Resource Loading & Leveling

Chapter 13
Digital Platforms, Automation and AI

Post Graduate Program in Project Management
Resource Loading & Leveling   •   Post Graduate

Digital Platforms, Automation and AI

Introduction

Resource loading and leveling have traditionally depended on schedules, spreadsheets, resource histograms, and periodic managerial judgment. Contemporary projects operate in a more connected environment. Enterprise resource planning (ERP) systems record labour, procurement, finance, and assets; project-management information systems (PMIS) manage scope, activities, dependencies, and baselines; workforce platforms maintain skills, availability, rates, and assignments; and portfolio systems compare competing initiatives. Cloud collaboration, automation, digital twins, predictive analytics, and artificial intelligence (AI) increasingly connect these capabilities.

The central managerial issue is not whether an organisation possesses digital tools, but whether those tools produce reliable, timely, interpretable, and governable resource decisions. A technically sophisticated platform can amplify poor data, conceal assumptions, or create false confidence. Integrated resource management therefore requires both systems thinking and professional judgment.

This chapter examines how digital platforms support resource loading and leveling, how data interoperability can be designed, and how analytics, optimization, and generative AI should be applied responsibly.

Learning Objectives

By the end of this chapter, the reader should be able to:

  1. Explain the roles of scheduling, ERP, workforce, and portfolio systems in integrated resource management.
  2. Evaluate data models, interfaces, interoperability, identity, and data-quality controls.
  3. Distinguish cloud collaboration, digital twins, predictive analytics, and optimization engines.
  4. Interpret resource-loading and capacity metrics without confusing them with performance measures.
  5. Assess appropriate uses and limitations of automation and generative AI.
  6. Design governance controls for security, privacy, accountability, bias, and human oversight.
  7. Apply an integrated approach to a practical resource-management case.

1. The Digital Resource-Management Landscape

A project schedule answers questions such as what work must occur, in what sequence, and when. Resource loading adds who or what is required, in what quantity, and at what cost. Leveling adjusts the timing or allocation of activities when demand exceeds available capacity. Digital platforms extend this logic across projects and organisational functions.

A typical architecture contains five connected layers:

LayerPrimary purposeTypical information
Project schedulingPlan work and dependenciesActivities, calendars, logic, milestones, baselines
ERP and financial systemsRecord organisational transactionsLabour cost, purchase orders, actuals, budgets, assets
Workforce and skills systemsRepresent people and availabilitySkills, roles, leave, location, contracts, rates
Portfolio systemsPrioritise and govern initiativesStrategic value, risk, funding, scenarios, benefits
Data and intelligence layerIntegrate and analyse informationAPIs, data warehouse, dashboards, forecasts, optimization

No single system should be assumed to be the universal source of truth. The schedule may be authoritative for planned dates, the workforce system for employment status, and the ERP for posted actual cost. A data-governance policy must define ownership for each attribute.

1.1 From isolated schedules to integrated planning

In an isolated schedule, a project manager may assign “Senior Engineer” to several activities without knowing that the person is committed elsewhere. Integrated systems can compare demand from multiple projects with enterprise capacity. They can also distinguish nominal capacity from usable capacity by accounting for leave, training, meetings, maintenance, shifts, location, and contractual restrictions.

Integration changes resource management from a project-by-project exercise into a coordinated decision process. It also introduces trade-offs. A portfolio may maximise strategic value by accepting temporary overload on a scarce specialist, whereas a project-only view would delay work to remove the overload. The correct decision depends on priorities, constraints, risk, and the cost of delay.

2. Core Data Model for Resource Loading

Digital resource management is fundamentally a data-modelling problem. Important entities commonly include:

  • Work package and activity: the unit of planned work.
  • Resource: a person, team, role, machine, facility, or material category.
  • Assignment: the relationship between an activity and a resource.
  • Calendar: working time, shifts, holidays, maintenance, and exceptions.
  • Capability: skills, certifications, experience, grade, or equipment attributes.
  • Demand: required effort, units, or capacity over a period.
  • Supply: available capacity over a period.
  • Cost rate: monetary cost associated with a resource or resource category.
  • Actual: recorded work, cost, consumption, or progress.
  • Baseline: approved reference plan against which change is evaluated.

The distinction between effort, duration, and capacity is essential. If a task requires 80 labour-hours and one analyst contributes 40 hours per week, the theoretical duration is two weeks, assuming uninterrupted availability and no efficiency loss. If two analysts work in parallel, duration may fall, but not necessarily to one week because work may be sequential, coordination may increase, or the task may have a minimum duration.

