Six Sigma Methodology

Chapter 11
Lean Six Sigma and Operational Excellence

Post Graduate Program in Total Quality Management
Six Sigma Methodology   •   Post Graduate

Lean Six Sigma and Operational Excellence

Introduction and Context

Lean Six Sigma integrates two complementary improvement traditions. Lean focuses on the rapid and systematic removal of activities that consume resources without creating customer value. Six Sigma focuses on reducing process variation, defects, and performance instability through disciplined measurement and statistical analysis. Operational excellence is the broader organizational capability of consistently delivering customer value through reliable, efficient, safe, and continuously improving processes.

The integration is necessary because waste and variation reinforce one another. Excess inventory may conceal unstable production; long queues may result from unreliable equipment; rework may create additional workload and disrupt flow; and large batches may be used to protect a process from changeover losses. Lean methods expose and remove non-value-adding work, while Six Sigma methods identify and control the causes of process variation. Neither approach should be treated as a collection of isolated tools. The central managerial task is to redesign the end-to-end value stream so that work flows according to customer demand, defects are prevented, and process performance is sustained.

This chapter examines value-stream mapping, flow, pull, takt time, 5S, SMED, Kaizen, the Theory of Constraints, and integrated process improvement. It also addresses implementation risks, measurement, digital technologies, and the governance conditions required for sustainable results.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Explain the relationship between Lean, Six Sigma, and operational excellence.
  2. Distinguish value-adding, business-value-adding, and non-value-adding activities.
  3. Construct and interpret a current-state and future-state value-stream map.
  4. Calculate and use takt time, cycle time, lead time, and process capability indicators appropriately.
  5. Apply 5S, SMED, Kaizen, flow, pull, and constraint-management principles.
  6. Integrate waste elimination and variation reduction in an end-to-end improvement project.
  7. Evaluate the managerial, ethical, technological, and organizational implications of Lean Six Sigma.

1. Foundations of Lean Six Sigma

1.1 Value and waste

Value is defined by the customer, not by the producer. An activity is value-adding when it transforms the product or service in a way the customer requires, is performed correctly the first time, and would reasonably be paid for by the customer. Activities such as machining a required feature or accurately processing a patient registration can be value-adding. Inspection, correction, waiting, transport, excess motion, and duplicated data entry generally do not transform the output in a customer-valued way.

A useful classification is:

CategoryMeaningTypical example
Value-addingDirectly creates required customer valueAssembly of a required component
Business-value-addingRequired by law, control, or organizational policy but not valued directly by the customerRegulatory record retention
Non-value-addingConsumes resources without necessary value creationWaiting for approval or rework

Lean commonly identifies eight wastes: defects, overproduction, waiting, non-utilized talent, transportation, inventory, motion, and extra-processing. The acronym DOWNTIME is often used to remember them. Waste is not merely a cost problem; it also increases process complexity and creates opportunities for error.

1.2 Variation and defects

Six Sigma treats process performance as the outcome of a system of inputs, methods, people, machines, materials, measurement systems, and environmental conditions. Common-cause variation is inherent in the current system. Special-cause variation arises from unusual, assignable conditions. Improvement requires distinguishing these causes rather than reacting indiscriminately to every fluctuation.

For a stable process, the process capability index is commonly expressed as:

Cp = (USL − LSL) ÷ (6σ)

where USL is the upper specification limit, LSL is the lower specification limit, and σ is the within-process standard deviation. Cp measures potential capability if the process is centered. It is meaningful only when the process is statistically stable, the measurement system is adequate, and the data represent the relevant operating conditions.

The centered capability index is:

Cpk = min[(USL − μ) ÷ (3σ), (μ − LSL) ÷ (3σ)]

where μ is the process mean. Cpk accounts for both dispersion and off-centering. Capability indices do not prove that every unit conforms; they summarize performance under stated assumptions. In non-normal processes, highly autocorrelated data, or unstable processes, alternative analyses may be required.

1.3 Integration rather than rivalry

Lean is often strongest in identifying visible waste and improving speed. Six Sigma is often strongest in diagnosing complex causes of variation and validating results statistically. A Lean-only intervention can accelerate a defective process. A Six Sigma-only intervention can optimize a local operation while leaving queues, handoffs, and unnecessary work untouched. Lean Six Sigma combines the two perspectives through a structured cycle such as Define–Measure–Analyze–Improve–Control (DMAIC), supported by Lean design principles.

