Market Analysis and Financial FeasibilityIntroductionReal estate development is an investment decision made under uncertainty. Before land is acquired, financing is arranged, or construction begins, the developer must establish whether a project is demanded by the market, legally permissible, physically achievable, financially profitable, and capable of producing an acceptable risk-adjusted return. Market analysis and financial feasibility therefore connect urban economics, property valuation, development management, and project finance. Market analysis identifies the likely users or buyers, the depth of demand, competing supply, achievable rents or prices, absorption speed, vacancy, and market risks. Financial feasibility translates those findings into a development budget, cash-flow forecast, funding requirement, profitability analysis, residual land value, and investment decision. The two activities are interdependent: an optimistic rent assumption can inflate land value, while an unrealistic absorption assumption can conceal liquidity risk. A feasibility study is not a prediction of the future. It is a structured decision model based on explicit assumptions, evidence, and sensitivity analysis. Its professional value depends less on the sophistication of its spreadsheet than on the quality, independence, and traceability of the assumptions used. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Explain the relationship between demand, supply, vacancy, absorption, rents, and prices.
- Define a market area and conduct a structured real estate market analysis.
- Evaluate alternative uses using the highest-and-best-use framework.
- Prepare a development cash-flow model and distinguish costs, revenues, financing flows, and returns.
- Calculate residual land value, development profit, yield on cost, and feasibility thresholds.
- Interpret sensitivity, scenario, and break-even analyses.
- Identify limitations, ethical risks, and governance requirements in feasibility studies.
1. The Logic of Market FeasibilityA market is feasible when sufficient users or purchasers are willing and able to transact at terms that support the proposed project. This involves more than proving that population or employment is growing. A project may fail despite strong aggregate growth if the product is poorly located, unaffordable, mistimed, or directly exposed to excessive competing supply. The principal analytical questions are: - Who are the intended occupants or purchasers?
- What is the relevant geographic market area?
- What product characteristics do they require?
- How much existing and future stock serves that market?
- At what rents, prices, incentives, and operating costs do transactions occur?
- How quickly can the proposed stock be absorbed?
- What alternative use would produce the greatest value consistent with legal, physical, financial, and market constraints?
1.1 Market area and segmentationThe market area is the geographic territory from which a project is likely to draw occupants or buyers. It should not be defined solely by administrative boundaries. Travel time, transport networks, employment clusters, school catchments, consumer preferences, and competing projects often provide better boundaries. Segmentation divides the market into groups with similar needs and willingness to pay. Examples include: | Property sector | Possible segments | Typical demand indicators |
|---|
| Residential | Students, first-time buyers, families, seniors | Household formation, income, mortgage access, rents | | Office | Technology firms, government, professional services | Employment, business formation, floor-space per worker | | Retail | Convenience, comparison, destination, food and beverage | Footfall, spending, catchment income, accessibility | | Industrial/logistics | Distribution, manufacturing, last-mile delivery | Trade flows, inventory demand, road access, rents | | Hospitality | Business, leisure, extended stay | Visitors, room nights, occupancy, average daily rate |
A market study should distinguish effective demand from theoretical demand. Effective demand is supported by purchasing power, financing access, and willingness to transact. A large population does not automatically create demand for a luxury apartment project if household incomes cannot support the price. 1.2 Demand estimationDemand can be estimated using several complementary approaches: - Trend analysis: extrapolates historical population, employment, household, or transaction trends.
- Ratio analysis: relates property demand to a measurable driver, such as office space per employee or beds per student.
- Capture-rate analysis: estimates the share of forecast market demand that the project can attract.
- Comparable-project analysis: observes leasing, sales, pricing, and absorption in similar developments.
- Economic-base analysis: links property demand to employment, income, tourism, trade, or institutional activity.
- Survey and stated-preference analysis: tests intended behaviour, while recognising that stated intentions may differ from actual transactions.
