritise technical performance; quality may prioritise risk reduction; operations may prioritise capacity; finance may prioritise working capital. Governance does not eliminate these legitimate interests; it makes them visible and resolves conflicts against agreed requirements. A practical responsibility structure is: | Activity | Accountable role | Core contributors |
|---|
| Define technical requirements | Engineering or quality | Operations, customer, regulatory affairs | | Conduct due diligence | Procurement | Finance, legal, compliance, security | | Audit process capability | Quality | Engineering, operations, supplier personnel | | Approve samples and tests | Engineering/quality | Laboratory, production, customer where required | | Approve commercial award | Procurement/business owner | Finance, quality, legal | | Authorise production release | Designated approval authority | Cross-functional review team | | Monitor after approval | Supplier quality manager | Procurement, operations, engineering |
Decision records should state who recommended, who approved, what evidence was used, which assumptions remain, and how risks will be monitored. This is particularly important when schedule pressure leads to conditional approval. 7. Total Cost, Risk and Commercial EvaluationPurchase price is only one component of economic value. A simplified total-cost model may be written as: TCO = P + Cq + Cd + Ci + Cr + Cw + Cs Here, TCO is total cost of ownership over a defined period; P is purchase and logistics cost; Cq is quality-related cost such as inspection, rework and returns; Cd is disruption or delay cost; Ci is implementation and qualification cost; Cr is risk-related expected cost; Cw is warranty or field-failure cost; and Cs is switching, administration or support cost. The terms must use a common currency, time horizon and boundary. Some terms are uncertain and should be expressed as ranges or scenarios rather than false precision. Expected risk cost can be represented, cautiously, as: E(Cr) = ∑k=1n pk Lk where pk is the estimated probability of risk event k, Lk is its financial loss, and n is the number of defined events. This assumes that probabilities and losses are sufficiently defined and that the decision-maker accepts an expected-value representation. Rare catastrophic events may require a separate risk constraint because a low expected value can conceal unacceptable consequences. 8. Case Study: Qualification of a Safety-Critical Valve SupplierThe following is an illustrative case designed for learning purposes. BackgroundA medical-equipment manufacturer needed a new supplier for a precision valve used in a gas-delivery subsystem. The incumbent supplier faced capacity constraints. The valve had tight dimensional requirements, a leakage test, material traceability and a documented change-control obligation. ProblemThree candidates submitted competitive quotations. Supplier X offered the lowest unit price but had limited evidence of process capability. Supplier Y had strong quality records and an established measurement laboratory but a higher price. Supplier Z had excellent capacity and automation but relied on an unassessed sub-tier coating supplier. AnalysisThe team defined knockout conditions: compliant materials, validated leakage testing, traceability to material lot, change notification and no unresolved critical legal or safety issue. All three passed initial legal screening, but Supplier X could not demonstrate a stable leakage-test method, so it was placed on hold rather than ranked as an ordinary candidate. For Y and Z, the team used quality (0.35), delivery (0.20), total cost (0.20), technical capability (0.15) and resilience (0.10). Scores were assigned from verified evidence, not quotations alone: | Supplier | Quality | Delivery | Cost | Technical | Resilience | Weighted total |
|---|
| Y | 92 | 82 | 68 | 90 | 78 | 84.2 | | Z | 84 | 91 | 86 | 80 | 70 | 83.8 |
For Supplier Y, the total is 0.35×92 + 0.20×82 + 0.20×68 + 0.15×90 + 0.10×78 = 84.2. Supplier Z is close, so the team performed sensitivity analysis. When resilience was increased to 0.20 and cost reduced to 0.10, Z became competitive. However, the unassessed coating sub-tier remained a mandatory risk issue, not something that could be traded away through score weighting. Approach and solutionSupplier Y was selected conditionally. The team required a process audit, gauge study, pilot lot, 100% leakage testing during the first three production lots, and evidence that material certificates were linked to valve serial numbers. A cross-functional review approved the pilot only after the supplier corrected a calibration-record weakness and demonstrated operator competence. The pilot produced 500 valves. Dimensional results met specification, but two units failed leakage testing. Investigation found a fixture-sealing issue rather than a valve-design defect. The supplier corrected the fixture, repeated the trial and added a start-up verification. The second trial passed the agreed acceptance criteria, and production approval was issued with enhanced monitoring for three months. Outcome and learning pointsThe manufacturer paid a higher unit price but avoided selecting on price alone. The process exposed a control weakness before customer shipment, verified sub-tier traceability and converted conditional approval into full qualification. The case demonstrates that a scorecard is useful only when paired with thresholds, evidence, technical trials and governance. It also shows why the first failed trial can be valuable: qualification is a learning process, not merely a ceremonial pass/fail event. 