14. Project Development, Policy, Markets and GovernanceIntroduction and ContextRenewable-energy projects are not created by technology alone. A photovoltaic plant, wind farm, biomass facility, small hydropower station, or battery-supported renewable system becomes viable only when technical design is aligned with land, regulation, finance, markets, institutions, and community interests. Project development is therefore a socio-technical process: it converts an energy resource into an investable, permitted, constructed, operated, and responsibly governed asset. The strategic importance of project development has increased as renewable energy moves from isolated demonstration projects to large-scale deployment and distributed systems. Developers must evaluate resource quality, grid capacity, land rights, environmental effects, revenue certainty, supply-chain risks, policy incentives, and social acceptance simultaneously. A technically excellent project can fail because of a delayed permit, inadequate transmission, an unrealistic tariff, weak contractual protections, or unresolved community opposition. This chapter examines the complete development environment for renewable-energy projects. It links feasibility assessment with siting and permitting, procurement and financing, tariffs and auctions, carbon markets and renewable certificates, contracts and standards, safety, stakeholder engagement, social justice, ethics, and governance. The emphasis is on decision-making under uncertainty and on the responsibilities of engineers and managers beyond the project boundary. Learning ObjectivesAfter studying this chapter, the reader should be able to: 1. Explain the development cycle of a renewable-energy project and distinguish its technical, commercial, legal, and social dimensions. 2. Evaluate site feasibility, grid access, permitting requirements, and major project risks. 3. Compare tariffs, auctions, corporate power-purchase agreements, and merchant-market arrangements. 4. Describe the roles of project finance, contracts, renewable certificates, carbon markets, and standards. 5. Design a stakeholder-engagement and social-justice approach for a renewable project. 6. Apply governance, ethics, safety, and risk-management principles to project decisions. 7. Interpret emerging trends in digital development, hybrid systems, storage, and market reform. From Energy Resource to Investable ProjectProject development normally progresses through a sequence of increasingly costly decisions. During origination, a developer identifies a resource opportunity, a possible site, a market need, and a policy environment. The screening stage then eliminates opportunities with obvious constraints such as insufficient solar irradiation, poor wind regime, lack of road access, protected habitats, uncertain land title, or unavailable grid capacity. A pre-feasibility study estimates energy yield, preliminary capital cost, operating expenditure, connection requirements, construction schedule, revenue, and major risks. If the opportunity remains attractive, detailed feasibility follows. At this stage, resource measurements, geotechnical surveys, environmental studies, energy modelling, grid studies, legal due diligence, financial modelling, and stakeholder consultations are undertaken. Development should be treated as a series of investment gates rather than as a linear paperwork exercise. A useful governance model is: - Gate 1—Opportunity screening: resource, policy, land, market, and grid compatibility.
- Gate 2—Pre-feasibility: preliminary technical and financial viability.
- Gate 3—Development commitment: land control, detailed studies, permits, and commercial strategy.
- Gate 4—Financial close: executable contracts, approved financing, and satisfactory risk allocation.
- Gate 5—Construction readiness: final design, procurement, permits, insurance, and safety plans.
- Gate 6—Operation and review: performance, compliance, community commitments, and lessons learned.