A simple resource-demand relationship is:

Dr,t = ∑a ∈ At ea,r,t

Here, Dr,t is demand for resource category or resource r in period t, At is the set of activities active in that period, and ea,r,t is the effort required from resource r by activity a in that period. The units must be consistent, such as labour-hours per week. The equation assumes that activity-level demand has already been time-phased.

Available capacity can be represented as:

Cr,t = Nr,t × Ht × ur,t

Cr,t is usable capacity in labour-hours; Nr,t is the number of available resource units; Ht is standard working hours per unit in period t; and ur,t is the usable-capacity factor between 0 and 1. The factor may reflect leave, training, non-project work, or expected availability. The calculation assumes that units are interchangeable; where skills differ, capacity must be represented by skill or competency rather than headcount alone.

A basic load ratio is:

Lr,t = Dr,t ÷ Cr,t

A value above 1 indicates nominal overload. A value below 1 indicates spare capacity, although spare capacity may not be usable if the resource lacks the required skill or if the time window is too short. Utilization should not automatically be maximized. Persistently high utilization can reduce resilience, increase waiting time, and make the system vulnerable to disruption.

3. Interoperability and Data Architecture

3.1 Syntactic and semantic interoperability

Syntactic interoperability means that systems can exchange data in a technically readable format. APIs, structured files, message queues, and standards support this level. Semantic interoperability means that the receiving system interprets the data in the same way. For example, “hours” may mean planned effort in one system and approved timesheet hours in another. “Complete” may mean physical progress, payment approval, or administrative closure.

Interoperability requires agreement on:

  1. common identifiers for projects, activities, people, skills, suppliers, and cost centres;
  2. units of measure and currency;
  3. calendars, time zones, fiscal periods, and cut-off dates;
  4. status definitions and allowed transitions;
  5. versioning and effective dates;
  6. data ownership and stewardship; and
  7. error handling, reconciliation, and audit history.

A practical design uses a canonical data model or governed data products rather than allowing every system to map directly to every other system. Direct point-to-point links can work at small scale but become difficult to maintain as the number of applications increases.

3.2 Master data and data quality

Resource decisions are only as reliable as their underlying data. Common quality dimensions include accuracy, completeness, consistency, timeliness, uniqueness, validity, and traceability. A dashboard showing a precise overload percentage may be misleading if half of the workforce has no current availability calendar.

Data-quality controls should include validation at entry, automated reconciliation, exception queues, periodic stewardship reviews, and visible confidence indicators. For example, a capacity report might identify that 85% of assignments use current calendars, while 15% rely on default assumptions. Decision-makers can then interpret the result appropriately.

3.3 Integration patterns

Common integration patterns include:

  • Batch exchange: periodic export and import; simple but may produce stale information.
  • API integration: systems request or submit data through defined interfaces.
  • Event-driven integration: a change, such as an approved leave request, triggers downstream processing.
  • Data warehouse or lakehouse: historical and cross-system data are consolidated for analysis.
  • Master-data service: shared identities and reference values are governed centrally.

Real-time integration is not always necessary. A weekly capacity review may be adequate for long engineering projects, while a control-room operation may require near-real-time updates. Integration frequency should be determined by decision latency, volatility, cost, and risk.

4. Cloud Collaboration and Digital Workspaces

Cloud platforms provide shared access to schedules, documents, risks, decisions, and dashboards. Their value is organisational as well as technical: they create a common workspace in which distributed participants can view current information and record decisions.

Important design considerations include role-based access, separation of duties, audit trails, retention rules, data residency, backup, service availability, and controlled configuration. Collaboration does not mean unrestricted editing. A sound system distinguishes draft, submitted, approved, baselined, and superseded information.

Cloud collaboration can support resource leveling through shared demand views, scenario comparison, automated notifications, and approval workflows. Nevertheless, a cloud dashboard is not automatically a reliable control system. It can display stale, duplicated, or poorly defined data at impressive speed.

5. Digital Twins for Resource and Project Control

A digital twin is a continuously updated digital representation of a physical or organisational system, linked to relevant real-world data and used to observe, analyse, or simulate behaviour. In project management, the concept may include a model of a facility under construction, a production line, a fleet, or an enterprise delivery system.

