Software Project Management

Chapter 8
Risk, Uncertainty, and Issue Management

Certificate in Software Project Management
Software Project Management   •   Certificate

Risk, Uncertainty, and Issue Management

Introduction and Context

Software projects operate in conditions of incomplete information. Requirements may change, technologies may fail, suppliers may underperform, security threats may evolve, and team members may become unavailable. These conditions create the possibility that project objectives will be affected. Effective software project management therefore requires more than planning activities and monitoring progress: it requires disciplined management of risk, uncertainty, and issues.

A risk is a possible future event or condition that may affect project objectives. An issue is a problem that has already occurred and requires action. Uncertainty is the broader condition of limited knowledge about future events, their causes, or their consequences. Risk management is the organized process of identifying, analyzing, prioritizing, responding to, and monitoring risks. Issue management focuses on recording, assigning, resolving, escalating, and learning from actual problems.

Risk management does not mean attempting to eliminate every uncertainty. Such an approach would be expensive, slow, and impossible. The purpose is to make informed decisions, reduce avoidable exposure, prepare for credible threats, exploit beneficial opportunities, and ensure that decision-makers are aware of material threats to project success.

Learning Objectives

By the end of this chapter, you should be able to:

  • distinguish risk, uncertainty, issue, assumption, dependency, and constraint;
  • identify technical, operational, security, schedule, financial, vendor, and people risks;
  • analyze probability, impact, proximity, exposure, and interdependence;
  • prioritize risks using qualitative and quantitative methods;
  • select appropriate risk responses and establish contingency actions;
  • create and maintain risk and issue registers;
  • apply escalation, governance, and communication practices;
  • evaluate ethical, legal, security, and organizational implications of risk decisions.

1. Foundational Concepts

Risk, uncertainty, and issue

A risk has three essential features: it is uncertain, it may occur in the future, and its occurrence could affect one or more objectives. Risks may be negative threats or positive opportunities. For example, a new framework may create a threat because the team lacks experience, but it may also provide an opportunity to reduce development time.

Uncertainty includes situations in which the outcomes or probabilities are not known with confidence. A project team may know that a supplier delay is possible but have insufficient historical data to estimate its probability. This is sometimes called epistemic uncertainty, arising from limited knowledge. Aleatory uncertainty refers to inherent variability, such as random fluctuations in service demand. The distinction matters because better information can reduce epistemic uncertainty, whereas variability may need to be managed through buffers, tolerance limits, or flexible design.

An issue is a present condition or event. “The database migration has failed in testing” is an issue. “The database migration may fail during testing” is a risk. Confusing the two causes poor management: an issue needs an owner and immediate action, while a risk needs analysis and a planned response.

Related terms

TermMeaningExample
AssumptionA condition believed to be true for planning purposesA specialist will be available in July
ConstraintA limitation imposed on the projectThe release must use an approved cloud provider
DependencyA relationship in which one activity, team, or deliverable relies on anotherTesting depends on a stable build
TriggerA warning sign that a risk may be occurringRepeated missed supplier milestones
Risk ownerPerson accountable for monitoring and responding to a riskTechnical lead for an integration risk
Issue ownerPerson accountable for resolving an actual problemRelease manager for a failed deployment
ContingencyA prepared action taken if a defined event occursSwitch to a backup hosting region
Risk appetiteThe amount and type of risk an organization is willing to acceptModerate schedule risk but very low privacy risk
Risk toleranceThe acceptable variation around an objectiveCost may exceed the baseline by no more than 5%

Threats and opportunities

Threat responses should reduce the probability or impact of an undesirable event. Opportunity responses seek to increase the probability or benefit of a desirable event. A project manager should avoid treating all risk as negative because opportunities can materially improve value. For example, automating regression testing may require early investment but create a significant opportunity to reduce future release effort.

2. A Risk Management Framework

A practical risk process is continuous rather than a one-time workshop. It normally contains the following activities:

  1. establish context and objectives;
  2. identify risks;
  3. analyze probability, impact, and other characteristics;
  4. evaluate and prioritize risks;
  5. plan and implement responses;
  6. monitor, review, and communicate;
  7. capture lessons and close or transfer ownership when appropriate.

The process should be integrated with requirements management, scheduling, budgeting, architecture, security, procurement, quality assurance, and change control. A risk that is absent from these connected processes may remain visible in a register but unmanaged in practice.

