Quality assurance & quality control

Chapter 11
Quality Audits, Reviews and Performance Management

Diploma in Construction Engineering
Quality assurance & quality control   •   Diploma

Quality Audits, Reviews and Performance Management

Introduction

Quality assurance and quality control do not end when an inspection is completed or a test result is recorded. Construction organisations must also determine whether their quality system is functioning as intended, whether suppliers and subcontractors are meeting agreed requirements, whether project processes are producing consistent results, and whether identified problems are being corrected. Audits, reviews and performance management provide the structured methods for doing this.

An audit is a planned, systematic and documented process for obtaining objective evidence and evaluating it against defined criteria. A review is a formal examination of performance, risks, resources, results or continuing suitability. Performance management is the process of selecting indicators, measuring results, analysing trends and taking action to improve outcomes.

Together, these activities support a cycle of planning, implementation, verification and improvement. They should not be treated as fault-finding exercises. A well-conducted audit identifies conformity, weaknesses, risks and opportunities for improvement while maintaining fairness and respect for the people involved.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Explain the purpose and principles of quality audits, reviews and performance management.
  2. Distinguish internal, supplier and project audits.
  3. Prepare an audit programme, plan, checklist and evidence-collection strategy.
  4. Collect, evaluate and record objective evidence.
  5. Classify findings and prepare clear audit reports.
  6. Select and interpret construction quality indicators.
  7. Participate in management reviews and follow up corrective actions.
  8. Recognise ethical, legal, technological and practical limitations of auditing.

1. The Quality Audit as a Management Tool

1.1 Definition and purpose

A quality audit evaluates whether specified arrangements are established, implemented and effective. The audit criteria may include a quality management standard, contract requirements, approved drawings, method statements, inspection and test plans, legislation, organisational procedures or client specifications.

An audit asks three related questions:

  • Are the required arrangements defined? This concerns documented requirements, responsibilities and acceptance criteria.
  • Are the arrangements implemented? This concerns what people actually do on site.
  • Are the arrangements effective? This concerns whether the process achieves acceptable and consistent results.

An audit is therefore different from a routine inspection. An inspection normally examines a product, material or activity against acceptance requirements. An audit examines the system and processes used to control that product, material or activity. For example, an inspector may check the concrete cover in a reinforced-concrete element, while an auditor examines whether reinforcement drawings, bar-bending schedules, pre-pour inspections and records provide reliable control of cover.

1.2 Audit principles

Credible auditing depends on several principles:

PrinciplePractical meaning
IntegrityAuditors act honestly, responsibly and professionally.
Fair presentationFindings, conclusions and unresolved differences are reported accurately.
Due professional careAuditors use appropriate judgement and diligence.
ConfidentialityInformation is protected and used only for legitimate purposes.
IndependenceAuditors avoid auditing their own work where practicable.
Evidence-based approachConclusions are based on verifiable evidence rather than opinion.
Risk-based thinkingGreater attention is given to activities with higher consequences or uncertainty.

Audits usually examine samples rather than every transaction or activity. Consequently, an audit conclusion provides reasonable confidence, not absolute proof that no problem exists. The limitation should be understood by auditors, managers and clients.

2. Types and Scope of Construction Audits

2.1 Internal audits

An internal audit is conducted by or for the organisation itself. It may be performed by quality personnel, trained employees from another department, or an independent internal audit team. Its purposes include checking implementation of the quality management system, assessing process effectiveness, preparing for external certification or identifying improvement opportunities.

Internal auditors should not normally audit activities for which they have direct responsibility. On a small project this may be difficult; in such cases, the organisation should manage the risk through cross-checking, peer review or an external auditor.

2.2 Supplier and subcontractor audits

A supplier audit evaluates whether a vendor or subcontractor can and does meet specified requirements. The audit may cover:

  • competence and staffing;
  • material purchasing and traceability;
  • calibration of measuring equipment;
  • production or installation controls;
  • inspection and testing;
  • management of nonconforming work;
  • document control;
  • previous performance and corrective action.

Supplier audits are especially important for critical materials and specialist work, such as structural steel, precast units, waterproofing, fire protection, lifts and mechanical or electrical systems. The audit should be proportionate to risk. A low-value, low-risk purchase does not normally require the same audit depth as a subcontractor installing a primary structural system.

2.3 Project audits

A project audit examines the implementation of quality requirements on a particular construction project. It may cover design management, procurement, site execution, testing, handover and records. Project audits often involve several organisations, so the audit criteria must clearly identify each party’s responsibilities.

