Introduction

Quality initiatives require resources before their benefits become visible. A revised inspection system, mistake-proofing device, laboratory information system, supplier-development programme, or process-capability project may reduce defects and customer complaints, but management must still determine whether the investment creates economic value. Financial appraisal provides a disciplined method for comparing the resources committed with the costs avoided, revenues protected, productivity released, and risks accepted.

Quality costing and financial appraisal are related but not identical. Quality costing classifies the economic consequences of conformance and nonconformance, commonly as prevention, appraisal, internal failure, and external failure costs. Financial appraisal evaluates the timing, scale, uncertainty, and opportunity cost of cash flows associated with a quality investment. A project can reduce reported failure cost yet have a poor financial return if it requires excessive capital, creates large operating expenses, or delivers benefits too late. Conversely, an initiative may show a modest accounting saving but be strategically valuable because it protects regulatory approval or a critical customer relationship.

The central managerial question is therefore not simply, “Will quality improve?” It is: “Relative to the alternative of doing nothing or choosing another intervention, does the quality investment generate sufficient risk-adjusted economic value?”

Learning Objectives

After studying this chapter, the learner should be able to:

  1. Identify investment costs, recurring operating costs, and relevant quality benefits.
  2. Construct incremental cash-flow forecasts for quality initiatives.
  3. Calculate payback period, accounting return, ROI, net present value, internal rate of return, profitability index, total cost of ownership, and benefit–cost ratio.
  4. Select an appropriate appraisal method and explain its limitations.
  5. Evaluate a quality investment under uncertainty, taxation, inflation, residual value, and alternative scenarios.
  6. Present a financially defensible recommendation while preserving quality, safety, legal, and ethical requirements.

1. The Economic Logic of a Quality Investment

A quality investment changes the future stream of costs and benefits relative to a baseline. The baseline is not necessarily “zero expenditure”; it is the most realistic counterfactual, such as continuing the existing process, renewing an existing contract, or adopting a less capable alternative.

Important terminology includes:

  • Initial investment: Cash paid at or before project commencement for equipment, software, installation, validation, training, and implementation.
  • Incremental operating cost: Additional cash expenditure caused by the initiative, such as licences, calibration, maintenance, data storage, or specialist labour.
  • Avoided cost: A future cost that would otherwise occur, such as scrap, rework, warranty claims, sorting, expedited freight, or complaint handling.
  • Incremental benefit: An additional cash inflow or saving attributable to the project.
  • Relevant cash flow: A future, incremental, after-tax cash flow that changes because of the decision.
  • Sunk cost: A past cost that cannot be recovered and must not affect the choice between alternatives.
  • Opportunity cost: The value of the best alternative use of a resource.
  • Residual value: Cash received, or cost avoided, when an asset is sold, transferred, or retired at the end of the appraisal period.

A quality project should normally be assessed using incremental cash flows:

CFt = Bt − OCt − Tt + RVt − WCt

Here, CFt is incremental cash flow in period t, Bt is cash benefit or avoided cost, OCt is incremental operating cash cost, Tt is incremental tax paid, RVt is residual-value cash flow, and WCt is any increase in working capital. All terms must use the same currency and time period. If working capital is recovered at project end, the recovery is added in the final period.

The initial cash flow is usually negative:

CF0 = −I0 − WC0 + S0

where I0 is initial investment, WC0 is initial working capital, and S0 is any immediate subsidy or sale proceeds. The project’s incremental cash-flow series is therefore CF0, CF1, …, CFn.

Relevant quality benefits

Benefits may arise from several mechanisms:

Benefit categoryExamplesMeasurement caution
Internal failure reductionLess scrap, rework, retesting, downtimeUse resource consumption, not merely standard accounting allocations
External failure reductionFewer returns, warranty claims, penalties, complaintsInclude logistics and reputation only when credibly measurable
Capacity releaseMore saleable output from existing resourcesIt is a cash benefit only if capacity is sold or avoids expansion
ProductivityReduced inspection, correction, or administrative timeDistinguish paid hours eliminated from hours merely reassigned
Revenue protectionRetention of customers and contractsAttribute conservatively and test probability
Risk reductionLower probability of recall, noncompliance, or shutdownRequires expected-value and scenario analysis

A reduction in a reported cost is not automatically a cash saving. For example, reducing inspection labour may release employees to other productive work without reducing payroll. The immediate cash saving is then zero, although capacity value may exist.