2. End-to-End Process Thinking

Operational excellence requires a shift from departmental optimization to value-stream performance. A value stream includes all actions, information flows, decisions, and material movements required to deliver a product or service from request to completion. The boundaries should include suppliers, internal functions, customers, and relevant support processes when they affect lead time or quality.

Important measures include:

  • Cycle time: elapsed time required for one process cycle under defined conditions.
  • Lead time: elapsed time from customer request to delivery or completion.
  • Processing time: time during which work is actively transformed.
  • Queue time: time work waits between activities.
  • First-pass yield: proportion completed correctly without rework.
  • Rolled throughput yield: probability that a unit passes all sequential process steps without defect or rework.

If independent step yields are assumed, rolled throughput yield is:

RTY = Y1 × Y2 × … × Yn

where Yi is the first-pass yield of step i and n is the number of steps. The independence assumption is often imperfect; therefore, the result should be interpreted as an estimate unless joint process data are available.

3. Value-Stream Mapping

Value-stream mapping (VSM) is a visual method for representing material and information flows, process data, inventories, queues, and customer requirements. It is not simply a flowchart. A conventional VSM makes time, demand, control points, and accumulation visible across the whole stream.

3.1 Current-state mapping

A current-state map should be created by observing the process where work occurs. Interviews alone may reproduce assumptions rather than actual practice. The team normally records customer demand, supplier deliveries, production-control signals, process cycle times, changeover times, uptime, staffing, inventories, queues, defects, and information delays.

The map should distinguish processing time from waiting time. If a stream has processing times of 4, 6, and 5 minutes and queues of 40, 70, and 25 minutes, processing time is 15 minutes while total elapsed time is 150 minutes. The difference is operationally significant: reducing machine time may have little effect if most lead time is waiting.

3.2 Future-state design

A future-state map should answer practical questions:

  1. What is the customer demand and required response time?
  2. Which process is the pacemaker, or the point scheduled to customer demand?
  3. Where can continuous flow be established?
  4. Where is a supermarket or controlled inventory buffer necessary?
  5. How will production be signaled through pull rather than forecast-driven pushing?
  6. What work must be leveled to avoid unstable demand on the process?
  7. Which quality controls must be built into the process?

A future-state map is a hypothesis about a better operating system. It should be tested through experiments and revised as evidence emerges.

Integrated value stream with flow and pull SupplierMaterials Process 1Flow cell PacemakerCustomer schedule CustomerDemand Information and production signal Pull supermarket / buffer replenishment Design principle: customer demand → pacemaker → replenishment pull → upstream flow
Value stream showing supplier, processes, customer, information flow, and pull signals
Figure: Value stream showing supplier, processes, customer, information flow, and pull signals

Figure: A simplified future-state value stream combining customer demand, a pacemaker process, flow, and pull replenishment.

4. Flow, Pull, and Takt Time

4.1 Takt time

Takt time expresses the pace required to meet customer demand. It is calculated as:

Takt time = Available production time ÷ Customer demand

Available production time must exclude planned breaks, scheduled maintenance, and other agreed non-production periods. Both numerator and denominator must use consistent time units.

Worked example. A work centre has 450 net production minutes per shift and customer demand of 150 units per shift:

Takt time = 450 min ÷ 150 units = 3 min/unit

The process should complete one acceptable unit every three minutes on average. Takt time is not the same as cycle time. Cycle time is the actual time between completed units at a process. For capacity to meet demand, effective cycle time generally must be no greater than takt time, after considering downtime, changeovers, yield losses, and staffing.

If a process has total manual work content of 11 minutes and takt time is 3 minutes, the theoretical minimum number of operators is:

Nmin = Ceiling(total work content ÷ takt time) = Ceiling(11 ÷ 3) = 4 operators

This is a lower bound, not a staffing prescription. Work balance, skill constraints, ergonomic limitations, and equipment availability must also be considered.

4.2 Flow

Flow means that work moves through a process with minimal interruption, batching, waiting, and backtracking. One-piece flow is an ideal, not a universal requirement. It is appropriate when product variety, equipment capability, changeover economics, and quality controls permit it. Where continuous flow is impractical, small controlled batches and FIFO lanes can provide a transitional design.

Flow reduces lead time and exposes problems quickly. This exposure can initially make performance appear worse because hidden defects and shortages become visible. Management must treat this visibility as information rather than suppressing it with excess inventory.