Establishing context

Before identifying risks, the team should clarify what could be affected. Typical objectives include scope, schedule, cost, quality, security, safety, compliance, customer value, and organizational reputation. The team should also identify stakeholders, legal obligations, assumptions, constraints, and risk appetite.

Risk criteria should be agreed before prioritization. For example, a privacy breach may be considered critical regardless of its probability, while a minor documentation delay may be accepted. Criteria should specify thresholds for escalation, such as a projected cost variance above a defined amount or a risk involving regulated personal data.

Risk identification techniques

Useful techniques include:

  • Workshops and brainstorming: cross-functional participants identify threats and opportunities.
  • Prompt lists: categories such as technical, security, vendor, and people risks stimulate systematic review.
  • Assumption analysis: each important assumption is tested for uncertainty.
  • Lessons learned: previous project records reveal recurring failure patterns.
  • Checklists and taxonomies: structured categories reduce omission.
  • Expert judgment: specialists identify risks that general project participants may miss.
  • Scenario analysis: plausible future situations are explored, including extreme but credible cases.
  • Technical reviews and prototypes: experiments expose feasibility risks.
  • Threat modeling: security risks are examined through assets, threats, vulnerabilities, and controls.

Identification should describe cause, uncertain event, and effect. “Vendor risk” is too vague. A stronger statement is: “Because the external identity provider has not confirmed its interface stability, an incompatible interface change may delay integration testing and the planned release.”

3. Categories of Software Project Risk

Technical risks

Technical risks concern architecture, code, infrastructure, performance, interoperability, data migration, scalability, and technology maturity. Examples include an unproven framework, inadequate test environments, integration incompatibility, poor code quality, and underestimated performance requirements.

Responses may include a proof of concept, architectural review, automated testing, performance testing, modular design, technical spikes, or postponing irreversible decisions until more evidence is available. Technical debt should be recorded when it creates future exposure rather than treated merely as a coding concern.

Operational risks

Operational risks affect the ability to run and support the software. They include inadequate monitoring, unclear incident procedures, insufficient backup and recovery, weak deployment practices, and lack of operational training. A project can be delivered on schedule yet fail operationally if support teams cannot diagnose incidents or restore service.

Operational readiness reviews, service-level objectives, runbooks, rehearsals, and controlled pilot releases reduce these risks.

Security and privacy risks

Security risks include unauthorized access, insecure dependencies, credential exposure, ransomware, weak encryption, vulnerable interfaces, and supply-chain compromise. Privacy risks include collecting excessive personal data, retaining data too long, or processing it without a lawful basis or appropriate transparency.

Security must be treated as a project and product responsibility. Appropriate controls may include least privilege, multifactor authentication, secure coding, dependency scanning, secrets management, threat modeling, penetration testing, logging, vulnerability remediation, and incident-response planning. Privacy impact assessments may be required where processing is extensive or sensitive.

Some security risks have low probability but catastrophic impact. Consequently, a simple probability-impact score may understate their importance. Regulatory obligations, safety consequences, and organizational risk appetite may require mandatory controls regardless of an estimated score.

Schedule risks

Schedule risks arise from uncertain effort, dependencies, resource constraints, rework, approval delays, and optimistic estimates. Common warning signs include activities with no schedule reserve, excessive parallel work, unresolved requirements, and critical-path tasks assigned to scarce specialists.

Schedule risk should not be managed by merely adding arbitrary padding. Better practices include decomposing work, estimating with the people who will perform it, identifying dependencies, using prototypes to reduce uncertainty, monitoring the critical path, and maintaining realistic buffers.

Financial risks

Financial risks include inaccurate estimates, scope growth, inflation, exchange-rate changes, licensing costs, rework, and insufficient contingency reserves. Financial exposure should include both direct project cost and consequential cost, such as lost revenue, penalties, or reputational damage.

A project manager should distinguish the approved budget baseline from management reserve and contingency reserve according to organizational policy. Use of reserves should be authorized and recorded rather than hidden through unexplained budget changes.

Vendor and supply-chain risks

Third-party risks include late delivery, poor quality, insolvency, service discontinuation, non-compliance, data exposure, and dependence on a single supplier. Due diligence should examine financial stability, security practices, service levels, support arrangements, subcontractors, exit provisions, data portability, and audit rights.

Mitigations include alternative suppliers, contractual milestones, acceptance criteria, escrow arrangements, dual sourcing, interface standards, and transition plans. A contract does not eliminate operational risk; it defines responsibilities and remedies.