2. Building the Investment Case

2.1 Define scope and the counterfactual

The appraisal begins with a project charter stating the process boundary, affected products, implementation date, expected life, baseline performance, and alternatives. Baseline quality data should cover adequate production volume and seasonal variation. Useful measures include defect opportunities, defects per unit, first-pass yield, rework hours, warranty cost per unit, complaint frequency, and process capability.

The analyst should compare:

  1. Continue the current process.
  2. Implement the proposed quality initiative.
  3. Consider credible alternatives, including a smaller pilot, outsourcing, or a different technology.

2.2 Estimate cost categories

The investment budget can include purchase price, design, integration, site preparation, cybersecurity, validation, training, commissioning, change management, and temporary dual running. Recurring costs may include preventive maintenance, calibration, software subscriptions, consumables, audits, and additional personnel.

Avoid double counting. If the project budget already includes implementation labour, that labour must not be deducted again as a benefit. Similarly, a reduction in warranty payments should not also be counted as a reduction in the same underlying failure cost unless the two are genuinely separate.

2.3 Estimate benefits from operational drivers

A defensible benefit model links quality outcomes to physical drivers. For example:

Annual ext{ avoided failure cost} = ΔQ × Cq

where ΔQ is the expected reduction in defective or failed units per year and Cq is the relevant cash cost per unit. If multiple failure categories exist, the total benefit is the sum across categories:

Bt = ∑j=1m ΔQjt Cjt + Rt + Pt

Here, j indexes benefit categories, Rt is incremental revenue or protected contribution margin, and Pt is other measurable benefit. The formula assumes categories are mutually exclusive or that overlap has been removed.

Revenue is not the same as profit. If additional sales result from improved quality, the relevant benefit is usually incremental contribution margin after variable costs, not total sales revenue. Fixed costs should be included only when they change because of the project.

2.4 Account for tax and depreciation

For a taxable organisation, tax affects cash flow. Depreciation is not itself a cash outflow, but it can create a tax shield. A simplified project cash-flow expression is:

CFt = (Bt − OCt)(1 − τ) + Dept τ + RVt − TaxRVt − WCt

where τ is the tax rate, Dept is depreciation, and TaxRVt is tax associated with disposal proceeds. This expression assumes benefits and operating costs are taxable, the organisation has sufficient taxable income to use the tax shield, and tax is paid in the same period. Actual tax rules may differ through capital allowances, loss carry-forwards, indirect taxes, and jurisdiction-specific treatment.

For a non-tax appraisal, omit tax terms consistently. Mixing pre-tax benefits with after-tax investment costs produces an invalid comparison.

3. Core Appraisal Measures

3.1 Payback period

The payback period is the time required for cumulative undiscounted cash flows to recover the initial investment. If annual cash flow is constant, the simple form is:

Payback = I0 ÷ CF

This form applies only when annual CF is positive and constant. With uneven cash flows, identify the last full year before recovery and interpolate:

Payback = k + (Unrecovered ext{ amount at end of year }k ÷ CFk+1)

Payback is easy to explain and useful for liquidity or risk screening. It ignores cash flows after recovery and, in its simple form, ignores the time value of money. A discounted payback replaces cash flows with discounted cash flows but still ignores later benefits.

3.2 Accounting rate of return

Accounting rate of return (ARR), also called return on investment in some organisations, is based on accounting profit rather than cash flow. A common definition is:

ARR = Average ext{ annual accounting profit} ÷ Average ext{ accounting investment} × 100

The denominator may be initial investment or average book value, so the organisation must state its policy. Accounting profit generally deducts depreciation and operating expenses but not the initial capital expenditure in the year of purchase. ARR is useful when managers are evaluated on accounting performance, but it is affected by depreciation conventions, accruals, and book-value definitions.

3.3 Simple ROI

A project-level simple ROI may be defined as:

ROI = (Total ext{ benefits} − Total ext{ project costs}) ÷ Total ext{ project costs} × 100

This is not a universally standard measure. Some organisations use average annual net benefit divided by initial investment; others use after-tax profit divided by invested capital. Therefore, the numerator, denominator, period, and treatment of depreciation must always be disclosed. ROI should not be presented as interchangeable with NPV or ARR.

