Purchasing & Procurement

Chapter 6
Solicitation, Tendering and Bid Evaluation

Diploma in Materials Management
Purchasing & Procurement   •   Diploma

Solicitation, Tendering and Bid Evaluation

Introduction and context

Purchasing decisions begin with a clearly defined requirement and become legally and commercially significant when an organisation invites suppliers to compete. Solicitation is the formal process of requesting offers. Tendering is a structured form of solicitation in which suppliers submit offers against stated conditions, usually within a fixed period. Bid evaluation is the disciplined comparison of offers to determine which proposal provides the best value while complying with organisational policy, applicable law and principles of fairness.

These activities connect internal demand with the external supply market. A poorly prepared solicitation may generate incomparable quotations, hidden costs, disputes and supply failure. A well-designed process creates competition, clarifies expectations, protects public or organisational funds and produces an auditable award decision.

The terminology and legal requirements vary between jurisdictions. Public procurement is usually governed by procurement legislation, financial regulations and administrative-law principles, whereas private organisations operate under internal policies, contract law and governance requirements. This chapter presents general professional principles; the applicable national law and organisation-specific rules must always take precedence.

Learning objectives

By the end of this chapter, the learner should be able to:

  1. Distinguish among an RFQ, RFP, invitation to tender and related solicitation methods.
  2. Prepare clear, complete and non-discriminatory solicitation documents.
  3. Manage quotations, sealed bids, electronic tendering and e-auctions.
  4. Apply commercial, technical, financial and risk-based evaluation methods.
  5. Document clarifications, scoring, approvals and award decisions transparently.
  6. Identify ethical, legal, cybersecurity and governance risks in procurement.

1. The solicitation decision

A solicitation should be selected after examining the requirement, market conditions, risk, urgency, value and regulatory threshold. The central question is not simply “Which document should be sent?” but “What type of competition will obtain the most suitable outcome?”

1.1 Request for Quotation (RFQ)

An RFQ is appropriate when the requirement is sufficiently specified and offers can be compared mainly on price, delivery and standard commercial conditions. Typical examples include standard office supplies, routine maintenance parts or commonly available equipment. The buyer normally states quantities, specifications, delivery location, requested delivery date, payment terms and quotation validity.

An RFQ is most effective where:

  • the specification is objective and complete;
  • suppliers are offering substantially equivalent goods or services;
  • price is an important evaluation factor; and
  • little negotiation or innovation is expected.

An RFQ does not mean that the buyer should accept the lowest numerical price automatically. Compliance, total cost, delivery capability and supplier reliability remain relevant.

1.2 Request for Proposal (RFP)

An RFP is used when the buyer understands the business outcome but suppliers may propose different technical solutions, methods or implementation plans. It is common for information systems, consulting, logistics design, training and integrated services. The RFP should describe the problem, required outcomes, minimum conditions, evaluation criteria and contractual framework without unnecessarily prescribing the supplier’s solution.

RFP evaluation commonly combines technical quality, implementation approach, experience, personnel, risk, sustainability and price. Because proposals may differ materially, the buyer must define scoring rules before opening or evaluating submissions.

1.3 Invitation to Tender or Invitation for Bids

A tender is generally a formal invitation to submit a binding offer against detailed requirements and conditions. In many jurisdictions, a compliant tender is evaluated according to pre-published criteria and negotiation is restricted or prohibited. Tenders are suitable for construction, standardised goods, public works and other requirements in which the buyer can define the deliverable precisely.

1.4 Request for Information and other methods

A Request for Information (RFI) is normally a market-research instrument rather than an offer request. It helps the buyer understand available technologies, supplier capacity, indicative costs and possible specifications. An RFI should state that it is not a commitment to purchase and should not give one supplier an unfair advantage in a later competition.

Other methods include requests for proposals with dialogue, framework agreements, reverse auctions, limited tendering, direct procurement and negotiated procurement. Their use should be justified by value, urgency, market structure and legal authority rather than convenience alone.

MethodBest suited toMain evaluation emphasisTypical risk
RFQClearly specified, routine requirementPrice and complianceIncomplete specification
RFPOutcome-based or complex requirementTechnical and commercial valueSubjective scoring
TenderFormal, detailed and competitive purchaseCompliance and stated criteriaProcedural challenge
RFIMarket intelligenceCapability and informationUnfair supplier advantage
E-auctionComparable, standardised itemsCompetitive price movementQuality erosion or unsuitable use

2. Designing a solicitation package

A solicitation package should allow every qualified supplier to understand what is required, how to respond and how the response will be evaluated. Ambiguity transfers risk into later disputes and encourages suppliers to price assumptions differently.