9. Challenges, Ethics and Regulatory GovernanceCommon limitationsWeighted models can create an illusion of objectivity. Scores may be subjective, data may be incomplete and criteria may overlap. Historical performance may favour incumbents and disadvantage capable new entrants. Audit evidence may describe yesterday’s conditions rather than current reality. Process capability indices may be misused with unstable or non-normal data. Finally, supplier risk can change rapidly because of geopolitical events, cyber incidents, labour disruption or sub-tier failure. Controls include documented scoring rules, independent review, sensitivity analysis, periodic reassessment, direct evidence, supplier-development opportunities and explicit treatment of uncertainty. Ethical issuesSupplier evaluation should protect confidential information, avoid discriminatory or corrupt practices and provide fair opportunity to respond to findings. Buyers should not demand unpaid development work without clear commercial terms. Auditors must declare conflicts of interest and preserve evidence integrity. Social and environmental claims should be verified proportionately rather than used as symbolic marketing criteria. Data protection is essential when supplier files contain personal, financial or technical information. Access should follow least privilege, retention periods should be defined and information should not be shared beyond legitimate purposes. Regulatory obligations vary by jurisdiction and sector; the organisation must map applicable product, safety, environmental, labour, anti-bribery and data requirements before qualification. 10. Technology and Contemporary PracticeDigital supplier portals can centralise questionnaires, certificates, audit findings, approvals and expiry alerts. Statistical dashboards can detect shifts in defect rates, delivery variation and corrective-action ageing. Artificial intelligence can assist with document classification, anomaly detection and supplier-risk monitoring, but it should not make an unreviewed approval decision for a critical supplier. Models may reproduce biased historical decisions, misunderstand incomplete evidence or generate plausible but unsupported conclusions. Good practice is to retain human accountability, document data provenance, validate automated outputs, protect confidential information and provide an override and escalation process. Technology should strengthen evidence management, not replace engineering judgement or supplier dialogue. Contemporary qualification increasingly includes resilience mapping beyond the immediate supplier: critical sub-tiers, geographic concentration, cyber dependency, climate exposure, single-source tooling and recovery time. Sustainable procurement is likewise moving from declarations toward measurable evidence on emissions, resource use, worker conditions and responsible minerals. These developments expand supplier quality from conformance of a delivered item to assurance of the entire value network. Best-Practice ChecklistBefore production approval, the organisation should be able to answer “yes” to the following: - Are requirements, critical characteristics and acceptance criteria unambiguous?
- Were mandatory legal, ethical, security and safety conditions screened first?
- Is each important score supported by dated and attributable evidence?
- Are weights, thresholds and veto criteria approved before the decision?
- Were measurement methods and process stability considered?
- Did samples represent intended materials, tooling and production methods?
- Was trial production conducted under representative conditions?
- Are open risks, concessions, owners and expiry dates documented?
- Did the appropriate cross-functional authority approve the decision?
- Are change notification, monitoring, escalation and requalification rules defined?
Chapter SummarySupplier evaluation, selection and qualification form a staged risk-control system. Screening removes suppliers that cannot meet essential conditions; due diligence tests legal, financial, ethical and operational credibility; capability assessment examines whether processes can repeatedly produce conforming output; and multicriteria decision-making makes trade-offs explicit. Weighted scorecards are useful when scores are comparable, weights are justified and mandatory thresholds prevent a high aggregate score from concealing a critical weakness. Sample approval demonstrates conformity and fitness for use, while trial production provides evidence under representative operating conditions. Qualification should be based on a documented dossier covering requirements, audits, measurement credibility, process results, continuity, traceability and change control. Cross-functional governance is essential because supplier decisions involve technical, commercial, operational and ethical consequences. Total cost and risk should be considered alongside price, and digital tools should support—not replace—human accountability. Effective supplier qualification is therefore a continuing assurance relationship rather than a one-time purchasing event. Key TermsSupplier evaluation: Systematic assessment of a supplier against defined criteria. Supplier selection: Decision to appoint a supplier from evaluated alternatives. Supplier qualification: Formal confirmation that a supplier, process and product meet specified requirements. Screening: Early elimination of suppliers that fail mandatory conditions. Due diligence: Evidence-based investigation of legal, financial, ethical and operational status. Weighted scorecard: Decision table combining criterion scores with approved weights. Veto criterion: Mandatory condition whose failure prevents approval regardless of total score. Critical-to-quality characteristic: Feature whose variation can significantly affect safety, function or compliance. Process audit: Examination of an actual or representative process and its controls. Measurement system: Instruments, methods, people and procedures used to obtain measurements. Process capability: Ability of a stable process to meet specification limits. Cₚ: Potential capability index based on specification width and process spread. Cₚₖ: Capability index incorporating process centring relative to specification limits. Sample approval: Formal review confirming that submitted samples meet requirements. Trial production: Controlled production run under representative operating conditions. Conditional approval: Permission subject to documented limitations and corrective actions. Total cost of ownership: All relevant acquisition, quality, disruption, risk and lifecycle costs. Traceability: Ability to link product, material, process and records through defined identifiers. Requalification: Reassessment required after defined changes, failures or risk shifts. Review Questions5 Short Answer Questions- Distinguish supplier screening from supplier qualification.