3.4 Net present value

NPV recognises that a monetary unit received today is worth more than one received later. Given discount rate r:

NPV = ∑t=0n CFt ÷ (1 + r)t

Equivalently, because CF0 is normally negative:

NPV = −I0 + ∑t=1n CFt ÷ (1 + r)t

The discount rate should reflect the organisation’s opportunity cost of capital and, where appropriate, project risk. Cash flows and the rate must be expressed in consistent nominal or real terms. A positive NPV indicates that the project is expected to create value relative to the chosen discount rate and baseline; a negative NPV indicates value destruction under those assumptions.

3.5 Internal rate of return

IRR is the discount rate that makes NPV equal to zero:

0 = ∑t=0n CFt ÷ (1 + IRR)t

For conventional cash flows—one initial outflow followed by positive inflows—IRR can be compared with the hurdle rate. If cash flows change sign more than once, multiple IRRs may exist or no economically meaningful IRR may exist. In such cases, NPV should be the primary decision measure; modified IRR may be used if its reinvestment and finance assumptions are explicitly stated.

3.6 Profitability index

The profitability index (PI) measures present value created per unit of initial investment:

PI = Present ext{ value of future inflows} ÷ Initial ext{ investment}

For a project with only the initial outflow at time zero:

PI = (NPV + I0) ÷ I0

PI greater than 1 indicates positive NPV. PI is useful when capital is rationed, but ranking projects solely by PI can favour small projects and may conflict with the greatest total NPV objective.

3.7 Total cost of ownership

TCO captures the full cost over the asset or service life, not merely the purchase price:

TCO = Acquisition + Implementation + Operating + Maintenance + Disposal − Residual ext{ value}

For a time-discounted TCO, each cost is discounted to present value. TCO is especially important for software, inspection equipment, laboratory systems, and outsourced quality services, where licences, integration, training, cybersecurity, calibration, and decommissioning can exceed the initial price.

TCO is a cost measure, whereas NPV is a value measure. TCO should be combined with expected benefits and service performance rather than used as the sole selection criterion.

3.8 Benefit–cost ratio

The benefit–cost ratio (BCR) compares discounted benefits with discounted costs:

BCR = Present ext{ value of benefits} ÷ Present ext{ value of costs}

Costs and benefits must be classified consistently. BCR greater than 1 indicates that discounted benefits exceed discounted costs. Unlike NPV, BCR is a relative measure and can be misleading when comparing projects of different scale or mutually dependent projects.

4. Worked Example: Automated Vision Inspection

A manufacturer is considering an automated vision system. The illustrative assumptions are:

  • Initial equipment, integration, validation, and training: $180,000 at time zero.
  • Additional working capital: $20,000 at time zero, recovered at the end of year 4.
  • Annual avoided scrap and rework: $120,000.
  • Annual avoided warranty and complaint-handling cash cost: $45,000.
  • Annual maintenance and software cost: $35,000.
  • Annual incremental net cash benefit before tax: $130,000.
  • Project life: four years.
  • Residual value at year 4: $25,000.
  • Discount rate: 10%.
  • Ignore tax for this illustration.

Thus:

CF0 = −180,000 − 20,000 = −200,000

Years 1–3 have cash flow $130,000. Year 4 has $130,000 + $25,000 + $20,000 = $175,000 because residual value and working capital recovery occur then.

YearCash flow ($)Discount factor at 10%Present value ($)Cumulative undiscounted flow ($)
0−200,0001.0000−200,000−200,000
1130,0000.9091118,182−70,000
2130,0000.8264107,43860,000
3130,0000.751397,666190,000
4175,0000.6830119,525365,000

The NPV is approximately:

NPV = −200,000 + 118,182 + 107,438 + 97,666 + 119,525 = $242,811

The simple payback occurs during year 2:

Payback = 1 + (70,000 ÷ 130,000) ≈ 1.54 years

The undiscounted total benefits include $130,000 × 4 plus the $45,000 residual value and working-capital recovery? Care is needed: the $130,000 already represents annual net benefit, while the final-year additions are $45,000. Total inflows are $565,000; net undiscounted gain over the $200,000 initial outflow is $365,000. A simple total-cost ROI, using initial investment as the denominator, is:

ROI = (565,000 − 200,000) ÷ 200,000 × 100 = 182.5%

This ROI is not an annual return and should not be compared directly with the 10% discount rate. The PI is:

PI = (242,811 + 200,000) ÷ 200,000 ≈ 2.21

The IRR is the rate that makes the cash-flow series (−200,000, 130,000, 130,000, 130,000, 175,000) have zero NPV. Numerical solution gives an IRR of approximately 61%. Because the cash-flow pattern is conventional, this IRR is unique in practical terms. The recommendation is financially attractive under the assumptions, but management should still test whether the defect reduction is causal, whether capacity benefits are monetised, and whether cybersecurity or validation costs have been fully included.