A professional package commonly contains:

  1. invitation letter and procurement reference;
  2. instructions to bidders;
  3. scope of supply or statement of work;
  4. technical specifications and drawings, where applicable;
  5. quantities, schedules and delivery locations;
  6. pricing schedule and currency requirements;
  7. qualification and eligibility requirements;
  8. contract terms and conditions;
  9. evaluation criteria and methodology;
  10. forms for declarations, bid security and conflicts of interest;
  11. timetable, submission address or electronic portal instructions; and
  12. clarification and communication arrangements.

2.1 Writing specifications

A specification should describe the required function, performance, quality, dimensions, standards, inspection requirements and acceptance criteria. It should be sufficiently precise for suppliers to price the same requirement, but not so restrictive that it excludes capable suppliers without justification.

Performance specifications state what the product or service must achieve. Technical specifications state characteristics or design details. A performance specification may encourage innovation, while a technical specification may be necessary for compatibility, safety or standardisation.

Brand names should generally be avoided unless compatibility or proprietary rights justify them. If a brand is mentioned, wording such as “or equivalent” may be required, together with a clear method for determining equivalence. Requirements should not be written to favour an incumbent or a preferred supplier.

2.2 Instructions to bidders

Instructions should address the submission deadline, permitted format, language, currency, validity period, permitted alternatives, subcontracting, confidentiality, communication, late bids, withdrawal, modification, bid security and grounds for rejection. The buyer should specify one official channel for questions and issue all material clarifications to all participating suppliers.

A “single source of truth” is important. If a clarification changes the requirement, the deadline should be extended when necessary to preserve equal opportunity.

2.3 Qualification and compliance requirements

Qualification requirements should be proportionate to the risk and value of the purchase. They may include legal registration, tax compliance, financial capacity, relevant experience, technical personnel, quality systems, safety performance, insurance and references. A requirement should be evaluated as pass/fail where it is a minimum condition, rather than being given arbitrary extra points.

The buyer should distinguish:

  • mandatory requirements, which must be satisfied;
  • rated requirements, which distinguish quality among compliant offers; and
  • informational requirements, which support due diligence but do not determine the score.

3. Managing the solicitation process

A controlled process protects both the buyer and suppliers. The procurement officer should maintain a procurement file containing the approved requisition, procurement strategy, solicitation document, supplier list, advertisements, questions and answers, received bids, opening record, evaluation reports, approvals, award notice and contract.

3.1 Supplier identification and market engagement

Potential suppliers may be identified through registration databases, market research, professional associations, prior performance records and public advertisements. A supplier list should be sufficiently broad for the market and should not be limited to familiar companies without objective justification.

Pre-solicitation conferences and site visits can clarify complex requirements. Attendance should be recorded, and material information should be circulated to all invited suppliers. One-to-one discussions must not disclose competitors’ information or provide unequal guidance.

3.2 Receipt and security of bids

For sealed bids, bids should remain inaccessible until the stated opening time. Physical bids require controlled receipt, time stamping and secure storage. Electronic bids require access controls, encryption where appropriate, reliable time records, audit logs and contingency arrangements for portal failure.

After the deadline, a bid should not normally be altered. Administrative clarification may be requested only within the limits of the governing rules and must not permit a supplier to improve its substantive offer unfairly. Late bids should be treated according to the stated procedure and applicable law.

3.3 Bid opening

A formal opening may record supplier name, bid price, discounts, currency, bid security and significant deviations. In a public tender, the opening process may be public or otherwise subject to statutory requirements. The opening record is not the evaluation report: it records receipt and opening, while evaluation determines compliance and value.

4. Bid evaluation architecture

Evaluation begins with a compliance review, followed by technical and commercial assessment. The sequence must be established in advance and applied consistently.

4.1 Preliminary examination

The preliminary examination checks whether the bid was submitted on time, signed by an authorised person, accompanied by required forms and securities, valid for the required period and submitted by an eligible supplier. A material failure may make a bid non-responsive. Minor informalities may sometimes be waived if the rules permit and the waiver does not prejudice other bidders.