The gates reduce sunk-cost exposure. They also make accountability visible: a project should not progress merely because substantial money has already been spent. Feasibility as an Integrated AssessmentTechnical and resource feasibilitySolar projects require analysis of irradiation, temperature, soiling, shading, terrain, module degradation, tracking configuration, and inverter loading. Wind projects require long-term wind-speed distributions, turbulence, extreme winds, wake effects, topography, transport logistics, and turbine suitability. Hydro projects depend on hydrology, sediment, head, flow variability, aquatic ecology, and dam or diversion conditions. Biomass projects require reliable feedstock quantity, quality, competing uses, transportation distance, and seasonal availability. Energy yield should be expressed probabilistically rather than as one optimistic annual value. P50 energy is the expected or central estimate, while P90 represents a more conservative production level with a specified probability of exceedance. Lenders may base debt sizing on a conservative yield estimate because debt service must continue during poor-resource years. Grid and system feasibilityGrid connection is frequently a project-critical constraint. The assessment should consider voltage level, short-circuit capacity, protection coordination, congestion, curtailment, ramping requirements, reactive-power capability, fault ride-through, and connection cost. A project with strong resource quality may be less valuable than a weaker-resource project near an unconstrained substation. The analysis must also consider system value. Generation during periods of high demand may have greater value than equal annual generation at low-demand periods. Storage, forecasting, flexible operation, hybridization, and demand response can improve the effective value of variable renewable generation. Environmental and social feasibilityEnvironmental impact assessment may address land transformation, biodiversity, birds and bats, water use, noise, visual effects, waste, cultural heritage, and cumulative impacts. Social assessment examines displacement, livelihood effects, access to common land, labour conditions, gender impacts, public health, and distribution of benefits. A project should distinguish between impacts that can be avoided, minimized, restored, or compensated. Compensation is not a substitute for avoiding avoidable harm. Free, prior, and informed consultation is particularly important where Indigenous peoples or customary land users may be affected; legal requirements vary by jurisdiction, but ethical responsibility is broader than minimum compliance. Commercial and financial feasibilityThe basic financial model links installed capacity, energy yield, degradation, availability, capital expenditure, operating expenditure, financing structure, tax, inflation, tariff, residual value, and decommissioning cost. Common indicators include net present value, internal rate of return, levelized cost of electricity, debt-service coverage ratio, payback period, and equity return. Levelized cost is useful for comparing technologies under defined assumptions, but it is not a complete measure of system value. It may exclude transmission reinforcement, balancing, land effects, reliability value, and timing of generation. A project with a slightly higher levelized cost may deliver greater value if it produces during system peaks or avoids expensive grid upgrades. Sensitivity analysis should vary resource yield, capital cost, interest rate, exchange rate, construction delay, curtailment, tariff, inflation, and equipment life. Scenario analysis is stronger than a single sensitivity table because variables often move together. For example, a currency crisis may increase equipment cost, interest rates, and tariff pressure at the same time. Siting, Permitting and the Social Licence to OperateSiting combines spatial analysis with legal and social judgement. Geographic information systems can overlay resource maps, slope, land use, protected areas, transmission, roads, settlements, water resources, and hazard zones. However, an apparently suitable parcel may have unresolved ownership, customary rights, archaeological importance, or cumulative ecological sensitivity. Land arrangements may include purchase, lease, easement, concession, or community agreement. Due diligence should verify title, boundaries, access rights, encumbrances, competing claims, and termination conditions. Developers should avoid treating landowners as a single homogeneous group; tenants, pastoralists, women using common resources, and seasonal users may have different interests. Permitting commonly involves energy authorities, environmental agencies, planning departments, aviation authorities, water regulators, labour inspectors, and local governments. A permit register should specify the responsible party, submission date, dependencies, approval conditions, expiry, and evidence of compliance. Delays often arise not from one major approval but from interactions among permits. Stakeholder engagement is most effective when it begins before project promises become fixed. A credible engagement plan identifies affected and interested parties, their influence and vulnerability, appropriate communication channels, information needs, grievance mechanisms, and feedback responsibilities. Consultation should provide understandable information about land use, noise, construction traffic, jobs, revenue, risks, and decommissioning—not only benefits. The social licence to operate is not a formal permit. It is an evolving level of acceptance based on trust, procedural fairness, perceived legitimacy, and observed behaviour. It can be weakened by secrecy, broken promises, unequal compensation, or dismissive treatment of opposition even when statutory permits have been obtained. Policy Instruments and Renewable-Energy MarketsGovernments shape renewable investment through regulation, public procurement, fiscal measures, grid rules, carbon