5. Risk, Uncertainty, and Sensitivity

Quality benefits are forecasts, not certainties. A robust appraisal separates measurable uncertainty from decision-maker optimism.

Sensitivity analysis

Change one assumption at a time—for example, benefit realisation, equipment life, maintenance cost, or discount rate—and observe the change in NPV. Sensitivity analysis identifies critical assumptions but does not assign probabilities.

Scenario analysis

Construct coherent cases such as conservative, expected, and optimistic. For example, the conservative case may assume only 60% of forecast failure reduction, a six-month implementation delay, and higher maintenance cost.

Expected monetary value

If scenarios are mutually exclusive and probabilities are credible:

Expected ext{ NPV} = ∑s=1q ps NPVs

where ps is the probability of scenario s, and the probabilities sum to 1. Expected value does not describe the full risk; decision-makers should also examine downside loss, variance, and exposure to catastrophic outcomes.

Real options

A pilot can create an option to expand, stop, or redesign after learning. Conventional NPV may undervalue this flexibility. However, option language should not be used to justify speculative benefits without evidence. A stage-gated quality programme is often preferable: pilot, validate, scale, and review.

6. Accounting, Governance, and Ethical Issues

Financial appraisal can be distorted by incentives. Managers may defer maintenance, classify recurring expenditure as capital, overstate avoided costs, or count the same benefit twice to obtain approval. Governance should therefore require:

  • a documented baseline and counterfactual;
  • traceable operational evidence for each benefit;
  • explicit treatment of tax, inflation, working capital, and residual value;
  • independent review of major assumptions;
  • post-implementation audit comparing forecast and realised benefits;
  • clear ownership for benefit realisation.

Safety, regulatory compliance, and human rights are constraints, not optional benefits to be traded away by a positive ROI. A project that prevents a legally unacceptable risk may be mandatory even when its financial NPV is negative. Conversely, financial attractiveness cannot excuse unsafe automation, discriminatory inspection algorithms, privacy violations, or manipulation of quality records.

Accounting standards and tax regulations differ across jurisdictions. Capitalisation, depreciation, impairment, provisions, lease treatment, and internally developed software must be reviewed with qualified finance professionals. The appraisal model should distinguish management decision analysis from external financial reporting.

7. Technology, Data, and AI in Quality Investment Appraisal

Digital quality systems can improve appraisal by providing time-stamped defect, process, maintenance, and customer data. Machine-learning inspection may reduce escapes, but its economic value depends on false positives, false negatives, model drift, explainability, validation, and the cost of human review. A reported accuracy percentage is not a cash benefit.

For an AI-enabled inspection project, the model should estimate:

  • defect prevalence and the cost of false negatives;
  • unnecessary rejection and the cost of false positives;
  • review labour and retraining costs;
  • cybersecurity and data-governance expenditure;
  • performance degradation over time;
  • human-override and escalation requirements.

Benefit claims should be based on controlled pilots or credible quasi-experimental evidence where possible. Data quality is itself an investment variable: incomplete failure coding can produce an apparently attractive but unreliable business case.

8. Illustrative Case: Supplier Quality Analytics Programme

Background

A fictional electronics manufacturer spends $900,000 annually on incoming inspection, supplier-related rework, expedited freight, and customer returns. The company is considering a two-year supplier-quality analytics programme costing $240,000 initially and $80,000 per year for software, training, and supplier audits.

Problem

Historical data show that a small group of suppliers causes most defects, but records are inconsistent. The proposed programme is expected to reduce supplier-related failure costs by 25% in year 1 and 40% in year 2. Management also expects $60,000 of annual inspection capacity to be reassigned to process improvement, although no layoffs are planned.

Analysis

The programme’s cash benefits should not automatically include the $60,000 capacity release. If staff remain fully paid and the released time is not linked to measurable additional output or avoided hiring, it is an operational benefit rather than an immediate cash saving. Assume validated cash benefits are $225,000 in year 1 and $360,000 in year 2. Annual programme cost is $80,000, and initial cost is $240,000. Ignore tax and terminal value.