The evaluator should distinguish a material deviation from a minor error. A material deviation affects price, scope, quality, delivery, risk or the buyer’s rights and obligations. It cannot be corrected without changing the substance of the offer.

4.2 Technical evaluation

Technical evaluation asks whether the proposed solution meets the mandatory specification and how well it performs against rated criteria. Typical criteria include functionality, quality, methodology, implementation plan, personnel, service support, sustainability, interoperability and risk management.

Technical evaluators should use evidence rather than impressions. Claims should be tested against drawings, test certificates, references, demonstrations and documented experience. Evaluators should independently score where feasible and then reconcile differences through a recorded moderation process.

4.3 Commercial evaluation

Commercial evaluation should compare offers on a consistent basis. The evaluated price may include transport, duties, taxes where relevant, installation, training, maintenance, consumables, warranty, financing and disposal costs. The buyer must state in advance which elements will be included and how taxes or discounts will be treated.

For a quantity-based purchase, the line extension is:

Extended amount = Quantity × Unit price

The extended amount has the currency unit of the transaction. A total evaluated price is the sum of relevant line amounts and other stated cost components. Arithmetic errors should be corrected according to the solicitation rules, normally giving precedence to the unit price unless the rules state otherwise.

4.4 Total cost of ownership

The lowest purchase price may not be the lowest economic cost. A total-cost model can include acquisition, operation, maintenance, energy, downtime, training and end-of-life costs. A simplified present-value model is:

TCO = C₀ + ∑[Cₜ ÷ (1 + r)ᵗ] − Rₙ ÷ (1 + r)ⁿ

Here, C₀ is the initial acquisition cost, Cₜ is the cost incurred in period t, r is the discount rate per period, Rₙ is residual or disposal value at period n, and n is the evaluation horizon. All monetary values must be expressed in the same currency and price basis. This model assumes that the timing and estimated values of future costs are reasonably known; uncertainty should be addressed through sensitivity or risk analysis.

4.5 Weighted scoring

For an RFP, a weighted model may be used. If criterion i has weight wi and a supplier receives a normalised score si, the total score is:

Total score = ∑(wᵢ × sᵢ)

Weights should sum to 1, or to 100 percent if percentage weights are used. Scores must use a defined scale, such as 0–5 or 0–100, and the same interpretation must be applied to every proposal. A criterion should not be weighted twice under different names.

For example, suppose technical quality has a weight of 60% and commercial value 40%. Supplier A receives 80/100 for technical quality and 90/100 for commercial value. Its weighted score is:

(0.60 × 80) + (0.40 × 90) = 84

Supplier B receives 90/100 technically and 75/100 commercially:

(0.60 × 90) + (0.40 × 75) = 84

The scores are equal. The buyer must then apply the stated tie-break rule, such as a higher technical score, lower evaluated cost, or another pre-published rule. It must not invent a new preference after seeing the result.

A price score may be calculated using a stated method such as:

Price score = (Lowest evaluated price ÷ Supplier’s evaluated price) × Maximum price score

This formula assumes that all compared bids are technically acceptable and that lower price is preferred. It should not be used to compensate for a failure to meet mandatory technical requirements.

5. Clarifications, negotiations and award

Clarification is used to understand an existing submission, not to permit a supplier to replace its proposal. Questions and responses should be documented. In a tender with strict no-negotiation rules, post-submission bargaining may be unlawful or procedurally unfair.

Negotiation may be appropriate in an RFP, competitive dialogue or negotiated procedure where the procurement rules permit it. Negotiation objectives should be approved in advance, and the process should preserve equal treatment. Important changes should be requested from all suppliers still in competition when the procedure requires it.

The evaluation report should explain:

  • the evaluation committee and declarations of impartiality;
  • the criteria and weights used;
  • the responsiveness findings;
  • technical and commercial scores;
  • treatment of arithmetic errors and clarifications;
  • risks, assumptions and exclusions;
  • the ranking and recommended award; and
  • approvals required under delegated authority.

A sound award decision is evidence-based, reproducible and traceable. It should state why the recommended supplier offers the best evaluated outcome, not merely state that it submitted the lowest price.

Unsuccessful suppliers should receive the notice required by policy or law. A debrief may explain strengths and weaknesses without revealing confidential competitor information. The contract should be signed only by an authorised officer, and a purchase order should not substitute for a contract where formal contracting is required.