Typical project-audit questions include:

  • Are the latest approved drawings available at the work location?
  • Are inspection and test plans being followed?
  • Are hold points released by authorised personnel?
  • Are test results complete, valid and traceable to the relevant work?
  • Are nonconformities controlled and closed effectively?
  • Are as-built records and operation manuals being prepared progressively?

2.4 First-, second- and third-party audits

A first-party audit is performed by the organisation on itself. A second-party audit is performed by a customer or another party with a contractual interest, such as a main contractor auditing a subcontractor. A third-party audit is performed by an independent certification or regulatory body. The scope, independence and consequences of each type differ, but all require clear criteria and objective evidence.

3. Planning an Audit Programme

An audit programme is a set of one or more audits planned for a defined period and purpose. It should not be simply a calendar of visits. It should explain why audits are needed, what risks they address and how results will be used.

3.1 Inputs to programme planning

Relevant inputs include:

  • project quality objectives and contractual requirements;
  • legal and regulatory obligations;
  • complexity and value of work;
  • safety, environmental and structural risks related to quality;
  • previous audit findings;
  • customer complaints and rework data;
  • changes in design, personnel, materials or methods;
  • supplier criticality and past performance;
  • stage of project completion.

A risk-based programme may audit high-risk activities more frequently than routine activities. For example, waterproofing of a basement may receive an audit before major backfilling because defects will be difficult and expensive to correct later.

3.2 Audit plan

An audit plan normally identifies:

ItemExample content
ObjectiveDetermine whether concrete placement controls are effective.
ScopeReinforced-concrete works for Levels 1–3.
CriteriaApproved method statement, drawings, inspection plan and specification.
Dates and locationsSite office, batching plant and work areas.
Audit teamLead auditor and technical specialist.
Auditee contactsProject manager, site engineer and laboratory technician.
MethodsInterviews, observation, record sampling and tracing.
OutputsFindings, report, corrective-action requests and follow-up date.

The auditor should review documents before the visit. This improves efficiency and allows questions to focus on risk rather than merely checking whether documents exist.

3.3 Audit checklist

A checklist can improve consistency, but it should not turn the audit into a mechanical tick-box exercise. Good checklists contain questions linked to criteria and evidence, such as:

  • What requirement controls this activity?
  • Who is authorised to perform or release it?
  • What record demonstrates completion?
  • How is nonconforming work identified and controlled?
  • What evidence shows that previous findings were addressed?

The auditor should follow evidence and investigate unexpected conditions even when they are not explicitly written on the checklist.

4. Collecting and Evaluating Objective Evidence

4.1 Sources of evidence

Objective evidence is information that can be verified. Common sources include:

  • approved drawings and specifications;
  • method statements and inspection and test plans;
  • material certificates and delivery records;
  • calibration certificates;
  • inspection records and test reports;
  • site observations and photographs;
  • interviews with personnel;
  • training and competency records;
  • nonconformance and corrective-action records;
  • correspondence, approved submittals and meeting minutes;
  • digital logs, building information models and field applications.

An interview statement can be useful, but it is stronger when confirmed by observation or records. For example, a supervisor may state that all concrete deliveries are checked, but the auditor should sample delivery tickets and inspection records to verify the statement.

4.2 Sampling

Because construction audits are usually based on samples, the auditor should define the population and sampling logic. A sample may be selected to represent different dates, crews, locations, materials, shifts or suppliers. Additional targeted samples may be taken when initial evidence indicates elevated risk.

Sampling is not the same as selecting only convenient records. Convenience sampling can conceal poor performance. The auditor should record what was sampled, how it was selected and any limitations affecting the conclusion.

4.3 Evidence triangulation

Triangulation means comparing different sources of evidence. For example, a test record may be compared with the relevant delivery ticket, location drawing, laboratory register and physical work. If these sources agree, confidence increases. If they conflict, the conflict itself requires investigation.

4.4 Interviewing techniques

Effective audit interviews are open, respectful and specific. Questions should begin with how, what, when, where and who rather than accusations such as “Why did you fail to follow the procedure?” The auditor should distinguish between:

  • what the procedure requires;
  • what the person believes is required;
  • what the person actually did; and
  • what records or other evidence demonstrate.

Auditors should avoid coaching the auditee toward a desired answer. They should also explain the purpose of the interview and protect confidential information.