PeriodCash benefit ($)Cash cost ($)Net cash flow ($)
00240,000−240,000
1225,00080,000145,000
2360,00080,000280,000

At a 12% discount rate:

NPV = −240,000 + 145,000 ÷ 1.12 + 280,000 ÷ 1.122

The result is approximately $101,071, so the programme is financially attractive under the validated assumptions. Undiscounted payback is between years 1 and 2:

Payback = 1 + (95,000 ÷ 280,000) ≈ 1.34 years

The team should next test a conservative scenario in which only 60% of predicted reductions occur. It should also establish supplier data definitions, avoid penalising suppliers solely on noisy data, and ensure that algorithmic rankings do not conceal systemic design or specification problems.

Outcome and learning points

The case illustrates four principles. First, benefits must be linked to cash consequences. Second, capacity release requires a utilisation plan before it becomes a financial benefit. Third, a positive NPV depends on evidence quality as well as arithmetic. Fourth, supplier analytics should support collaborative corrective action rather than become an unexamined mechanism for blame.

9. Best-Practice Appraisal Process

A mature organisation can use the following sequence:

  1. Define the quality problem, decision boundary, and counterfactual.
  2. Establish a measured baseline and identify causal drivers.
  3. List all initial, recurring, transition, compliance, and disposal costs.
  4. Quantify benefits conservatively and remove double counting.
  5. Build annual incremental, after-tax cash flows with documented assumptions.
  6. Select and disclose the discount rate and price basis.
  7. Calculate NPV, IRR, payback, PI, TCO, BCR, and any required accounting measure.
  8. Test sensitivity, scenarios, implementation delay, and benefit ramp-up.
  9. Apply non-financial gates for safety, law, ethics, quality, and resilience.
  10. Approve with an owner, milestones, post-investment review, and benefit audit.

NPV should usually be the principal value criterion, while payback, PI, TCO, ROI, ARR, and BCR provide complementary perspectives. No single ratio can replace engineering judgement, process evidence, or governance.

Challenges and Limitations

Financial appraisal faces several limitations. Quality outcomes may have long causal chains, making attribution difficult. Benefits may be probabilistic, delayed, or dependent on employee adoption. Accounting allocations can obscure true resource use. Discount rates may undervalue long-term resilience, learning, and safety. Inflation and exchange-rate assumptions can become unreliable. Correlated projects may double count the same defect reduction. Finally, financial models can create false precision when input data are weak.

The appropriate response is not to abandon appraisal but to make uncertainty visible. Use ranges, scenario narratives, pilot evidence, sensitivity charts, and explicit decision gates. When a benefit cannot be monetised credibly, record it separately as a strategic, regulatory, customer, safety, or capability benefit rather than inserting an arbitrary number.

Chapter Summary

Financial appraisal of quality investments compares incremental, time-phased costs and benefits against a realistic baseline. A sound model distinguishes capital expenditure, recurring operating cost, avoided failure cost, capacity release, revenue protection, risk reduction, working capital, tax, and residual value. Cash-flow analysis is essential because accounting profit and cash movement are different.

Payback evaluates recovery speed but ignores later value; ARR and simple ROI depend on accounting definitions; NPV measures value creation after discounting; IRR identifies the rate that sets NPV to zero; PI supports capital-rationing decisions; TCO exposes life-cycle cost; and BCR compares discounted benefits with discounted costs. NPV is generally the strongest primary criterion, but complementary measures help address liquidity, accounting, scale, and communication needs.

Reliable appraisal requires a measured counterfactual, causal benefit logic, unit consistency, avoidance of double counting, sensitivity and scenario analysis, and post-implementation verification. Safety, regulatory compliance, ethical treatment, data governance, and quality integrity must remain decision constraints even when a financial model appears attractive.

Key Terms

Accounting rate of return: Average accounting profit divided by a stated accounting investment base.

Benefit–cost ratio: Present value of benefits divided by present value of costs.

Cash flow: Cash entering or leaving an organisation during a specified period.

Counterfactual: The outcome expected if the proposed investment is not undertaken.

Discount rate: Rate used to convert future cash flows to present value.

Incremental cash flow: Cash flow that changes because of the investment decision.

Internal rate of return: Discount rate at which project NPV equals zero.

Net present value: Present value of all incremental cash flows, including initial investment.

Opportunity cost: Value of the best alternative use of a resource.

Payback period: Time required for cumulative cash flows to recover initial investment.

Profitability index: Present value of future inflows divided by initial investment.

Residual value: Value recovered from an asset or working capital at project end.

Risk-adjusted appraisal: Evaluation that incorporates uncertainty, probabilities, or risk premiums.