6. Sealed bids, electronic tendering and e-auctions

6.1 Sealed bidding

Sealed bidding is designed to prevent suppliers or officials from knowing competitors’ offers before the deadline. It is particularly suitable where the requirement is clearly specified and price competition is important. Controls include separated duties, secure storage, time-stamped receipt, controlled opening and an immutable record.

6.2 Electronic tendering

Electronic procurement portals can widen supplier access, reduce processing time and create searchable audit trails. They also introduce risks such as unauthorised access, identity compromise, system outages, malware and accidental disclosure. Access rights should follow least-privilege principles, and critical actions should be logged and reviewed.

6.3 E-auctions

A reverse e-auction allows qualified suppliers to compete by lowering prices during a defined online event. It is suitable only when the requirement is sufficiently standardised, suppliers understand the specifications and price is a meaningful differentiator. It is unsuitable where proposals are technically complex, quality is difficult to observe or the purchase depends on innovation and partnership.

Before an auction, the buyer should complete qualification and technical evaluation, define the starting or reference price, auction duration, decrement rules, extension rules and award method. The auction should not be used to pressure suppliers into unsustainable prices. A low auction price can create later variation claims, quality failure or contract abandonment.

7. Ethics, governance and regulatory responsibility

Procurement is exposed to conflicts of interest, bribery, collusion, bid-rigging, insider information, discrimination and falsification. Ethical controls are therefore part of technical competence, not an optional administrative activity.

Important safeguards include:

  • conflict-of-interest declarations and recusal;
  • segregation of requisition, evaluation, approval and payment duties;
  • documented contact with suppliers;
  • rotation or independent review for sensitive evaluations;
  • prohibition of gifts and improper hospitality;
  • whistle-blowing and protected reporting channels;
  • supplier due diligence and sanctions screening where required;
  • transparent records and retention periods; and
  • proportionate audit and review.

Collusion indicators may include identical unusual errors, unexplained rotation of winning suppliers, suspiciously similar formatting, cover bids and prices that do not respond to market conditions. Indicators are not proof, but they justify escalation to the appropriate authority and protection of records.

Sustainable procurement can include lifecycle emissions, labour standards, accessibility, responsible sourcing, waste reduction and supplier diversity. Such criteria must be relevant, measurable and disclosed in the solicitation. Sustainability should not become a vague preference that undermines objective evaluation.

8. Technology and responsible use of AI

Digital procurement systems can automate document distribution, deadline control, bid opening logs, arithmetic checks, supplier communication and contract analytics. Artificial intelligence may assist in classifying requirements, identifying missing documents, comparing clauses or detecting unusual pricing patterns.

AI outputs should support—not replace—professional judgment. Risks include biased training data, incorrect interpretation of specifications, disclosure of confidential bids, fabricated explanations and opaque scoring. Sensitive procurement documents should not be uploaded to an unapproved public AI service. Human evaluators remain responsible for decisions, evidence verification, confidentiality and legal compliance. Any automated scoring model should be validated, explainable and auditable.

9. Applied case: municipal water-pump procurement

The following is an illustrative case, not a report of an actual procurement.

Background

A municipal utility needed ten electrically driven pumps for wastewater stations. The pumps had to meet flow and pressure requirements, fit existing connections and include installation, a two-year warranty and maintenance training. The estimated value exceeded the organisation’s competitive-procurement threshold.

Problem

An initial RFQ produced four prices that were not comparable. One supplier excluded installation, another quoted a different motor efficiency class, and a third used a shorter warranty. Selecting the lowest headline price would have created a substantial risk of hidden cost and technical incompatibility.

Analysis

The procurement team reviewed the requirement and found that the desired outcome was clear but the solution included important technical and lifecycle variables. It therefore changed from a simple price RFQ to a structured tender with a detailed technical schedule and an evaluated-cost model. Mandatory requirements included hydraulic performance, dimensional compatibility, safety certification and minimum warranty. Rated criteria covered energy efficiency, maintenance plan, delivery programme and relevant experience.

The pricing schedule required separate prices for pumps, installation, commissioning, training, spare parts and annual maintenance. The tender stated how taxes, transport and warranty costs would be treated. A site visit and common written clarification process were provided.