4.3 Pull

A pull system authorizes upstream replenishment in response to actual downstream consumption. Kanban cards, electronic signals, two-bin systems, and supermarket buffers are common mechanisms. Pull does not mean that all production is triggered by individual customer orders; it means that replenishment is governed by consumption and explicit rules rather than uncontrolled forecasts and local preferences.

A simple inventory-control relationship is:

Reorder point = Demand during replenishment lead time + Safety stock

The formula assumes that demand and replenishment lead time are defined on a common time basis. Safety stock should reflect measured uncertainty and service requirements, not merely be added as an unexamined cushion.

5. Core Lean Improvement Methods

5.1 5S

5S is a workplace-management system: Sort, Set in order, Shine, Standardize, and Sustain. It is not equivalent to housekeeping. Its purpose is to make abnormalities visible, reduce search and motion, support standard work, and create conditions for reliable work.

  • Sort: remove unnecessary items.
  • Set in order: locate required items for easy identification and retrieval.
  • Shine: clean while inspecting for abnormal conditions.
  • Standardize: establish visual and procedural standards.
  • Sustain: audit, learn, and improve the system rather than relying on periodic campaigns.

5S should not become an instrument of surveillance or cosmetic compliance. Standards must be co-designed with users and connected to safety, quality, and process performance.

5.2 SMED

Single-Minute Exchange of Die (SMED) is a method for reducing changeover time, traditionally targeting a changeover completed in less than ten minutes, although the deeper principle is rapid, repeatable changeover. The method separates internal activities, which require the equipment to stop, from external activities, which can be completed while it operates. Internal work is converted to external work where possible; remaining tasks are simplified, standardized, and synchronized.

Typical actions include preparing tools in advance, using quick-release fittings, parallelizing tasks, eliminating adjustment through locating devices, and verifying first-off quality rapidly. Changeover reduction enables smaller batches, which support flow and lower inventory. However, speed must not compromise operator safety, equipment protection, or product verification.

5.3 Kaizen and standard work

Kaizen means ongoing, incremental improvement involving the people who perform the work. A Kaizen event may be a focused, short-duration intervention, but Kaizen as a management philosophy is continuous. It uses direct observation, problem definition, experimentation, and follow-up.

Standard work specifies the current best-known sequence, work-in-process limit, and expected time under defined conditions. It is not intended to prevent improvement. Rather, without a standard, improvement cannot be reliably compared: the process may simply be changing from one uncontrolled condition to another. Standards must include quality and safety requirements and should be revised when evidence supports a better method.

6. Theory of Constraints

The Theory of Constraints (TOC) views every system as constrained by at least one factor that limits its performance. The constraint may be a machine, policy, approval rule, skill, market, supplier, or information system. The five focusing steps are:

  1. Identify the system constraint.
  2. Exploit it by using existing capacity effectively.
  3. Subordinate other activities to the constraint’s needs.
  4. Elevate the constraint by adding capacity or changing the system.
  5. Repeat when the constraint moves.

TOC emphasizes that local efficiency is not the same as system improvement. Producing more at a non-constraint process can create inventory without increasing throughput. Lean flow and TOC are compatible: Lean reduces interruptions and waste around the constraint, while TOC directs improvement attention toward the system’s limiting point.

A practical warning is that a constraint should be identified from system evidence, such as persistent queue accumulation, lost throughput, or demand exceeding available capacity. The busiest resource is not necessarily the constraint if its work does not determine end-to-end output.

7. Integrated Lean Six Sigma Methodology

A robust project combines Lean observation with Six Sigma analysis.

Define

Define the customer, problem, business case, process boundary, project goal, stakeholders, and expected benefits. A precise problem statement describes what is happening, where, when, and at what magnitude without prematurely asserting a cause.

Measure

Validate the measurement system, establish operational definitions, collect baseline data, and map the value stream. Metrics should include quality, delivery, cost, safety, employee impact, and customer outcomes. A process may show improved cycle time while increasing defects; therefore, single-metric optimization is unsafe.

Analyze

Use stratification, Pareto analysis, process observation, cause-and-effect analysis, control charts, capability analysis, and, where appropriate, designed experiments. Lean waste observations should be tested against data. For example, a suspected bottleneck may actually be caused by changeover variation or schedule instability.