5. Audit Findings and Reporting

5.1 Classification of findings

Organisations use different classifications, but a practical system is shown below.

FindingMeaningTypical response
ConformityRequirement is met and evidence supports implementation.Retain as evidence of effective practice.
ObservationA condition that may become a problem or deserves attention.Monitor or improve before failure occurs.
Minor nonconformityA limited failure that does not indicate total breakdown of the requirement.Correct within an agreed period.
Major nonconformitySignificant failure, repeated failure or absence of an essential control.Immediate containment and formal corrective action.
Opportunity for improvementA practical improvement not necessarily required for conformity.Consider through improvement planning.

The exact classification should follow the organisation’s procedure or contract. Auditors must not exaggerate findings to make a report appear more serious, nor minimise them to avoid conflict.

5.2 Structure of a finding

A strong finding contains four elements:

  1. Requirement: the applicable criterion.
  2. Evidence: the verified facts observed or sampled.
  3. Gap: the difference between the requirement and the evidence.
  4. Risk or consequence: why the gap matters, where relevant.

For example:

Requirement: The inspection plan requires reinforcement inspections to be recorded before concrete placement. Evidence: In a sample of 12 pours, three records were signed after placement, and two had no recorded cover measurement. Finding: The required pre-pour control was not consistently implemented. Risk: Reinforcement defects may be concealed and become costly to correct.

This is more useful than writing “Poor reinforcement control.”

5.3 Audit report

A report should be clear, factual and issued promptly. It commonly includes:

  • audit objective, scope and criteria;
  • dates, locations and audit team;
  • organisations or departments audited;
  • records and activities sampled;
  • summary of positive practices;
  • findings and supporting evidence;
  • limitations or unresolved issues;
  • conclusions;
  • required corrective actions and due dates;
  • distribution and approval details.

The report should distinguish facts from interpretation. Draft findings may be discussed with the auditee to confirm factual accuracy, but management should not alter evidence merely because a finding is inconvenient.

6. Corrective Action and Follow-Up

6.1 Correction, corrective action and preventive thinking

A correction removes an observed problem. For example, a missing test report may be located and filed. Corrective action addresses the cause of the problem so that it does not recur. This may require revising responsibilities, training personnel, improving software controls or changing the inspection sequence.

A useful investigation asks:

  • What happened?
  • Where and when did it happen?
  • What immediate containment is required?
  • Why did the control fail?
  • Were procedures unclear, unavailable or impractical?
  • Were competence, resources or supervision adequate?
  • Could the same cause affect other work?
  • How will effectiveness be verified?

The “five whys” technique can help with simple problems, but it should not be applied mechanically. Complex failures may have several interacting causes, including design ambiguity, procurement pressure, poor communication and inadequate supervision.

6.2 Corrective-action register

A corrective-action register should identify the finding, responsible person, containment, root cause, action, due date, status and verification result. Closure should not mean merely receiving a reply. The auditor or responsible manager should verify that the action was implemented and effective.

A finding may be closed when:

  • the immediate problem has been controlled;
  • the cause has been addressed to a reasonable extent;
  • required documents or process changes are implemented;
  • affected personnel understand the change; and
  • follow-up evidence shows that recurrence is unlikely or controlled.

Overdue actions should be escalated according to risk. A repeated overdue action may itself indicate weak management control.

7. Quality Performance Management

7.1 From activity measures to outcome measures

Quality performance management translates quality objectives into measurable information. Indicators should help managers make decisions, not simply create paperwork.

Indicators may be classified as:

  • Leading indicators: measures of activities expected to influence future results, such as percentage of planned inspections completed before work proceeds.
  • Lagging indicators: measures of results after an event, such as rework cost, rejected tests or defects at handover.
  • Process indicators: measures of process performance, such as document review turnaround time.
  • Outcome indicators: measures of the effect on the project or client, such as customer complaints or handover defects.

A balanced set normally includes both leading and lagging indicators. A project with zero recorded defects may appear excellent, but if inspections are incomplete and reporting is discouraged, the result is misleading.

7.2 Common construction quality indicators

IndicatorPossible interpretation
First-time acceptance rateProportion of inspected work accepted without rework.
Rework hours or costResources consumed correcting nonconforming work.
Nonconformities per work packageFrequency of recorded failures, interpreted with reporting context.
Test failure rateFrequency of failed material or workmanship tests.
Inspection-plan completionDegree to which required inspections occur as planned.
Overdue corrective actionsTimeliness of response to known problems.
Supplier defect ratePerformance of a supplier relative to delivered units or lots.
Handover defectsQuality issues remaining at completion.
Customer complaintsExternal perception and service performance.