policy, and market design. Policy should be assessed not only by its nominal incentive but also by its predictability, administrative quality, bankability, and compatibility with grid development. A feed-in tariff guarantees an administered price for eligible electricity, often for a defined period. It can accelerate early deployment by reducing revenue uncertainty, but poorly calibrated tariffs may create excessive costs, overbuilding, or windfall returns. A feed-in premium adds a payment to a market price and therefore exposes producers to some market risk. Competitive auctions procure renewable capacity or energy through bids. They can reveal prices and reduce procurement cost, but aggressive bidding may produce underdevelopment, renegotiation, or poor project quality. Auction design must specify site responsibility, grid connection, indexation, bid bonds, delivery milestones, penalties, curtailment treatment, and termination rights. The lowest bid is not necessarily the lowest system cost or the most credible offer. Corporate power-purchase agreements allow a company to buy renewable electricity or its environmental attributes under a long-term contract. Physical PPAs involve delivery through the grid or a dedicated connection; virtual or financial PPAs settle differences between a contracted strike price and a market price. PPAs can support investment, but parties must examine volume risk, basis risk, imbalance charges, credit quality, termination, change in law, and certificate ownership. Merchant projects sell at market prices without a fixed long-term offtake. They may benefit from high prices but face substantial price volatility, capture-price decline, congestion, and curtailment risk. Hybrid projects combining renewable generation, storage, and flexible loads can diversify revenue through energy, capacity, ancillary-service, and certificate markets. Environmental Attributes, Carbon Markets and Renewable CertificatesRenewable-energy projects may generate attributes separate from physical electricity. A renewable-energy certificate represents a defined environmental attribute associated with renewable generation, subject to the rules of the relevant tracking system. Certificates can be sold bundled with electricity or separately. The contract must state who owns, retires, reports, and bears the risk of invalidation or double counting. Carbon credits represent quantified greenhouse-gas reductions, removals, or avoided emissions under an approved methodology. Their credibility depends on additionality, accurate baselines, monitoring, reporting, verification, permanence where relevant, leakage control, and avoidance of double claiming. Renewable electricity should not automatically be assumed to produce a credible carbon credit; the applicable market rules and baseline must be examined. Additionality asks whether the claimed environmental benefit would occur without the incentive. Double counting can occur when the same attribute is sold to multiple buyers, counted in both a national inventory and a private claim without appropriate accounting, or represented simultaneously as a renewable certificate and an incompatible carbon reduction. Transparent registries, retirement records, chain-of-custody controls, and precise claims are essential. Procurement, Finance and Contract ArchitectureProcurement strategy should reflect technology maturity, supply-chain conditions, quality requirements, and the developer’s capability. Engineering, procurement, and construction contracts allocate design, performance, schedule, warranty, interface, and commissioning responsibilities. A turnkey contract may simplify coordination but can carry a price premium and obscure owner responsibilities. Multi-contract strategies may reduce cost but increase interface risk. Important contract provisions include liquidated damages for delay and underperformance, performance testing, availability guarantees, force majeure, change in law, defects, warranties, spare parts, cybersecurity, insurance, dispute resolution, and termination. Liquidated damages should be a genuine pre-estimate of loss rather than an unenforceable penalty, subject to applicable law. Project finance relies primarily on project cash flows rather than the sponsors’ balance sheets. Lenders examine the bankability of the resource assessment, offtake agreement, permits, EPC contract, operations contract, insurance, and reserve accounts. Risk allocation should place each risk with the party best able to control or price it. Transferring every risk to a contractor does not eliminate risk; it may increase price or create disputes. Common financial risks include construction-cost escalation, interest-rate changes, currency mismatch, refinancing, offtaker default, resource underperformance, grid curtailment, political intervention, and equipment failure. Hedging, guarantees, indexed tariffs, political-risk insurance, diversified suppliers, and reserve accounts can reduce exposure, although each introduces cost or contractual complexity. Standards, Safety and Responsible GovernanceStandards provide common expectations for design, testing, quality, interoperability, environmental management, and worker protection. Depending on the technology and jurisdiction, relevant standards may address photovoltaic modules and inverters, wind-turbine design, electrical installations, grid interconnection, occupational health and safety, environmental management, quality management, and information security. Standards do not replace engineering judgement or legal compliance; they support repeatable and auditable practice. Renewable projects contain serious hazards: electrical shock and arc flash, work at height, lifting operations, rotating machinery, confined spaces, high voltage, fire, battery thermal runaway, extreme weather, construction traffic, and chemical exposure. A robust safety system includes hazard identification, risk assessment, permit-to-work controls, lockout/tagout, competency verification, emergency