Improve

Design future-state flow, establish takt-based work balance, reduce changeover, mistake-proof critical steps, introduce pull controls, and remove root causes of variation. Pilot changes under controlled conditions. Evaluate both direct effects and unintended consequences.

Control

Standardize the improved process, establish visual controls, train personnel, monitor key measures, define reaction plans, and transfer ownership to process management. Control plans should specify what is measured, how often, acceptable limits, who responds, and how learning is incorporated.

8. Detailed Applied Case: Illustrative Medical-Device Assembly Cell

This fictional case is illustrative and is not a report of a particular organization.

Background and problem

A medical-device assembly cell produced a disposable sensor. Customer demand was 480 units per day. The cell operated one 480-minute shift, including 30 minutes of planned breaks, giving 450 net minutes. The current process had four stages, substantial WIP, and a final inspection queue. On-time delivery was 86%, first-pass yield was 93%, and operators reported frequent searching for tools and materials.

Analysis

Takt time was:

Takt time = 450 min ÷ 480 units = 0.9375 min/unit = 56.25 s/unit

Observed processing times were 42, 61, 48, and 39 seconds. The second stage exceeded takt time and accumulated a queue. However, observation showed that 14 seconds of its 61-second cycle involved searching and adjustment. A measurement-system review also found inconsistent defect classification at final inspection. Thus, the apparent constraint included both work-content waste and measurement inconsistency.

The team mapped 1,920 units of WIP across the cell. If average customer demand was 480 units per day, the inventory represented approximately four days of demand:

Days of supply = WIP ÷ Daily demand = 1,920 ÷ 480 = 4 days

This inventory concealed the instability of the second stage and delayed feedback on defects.

Improvement approach

The team applied 5S to locate tools at point of use, created a standard replenishment route, and separated internal from external setup activities. A SMED trial reduced changeover from 38 minutes to 14 minutes. Work was rebalanced by moving a preparation task from stage two to stage one and introducing a simple fixture that prevented incorrect orientation. A FIFO lane limited WIP between stages one and two. The pacemaker was scheduled to customer demand, while upstream replenishment used a controlled pull signal.

The inspection team established a common defect taxonomy and conducted measurement-agreement checks before using defect data for further analysis. Operators participated in daily Kaizen reviews, and a reaction plan was posted for abnormal cycle time, missing material, and fixture failure.

Outcome

After four weeks of controlled operation, average WIP fell to 720 units, first-pass yield increased to 98%, and on-time delivery rose to 97%. The revised stage-two cycle time was 51 seconds, below the 56.25-second takt requirement. The improvement was not attributed to one tool: it resulted from combining waste removal, work balancing, error prevention, measurement discipline, pull control, and management follow-up.

Learning points

  1. A visible bottleneck may contain several interacting causes.
  2. Reducing WIP can expose problems but also accelerate learning.
  3. Takt time is a demand-based design reference, not a target for unsafe overwork.
  4. Measurement-system quality is essential before interpreting defect trends.
  5. Sustainable improvement requires standards, ownership, and reaction plans.

9. Measurement, Economics, and Governance

Operational excellence should be evaluated through a balanced set of indicators. Useful categories include customer service, quality, lead time, cost, productivity, safety, environmental impact, and employee capability. Financial benefits should distinguish hard savings, cost avoidance, capacity release, revenue protection, and intangible benefits. A reduction in labor hours is not automatically a realized saving if staffing cannot be changed or redeployed.

Governance is particularly important in regulated industries. Process changes may require validation, document control, traceability, segregation of duties, or regulatory approval. In healthcare, aviation, pharmaceuticals, and medical devices, faster flow cannot override patient or product safety. Ethical implementation also requires attention to workload, psychological safety, inclusion, and the risk that productivity targets encourage concealment of defects or unsafe shortcuts.

10. Technology, Data, and Contemporary Developments

Digital Lean Six Sigma uses sensors, manufacturing execution systems, process mining, real-time dashboards, and automated data capture to improve visibility. Process mining can reconstruct actual event sequences from timestamps and reveal loops, delays, and rework that conventional mapping misses. Digital twins can test alternative flow and capacity scenarios before physical implementation.

Artificial intelligence may support anomaly detection, demand sensing, image-based inspection, root-cause exploration, and maintenance prediction. Nevertheless, AI outputs require validated data, explainable decision rules where decisions affect safety or employment, cybersecurity controls, and human accountability. Automation can also create new waste through excessive alerts, poor data quality, or rigid workflows. Technology should follow a verified process need rather than being adopted as a substitute for process understanding.