A schedule alone is a plan. A digital twin combines a model with observations and relationships to the evolving real system. For example, a construction twin might combine the schedule, building information model, equipment telemetry, inspection records, weather data, and workforce location information.

Digital twins support:

  • comparison of planned and observed progress;
  • simulation of sequencing and access constraints;
  • detection of resource conflicts;
  • maintenance and asset-readiness planning;
  • scenario analysis under disruption; and
  • learning from historical project performance.

Their limitations are significant. Sensors may be incomplete, models may become obsolete, and correlation between physical signals and productivity may be uncertain. A twin should therefore expose data provenance and uncertainty rather than presenting a single unquestionable representation.

6. Automation in Loading and Leveling

Automation is most valuable when rules are stable, decisions are frequent, and exceptions can be escalated. Typical automations include:

  • creating assignments from approved work packages;
  • updating capacity after leave or calendar changes;
  • notifying managers when thresholds are exceeded;
  • routing requests for scarce skills;
  • reconciling planned and actual hours;
  • generating weekly resource reports; and
  • testing predefined leveling scenarios.

Rule-based automation is usually easier to audit than opaque predictive automation. A rule might state: “If projected load exceeds 110% for two consecutive weeks, create an exception for resource management review.” The threshold is not a universal truth; it is a policy choice that should reflect the organisation’s risk tolerance and the resource type.

Automation should include safeguards: idempotent processing so repeated messages do not duplicate assignments, approval gates for material changes, exception handling, rollback capability, and logs showing what changed, when, and why.

7. Predictive Analytics and Optimization Engines

7.1 Descriptive, diagnostic, predictive, and prescriptive analytics

Descriptive analytics reports what has happened or what is currently planned. Diagnostic analytics investigates causes. Predictive analytics estimates likely future states, such as completion dates, demand, absence, or cost. Prescriptive analytics evaluates actions, such as reallocating work or changing sequence.

A simple forecast model illustrates the principle without claiming universal accuracy. If demand in period t is forecast from a weighted moving average:

Ft+1 = ∑i=1k wi At+1-i

where A is observed demand, F is forecast demand, wi are non-negative weights, and ∑wi = 1. The method assumes that recent historical demand contains useful information and that the selected window is appropriate. It does not account automatically for structural changes, new projects, seasonality, or policy shifts.

Forecast error should be measured rather than hidden. Mean absolute error is:

MAE = (1 ÷ n) ∑t=1n |At − Ft|

where n is the number of evaluated periods. MAE has the same unit as demand, making interpretation straightforward. It should be calculated on data not used to tune the model when the purpose is performance evaluation.

7.2 Optimization

An optimization engine searches for an allocation or schedule that satisfies constraints while minimizing or maximizing an objective. A generic formulation is:

Minimize Z = ∑t∑r cr,t xr,t + ∑t pr,t or,t

subject to capacity, precedence, skill, budget, and deadline constraints.

Here, xr,t may represent assigned effort, cr,t its cost, and or,t an overload or violation variable penalized by pr,t. The exact objective and constraints depend on the decision problem. A model is meaningful only when variables, units, feasible values, and trade-offs are explicitly defined.

For example, a capacity constraint may be written as:

∑a xa,r,t ≤ Cr,t

where xa,r,t is effort assigned to activity a for resource r in period t, and Cr,t is available capacity. If controlled overtime is allowed, an overtime variable may be added with an appropriate cost and legal limit. If activities require particular skills, a headcount constraint is insufficient; the model must constrain qualified capacity.

Optimization does not decide the “best” plan in an absolute sense. It finds a solution relative to the objective, data, constraints, and assumptions supplied. An apparently optimal solution may be operationally unacceptable if it fragments work, ignores learning curves, or allocates people in ways managers cannot implement.

7.3 Scenario analysis

Scenario analysis is often more useful than a single optimized answer. Managers may compare: baseline staffing; recruitment of a scarce specialist; subcontracting; schedule delay; overtime; or reprioritization of a lower-value project. Each scenario should report effects on delivery date, cost, risk, utilization, quality, and strategic value.

8. Responsible Generative AI in Resource Management

Generative AI can produce text, summarize meetings, classify requests, explain anomalies, draft scenarios, and provide natural-language access to project data. It can assist—but should not silently replace—professional accountability.