response, contractor management, incident reporting, and learning from near misses. Governance should define decision rights, delegated authority, independent assurance, conflict-of-interest controls, records management, whistle-blower protection, and escalation routes. Ethical governance rejects bribery, undisclosed conflicts, manipulation of resource data, misleading community claims, labour exploitation, and concealment of safety incidents. Engineers have a professional duty to communicate uncertainty rather than present a preferred investment outcome as established fact. Social Justice and Distribution of BenefitsThe energy transition can reproduce inequality if benefits and burdens are distributed unfairly. Rural communities may bear land-use and ecological impacts while urban consumers and investors receive most benefits. A justice-oriented project considers distributive justice, procedural justice, recognition of affected identities and rights, and intergenerational responsibility. Practical measures may include transparent compensation, shared ownership, community development funds, local procurement where viable, training, restoration of livelihoods, affordable access to energy, and participation in monitoring. Benefit sharing should be designed with communities rather than announced after agreements are finalized. Local employment claims should distinguish temporary construction jobs from durable skilled employment. A just approach also considers workers in displaced fossil-fuel industries, consumers exposed to tariff increases, and households unable to finance distributed energy. Project managers should avoid token consultation, unequal information, coercive land negotiation, and claims that opposition reflects ignorance. Legitimate dissent may reveal design weaknesses or unrecognized impacts. Digital Tools, Analytics and Emerging PracticeDigital platforms support site screening, geospatial constraint mapping, document control, permit tracking, contract management, and stakeholder records. Digital twins and operational analytics can compare expected and actual performance, detect degradation, predict failures, and optimize storage dispatch. Machine-learning models may improve forecasting of solar irradiance, wind power, equipment faults, and market prices. These tools require disciplined data governance. Poor sensor calibration, biased training data, model drift, cyberattack, opaque algorithms, and false confidence can produce harmful decisions. Human review remains essential for safety, permitting, financial approval, and community commitments. Cybersecurity should include network segmentation, access control, patching, backup, incident response, supplier assurance, and secure remote access. Emerging project models include co-located solar and storage, renewable hydrogen, offshore wind, agrivoltaics, floating solar, repowering, virtual power plants, and energy communities. Their feasibility depends on market rules and system integration, not novelty alone. Repowering may increase output on an existing site but can reopen questions about visual impact, biodiversity, permits, and benefit agreements. Illustrative Case: A Wind–Storage Project Facing Development UncertaintyBackgroundA developer proposes a 180 MW onshore wind farm with a 60 MW/120 MWh battery in a semi-rural region. The site has strong wind resources and is near a transmission corridor. The project is intended to sell electricity through a competitive auction and to monetize renewable certificates. Situation and problemInitial screening reveals three difficulties. First, the nearest substation has limited hosting capacity and the transmission operator predicts curtailment during high-wind periods. Second, the land includes grazing routes used seasonally by several households, although formal title is held by a smaller number of owners. Third, the auction deadline encourages an aggressive bid, but turbine prices and interest rates are uncertain. AnalysisThe development team separates controllable from uncontrollable risks. Grid studies quantify curtailment under several expansion scenarios and evaluate whether the battery can shift output or provide grid services. Social mapping identifies formal owners, customary users, local government, grazing associations, and conservation groups. The financial model tests auction prices against equipment escalation, debt rates, delays, curtailment, and certificate revenue. The team finds that the lowest auction bid produces an acceptable return only if certificate revenue is counted twice—once in the project model and again in the corporate buyer’s claim. This is rejected as an integrity risk. A second scenario includes a conservative certificate price, a curtailment cap negotiated in the offtake contract, and a community benefit payment. It produces a lower equity return but remains financeable. Approach and solutionThe developer postpones the final bid until the grid operator provides a binding connection pathway. It proposes staged construction, a battery dispatch plan, and a contractual allocation of curtailment risk. A community agreement creates transparent payments linked to installed capacity, funds independent environmental monitoring, protects seasonal grazing access, and establishes a grievance panel. The project publishes a non-technical summary of noise, shadow flicker, traffic, land access, decommissioning, and emergency procedures. Procurement documents require verified turbine performance, worker-safety controls, cybersecurity provisions, and supply-chain labour standards. The financial close condition includes evidence of certificate retirement rules and an independent review of the resource assessment. OutcomeThe project does not win the first auction because its bid is above the lowest offer. However, it avoids committing capital to an underpriced project with unresolved grid and social risks. In a later procurement round, the improved connection terms and revised battery revenue model support a bankable bid. The case