Contemporary operational-excellence programs increasingly combine Lean Six Sigma with sustainability. Energy, material loss, emissions, water use, and worker well-being can be treated as process outcomes. Circular flows, repairability, and resource efficiency extend the meaning of value beyond immediate transaction cost. Resilience has also become important: a highly efficient but fragile supply chain may fail under disruption. Future-state design should therefore consider capacity buffers, supplier risk, cybersecurity, and recovery time alongside inventory reduction.

11. Challenges and Limitations

Lean Six Sigma can fail when it is reduced to tool deployment, short-term cost cutting, or certification activity. Common limitations include:

  • Local optimization: improving one department while worsening total lead time.
  • Metric distortion: pursuing utilization or output at the expense of quality and flow.
  • False precision: treating capability indices as valid despite unstable processes or poor measurement.
  • Change fatigue: launching too many projects without completing control actions.
  • Cultural resistance: imposing standards without engaging process users.
  • Over-reduction of buffers: removing inventory without addressing supplier, equipment, or demand uncertainty.
  • Inadequate problem definition: confusing symptoms with causes.
  • Automation bias: trusting dashboards or algorithms without verifying the underlying process.

Managers should ask whether the improvement increases customer value, reduces total system burden, protects people, and remains effective under realistic variation. Operational excellence is not the elimination of all slack; some capacity, inventory, and redundancy may be rational risk controls.

Best-Practice Guidelines

  1. Start with customer requirements and an explicit process boundary.
  2. Observe the actual work before designing solutions.
  3. Validate measurement systems and operational definitions.
  4. Use takt time to design capacity, but never to justify unsafe pace.
  5. Improve the whole value stream rather than maximizing isolated utilization.
  6. Reduce variation before relying on tight flow where instability is high.
  7. Treat standards as a platform for learning, not as immutable rules.
  8. Identify the system constraint and align improvement around it.
  9. Combine visual management with reliable data and statistical reasoning.
  10. Build control plans, ownership, and employee capability before declaring success.
  11. Evaluate financial, customer, safety, environmental, and workforce outcomes together.
  12. Use digital and AI tools only when their data, governance, and decision responsibilities are clear.

Chapter Summary

Lean Six Sigma integrates Lean’s emphasis on value, waste elimination, flow, and pull with Six Sigma’s emphasis on variation reduction, measurement, and statistical control. Value-stream mapping reveals the relationship between material flow, information flow, processing time, waiting, inventory, and customer demand. Takt time translates demand into a required pace, while cycle time, lead time, yield, and capability measures help evaluate whether the process can reliably meet that demand.

5S, SMED, Kaizen, standard work, and mistake-proofing improve workplace reliability and flexibility. The Theory of Constraints prevents local optimization by directing attention to the factor limiting total system performance. DMAIC provides a disciplined structure for integrating observation, data analysis, experimentation, and control. The illustrative case demonstrates that sustainable improvement comes from combining methods rather than applying isolated tools.

Operational excellence is ultimately a management system. It requires balanced metrics, ethical governance, employee participation, validated data, and continual learning. Digital technologies and AI can strengthen visibility and prediction, but they cannot replace process understanding, human accountability, or sound improvement logic.

Key Terms

Lean Six Sigma: An integrated approach combining waste elimination with variation and defect reduction.

Operational excellence: The sustained capability to deliver customer value efficiently, reliably, safely, and continuously improve.

Value stream: All actions and information flows required to deliver a product or service.

Value-stream mapping: A visual representation of end-to-end material, information, and time flows.

Value-adding activity: Work that transforms output in a way required by the customer and done correctly.

Waste: Resource consumption that does not create necessary customer or business value.

Takt time: Available production time divided by customer demand.

Cycle time: Time between completed units or time required for one process cycle.

Lead time: Total elapsed time from request to delivery or completion.

Flow: Movement of work with minimal interruption, batching, and waiting.

Pull: Replenishment authorized by downstream consumption.

5S: Sort, Set in order, Shine, Standardize, and Sustain.

SMED: A method for reducing and stabilizing equipment changeover time.

Kaizen: Continuous, participative improvement.

Standard work: The documented best-known sequence, timing, and work-in-process condition.