People risks

People risks involve skill shortages, turnover, burnout, conflict, unclear accountability, weak communication, and dependence on one individual. They should be discussed respectfully and without assigning blame. A risk register should describe project exposure, not label individuals as inherently risky.

Cross-training, documentation, succession planning, realistic workloads, psychological safety, and early conflict resolution are effective controls. Retaining a critical specialist through excessive overtime may create a new health, quality, and continuity risk.

4. Risk Analysis and Prioritization

Qualitative analysis

Qualitative analysis classifies risks using scales such as very low to very high. A probability-impact matrix combines the estimated likelihood of occurrence with the consequence if it occurs. For a simple ordinal matrix, a risk score may be represented as:

S = P × I

Here, S is a relative risk score, P is the assigned probability category, and I is the assigned impact category. The categories are ordinal ratings, such as 1 to 5, not precise measurements. Therefore, the score supports discussion and prioritization but should not be interpreted as a monetary expectation. The matrix must define what each category means and should be calibrated to the organization’s context.

ProbabilityTypical interpretation
1Rare or highly unlikely
2Unlikely
3Possible
4Likely
5Almost certain

Impact should be assessed separately for relevant objectives. A risk may have low cost impact but severe security or reputational impact. Where appropriate, the highest material impact should drive escalation rather than an average that conceals a severe consequence.

Quantitative analysis

When probability and consequences can be estimated credibly, expected monetary value can support financial decisions:

EMV = p × C

In this formula, EMV is expected monetary value, p is the probability of the event expressed as a number from 0 to 1, and C is the monetary consequence. For a threat, C is normally represented as a positive loss amount when calculating expected loss. The formula assumes that the probability estimate is meaningful, the consequence is measured consistently, and the decision-maker is using expected value appropriately. It does not predict the exact outcome of one project and should not replace judgment where outcomes are catastrophic, interdependent, or ethically unacceptable.

Worked example. A supplier delay has an estimated probability of 0.30 and would cost £20,000 in rework and delay if it occurred. Its expected loss is:

EMV = 0.30 × £20,000 = £6,000

This does not mean that the project will lose exactly £6,000. It means that £6,000 is the probability-weighted loss useful for comparing response investments. If a mitigation costing £2,500 reduces the probability to 0.10, the residual expected loss becomes £2,000. The expected reduction is £4,000, so the direct expected-value benefit is £4,000 against a £2,500 mitigation cost. Non-financial factors may still change the decision.

For multiple mutually exclusive outcomes, expected value is calculated as:

E(X) = ∑ pᵢxᵢ

Here, xᵢ is outcome i, pᵢ is its probability, and the probabilities must be non-negative and sum to 1. This method is appropriate only when the outcomes and probabilities are defined consistently. Correlated risks should not be treated as independent without justification.

Proximity, velocity, and detectability

Probability and impact are not the only useful attributes. Proximity indicates how soon a risk may occur; velocity indicates how quickly its impact would be felt; detectability indicates how easily warning signs can be observed. A high-impact risk with little warning may require preventive action even if its probability is modest.

Risk prioritization

Prioritization should consider score, legal duties, strategic importance, urgency, response cost, interdependencies, and risk appetite. A risk register should show the rationale for priority, not only a number. Risk owners should review high and escalating risks at appropriate governance levels.

5. Risk Responses and Contingency Planning

For threats, common responses are:

  • Avoid: change the plan to remove the threat, such as replacing an unproven technology.
  • Reduce or mitigate: lower probability or impact, such as building a prototype or adding automated tests.
  • Transfer or share: allocate responsibility to another party through insurance, contract, or partnership, recognizing that accountability may not be completely transferred.
  • Accept: take no proactive action beyond monitoring, usually because exposure is low or response cost is disproportionate.
  • Escalate: move the risk to a level with the authority or resources to manage it.

For opportunities, responses include exploit, enhance, share, accept, and escalate. A response should identify an action owner, due date, required resources, trigger, and expected residual exposure.

A contingency plan is activated if a risk occurs or a trigger threshold is reached. It should state who decides, what action is taken, how stakeholders are informed, and what resources are available. For example, if the primary hosting region fails, a tested failover procedure may redirect traffic to a secondary region. A plan that has never been tested may provide false confidence.

A fallback plan is a further alternative if the contingency response is ineffective. The distinction is practical: mitigation acts before an event, contingency acts when the event occurs, and fallback provides another option if the contingency fails.