illustrates that disciplined non-participation can be a successful development decision. Learning pointsThe case demonstrates that resource quality does not guarantee feasibility; grid capacity, social legitimacy, revenue integrity, and realistic risk pricing are equally important. It also shows why certificates must be treated as contractual and accounting attributes, not as automatic additional revenue. Finally, governance gates can protect both investors and affected communities from premature commitment. Common Failure Modes and Best PracticesFrequent mistakes include using short-term resource measurements without uncertainty analysis, assuming grid capacity from geographic proximity, treating permits as administrative rather than technical conditions, accepting unrealistic auction bids, ignoring decommissioning, and relying on informal promises to communities. Other failures arise when environmental and social studies begin after the design is fixed, or when responsibility for interfaces is unclear between the owner, EPC contractor, operator, and grid company. Good practice is to maintain a live risk register with owners, triggers, mitigation, residual exposure, and escalation thresholds. Independent technical, legal, environmental, and financial reviews should occur before major gates. Assumptions must be version-controlled, auditable, and clearly distinguished from verified data. Contracts should align with the actual risk model, and community commitments should be budgeted, monitored, and reported. A responsible project also plans its end of life from the beginning. Decommissioning, recycling, land restoration, battery replacement, financial security, and transfer of liability should be addressed in permits and contracts. The project’s success criteria should include safety, compliance, performance, financial resilience, stakeholder trust, and environmental outcomes—not merely installed megawatts. Current Strategic DirectionsPolicy is increasingly shifting from technology-specific support toward competitive, system-oriented procurement. Auctions are being redesigned to recognize delivery quality, local value, grid readiness, resilience, and non-price criteria. Storage and hybrid projects are gaining importance as markets seek flexibility rather than energy volume alone. Corporate buyers are demanding more credible claims about additionality, temporal matching, and geographic matching of renewable electricity. This may lead to more sophisticated certificate markets and greater scrutiny of environmental claims. Supply-chain due diligence is also expanding to include critical minerals, labour rights, traceability, and geopolitical concentration. Climate adaptation is becoming a core development requirement. Wind, solar, hydro, and transmission assets must be assessed against changing heat, flooding, drought, wildfire, storms, and water availability. A project designed only for historical conditions may have an attractive initial model but poor lifetime resilience. Chapter SummaryRenewable-energy project development is an integrated process linking resource assessment, siting, grid access, permits, finance, contracts, markets, environmental performance, and social legitimacy. Feasibility should be evaluated through staged decision gates and probabilistic technical and financial analysis. Tariffs, auctions, PPAs, and merchant arrangements distribute market and delivery risks differently; contract design must make those allocations explicit. Renewable certificates and carbon credits require clear ownership, credible accounting, additionality, verification, and protection against double counting. Standards support quality and safety, while governance systems provide accountability, ethical conduct, and independent assurance. Stakeholder engagement and social justice are substantive elements of project viability, not public-relations additions. Digital tools can improve screening, forecasting, monitoring, and control, but require cybersecurity, data quality, and human oversight. The most responsible project is one that remains technically reliable, financially resilient, legally compliant, socially legitimate, and environmentally credible throughout its life cycle. Key TermsAuction: A competitive procurement process in which developers bid to supply renewable capacity or electricity under specified conditions. Bankability: The degree to which a project’s risks, contracts, permits, and cash flows are acceptable to lenders and investors. Carbon credit: A tradable unit representing a verified greenhouse-gas reduction, removal, or avoided emission under defined rules. Capture price: The average market price received by a generating technology, weighted by when it produces electricity. Curtailment: The reduction of available generation because of grid constraints, market conditions, or system security requirements. Environmental attribute: A non-energy characteristic of electricity, such as renewable origin or emissions benefit, that may be separately tracked. Financial close: The stage at which financing agreements are executed and conditions for funding are satisfied. Feed-in tariff: An administratively determined price paid for eligible renewable electricity over a specified period. Grid hosting capacity: The amount and type of additional generation that a network can accommodate without unacceptable technical effects. Levelized cost of electricity: The discounted average cost of producing electricity over an asset’s lifetime under stated assumptions. Merchant project: A project whose revenue is substantially exposed to market electricity prices rather than a fixed long-term offtake price. P50/P90: Probabilistic energy-yield estimates indicating central and conservative production expectations. Power-purchase agreement: A contract defining the sale and purchase of electricity and related attributes over an agreed period. Project finance: Financing based primarily on the projected cash flows and assets of the project rather than the sponsors’ general balance sheets. Renewable-energy certificate: A tracked unit representing specified renewable electricity attributes under an applicable registry system. Social licence to operate: Continuing societal acceptance of a project based on trust, legitimacy, fairness, and conduct. Stakeholder engagement: Structured interaction with people and organizations affected by or interested in a project. Additionality: The condition that a claimed environmental benefit would not have occurred without the relevant project or incentive. Review QuestionsShort Answer Questions1. Why should renewable project development use investment gates rather than a purely linear process? 