Approach and solution

A cross-functional committee from engineering, operations, finance and procurement evaluated the bids. Engineering first completed a pass/fail compliance review. Finance then checked arithmetic and calculated total evaluated cost. The committee applied pre-approved weights of 55% technical and lifecycle value, 35% evaluated price and 10% delivery and implementation.

One bid was rejected as non-responsive because its proposed pump could not meet the mandatory pressure requirement. Two compliant bids were scored. The apparently cheaper bid received a lower technical score because it used more energy and excluded an essential training component. The recommended supplier did not have the lowest headline price but achieved the highest total evaluated score and provided a lower estimated lifecycle cost.

Outcome

The evaluation report documented the criteria, evidence, calculations, clarifications and approval trail. The unsuccessful suppliers were notified and offered a controlled debrief. The contract included performance tests, delivery milestones, warranty obligations, service-level requirements and remedies for failure.

Learning points

  1. A low headline price is not necessarily the lowest evaluated cost.
  2. A specification must define compatibility and acceptance, not merely product names.
  3. Price schedules should expose excluded costs.
  4. Technical and commercial evaluators need clearly separated responsibilities.
  5. The evaluation method must be published and applied consistently.
  6. A complete procurement file is essential for accountability and future learning.

10. Common challenges and best practices

Challenge: vague requirements

Response: engage users early, define measurable outputs and test the specification with potential users and technical specialists.

Challenge: too few bids

Response: analyse whether the requirement is unnecessarily restrictive, advertise appropriately, allow reasonable response time and use market research before finalising the solicitation.

Challenge: excessive subjectivity

Response: use defined scoring anchors, evidence requirements, independent scoring and documented moderation.

Challenge: unrealistic lowest price

Response: examine abnormal pricing under the applicable rules, request explanations where permitted and assess financial, technical and delivery risk.

Challenge: procurement delay

Response: establish a procurement timetable, allocate evaluation resources before issue and use electronic workflows without weakening controls.

Challenge: supplier complaints

Response: maintain complete records, apply the published method, provide the required debrief and use an independent review or complaints mechanism.

Best practice is to treat procurement as a controlled decision process rather than a document exchange. Planning, proportionality, equal treatment, confidentiality, evidence and auditability should be visible at every stage.

Chapter Summary

Solicitation converts an approved requirement into a competitive market request. RFQs suit standardised, clearly specified purchases; RFPs suit complex or outcome-based requirements; tenders provide a formal process for detailed and binding offers; and RFIs support market understanding. A good solicitation contains clear specifications, instructions, qualification conditions, pricing schedules, contract terms and published evaluation criteria.

Bid management requires secure receipt, controlled opening, documented clarifications and protection of confidential information. Evaluation normally proceeds from preliminary compliance to technical assessment and commercial comparison. Total evaluated cost may include lifecycle costs, while weighted scoring can combine technical and commercial dimensions when its criteria, weights and scoring rules are defined in advance.

Sealed bids and electronic tendering strengthen control when properly governed. E-auctions are useful only for suitable, comparable requirements and should not replace technical qualification. Ethical procurement requires impartiality, segregation of duties, conflict management, anti-collusion controls and complete records. Digital tools and AI can improve efficiency but require human accountability, confidentiality and auditability. The final award should be transparent, reproducible, authorised and demonstrably aligned with best value and applicable rules.

Key Terms

Solicitation: A formal request inviting suppliers to submit information, quotations, tenders or proposals.

RFQ: Request for Quotation, normally used for clearly specified and comparable purchases.

RFP: Request for Proposal, used when suppliers may offer different solutions to achieve stated outcomes.

Tender: A formal invitation to submit a binding offer under stated conditions.

RFI: Request for Information used to obtain market intelligence before a purchase process.

Bid: A supplier’s submitted offer in response to a solicitation.

Bid security: A financial assurance supporting the seriousness and validity of a bid.

Responsive bid: A bid that materially complies with the solicitation requirements.

Mandatory criterion: A minimum condition that must be satisfied.

Rated criterion: A criterion used to distinguish the quality or value of compliant offers.

Technical evaluation: Assessment of whether and how well a proposed solution meets technical requirements.

Commercial evaluation: Comparison of price, cost, terms, delivery and other business conditions.

Total cost of ownership: The acquisition, operating, maintenance and disposal costs associated with an item or solution.

Weighted scoring: Combining criterion scores according to pre-established weights.