No indicator should be interpreted without its denominator, time period, scope and data quality. For example, “10 defects” is not meaningful without knowing whether the project produced 100 or 10,000 comparable units.

7.3 Basic performance calculations

A percentage indicator is calculated as:

Percentage = (Number meeting the defined condition ÷ Total number assessed) × 100

The numerator and denominator must refer to the same population and period. For example, if 92 of 100 planned inspections were completed before work proceeded:

Inspection completion = (92 ÷ 100) × 100 = 92%

A rework rate based on cost may be expressed as:

Rework cost rate = (Cost of rework ÷ Total construction cost) × 100

This calculation assumes that both costs use the same currency, cost basis and reporting period. A high rework rate may indicate poor workmanship, design changes, material problems or inadequate planning; the indicator alone does not establish causation.

Trend analysis compares results across consistent periods or work packages. A control chart may be useful in larger or repetitive operations, but its interpretation requires an appropriate process, sufficient data and distinction between common-cause and special-cause variation. A small project should not use statistical terminology to give false precision to a very small sample.

7.4 Targets and unintended behaviour

Targets should be realistic, understood and connected to project objectives. Poorly designed targets can produce undesirable behaviour. For example, a target of “zero nonconformities” may encourage under-reporting, whereas a target for timely reporting and effective closure encourages transparency.

Performance information should therefore be reviewed alongside qualitative evidence, audits, workforce feedback and client outcomes. Indicators are signals for investigation, not automatic judgements of individual performance.

8. Management Review

Management review is a formal evaluation by senior management of whether the quality management system remains suitable, adequate and effective. It links operational evidence to organisational decisions.

8.1 Typical inputs

Management review inputs may include:

  • status of actions from previous reviews;
  • changes in internal and external issues;
  • achievement of quality objectives;
  • audit results;
  • customer feedback and complaints;
  • process performance and product conformity;
  • nonconformities and corrective actions;
  • supplier and subcontractor performance;
  • adequacy of people, equipment and other resources;
  • risks and opportunities;
  • improvement proposals.

8.2 Outputs and decisions

A review should produce decisions and assigned actions, not only minutes. Outputs may concern:

  • improvement of processes and controls;
  • changes to quality objectives or indicators;
  • resource requirements;
  • training and competence;
  • supplier controls;
  • design or construction methods;
  • risk treatment;
  • communication and responsibilities.

Actions should have an owner, due date and method of follow-up. Management review is effective when decisions are implemented and their results are checked.

9. Applied Case: Illustrative Basement Waterproofing Audit

Background

A contractor is constructing a five-storey office building with a reinforced-concrete basement. The project specification requires a waterproofing system comprising a membrane, protection board and sealed joints. The inspection and test plan includes hold points before reinforcement placement and before backfilling.

Problem

During early construction, the client reports damp patches in one basement wall. The project manager requests an audit of waterproofing controls and related records.

Analysis

The audit team defines the criteria as the approved method statement, manufacturer instructions, drawings, inspection and test plan and contract specification. It samples six wall sections, interviews the waterproofing supervisor and examines delivery records, weather conditions, photographs and hold-point releases.

The audit finds that:

  • the membrane material was approved and traceable;
  • four wall sections had complete inspection records;
  • two records were signed after reinforcement had been fixed, although the inspection was required before that activity;
  • photographs did not clearly identify locations;
  • one joint detail had been changed in the field without an approved technical submission;
  • backfilling had proceeded before a documented final inspection in one area.

The damp patch is not automatically attributed to the audit findings. A technical investigation is required, including examination of the affected location, water testing where appropriate and review of design and installation details.

Approach and solution

The team requires immediate containment: affected areas are protected from further concealment, and backfilling is suspended in unverified zones. The contractor maps all waterproofing sections and performs a targeted inspection. The unapproved joint detail is assessed by the designer and waterproofing specialist. The contractor then:

  1. revises the hold-point release process;
  2. assigns one authorised person to control waterproofing records;
  3. introduces location-coded photographs;
  4. requires approval before field changes;
  5. retrains supervisors and installers;
  6. audits the next three waterproofing work packages;
  7. investigates the damp patch separately and records the technical conclusion.