6. Risk and Issue Registers

A risk register is a controlled record of identified risks. A compact but useful structure is shown below.

FieldPurpose
IdentifierProvides traceability
Date and sourceShows when and how the risk was identified
Cause-event-effect statementMakes the risk specific
CategorySupports analysis by risk type
Probability and impactRecords current assessment
Priority and rationaleExplains urgency
OwnerAssigns accountability
Preventive responseReduces likelihood or impact
Trigger and contingencyDefines action if exposure increases or occurs
Due date and statusSupports monitoring
Residual riskRecords exposure after response
LinksConnects requirements, issues, decisions, or changes

An issue register records actual problems. It commonly includes issue description, date raised, severity, impact, owner, target resolution date, corrective action, escalation status, decision authority, and closure evidence.

Registers must be maintained, not merely created for an audit. At each review, obsolete risks should be closed with a reason, new risks should be added, ratings should be updated, and issues should be linked to change requests or lessons learned. Access should be controlled because registers may contain commercially sensitive, security-sensitive, or personally sensitive information.

7. Issue Management and Escalation

Issue management begins with accurate logging and triage. The team should establish severity definitions, response targets, communication rules, and decision rights. A high-severity production outage, a minor documentation defect, and a disputed requirement should not follow identical pathways.

A practical issue workflow is:

  1. record the issue and evidence;
  2. assess impact, urgency, and affected stakeholders;
  3. assign an owner and target date;
  4. identify immediate containment;
  5. investigate root causes where appropriate;
  6. agree corrective action and required change control;
  7. escalate when authority, risk, or delay exceeds tolerance;
  8. verify resolution;
  9. close the issue and capture learning.

Root-cause analysis should avoid stopping at symptoms. Techniques such as the five whys, fault-tree analysis, and cause-and-effect diagrams can help, but they should be applied carefully. A single root cause is not always realistic; complex failures may arise from interacting technical, organizational, and process conditions.

Escalation is not failure. It is a governance mechanism. Escalate when a risk exceeds tolerance, when the owner lacks authority or resources, when a decision affects another project, when regulatory or security obligations are involved, or when resolution is overdue. Escalation should provide facts, options, consequences, and a requested decision rather than merely forwarding a complaint.

8. Applied Case: The Northstar Health Portal

The following is an illustrative fictional case.

Background

A software team is developing Northstar, an online appointment portal for a regional healthcare provider. The release must integrate with an external identity service, protect personal information, and support a high volume of appointments. The target launch is in four months.

Problem

During early integration, the identity-service vendor announces an interface change. At the same time, performance tests show slow response under peak load, and the only engineer familiar with the legacy patient database plans to leave in six weeks. These conditions threaten schedule, security, service quality, and continuity.

Analysis

The team records three risks. First, an interface change may delay integration testing. Second, insufficient performance may cause service disruption at launch. Third, loss of specialist knowledge may delay migration and increase defects. The team rates the first risk as probability 4 and impact 4 on a five-point scale, giving a relative score of 16. The performance risk is probability 3 and impact 5, giving 15. The knowledge risk is probability 4 and impact 4, also 16. The performance risk is escalated despite its similar score because its impact includes patient access and reputational harm.

The security lead also identifies a privacy concern: test data contains realistic patient information. This is treated as a high-priority issue rather than an ordinary risk because the unsafe practice is already occurring.

Approach and solution

The project manager assigns owners and introduces the following actions:

  • the vendor provides a sandbox and a versioned interface contract;
  • the team creates an adapter layer to reduce dependence on vendor-specific changes;
  • performance engineers establish measurable response-time thresholds and run tests before each major release;
  • the database specialist pairs with two team members and records migration procedures;
  • realistic but synthetic test data replaces patient data;
  • a go/no-go review is scheduled with explicit security, performance, and operational criteria;
  • a tested rollback and hosting failover procedure is prepared;
  • the vendor risk is linked to a procurement decision and a contingency supplier assessment.

The interface change occurs, but the adapter limits rework. Performance improves after query optimization and caching, although the team retains a reduced launch scope as a fallback. The specialist leaves with knowledge transfer completed. The privacy issue is closed after data removal, access review, and evidence of the new test-data process.

Outcome and learning points

The release is delayed by one week but meets the revised security and performance criteria. The case demonstrates that early escalation can protect value even when it changes the schedule. It also shows that risk responses must be specific, owned, tested, and connected to decisions. A risk register alone would not have solved the problem; action and governance were necessary.