ROI: A stated ratio of net benefit or return to a defined investment or cost base.

Sunk cost: Past cost that cannot be changed by the current decision.

Tax shield: Tax saving created by an allowable deduction such as depreciation.

Total cost of ownership: Acquisition, operating, maintenance, implementation, and disposal costs over an asset’s life, less residual value.

Working capital: Funds tied up in inventories, receivables, or other operating resources.

Review Questions

Short Answer Questions

  1. Why is a counterfactual necessary when appraising a quality investment?
  2. Distinguish an avoided cash cost from a capacity release.
  3. State the principal difference between NPV and payback period.
  4. Why should a project’s cash flows and discount rate use consistent nominal or real terms?
  5. What is the purpose of a post-implementation benefit audit?

Long Answer Questions

  1. Explain how prevention, appraisal, internal failure, and external failure costs may enter a quality investment appraisal.
  2. Compare payback, ARR, ROI, NPV, IRR, PI, TCO, and BCR, including one limitation of each.
  3. Develop a framework for estimating and validating the benefits of an automated inspection system.
  4. Discuss how tax, depreciation, working capital, inflation, and residual value affect project cash flows.
  5. Explain why financial appraisal must be integrated with safety, regulatory, ethical, and quality governance.

Analytical / Application Questions

  1. A project requires $300,000 initially and produces annual net cash flows of $110,000 for four years, with a $30,000 residual value in year 4. At a 10% discount rate, calculate payback, NPV, and PI, and recommend whether the project should proceed financially.
  2. A quality programme claims $200,000 of annual savings, but only $80,000 represents eliminated expenditure; the remainder is employee capacity released without a staffing or output plan. Explain how the appraisal should treat the two amounts and why.
  3. Construct conservative, expected, and optimistic scenarios for a supplier-quality analytics investment. Identify at least four uncertain assumptions and explain which decision rule should be used if the scenarios produce conflicting results.

Multiple Choice Questions with Answers

Question 1

Which measure explicitly discounts all project cash flows to present value?

A. Simple payback period

B. Net present value

C. Accounting rate of return

D. Undiscounted ROI

Correct Answer: B. Net present value

Question 2

An investment has an initial cost of $100,000 and constant annual cash flow of $25,000. What is its simple payback period?

A. 2 years

B. 3 years

C. 4 years

D. 5 years

Correct Answer: C. 4 years

Question 3

Which item is normally a sunk cost in a current investment decision?

A. Future maintenance cost

B. Initial installation cost

C. Past feasibility-study expenditure

D. Future training cost

Correct Answer: C. Past feasibility-study expenditure

Question 4

If the present value of future inflows is $150,000 and initial investment is $120,000, the profitability index is:

A. 0.80

B. 1.00

C. 1.25

D. 2.25

Correct Answer: C. 1.25

Question 5

Which statement about IRR is correct?

A. It is always equal to the discount rate

B. It is the rate that makes NPV zero

C. It ignores the timing of cash flows

D. It is calculated only from accounting profit

Correct Answer: B. It is the rate that makes NPV zero

Question 6

A reduction in paid defects is financially relevant primarily when it:

A. Changes an incremental cash cost or benefit

B. Is reported in a quality dashboard

C. Increases the number of inspections

D. Changes a non-cash allocation only

Correct Answer: A. Changes an incremental cash cost or benefit

Question 7

Which cost is most likely included in total cost of ownership?

A. Only purchase price

B. Only annual depreciation

C. Acquisition, operation, maintenance, and disposal costs

D. Only external failure cost

Correct Answer: C. Acquisition, operation, maintenance, and disposal costs

Question 8

If a project has one initial cash outflow followed by positive inflows, its cash-flow pattern is called:

A. Conventional

B. Non-cash

C. Multiple-sign recurrent

D. Sunk

Correct Answer: A. Conventional

Question 9

A positive NPV at the selected discount rate generally indicates that the project:

A. Has the shortest payback of all projects

B. Creates expected value relative to the baseline

C. Has no implementation risk

D. Must have a positive accounting profit every year

Correct Answer: B. Creates expected value relative to the baseline

Question 10

Why should capacity release not automatically be counted as a cash saving?

A. Capacity can never have value

B. Released employees may remain paid and be reassigned

C. Capacity is always a sunk cost

D. Capacity is excluded from quality costing

Correct Answer: B. Released employees may remain paid and be reassigned

Quality Costing & Financial ROI
Chapter 8 of 14