Outcome

The follow-up audit confirms that hold points are being released before concealment and that photographs can be traced to wall locations. One further documentation error is detected and corrected before backfilling. The management review decides to apply the improved control to roofing and below-ground services, where concealment creates similar risk.

Learning points

The case demonstrates that an audit should examine the complete control chain rather than focus only on the visible defect. It also shows the value of objective evidence, containment, technical investigation, corrective action and transfer of learning to other activities.

10. Governance, Ethics and Technology

Auditors must respect contractual confidentiality, personal-data requirements and organisational access controls. Records should be stored securely and retained for the period required by contract, law or the quality plan. Auditors should disclose conflicts of interest and should not accept gifts or pressure that could affect impartiality.

Digital tools can improve audit performance. Mobile inspection applications can time-stamp records, attach location information and reduce transcription errors. Dashboards can display trends in rework, testing and corrective actions. Building information modelling can link nonconformities to locations and components. Artificial intelligence may assist with searching records, identifying unusual trends or suggesting areas for review.

However, technology does not replace professional judgement. AI-generated classifications may be wrong, incomplete or biased by poor historical data. Sensitive project information should not be uploaded to unauthorised systems. Automated alerts require human verification, and the organisation remains accountable for decisions made using digital tools. A digitally complete record is not necessarily an accurate record.

11. Challenges and Limitations

Common challenges include limited auditor competence, inadequate time, resistance from site personnel, poor record quality, fragmented subcontracting and pressure to report favourable results. Audits can also become ritualistic when checklists are copied from previous projects without considering current risks.

Other limitations include:

  • sampling may not detect rare defects;
  • interviews may be influenced by fear or memory;
  • records may be completed after the event;
  • performance indicators may encourage unintended behaviour;
  • a finding may have several interacting causes;
  • management review may fail if actions are not resourced;
  • project conditions may change faster than audit schedules.

These limitations should be openly reported. Improvement depends on learning from evidence, not claiming certainty that the audit cannot provide.

12. Good Practice for Diploma-Level Practitioners

A construction engineering technician or quality assistant can make a substantial contribution by:

  1. understanding the applicable drawings, specifications and inspection plans;
  2. preparing organised, risk-based audit evidence;
  3. recording facts with dates, locations and document references;
  4. asking respectful questions and listening carefully;
  5. distinguishing correction from corrective action;
  6. checking that records are traceable to actual work;
  7. reporting concerns early, especially before concealment;
  8. maintaining accurate action registers;
  9. interpreting indicators in their context;
  10. escalating issues that exceed personal authority or competence.

Quality auditing is most valuable when it supports reliable construction, protects the client and public, reduces avoidable rework and encourages a culture in which problems can be reported and solved.

Chapter Summary

Quality audits, reviews and performance management provide the verification and improvement functions of a construction quality system. Audits compare objective evidence with defined criteria and may be internal, supplier, project, first-party, second-party or third-party activities. Effective audits are planned according to risk, use competent and sufficiently independent auditors, and rely on evidence from records, observations, interviews and samples.

Findings should identify the requirement, evidence, gap and relevant risk. Corrections address immediate problems, while corrective actions address causes and must be followed up for effectiveness. Performance management combines leading and lagging indicators, but indicators must be interpreted with their scope, denominator, data quality and context. Management reviews convert audit results and performance information into decisions concerning resources, objectives, risks and improvement.

Ethical conduct, confidentiality, impartiality and accurate reporting are essential. Digital tools and AI can improve traceability and analysis, but they require human oversight. The ultimate purpose of auditing is not to produce paperwork; it is to provide confidence that construction processes are controlled and to promote timely, sustainable improvement.

Key Terms

Audit: A systematic, independent and documented process for obtaining and evaluating evidence against criteria.

Audit criteria: Requirements, policies, procedures, specifications or standards used for comparison.

Audit evidence: Verifiable records, statements, observations or other information relevant to the criteria.

Audit programme: Planned set of audits for a defined period and purpose.

Audit plan: Detailed arrangement for a particular audit.

Auditee: Organisation, department or person being audited.

Auditor: Person who conducts an audit.

Conformity: Fulfilment of a specified requirement.

Nonconformity: Failure to fulfil a requirement.

Correction: Action to eliminate an identified nonconformity.

Corrective action: Action to eliminate the cause of a nonconformity and prevent recurrence.