A simple stock-demand relationship is: Nt = Ht × rt where Nt is total demand for units or floor area in period t, Ht is the relevant number of households, employees, visitors, or other demand drivers, and rt is the required space or units per driver. The relationship is useful only when the ratio is stable or when its expected change is explicitly modelled. Incremental demand over a period may be expressed as: ΔD = D1 − D0 + R − S where D0 and D1 are demand at the beginning and end of the period, R is replacement or obsolescence demand, and S represents stock released from other uses or supplied through substitution. In practice, analysts must avoid double counting household growth, replacement demand, and migration. 1.3 Supply and pipeline analysisSupply analysis includes existing stock, vacant stock, committed projects, projects under construction, and plausible but uncommitted proposals. Each category has a different probability and timing of delivery. A planning approval does not guarantee completion; financing, construction, and market conditions may delay or cancel a project. A supply schedule should record project location, size, tenure, quality, completion date, asking and achieved rents or prices, incentives, occupancy, developer, and construction status. Direct competitors should be distinguished from substitutes. For example, a suburban townhouse project may compete with apartments, existing homes, and rental properties even though their physical forms differ. A basic vacancy measure is: Vt = Ut ÷ Tt × 100 where Vt is the vacancy rate in period t, Ut is vacant stock, and Tt is total stock. Units must be consistent: vacant square metres divided by total square metres, or vacant units divided by total units. The effective vacancy rate should distinguish structural vacancy, normal frictional vacancy, and temporarily unavailable stock. A newly completed building with units not yet released for sale should not necessarily be treated as equivalent to permanently obsolete stock. 1.4 AbsorptionAbsorption is the rate at which available units or floor area are leased or sold. A gross absorption rate measures transactions without adjusting for competing deliveries. A net absorption measure considers the change in occupied stock: NAt = Ot − Ot−1 where NAt is net absorption and Ot is occupied stock at time t. If occupied stock rises from 10,000 to 10,600 square metres, net absorption is 600 square metres, regardless of the amount of new supply delivered. For a project with Q saleable units and expected monthly absorption a, a simplified sell-out period is: Ts = Q ÷ a This is a planning approximation. It assumes a constant absorption rate, ignores staging, cancellations, seasonality, price changes, and competition, and should not be used as a substitute for a period-by-period forecast. Absorption is often non-linear. Early sales may be accelerated by launch discounts, while later sales may slow as the remaining inventory becomes less attractive. A credible model therefore uses phases, such as pre-launch, launch, construction, completion, and stabilisation. 1.5 Rents, prices, incentives, and effective incomeAsking rent is not necessarily economic rent. Free-rent periods, fit-out contributions, commissions, escalation clauses, parking charges, service charges, and renewal probability affect effective income. A simplified annual effective gross income formula is: EGI = PGI × (1 − v) + OI where EGI is effective gross income, PGI is potential gross income at fully occupied contractual rent, v is the combined vacancy and collection-loss rate expressed as a decimal, and OI is other operating income. This formula assumes vacancy losses and collection losses can reasonably be represented by one rate and that other income is not already included in PGI. For a lease offering one month free on a twelve-month term, ignoring other incentives, the effective rent is: Re = Rc × 11 ÷ 12 where Re is effective monthly rent and Rc is contractual monthly rent. The calculation must be adjusted if the free period occurs during a different term or if the tenant receives additional concessions. 1.6 Price and rent analysisComparable evidence should be adjusted for location, size, age, quality, tenure, floor level, view, parking, timing, and transaction conditions. Median values may be more informative than averages where a few high-value transactions distort the sample. Analysts should separate asking data from completed transactions and disclose the date and source of each observation. A useful rent-to-price indicator is the gross rental yield: yg = Annual contractual rent ÷ Purchase price × 100 Gross yield is not a net investment return because it ignores vacancy, operating expenses, capital expenditure, taxes, financing, and transaction costs. It is mainly a market comparison indicator. 2. Highest and Best UseHighest and best use is the reasonably probable and legal use of land that is physically possible, appropriately supported, financially feasible, and results in the highest value. The tests are cumulative: a use that fails any test cannot qualify. - Legally permissible: zoning, planning permissions, environmental restrictions, title conditions, heritage controls, and building regulations are considered.