9. Governance, Ethics, and Contemporary Practice

Risk decisions involve ethical responsibilities. Project leaders should not conceal material risks to protect a status report, manipulate probability ratings to avoid escalation, or pressure staff to accept unsafe workloads. Stakeholders need timely, comprehensible information about consequences that affect them.

Security and privacy obligations may arise from legislation, contracts, professional standards, and organizational policy. Teams should apply data minimization, appropriate access controls, retention limits, auditability, and breach-response procedures. Where software affects health, finance, employment, safety, or vulnerable users, risk analysis should consider unequal impacts and explainability.

AI tools can assist with identifying patterns in historical registers, summarizing issue data, suggesting risk categories, and generating scenario prompts. However, AI-generated assessments may reproduce historical bias, miss novel threats, expose confidential information, or create unjustified confidence. Human owners must verify outputs, protect sensitive data, document material decisions, and avoid treating generated text as evidence. AI should augment—not replace—professional judgment and accountability.

Contemporary practice increasingly emphasizes resilience, DevSecOps, continuous monitoring, software supply-chain security, infrastructure as code, automated compliance evidence, and scenario-based testing. These practices shift risk management from periodic reporting toward continuous sensing and response. They do not remove the need for governance: automation can accelerate both safe and unsafe decisions.

10. Challenges and Limitations

Risk management has several limitations. Estimates may be biased by optimism, anchoring, availability of recent events, or pressure from sponsors. Teams may overpopulate registers with trivial items while overlooking systemic threats. Quantitative models can create a misleading appearance of precision when probability data are weak. Risk owners may be assigned without authority, and mitigations may be recorded without budget or time.

To address these limitations, use multiple perspectives, document assumptions, distinguish evidence from judgment, review ratings over time, test contingency actions, and examine cumulative exposure. Also consider interactions: a staffing shortage may increase defects, which increase rework, which increases schedule pressure and burnout. Managing risks independently can therefore underestimate total exposure.

Best-Practice Checklist

A competent software project manager should ensure that:

  • risk criteria and escalation thresholds are agreed early;
  • risks are written as clear cause-event-effect statements;
  • threats and opportunities are both considered;
  • security, privacy, vendor, and operational risks receive specialist input;
  • every significant risk has an accountable owner;
  • responses include triggers, dates, resources, and residual-risk assessment;
  • issues are separated from future risks and managed immediately;
  • registers are reviewed at meaningful project and governance events;
  • contingency and rollback procedures are tested;
  • decisions, assumptions, and evidence are traceable;
  • sensitive information is protected;
  • lessons learned are converted into changes in practice.

Chapter Summary

Risk is an uncertain future event or condition that may affect project objectives; an issue is a problem that has already occurred. Uncertainty may arise from incomplete knowledge or inherent variability. Effective management establishes context, identifies risks systematically, analyzes probability and impact, prioritizes exposure, plans responses, and monitors changing conditions.

Software projects face technical, operational, security, schedule, financial, vendor, and people risks. Qualitative probability-impact matrices support relative prioritization, while expected monetary value can support decisions when probabilities and consequences are credible. Risk responses include avoidance, mitigation, transfer, acceptance, and escalation; contingency and fallback plans define action when risks materialize.

Risk and issue registers provide traceability, ownership, status, and evidence, but they create value only when actively maintained. Issue management requires triage, containment, corrective action, escalation, verification, and learning. Ethical governance demands honest reporting, protection of personal and security-sensitive information, respect for staff, and appropriate human oversight of AI-supported analysis. The central professional principle is that risk management is continuous decision-making, not administrative record keeping.

Key Terms

Risk: An uncertain future event or condition that may affect objectives.

Uncertainty: Limited knowledge or variability concerning future events and outcomes.

Issue: A problem or condition that has already occurred.

Threat: A risk with a potentially negative effect.

Opportunity: A risk with a potentially positive effect.

Risk owner: The person accountable for monitoring and responding to a risk.

Issue owner: The person accountable for resolving an actual problem.

Risk appetite: The amount and type of risk an organization is willing to pursue or accept.

Risk tolerance: The acceptable variation around an objective.

Trigger: A warning sign that a risk may be occurring or changing.

Contingency: A prepared action activated when a defined event occurs.

Fallback: An alternative action used when the primary contingency is ineffective.

Risk register: A controlled record of identified and managed risks.