Appropriate uses include:

  • summarizing approved schedule and capacity changes;
  • converting a manager’s request into a draft query;
  • identifying missing fields or inconsistent terminology;
  • drafting an explanation of a forecast, with links to source data;
  • proposing alternative leveling scenarios for human review; and
  • supporting training and question-answering over governed documents.

High-risk uses include automatic employment decisions, unsupported performance judgments, disclosure of confidential staffing information, and autonomous changes to baselines or assignments. Generative systems can hallucinate, reproduce bias, expose confidential prompts, or present uncertain inferences as facts.

A responsible operating model includes:

  1. Purpose limitation: define the decision the system may support.
  2. Data controls: restrict personal, commercially sensitive, and regulated data.
  3. Human review: require an accountable person to approve consequential decisions.
  4. Traceability: preserve prompts, source records, model version, outputs, and approvals where proportionate.
  5. Validation: test accuracy, bias, robustness, and failure modes.
  6. Transparency: distinguish observed data, forecast, recommendation, and human decision.
  7. Contestability: provide a route to challenge or correct an output.
  8. Security: control access, prevent prompt injection, and monitor abnormal use.

AI recommendations should be treated as evidence to examine, not instructions to obey. A manager remains responsible for legal compliance, fairness, safety, and the consequences of resource decisions.

9. Integrated Case: The Northstar Hospital Expansion

The following is an illustrative case.

Background

Northstar Health Authority is delivering a hospital expansion involving civil works, medical systems, information technology, commissioning, and staff training. Five projects share a limited pool of clinical-informatics specialists, safety engineers, and commissioning managers. The organisation uses a scheduling platform, an ERP system, a workforce skills system, and a portfolio dashboard, but the systems were previously maintained independently.

Problem

The portfolio dashboard reported 72% average specialist utilization. A detailed review found that several calendars used 40-hour weeks although staff worked four-day shifts, training time was omitted, and two projects used different identifiers for the same specialist. The apparent spare capacity was therefore unreliable. Commissioning activities began to collide, threatening the opening date.

Analysis

The programme established a canonical resource identifier and mapped project roles to verified skills and certifications. Planned demand was exported from schedules, while availability and leave came from the workforce system. Actual hours and contractor commitments came from the ERP system. A weekly integration process reconciled records and flagged missing calendars.

The team calculated demand and usable capacity by week. For one commissioning skill, week 14 showed 156 hours of demand and 120 hours of usable capacity:

L = 156 ÷ 120 = 1.30

The resulting 130% load was a genuine overload, not merely a dashboard anomaly. The programme then tested three scenarios: delay a low-priority training package; subcontract part of systems testing; or approve limited overtime. The selected solution combined a two-week shift in the training package with a qualified contractor for specialist testing. It preserved the hospital opening milestone while avoiding sustained overtime.

A natural-language AI assistant was introduced only to summarize weekly exceptions and explain the source records behind each flag. It could not change assignments, approve overtime, or access personnel performance notes. Managers reviewed every generated summary.

Outcome

Within six weeks, the portfolio obtained a consistent view of demand and capacity. Forecast errors declined as actual hours and calendar exceptions were incorporated. More importantly, managers could explain why a resource was considered available, which assumptions were used, and who approved the response. The technology did not eliminate scarcity; it made trade-offs visible earlier.

Learning points

  • Integration begins with identifiers, definitions, and ownership, not dashboards.
  • Averages can conceal critical skill bottlenecks.
  • Usable capacity differs from contractual or theoretical capacity.
  • Scenario comparison supports better decisions than a single “optimal” answer.
  • Generative AI is safest when it explains governed information and remains outside autonomous approval of consequential actions.

10. Governance, Risk, and Implementation

10.1 Governance risks

Digital resource systems create risks involving privacy, cybersecurity, labour law, discrimination, surveillance, intellectual property, and vendor dependence. Individual availability data may reveal health, family, or religious information. Skill ratings may influence promotion or employment decisions. Automated prioritization may systematically disadvantage certain locations, employment categories, or working patterns.

Controls should be proportionate to risk. Access should follow least privilege. Sensitive attributes should not be exposed merely because they are technically available. Retention should be limited to legitimate purposes. Contracts with cloud and AI vendors should address data use, breach notification, service continuity, subcontractors, portability, and audit rights.