- Physically possible: site area, shape, access, soil, topography, utilities, flood risk, and construction technology are assessed.
- Financially feasible: revenues must support all development, operating, financing, and risk costs.
- Maximally productive: among qualifying uses, the selected use provides the highest land value or investment value.
Highest-and-best-use analysis is not simply a search for the largest building. Density may increase revenue but also increase construction cost, parking requirements, infrastructure contributions, marketing risk, and delivery time. Alternative uses should be tested using consistent assumptions and a common valuation date. A practical alternative-use matrix may include residential apartments, build-to-rent, offices, retail, hotel, logistics, or a mixed-use scheme. The analyst should show why rejected uses fail or produce lower value rather than selecting the preferred use first and rationalising it afterward. 3. From Market Evidence to a Financial ModelA feasibility model normally contains five linked schedules: - Development programme: acquisition, approvals, design, construction, marketing, completion, lease-up or sell-out.
- Revenue schedule: units, floor area, rents or prices, timing, incentives, vacancy, escalation, and other income.
- Cost schedule: land, construction, professional fees, statutory charges, marketing, contingency, operating costs, and exit costs.
- Financing schedule: equity, debt drawdowns, interest, fees, repayment, and refinancing.
- Return and sensitivity schedule: profit, yield on cost, present value, internal rate of return, break-even variables, and scenarios.
The model should use nominal or real terms consistently. A nominal model includes expected inflation in both revenues and costs and uses a nominal discount rate. A real model excludes general inflation and uses a real discount rate. Mixing the two produces biased results. 3.1 Development costsTypical costs include: - land acquisition price and transaction taxes;
- demolition, remediation, and enabling works;
- construction and infrastructure;
- architecture, engineering, project management, and legal fees;
- planning contributions and utility charges;
- marketing, sales commissions, and leasing costs;
- finance interest, arrangement fees, and monitoring fees;
- insurance, rates, security, and project overheads;
- contingency for identified cost uncertainty; and
- applicable taxes and exit costs.
Contingency should not be used to conceal poorly estimated costs. It should be linked to the maturity of design, procurement certainty, market volatility, and identified risks. A construction contingency and a market contingency are conceptually different. 3.2 Revenue and net operating incomeFor an income-producing project, net operating income is generally: NOI = EGI − OE where NOI is net operating income, EGI is effective gross income, and OE is operating expenditure. Debt service, income tax, depreciation, and capital expenditure are not normally included in NOI, although reserves for recurring capital items may be presented separately depending on the valuation convention. For a sale project, revenue is the sum of expected sale proceeds by period. Sale proceeds should reflect realistic net prices after discounts, incentives, commissions, taxes, and disposal costs where the analysis is intended to measure net development proceeds. 4. Core Feasibility Measures4.1 Development profitA simple unlevered development profit is: P = R − C where P is development profit, R is total development revenue, and C is total development cost including land, but excluding financing if the objective is an unlevered comparison. If financing costs are included, the analyst must label the result clearly as profit after finance costs. Profit margin may be expressed in different ways: Profit margin on revenue = P ÷ R × 100 Profit on cost = P ÷ C × 100 These are not interchangeable. A project with revenue of 15 million and total cost of 12 million has profit of 3 million, a margin on revenue of 20%, and profit on cost of 25%. 4.2 Yield on costFor an income-producing development, yield on cost is: YOC = Stabilised NOI ÷ Total development cost × 100 Total development cost should be defined consistently and generally includes land, construction, professional costs, financing costs if relevant to the convention, and other costs required to create the completed asset. Stabilised NOI should represent sustainable income after normal vacancy and operating expenses, not a temporary lease-up peak. Yield on cost is useful when compared with the market yield or capitalisation rate for a comparable completed asset. A positive development spread can be expressed as: Spread = YOC − Market capitalisation rate The spread is only meaningful if NOI definitions, timing, asset quality, and risk are comparable. A high spread may indicate genuine value creation, but it may also reflect optimistic rents, understated costs, or an inappropriate market yield. 