Theory of Constraints: A system-improvement approach centered on identifying and managing the limiting constraint.

First-pass yield: The proportion completed correctly without rework.

Rolled throughput yield: The combined probability of passing all sequential process steps without defect.

C_p: A capability index measuring potential performance relative to specification width.

C_{pk}: A capability index accounting for both variation and process centering.

Review Questions

Short Answer Questions

  1. Distinguish value-adding, business-value-adding, and non-value-adding activities.
  2. What is the difference between takt time and cycle time?
  3. List the five steps of 5S.
  4. Why is a current-state value-stream map based on direct observation?
  5. State the five focusing steps of the Theory of Constraints.

Long Answer Questions

  1. Explain how Lean and Six Sigma complement one another in an end-to-end improvement project.
  2. Describe how a future-state value-stream map can use flow, pull, a pacemaker, and controlled buffers.
  3. Explain SMED and discuss how changeover reduction affects batch size, inventory, and flexibility.
  4. Discuss the assumptions and limitations of Cp and Cpk.
  5. Evaluate the role of standard work, visual management, and control plans in sustaining improvement.

Analytical / Application Questions

  1. A process has 390 net available minutes per shift and demand of 260 units per shift. Calculate takt time and explain how it should be used in line balancing.
  2. A four-step process has first-pass yields of 0.98, 0.95, 0.97, and 0.99. Calculate the rolled throughput yield under the independence assumption and interpret the result.
  3. A value stream has a persistent queue before one operation, but that operation is not always the busiest resource. Design an evidence-based analysis using VSM, cycle-time data, yield data, and TOC principles to identify the true system constraint.

Multiple Choice Questions with Answers

Question 1

Which statement best describes takt time?

A. The time required to complete a changeover

B. The average time available per unit to meet customer demand

C. The total elapsed time from order to delivery

D. The time an operator spends inspecting one unit

Correct Answer: B. The average time available per unit to meet customer demand

Question 2

A process has 450 net production minutes and demand of 150 units per shift. What is the takt time?

A. 2 minutes per unit

B. 3 minutes per unit

C. 150 minutes per unit

D. 600 minutes per unit

Correct Answer: B. 3 minutes per unit

Question 3

Which activity is generally non-value-adding?

A. Transforming material into a required feature

B. Assembling a component to customer specification

C. Waiting for an approval before work can continue

D. Configuring a product to a requested option

Correct Answer: C. Waiting for an approval before work can continue

Question 4

What is the primary purpose of value-stream mapping?

A. To rank employees by productivity

B. To represent end-to-end material and information flows

C. To calculate only machine depreciation

D. To replace all statistical analysis

Correct Answer: B. To represent end-to-end material and information flows

Question 5

In SMED, which activity should preferably be converted from internal to external?

A. An activity requiring the machine to be stopped

B. An activity that can be completed while the machine is operating

C. A safety verification that must occur during shutdown

D. A repair requiring disassembly of the machine

Correct Answer: B. An activity that can be completed while the machine is operating

Question 6

Which Theory of Constraints step follows identification of the constraint?

A. Exploit the constraint

B. Eliminate all inventory

C. Increase every department’s utilization

D. Standardize all suppliers immediately

Correct Answer: A. Exploit the constraint

Question 7

If two sequential process steps have first-pass yields of 0.95 and 0.98, what is their rolled throughput yield under the independence assumption?

A. 0.931

B. 0.960

C. 0.975

D. 1.930

Correct Answer: A. 0.931

Question 8

Which statement about Cpk is correct?

A. It considers only specification width

B. It accounts for variation and distance from the nearest specification limit

C. It is valid regardless of process stability

D. It measures customer satisfaction directly

Correct Answer: B. It accounts for variation and distance from the nearest specification limit

Question 9

What is the central purpose of a pull system?

A. To maximize upstream production regardless of demand

B. To authorize replenishment based on downstream consumption

C. To eliminate all safety stock in every process

D. To ensure every machine operates continuously

Correct Answer: B. To authorize replenishment based on downstream consumption

Question 10

Why is measurement-system quality important in Lean Six Sigma?

A. It guarantees that the process has no waste

B. It ensures that observed data can be interpreted with confidence

C. It automatically identifies the Theory of Constraints

D. It makes customer requirements unnecessary

Correct Answer: B. It ensures that observed data can be interpreted with confidence

Six Sigma Methodology
Chapter 11 of 15