Issue register: A controlled record of actual problems and their resolution.

Residual risk: Exposure remaining after a response is implemented.

Probability-impact matrix: A qualitative tool that combines likelihood and consequence ratings.

Expected monetary value: Probability-weighted monetary consequence used to compare uncertain exposures.

Escalation: Moving a risk or issue to a level with suitable authority or resources.

Root-cause analysis: Investigation of underlying contributing conditions rather than only symptoms.

Risk response: An action or strategy selected to address a threat or opportunity.

Review Questions

Short Answer Questions

  1. What is the difference between a risk and an issue?
  2. Name four categories of software project risk.
  3. What is the purpose of a risk trigger?
  4. Identify two limitations of a probability-impact matrix.
  5. Why should a contingency plan be tested?

Long Answer Questions

  1. Explain a complete risk management process from establishing context through monitoring and closure.
  2. Compare avoidance, mitigation, transfer, acceptance, and escalation as responses to threats.
  3. Describe the contents and management uses of a software project risk register.
  4. Explain how security and privacy risks should be integrated into software project governance.
  5. Discuss how people and vendor risks can interact with schedule and technical risks.

Analytical / Application Questions

  1. A project team estimates that a supplier delay has a 0.25 probability and would cause a £40,000 loss. Calculate the expected monetary value and explain why the result is not a guaranteed loss.
  2. A critical engineer is leaving in one month, and no one else can deploy the system. Identify the risk statement, likely impacts, triggers, owners, and at least three appropriate responses.
  3. A production defect is discovered in software processing sensitive personal data. Explain how the project manager should classify, contain, escalate, investigate, communicate, and close the matter.

Multiple Choice Questions with Answers

Question 1

Which statement best distinguishes a risk from an issue?

A. A risk is always negative, while an issue is always positive.

B. A risk is uncertain and future-oriented, while an issue has already occurred.

C. A risk belongs to the sponsor, while an issue belongs to the developer.

D. A risk is recorded after resolution, while an issue is recorded before analysis.

Correct Answer: B. A risk is uncertain and future-oriented, while an issue has already occurred.

Question 2

What is the primary purpose of a risk owner?

A. To approve every project expenditure

B. To write all project requirements

C. To monitor a risk and coordinate its response

D. To replace the project sponsor

Correct Answer: C. To monitor a risk and coordinate its response

Question 3

A risk has probability 0.30 and a monetary consequence of £20,000. What is its expected monetary value?

A. £600

B. £2,000

C. £6,000

D. £66,667

Correct Answer: C. £6,000

Question 4

Which response changes the plan to remove a threat entirely?

A. Avoidance

B. Acceptance

C. Transfer

D. Enhancement

Correct Answer: A. Avoidance

Question 5

What is a contingency plan?

A. A historical report of closed risks

B. An action prepared for activation if a defined event occurs

C. A replacement for project objectives

D. A method for assigning blame after failure

Correct Answer: B. An action prepared for activation if a defined event occurs

Question 6

Which item is most appropriate for an issue register rather than a risk register?

A. Possible future supplier insolvency

B. Potential loss of a specialist next quarter

C. A database migration that has already failed testing

D. Possible performance degradation after launch

Correct Answer: C. A database migration that has already failed testing

Question 7

Why might a high-impact security risk require action even when its probability is low?

A. Probability is irrelevant to all risks

B. Security risks never have measurable consequences

C. Legal, ethical, or organizational risk appetite may require controls regardless of score

D. Low-probability risks are automatically certain to occur

Correct Answer: C. Legal, ethical, or organizational risk appetite may require controls regardless of score

Question 8

Which practice best reduces people risk caused by dependence on one specialist?

A. Preventing documentation to save time

B. Cross-training and knowledge transfer

C. Increasing overtime indefinitely

D. Removing the specialist from all decisions immediately

Correct Answer: B. Cross-training and knowledge transfer

Question 9

What does residual risk mean?

A. Risk that has not yet been identified

B. Risk remaining after a response is implemented

C. Risk transferred to a completed project

D. Risk that has no owner

Correct Answer: B. Risk remaining after a response is implemented

Question 10

When is escalation most appropriate?

A. Whenever any minor task is late

B. When a risk exceeds tolerance or requires authority unavailable to its owner

C. Only after the project has failed

D. Whenever the register contains more than ten entries

Correct Answer: B. When a risk exceeds tolerance or requires authority unavailable to its owner

Software Project Management
Chapter 8 of 15