4.3 Residual land valueResidual land valuation estimates the maximum amount that can be paid for land while meeting a specified return requirement. In its simplest form: RLV = GDV − D − Pr where RLV is residual land value, GDV is gross development value, D is all development cost excluding land, and Pr is the required developer profit. If costs and revenues occur over time, a discounted cash-flow approach is preferable because the simple residual ignores timing. For a completed income-producing property valued by capitalisation: GDV = Stabilised NOI ÷ ym where ym is the market capitalisation rate expressed as a decimal. This relationship assumes a sustainable NOI, a suitable comparable yield, and a property whose income characteristics justify capitalisation. 4.4 Discounted cash flow and feasibility thresholdThe net present value of an unlevered project is: NPV = ∑t=0T CFt ÷ (1 + k)t where CFt is net project cash flow in period t, k is the periodic discount rate, and T is the final period. Cash flows must be measured at the same periodic frequency as the discount rate. A project is financially acceptable under the selected assumptions when NPV ≥ 0, although investment committees may impose additional minimum returns and risk criteria. The internal rate of return is the discount rate r that makes NPV equal to zero: 0 = ∑t=0T CFt ÷ (1 + r)t IRR can be misleading when cash flows change sign more than once, because multiple IRRs may exist. It should therefore be accompanied by NPV, a stated discount rate, and an explanation of the cash-flow pattern. A feasibility threshold is the value of a key assumption at which the project just meets a specified criterion. For example, the break-even sale price under a simple undiscounted model is: Break-even average price = (C + Pr) ÷ Q where C is total cost excluding revenue, Pr is required profit, and Q is the number of saleable units. For a time-phased project, the threshold must be solved using the full cash-flow model because timing affects NPV. 5. Worked Example: Illustrative Residential DevelopmentThe following is an illustrative example, not a market forecast. A developer is considering a 40-unit apartment project. The expected average net sale price is 320,000 monetary units per unit. Total revenue is therefore: R = 40 × 320,000 = 12,800,000 The estimated costs are: | Cost item | Amount |
|---|
| Land | 2,400,000 | | Construction | 6,000,000 | | Professional and statutory costs | 900,000 | | Marketing and sales | 300,000 | | Finance and arrangement costs | 500,000 | | Contingency | 400,000 | | Total cost | 10,500,000 |
Development profit is: P = 12,800,000 − 10,500,000 = 2,300,000 Profit on cost is: P ÷ C × 100 = 2,300,000 ÷ 10,500,000 × 100 ≈ 21.90% Profit margin on revenue is: P ÷ R × 100 = 2,300,000 ÷ 12,800,000 × 100 ≈ 17.97% If the developer requires a profit of 20% of total cost, the maximum total cost consistent with revenue is: Maximum cost = R ÷ 1.20 = 12,800,000 ÷ 1.20 = 10,666,667 The project’s estimated cost of 10,500,000 is below this threshold by approximately 166,667. If all non-land costs are fixed at 8,100,000 and the required profit is 20% of total cost, the maximum land value satisfies: 12,800,000 − (8,100,000 + L) = 0.20 × (8,100,000 + L) Solving: 12,800,000 − 8,100,000 − L = 1,620,000 + 0.20L 3,080,000 = 1.20L L = 2,566,667 Thus, under the stated undiscounted assumptions, the maximum land price is approximately 2,566,667. The proposed land price of 2,400,000 leaves a nominal feasibility margin of approximately 166,667. Because the margin is small, the project is highly sensitive to sale prices, construction costs, delays, and absorption. Suppose instead that the completed project will be retained as a rental asset. Stabilised NOI is estimated at 900,000 per year and the market capitalisation rate is 6.5%. Gross development value is: GDV = 900,000 ÷ 0.065 ≈ 13,846,154 If development costs excluding land are 8,100,000 and the required profit is 20% of total cost, the residual land equation is: 13,846,154 − (8,100,000 + L) = 0.20 × (8,100,000 + L) Therefore: L = (13,846,154 − 1.20 × 8,100,000) ÷ 1.20 ≈ 3,438,462 This