10.2 Implementation roadmap

A staged implementation is generally safer than a platform-first transformation:

  1. Define decisions: identify which resource decisions need better information.
  2. Map processes: document demand creation, approval, assignment, actuals, and change.
  3. Establish data ownership: define authoritative sources and stewardship roles.
  4. Clean master data: reconcile projects, people, skills, calendars, rates, and units.
  5. Integrate a pilot: select a bounded portfolio with measurable outcomes.
  6. Create controls: implement access, audit, quality, exception, and approval mechanisms.
  7. Measure value: assess forecast accuracy, decision cycle time, schedule reliability, and user trust.
  8. Scale deliberately: expand only after operating processes and governance are stable.

Useful performance indicators include the percentage of assignments with current calendars, demand forecast error, time to resolve overload exceptions, proportion of recommendations accepted after review, unplanned overtime, and the frequency of manual data corrections. These indicators should not encourage gaming. For example, reducing overload by deleting demand is not genuine improvement.

Challenges and Limitations

Digital platforms do not remove fundamental uncertainty. Future demand may be unknown, productivity may vary, and new constraints may emerge. Models may encourage false precision, while dashboards can privilege measurable work over essential relational or creative work. Optimization may produce brittle schedules that have no resilience to absence or disruption.

Integration also has social limitations. Professionals may resist systems perceived as surveillance or as undermining judgment. Data entry may become an administrative burden. Different departments may protect local definitions or refuse to share information. Successful implementation therefore requires participation, training, feedback, and visible use of data for fairer—not merely more intensive—decision-making.

A mature organisation recognizes the difference between decision automation and decision support. Automating a repetitive notification is generally low risk. Automatically reallocating people, changing contractual commitments, or making employment-related inferences is high risk and requires stronger controls.

Best-Practice Principles

  1. Model effort, duration, capacity, skills, and cost as distinct concepts.
  2. Assign authoritative ownership to every critical data element.
  3. Use common identifiers, units, calendars, and status definitions.
  4. Display data quality and uncertainty beside analytical results.
  5. Integrate at the frequency required by the decision, not simply at the fastest technically possible rate.
  6. Use optimization to expose trade-offs, not to conceal managerial choices.
  7. Validate forecasts on relevant, unseen data and monitor drift.
  8. Preserve human accountability for consequential decisions.
  9. Protect personal and commercially sensitive information.
  10. Treat resilience, fairness, and explainability as design requirements.

Chapter Summary

Digital resource management connects project schedules with ERP, workforce, portfolio, and analytical systems. Its foundation is a coherent data model covering activities, resources, assignments, calendars, skills, demand, capacity, costs, actuals, and baselines. Interoperability requires both technical exchange and shared meaning, supported by identifiers, master-data governance, validation, reconciliation, and auditability.

Cloud collaboration provides shared access and workflow; digital twins connect models with observed operational conditions; automation executes repeatable rules; predictive analytics estimates future demand or outcomes; and optimization evaluates constrained alternatives. Load ratios and forecasts are useful only when their units, assumptions, and data quality are understood.

Generative AI can summarize, explain, classify, and draft recommendations, but it can also hallucinate, reproduce bias, expose confidential data, and obscure accountability. Responsible use requires purpose limitation, security, human review, traceability, validation, transparency, and contestability. The strategic goal is not maximum automation. It is earlier, clearer, fairer, and more defensible resource decisions.

Key Terms

Application programming interface (API): A defined mechanism through which software systems exchange data or invoke functions.

Canonical data model: A governed common representation used to align information across systems.

Capacity: The usable amount of resource time or capability available in a specified period.

Digital twin: A data-linked digital representation of a physical or organisational system used for observation, analysis, or simulation.

Event-driven integration: Integration in which a change in one system triggers a downstream action or message.

Generative AI: AI that produces new text, code, images, recommendations, or other outputs from learned patterns.

Interoperability: The ability of systems to exchange and meaningfully use information.

Load ratio: Resource demand divided by usable capacity for a specified resource and period.

Master data: Stable reference information such as people, projects, skills, cost centres, and units.

Optimization engine: Software that searches for solutions satisfying constraints while pursuing a defined objective.

Portfolio management system: A system used to evaluate, prioritize, fund, and govern multiple initiatives.

Predictive analytics: Analysis that estimates future conditions or outcomes using historical and current data.

Resource leveling: Adjusting activity timing or allocation to resolve resource conflicts and overloads.

Semantic interoperability: Shared interpretation of exchanged data, not merely shared technical format.

Source of truth: The system or governed record designated as authoritative for a particular data element.

Usable-capacity factor: The proportion of nominal working time available for the relevant work.