Containment: Immediate action taken to control the effects of a problem.

Leading indicator: Measure of an activity expected to influence future performance.

Lagging indicator: Measure of a result after an event or process outcome.

Key performance indicator: Selected measure used to monitor important performance.

Management review: Formal management evaluation of system suitability, adequacy and effectiveness.

Objective evidence: Information that can be verified as true or reliable.

Traceability: Ability to relate a product, activity or record to its origin, location, time or responsible party.

Review Questions

Short Answer Questions

  1. What is the difference between a quality audit and a routine inspection?
  2. State four principles that support credible auditing.
  3. Distinguish between correction and corrective action.
  4. What is the purpose of an audit checklist?
  5. Give two examples each of leading and lagging quality indicators.

Long Answer Questions

  1. Explain how an organisation should plan a risk-based internal audit programme for a construction project.
  2. Describe the process of collecting, evaluating and documenting objective audit evidence.
  3. Explain the structure of a well-written nonconformity finding and illustrate it with a construction example.
  4. Discuss the purpose, inputs and outputs of a management review.
  5. Explain why quality indicators can produce misleading conclusions if their context and data quality are ignored.

Analytical / Application Questions

  1. A subcontractor has completed waterproofing, but several inspection records were signed after the membrane was concealed. Analyse the risks, identify the evidence you would collect and propose corrective actions.
  2. A project reports zero nonconformities for three months, but inspection-plan completion has fallen from 96% to 72% and complaints have increased. Evaluate what may be happening and recommend management actions.
  3. Design a small audit plan for concrete placement covering objective, scope, criteria, sample, audit methods, expected findings and follow-up arrangements.

Multiple Choice Questions with Answers

Question 1

What is the primary purpose of a quality audit?

A. To replace all routine site inspections

B. To compare objective evidence with defined criteria

C. To discipline workers who make mistakes

D. To approve construction drawings

Correct Answer: B. To compare objective evidence with defined criteria

Question 2

Which activity is most characteristic of a supplier audit?

A. Checking whether a supplier controls material traceability

B. Measuring the temperature of freshly placed concrete only

C. Preparing the project cash-flow forecast

D. Issuing the building permit

Correct Answer: A. Checking whether a supplier controls material traceability

Question 3

Which item is objective audit evidence?

A. The auditor’s personal suspicion

B. An unverified rumour from a worker

C. A traceable, approved inspection record

D. A prediction about future defects

Correct Answer: C. A traceable, approved inspection record

Question 4

Which four elements should a strong audit finding contain?

A. Cost, programme, labour and weather

B. Requirement, evidence, gap and relevant risk

C. Opinion, blame, penalty and publicity

D. Drawing, invoice, salary and forecast

Correct Answer: B. Requirement, evidence, gap and relevant risk

Question 5

A correction differs from corrective action because correction:

A. Addresses the immediate observed problem

B. Always requires a management review

C. Can only be performed by an external auditor

D. Eliminates every possible future risk

Correct Answer: A. Addresses the immediate observed problem

Question 6

If 92 of 100 planned inspections were completed before work proceeded, what was the completion percentage?

A. 8%

B. 92%

C. 100%

D. 108%

Correct Answer: B. 92%

Question 7

Which is a leading quality indicator?

A. Defects remaining at handover

B. Customer complaints received

C. Percentage of planned inspections completed before work proceeds

D. Cost of completed rework

Correct Answer: C. Percentage of planned inspections completed before work proceeds

Question 8

What is the main purpose of management review?

A. To evaluate the continuing suitability, adequacy and effectiveness of the quality system

B. To replace the contractor’s construction programme

C. To perform laboratory tests on every material

D. To remove the need for corrective actions

Correct Answer: A. To evaluate the continuing suitability, adequacy and effectiveness of the quality system

Question 9

Why should an audit sample be documented?

A. To guarantee that no defect exists anywhere

B. To show what was examined and identify limitations of the conclusion

C. To avoid communicating findings to management

D. To ensure only favourable records are selected

Correct Answer: B. To show what was examined and identify limitations of the conclusion

Question 10

Which practice best supports effective corrective-action follow-up?

A. Closing the finding when a reply is received

B. Ignoring overdue actions until project completion

C. Verifying implementation and effectiveness of the action

D. Changing the audit criteria after the finding is issued

Correct Answer: C. Verifying implementation and effectiveness of the action

Quality assurance & quality control
Chapter 11 of 14