result differs substantially from the sale-case residual because the use, income assumptions, valuation method, and exit risk differ. It does not prove that the rental use is superior. The analyst must also assess lease-up, operating expenses, financing, holding period, tax, management capability, and the reliability of the 6.5% capitalisation rate. 6. Sensitivity, Scenario, and Risk AnalysisA base case is not a forecast with certainty; it is a reference case. Sensitivity analysis changes one variable at a time to show exposure. For example, sale prices may be reduced by 5% and 10%, construction costs increased by 5% and 10%, or completion delayed by six and twelve months. Scenario analysis changes several related assumptions simultaneously. A downside scenario might combine lower prices, slower absorption, higher interest rates, and delayed completion. An upside scenario should be equally plausible rather than promotional. A useful sensitivity measure is the percentage change in an output divided by the percentage change in an input: Elasticity = Percentage change in output ÷ Percentage change in input For instance, if a 5% fall in sale prices produces a 25% fall in profit, the profit elasticity with respect to price is −5, subject to the model’s assumptions. This is not a universal property of the market; it is a result of that model. Monte Carlo simulation can assign probability distributions to uncertain inputs and produce a distribution of NPV, profit, or completion date. It is useful when correlations are modelled properly. A simulation with arbitrary independent inputs may create a false appearance of precision. Correlated risks, such as inflation increasing both construction costs and rents, require explicit treatment. 7. Illustrative Case: Riverside Mixed-Use SiteBackgroundThis illustrative case concerns a 1.8-hectare brownfield site near a regional rail station. The site is legally capable of supporting apartments, offices, or a mixed-use scheme, subject to planning approval and remediation. The developer is deciding whether to sell the land, develop apartments for sale, or create a build-to-rent asset. ProblemThe initial concept proposed 220 apartments at premium prices. However, market evidence showed rising competing supply, elevated mortgage costs, and slower sales in the premium segment. A competing office project had been delayed, while demand for smaller rental units remained comparatively resilient. AnalysisThe team defined a 20-minute travel-time market area and segmented demand into owner-occupiers, private renters, and small businesses. It collected achieved transaction data rather than relying only on asking prices, inspected competing projects, and identified approximately 900 units in the pipeline. The project’s initial absorption assumption of 18 units per month implied a sell-out period of about 12.2 months, but comparable projects suggested 10 to 14 units per month after launch incentives. Three alternatives were modelled: | Alternative | Key revenue basis | Principal risk |
|---|
| Premium apartments for sale | High unit prices | Affordability and slow absorption | | Mid-market apartments for sale | Moderate prices | Margin compression | | Build-to-rent | Stabilised NOI and exit yield | Lease-up, operating and valuation risk |
The premium scheme generated the highest headline revenue but failed the required NPV in a downside scenario. The mid-market scheme produced a lower nominal profit but stronger absorption and a wider range of feasible sale prices. The build-to-rent scheme produced a competitive yield on cost, but its residual land value was highly sensitive to the exit capitalisation rate. A 0.50 percentage-point increase in the exit yield materially reduced gross development value. Approach and solutionThe developer adopted a staged mid-market scheme with a smaller first phase, pre-sales before full construction commitment, and design flexibility to convert part of the later phase to rental use. The land offer was tied to planning approval and included a price adjustment mechanism if remediation costs exceeded an agreed threshold. OutcomeThe selected plan did not maximise theoretical revenue. It improved feasibility by reducing peak funding, matching product to effective demand, limiting exposure to premium pricing, and preserving an alternative exit strategy. The investment committee approved the project subject to minimum pre-sales, a construction-cost cap, and updated market evidence at financial close. Learning points- Highest revenue is not necessarily highest value.