Validation: Testing whether data, models, or outputs meet specified quality and fitness criteria.

Workforce management system: A system that records workforce availability, skills, roles, contracts, and related attributes.

Review Questions

Short Answer Questions

  1. Distinguish effort, duration, and capacity in resource planning.
  2. What is the difference between syntactic and semantic interoperability?
  3. Why can average portfolio utilization conceal a critical resource bottleneck?
  4. State two appropriate and two high-risk uses of generative AI in resource management.
  5. What is the purpose of a canonical data model?

Long Answer Questions

  1. Explain how scheduling, ERP, workforce, and portfolio systems can be integrated into an enterprise resource-management capability.
  2. Discuss the assumptions and limitations of using a load ratio to identify resource overload.
  3. Compare rule-based automation, predictive analytics, and optimization engines in terms of purpose, inputs, outputs, and governance.
  4. Explain how digital twins can support project control and why their outputs should include uncertainty and data provenance.
  5. Develop a governance framework for responsible use of AI in workforce and portfolio resource decisions.

Analytical / Application Questions

  1. A project has 200 hours of weekly demand, 6 available specialists, 40 contractual hours per specialist, and a usable-capacity factor of 0.75. Calculate usable capacity and the load ratio. Interpret the result and identify two actions that should be investigated.
  2. A portfolio dashboard reports low utilization, but project teams report severe specialist shortages. Design a data-quality and interoperability investigation, specifying the records, definitions, and reconciliations you would examine.
  3. Compare three responses to a forecast overload—delaying work, subcontracting, and overtime—and recommend a decision framework that considers cost, schedule, quality, risk, fairness, and resilience.

Multiple Choice Questions with Answers

Question 1

Which system is normally the authoritative source for posted actual labour cost?

A. The project schedule

B. The ERP or financial system

C. The skills taxonomy

D. The portfolio prioritization register

Correct Answer: B. The ERP or financial system

Question 2

A resource has 156 hours of demand and 120 hours of usable capacity in one week. What is the load ratio?

A. 0.77

B. 1.00

C. 1.30

D. 276

Correct Answer: C. 1.30

Question 3

What does semantic interoperability primarily ensure?

A. Every system uses the same programming language

B. Data are exchanged through a cloud service

C. The receiving system gives exchanged data the intended meaning

D. All systems update every second

Correct Answer: C. The receiving system gives exchanged data the intended meaning

Question 4

Which expression correctly represents usable capacity when there are N resource units, H hours per unit, and utilization factor u?

A. C = N + H + u

B. C = N × H × u

C. C = N ÷ H × u

D. C = H − N − u

Correct Answer: B. C = N × H × u

Question 5

Which is a defining characteristic of a digital twin?

A. It is a static schedule baseline only

B. It is a data-linked representation of a real physical or organisational system

C. It is exclusively a financial ledger

D. It automatically makes all management decisions

Correct Answer: B. It is a data-linked representation of a real physical or organisational system

Question 6

What is the main purpose of an optimization engine in resource management?

A. To remove all constraints from a project

B. To search for feasible solutions against defined objectives and constraints

C. To replace master-data governance

D. To guarantee that forecasts are correct

Correct Answer: B. To search for feasible solutions against defined objectives and constraints

Question 7

Which is the most appropriate control for a generative-AI recommendation affecting staffing?

A. Allowing automatic implementation without review

B. Deleting the source records after generation

C. Human approval, traceability, and a way to challenge the recommendation

D. Using only the longest possible prompt

Correct Answer: C. Human approval, traceability, and a way to challenge the recommendation

Question 8

For a weighted moving-average forecast, what condition must the weights satisfy in the model presented?

A. They must all be negative

B. Their sum must equal one

C. They must all exceed one

D. They must be measured in labour-hours

Correct Answer: B. Their sum must equal one

Question 9

Which integration pattern is triggered by a change or event in one system?

A. Event-driven integration

B. Manual archiving

C. Static baseline management

D. Uncontrolled spreadsheet copying

Correct Answer: A. Event-driven integration

Question 10

Why should an optimization result not automatically be treated as the managerial decision?

A. Optimization cannot use constraints

B. The result depends on the objectives, data, assumptions, and constraints supplied

C. Optimization always increases cost

D. Optimization is unrelated to resource allocation

Correct Answer: B. The result depends on the objectives, data, assumptions, and constraints supplied

Resource Loading & Leveling
Chapter 13 of 14