- Why should a scorecard include veto criteria as well as weighted criteria?
- What evidence should be examined during supplier due diligence?
- State the difference between sample approval and trial production.
- Why is measurement-system adequacy important in capability assessment?
5 Long Answer Questions- Explain how a risk-based supplier qualification architecture can be designed from requirement definition through post-qualification monitoring.
- Discuss the assumptions and limitations of weighted scorecards in supplier selection.
- Explain the meaning and appropriate use of Cₚ and Cₚₖ in supplier process assessment.
- Analyse the roles of procurement, quality, engineering, operations, finance and legal functions in supplier governance.
- Evaluate how total cost of ownership can improve decisions compared with unit-price comparison.
3 Analytical / Application Questions- Construct a supplier scorecard for a safety-critical component. Define at least five criteria, weights, minimum thresholds and two veto conditions, and justify each choice.
- A supplier has a high aggregate score but unresolved traceability failures at a critical sub-tier. Decide whether it should be approved and design an evidence-based action plan.
- Design a trial-production protocol for a new supplier, including representative conditions, measurements, acceptance criteria, records, escalation rules and requalification triggers.
Multiple Choice Questions with AnswersQuestion 1Which activity primarily verifies that a selected supplier can repeatedly meet requirements under representative production conditions? A. Market screening B. Supplier qualification C. Quotation comparison D. Initial supplier identification Correct Answer: B. Supplier qualification Question 2In a weighted scorecard, what must the criterion weights normally sum to? A. 0 B. 10 C. 100 only when scores are percentages D. 1 Correct Answer: D. 1 Question 3A supplier has scores of 90, 80, 70 and 60, with weights 0.35, 0.25, 0.20 and 0.20. What is its weighted score? A. 72.5 B. 75.0 C. 77.5 D. 80.5 Correct Answer: C. 77.5 Question 4Why is a veto criterion used in supplier selection? A. To ensure every supplier receives the same price B. To prevent a critical failure from being hidden by a high aggregate score C. To eliminate the need for supplier audits D. To replace all quantitative scoring Correct Answer: B. To prevent a critical failure from being hidden by a high aggregate score Question 5Under the stated assumptions, what does Cₚ primarily measure? A. Process centring only B. Supplier financial strength C. Potential capability based on specification width and process spread D. The percentage of delivered units inspected Correct Answer: C. Potential capability based on specification width and process spread Question 6For USL = 10.10, LSL = 9.90 and σ = 0.02, what is Cₚ? A. 0.83 B. 1.17 C. 1.67 D. 3.33 Correct Answer: C. 1.67 Question 7Which evidence most directly tests whether a supplier’s measurement results are credible? A. A marketing brochure B. A measurement-system study and calibration records C. A low quoted price D. An unsigned capacity estimate Correct Answer: B. A measurement-system study and calibration records Question 8What is the main purpose of trial production? A. To avoid defining acceptance criteria B. To test representative production conditions before routine release C. To guarantee zero defects forever D. To replace all due diligence Correct Answer: B. To test representative production conditions before routine release Question 9Which statement about Cₚₖ is correct? A. It reflects both process spread and centring relative to specification limits B. It is valid for any unstable process without qualification C. It measures only purchase price D. It is always greater than Cₚ Correct Answer: A. It reflects both process spread and centring relative to specification limits Question 10Which is an appropriate governance practice for AI-assisted supplier risk monitoring? A. Allowing the model to approve critical suppliers without review B. Ignoring data provenance because the output is automated C. Retaining human accountability and validating automated outputs D. Using only historical supplier scores without reassessment Correct Answer: C. Retaining human accountability and validating automated outputs
|