- Absorption assumptions can be as important as price assumptions.
- Flexibility has economic value when demand is uncertain.
- Residual land value must be tested against downside scenarios.
- Conditions precedent and staged commitments can reduce irreversible risk.
8. Governance, Ethics, and Professional PracticeFeasibility analysis can influence land prices, public infrastructure decisions, lender exposure, and investor wealth. Analysts should disclose sources, dates, adjustment methods, assumptions, conflicts of interest, and limitations. Selective use of favourable comparables, unsupported growth assumptions, and omission of competing supply are professional failures even when the spreadsheet is mathematically correct. Regulatory issues may include planning policy, environmental assessment, affordable-housing requirements, accessibility, fire and life safety, taxation, anti-money-laundering rules, consumer protection, and disclosure obligations. Financial feasibility must not be used to justify unlawful or unsafe development. Artificial intelligence and automated analytics can assist with comparable selection, geospatial analysis, document review, scenario generation, and anomaly detection. They do not remove the need for professional judgement. Models may reproduce biased historical data, confuse asking prices with achieved prices, or generate unsupported assumptions. AI-assisted outputs should be traceable, validated against primary evidence, and reviewed by a qualified analyst. 9. Best-Practice ChecklistA robust feasibility study should: - define the market area and product segment explicitly;
- distinguish effective demand from population or employment totals;
- separate existing, committed, and speculative supply;
- use achieved rents and prices where available;
- model incentives, vacancy, operating costs, and absorption timing;
- identify legal, physical, environmental, and infrastructure constraints;
- test alternative uses before committing to a concept;
- distinguish nominal from real assumptions;
- reconcile the development programme with the cash-flow schedule;
- define whether profit and yield include finance costs;
- calculate residual land value using the required return;
- report NPV alongside IRR and simple profit measures;
- conduct sensitivity and integrated downside scenarios;
- document data sources, assumptions, and version control; and
- establish approval gates and conditions precedent before capital is committed.
Chapter SummaryMarket analysis and financial feasibility are integrated processes for deciding whether a real estate project should proceed, in what form, and at what land price. Demand analysis must consider effective purchasing or leasing capacity, segmentation, location, product fit, and the timing of transactions. Supply analysis must cover existing stock, vacancy, committed projects, competing uses, and the probability of delivery. Absorption, effective rents, incentives, and achieved prices are essential for converting market evidence into a realistic revenue schedule. Highest-and-best-use analysis tests legal permissibility, physical possibility, financial feasibility, and maximum productivity. A financial model then links programme, revenue, costs, financing, and returns. Development profit, profit on cost, profit margin, yield on cost, residual land value, NPV, IRR, and break-even thresholds answer different questions and must not be treated as interchangeable. Because development outcomes are uncertain, a credible feasibility study uses sensitivity analysis, integrated scenarios, transparent assumptions, and governance controls. The strongest project is not necessarily the one with the greatest theoretical revenue; it is the one whose market fit, risk, funding capacity, and return remain acceptable under credible adverse conditions. Key TermsMarket area: Geographic territory from which a project is likely to attract users or purchasers. Effective demand: Demand supported by willingness and ability to transact. Segmentation: Division of a market into groups with similar needs and behaviour. Supply pipeline: Existing, committed, under-construction, and proposed competing stock. Vacancy rate: Vacant stock expressed as a proportion of total stock. Absorption: Rate at which available property is leased or sold. Net absorption: Change in occupied stock over a specified period. Effective rent: Rent after concessions, incentives, and free-rent periods are considered. Gross development value: Value of the completed project before deducting development costs. Net operating income: Effective gross income less operating expenditure. Highest and best use: Legally permissible, physically possible, financially feasible, and maximally productive use. Development profit: Development revenue less defined development costs. Profit on cost: Profit divided by total development cost. Yield on cost: Stabilised NOI divided by total development cost. Residual land value: Maximum land value after deducting costs and required profit from development value. Capitalisation rate: Rate used to convert stabilised NOI into an indication of value. Net present value: Present value of project cash inflows and outflows at a specified discount rate. Internal rate of return: Discount rate that makes project NPV equal to zero. Sensitivity analysis: Examination of output changes caused by varying selected inputs. Feasibility threshold: Input value at which a project just meets a specified financial criterion. Review QuestionsShort Answer Questions- Distinguish effective demand from theoretical demand.