2. Distinguish between P50 and P90 energy-yield estimates. 3. What is the principal difference between a feed-in tariff and a competitive auction? 4. Why can a renewable certificate not automatically be treated as a carbon credit? 5. Identify four hazards requiring control in renewable-energy construction or operation. Long Answer Questions1. Explain how technical, grid, environmental, social, and financial feasibility interact in renewable project development. 2. Compare auction procurement, corporate PPAs, and merchant-market development in terms of revenue certainty and risk allocation. 3. Discuss the role of project-finance contracts in allocating construction, performance, resource, grid, and offtaker risks. 4. Explain how social justice and stakeholder engagement can influence project design, cost, schedule, and legitimacy. 5. Describe a governance framework for ensuring ethical conduct, safety, compliance, and accountability throughout a project life cycle. Analytical / Application Questions1. A solar project has excellent irradiation but requires a costly transmission upgrade and faces seasonal curtailment. Develop a decision framework for determining whether it should proceed. 2. An auction bid appears financially attractive only when certificate revenue is assumed to be sold to two different claimants. Identify the governance and accounting problems and propose corrective actions. 3. Design a stakeholder-engagement and benefit-sharing strategy for a wind project affecting titled landowners, customary grazing users, local authorities, and conservation groups. 22. Multiple Choice Questions with AnswersQuestion 1Which decision gate is most directly associated with executable contracts, approved financing, and satisfactory risk allocation? A. Opportunity screening B. Pre-feasibility C. Financial close D. Operational review Correct Answer: C. Financial close Question 2Why is P90 energy yield commonly relevant to lenders? A. It represents the project’s maximum possible generation B. It provides a conservative production basis for debt sizing C. It excludes equipment degradation entirely D. It guarantees the tariff received by the project Correct Answer: B. It provides a conservative production basis for debt sizing Question 3A project located near a transmission line may still face poor grid feasibility because of inadequate: A. Module warranty B. Short-circuit capacity or hosting capacity C. Community-development funding D. Certificate retirement Correct Answer: B. Short-circuit capacity or hosting capacity Question 4Which feature is most characteristic of a competitive renewable-energy auction? A. An administratively fixed price offered to every eligible generator B. Bids submitted by developers under specified delivery conditions C. Complete insulation from construction and market risks D. Automatic ownership of all environmental attributes by the government Correct Answer: B. Bids submitted by developers under specified delivery conditions Question 5In a power-purchase agreement, certificate ownership should be specified primarily to prevent: A. Wind turbulence B. Double counting of environmental claims C. Transformer overheating D. Land degradation Correct Answer: B. Double counting of environmental claims Question 6Which statement best describes additionality in carbon-market accounting? A. The project produces more electricity than its rated capacity B. The environmental benefit would not have occurred without the relevant incentive or project C. The project uses only domestically manufactured equipment D. The project has a tariff higher than its levelized cost Correct Answer: B. The environmental benefit would not have occurred without the relevant incentive or project Question 7Which approach best reflects responsible stakeholder engagement? A. Consulting communities only after the design is final B. Providing only benefits information to avoid opposition C. Identifying affected groups, disclosing impacts, and maintaining a grievance mechanism D. Treating formal landowners as the only relevant stakeholders Correct Answer: C. Identifying affected groups, disclosing impacts, and maintaining a grievance mechanism Question 8A battery project is exposed to thermal runaway risk. Which control is most appropriate? A. Removing all performance guarantees B. Combining hazard assessment, monitoring, emergency response, and trained personnel C. Relying only on the project’s feed-in tariff D. Avoiding independent safety review Correct Answer: B. Combining hazard assessment, monitoring, emergency response, and trained personnel Question 9Why may the lowest auction bid not represent the lowest system cost? A. It may ignore grid, balancing, curtailment, or delivery risks B. It always includes excessive community benefits C. It necessarily uses conservative energy estimates D. It cannot be compared with any other bid Correct Answer: A. It may ignore grid, balancing, curtailment, or delivery risks Question 10Which principle best supports allocation of project risks in contracts? A. Assign every risk to the contractor regardless of control B. Assign each risk to the party best able to control or price it C. Leave major risks undefined to preserve flexibility D. Transfer all social risks to local government Correct Answer: B. Assign each risk to the party best able to control or price it
|