Clarification: A controlled request to understand an existing submission without unfairly changing it.

Sealed bid: An offer protected from access until the specified opening time.

E-auction: An electronic event in which qualified suppliers compete, usually by reducing prices.

Conflict of interest: A situation in which personal or external interests could improperly influence procurement judgment.

Audit trail: A chronological record showing actions, decisions, evidence and approvals.

Best value: The most advantageous overall outcome considering relevant cost, quality, risk, performance and sustainability.

Review Questions

Short Answer Questions

  1. What is the principal difference between an RFQ and an RFP?
  2. Why should mandatory and rated criteria be distinguished?
  3. What is meant by a responsive bid?
  4. State two controls used in sealed-bid procurement.
  5. Why may the lowest purchase price fail to represent the lowest economic cost?

Long Answer Questions

  1. Explain the contents of a professional tender package and the purpose of each major component.
  2. Describe the stages of bid evaluation from preliminary examination to award recommendation.
  3. Discuss how technical specifications can encourage competition while protecting compatibility and performance.
  4. Explain the ethical and governance controls required for transparent procurement.
  5. Compare sealed bidding, electronic tendering and e-auctions, including their advantages and limitations.

Analytical / Application Questions

  1. An organisation receives three quotations for equipment, but one excludes delivery and another fails a mandatory safety requirement. Design a fair evaluation sequence and explain which costs and conditions should be compared.
  2. A supplier submits the lowest price in an RFP but scores poorly on implementation risk and after-sales support. Using a weighted evaluation framework, explain how the award decision should be justified.
  3. During an e-auction, prices fall below what appears commercially sustainable. Identify the risks, the checks that should be performed and the procurement actions that may be appropriate under the governing rules.

Multiple Choice Questions with Answers

Question 1

Which procurement method is generally most suitable when a requirement is standardised and fully specified?

A. Request for Quotation

B. Request for Information

C. Request for Proposal

D. Competitive dialogue

Correct Answer: A. Request for Quotation

Question 2

What is the main purpose of a Request for Information?

A. To make a final contract award

B. To obtain market intelligence

C. To replace bid evaluation

D. To negotiate secretly with one supplier

Correct Answer: B. To obtain market intelligence

Question 3

A mandatory criterion is best described as a criterion that:

A. Receives extra points only

B. Must be satisfied for the bid to remain acceptable

C. Applies only after contract signature

D. Can always be waived without record

Correct Answer: B. Must be satisfied for the bid to remain acceptable

Question 4

Which action best protects the integrity of sealed bids?

A. Allowing evaluators to view bids as they arrive

B. Changing the deadline for one supplier only

C. Keeping bids inaccessible until the stated opening time

D. Permitting suppliers to revise prices after opening

Correct Answer: C. Keeping bids inaccessible until the stated opening time

Question 5

If technical quality has a weight of 60% and a supplier scores 80/100, what is its weighted contribution?

A. 20 points

B. 40 points

C. 48 points

D. 80 points

Correct Answer: C. 48 points

Question 6

Which cost is most clearly part of total cost of ownership?

A. Only the catalogue price

B. Only the supplier’s advertising cost

C. Operating and maintenance cost over the asset’s life

D. The evaluator’s personal preference

Correct Answer: C. Operating and maintenance cost over the asset’s life

Question 7

A clarification should normally be used to:

A. Permit a supplier to replace its entire proposal

B. Understand an existing submission without unfairly changing it

C. Reveal competitors’ prices

D. Create a new evaluation criterion

Correct Answer: B. Understand an existing submission without unfairly changing it

Question 8

An e-auction is generally least suitable when:

A. The product is standardised

B. Qualified suppliers can compare the same requirement

C. Quality and solution design are difficult to compare objectively

D. Price is an important differentiator

Correct Answer: C. Quality and solution design are difficult to compare objectively

Question 9

Which document most directly records the reasons for the recommended award?

A. The evaluation report

B. The supplier’s brochure

C. The goods receipt note

D. The warehouse bin card

Correct Answer: A. The evaluation report

Question 10

Why should procurement evaluators declare conflicts of interest?

A. To increase the bid price

B. To protect impartiality and confidence in the decision

C. To eliminate all competition

D. To avoid preparing a procurement file

Correct Answer: B. To protect impartiality and confidence in the decision

Purchasing & Procurement