- Define net absorption and explain how it differs from gross absorption.
- State the four tests used in highest-and-best-use analysis.
- What is the difference between profit on cost and profit margin on revenue?
- Why should residual land value be tested using sensitivity analysis?
Long Answer Questions- Explain how market area definition, segmentation, demand, supply, vacancy, and absorption interact in a development feasibility study.
- Discuss the principal components of a real estate development cash-flow model and explain why timing matters.
- Compare development profit, yield on cost, NPV, and IRR as project evaluation measures.
- Explain the highest-and-best-use framework and discuss why the use with the greatest revenue may not create the greatest value.
- Critically evaluate the ethical, regulatory, and governance responsibilities of a feasibility analyst.
Analytical / Application Questions- A 60-unit project has an average net sale price of 280,000 monetary units per unit and total cost of 14,400,000. Calculate total revenue, development profit, and profit on cost. Interpret the result if the developer requires a minimum profit on cost of 20%.
- A rental project has stabilised NOI of 1,200,000 and total development cost of 18,000,000. Calculate yield on cost. Explain how a change in the market capitalisation rate could affect residual land value even if NOI remains unchanged.
- Design a downside scenario for a mixed-use development and explain how lower rents, slower absorption, higher construction costs, and delayed completion could affect NPV, funding requirements, and the development decision.
Multiple Choice Questions with AnswersQuestion 1Which condition is NOT one of the standard highest-and-best-use tests? A. Legally permissible B. Physically possible C. Financially feasible D. Politically popular Correct Answer: D. Politically popular Question 2A project has 50 units and expected absorption of 5 units per month. Using the simplified constant-rate assumption, the sell-out period is: A. 5 months B. 10 months C. 25 months D. 250 months Correct Answer: B. 10 months Question 3If vacant stock is 800 square metres and total stock is 10,000 square metres, the vacancy rate is: A. 0.8% B. 8% C. 12.5% D. 80% Correct Answer: B. 8% Question 4A project generates revenue of 15,000,000 and total cost of 12,000,000. Its profit on cost is: A. 20% B. 25% C. 30% D. 80% Correct Answer: B. 25% Question 5Which item is normally deducted from effective gross income to calculate NOI? A. Land acquisition price B. Debt principal repayment C. Operating expenditure D. Developer profit Correct Answer: C. Operating expenditure Question 6Residual land value is best described as: A. The historical price paid for the land B. The maximum land value after allowing for development costs and required profit C. The market rent divided by vacancy D. The construction cost divided by floor area Correct Answer: B. The maximum land value after allowing for development costs and required profit Question 7Yield on cost is calculated as: A. Total cost divided by revenue B. Stabilised NOI divided by total development cost C. Profit divided by saleable units D. Market value divided by vacancy Correct Answer: B. Stabilised NOI divided by total development cost Question 8If stabilised NOI is 900,000 and the market capitalisation rate is 6%, the indicated value is: A. 5,400,000 B. 15,000,000 C. 54,000,000 D. 150,000 Correct Answer: B. 15,000,000 Question 9The principal purpose of sensitivity analysis is to: A. Guarantee the project outcome B. Replace market research C. Show how changes in assumptions affect project results D. Eliminate the need for a discount rate Correct Answer: C. Show how changes in assumptions affect project results Question 10In a nominal cash-flow model, the analyst should generally use: A. Inflation-adjusted revenues with a real discount rate B. Uninflated revenues with a nominal discount rate C. Nominal revenues and costs with a nominal discount rate D. Only historical costs and no discount rate Correct Answer: C. Nominal revenues and costs with a nominal discount rate
|