Cost, Price and Value AnalysisIntroductionPurchasing decisions are often judged by the price printed on a quotation. Professional procurement, however, asks a wider question: what economic value will the purchase create over its entire life? A low quoted price may conceal high freight, inspection, maintenance, energy, failure, disposal, or administrative costs. Conversely, a higher price may be justified by superior quality, longer life, lower risk, or improved service. Cost, price, and value are related but distinct concepts. Cost is the expenditure incurred to produce, acquire, operate, or dispose of an item. Price is the amount charged by a seller or paid by a buyer in a transaction. Value is the worth of the benefits received in relation to the resources sacrificed. Cost analysis examines the buyer's or supplier's cost structure; price analysis evaluates whether the offered price is reasonable by comparing it with market or historical evidence; value analysis examines the relationship between function, performance, cost, and risk. This chapter develops practical methods for procurement professionals: cost and price analysis, cost structures, break-even analysis, learning curves, cost indexes, should-cost estimation, landed cost, total cost of ownership, and procurement savings. The emphasis is on transparent assumptions, reliable data, and decisions that can be defended to management, auditors, suppliers, and other stakeholders. Learning ObjectivesAfter studying this chapter, the learner should be able to: - Distinguish cost analysis from price analysis and value analysis.
- Classify direct, indirect, fixed, variable, controllable, and opportunity costs.
- Calculate break-even quantity and interpret its procurement relevance.
- Explain learning curves and use them cautiously in cost estimation.
- Apply cost indexes to update historical costs.
- Prepare a basic should-cost estimate.
- Calculate landed cost and total cost of ownership.
- Measure procurement savings using an agreed baseline.
- Evaluate cost information ethically and use it to support evidence-based decisions.
1. The Procurement Meaning of Cost, Price and ValueCostCost may be recorded at different stages: - Acquisition cost: the amount paid to obtain a good or service.
- Conversion cost: labour and manufacturing overhead used to transform materials.
- Operating cost: expenditure incurred while using an asset or service.
- Transaction cost: searching, negotiating, contracting, expediting, inspecting, and administering a purchase.
- Failure cost: warranty claims, rework, downtime, returns, recalls, and reputational damage.
- Disposal cost: removal, recycling, decommissioning, or environmental treatment.
The same item can have different costs for different decision purposes. A historical accounting cost may be appropriate for reporting but unsuitable for a forward-looking make-or-buy decision. A relevant cost is a future cost that changes as a result of the decision. A sunk cost has already been incurred and should not normally influence a choice between current alternatives. PricePrice is observable in a quotation, contract, catalogue, auction, or market transaction. It may include or exclude taxes, freight, discounts, rebates, tooling, installation, warranty, and payment terms. Therefore, comparing prices requires a common commercial basis. A unit price quoted ex-works cannot be compared directly with a delivered, duty-paid price. ValueValue is not simply low cost. A useful procurement interpretation is: Value = Function delivered ÷ Total resources consumed The expression is conceptual rather than a universal accounting formula. Function may include performance, reliability, safety, availability, compliance, and user benefit. Resources include purchase cost, operating cost, time, risk, and environmental burden. Value analysis seeks the required function at the lowest total cost without reducing necessary quality, safety, or performance. Cost analysis and price analysisPrice analysis evaluates the reasonableness of a price without necessarily examining the supplier's internal costs. Evidence can include competitive bids, published prices, previous purchases adjusted for market change, catalogues, independent estimates, and prices paid for comparable items. Cost analysis examines the components that build the price, such as material, labour, overhead, tooling, profit, logistics, and risk allowances. It is particularly useful when there is little competition, the item is highly engineered, the specification is new, or the buyer is negotiating a major contract. | Feature | Price analysis | Cost analysis |
|---|
| Main question | Is the total price reasonable? | Are the cost elements reasonable? | | Main evidence | Market and transaction comparisons | Supplier cost data and engineering estimates | | Supplier disclosure | Usually limited | Often substantial | | Best use | Competitive, standard, market-priced items | Complex, unique, or negotiated items | | Main risk | Poor comparability | Inaccurate or unverifiable cost data |
Value analysis goes further by asking whether all specified functions are necessary and whether alternative designs, materials, processes, or service levels can deliver them economically. It must not be confused with indiscriminate cost cutting. Removing a safety feature is not value improvement. 2. Cost Structures and Cost BehaviourA procurement analyst should understand how a supplier's costs behave as volume, time, quality, and design change. Direct and indirect costsA direct cost can be traced economically to a specific product, order, or service. Examples include steel used in a fabricated component and assembly labour recorded against that component. An indirect cost supports several products or activities and must be allocated, such as factory rent, information technology, supervision, and purchasing administration. Allocation is useful for reporting, but an allocated cost is not automatically an avoidable cost. For example, a supplier may allocate factory rent to every product, yet accepting one additional order may not increase rent. Procurement negotiations should distinguish accounting allocations from incremental economic costs. Fixed and variable costsA fixed cost remains constant within a relevant range and period, such as annual insurance or machine lease cost. A variable cost changes with output, such as direct material or packaging. Some costs are semi-variable: a base amount is fixed while the remainder varies with use. Electricity, maintenance, and technical support commonly behave this way. Total cost can be represented as: TC = F + vQ where TC is total cost in monetary units, F is total fixed cost, v is variable cost per unit, and Q is quantity. This linear model assumes constant unit variable cost and fixed cost within the relevant operating range. It is an approximation, not a law: quantity discounts, overtime, capacity constraints, and step costs can make the relationship nonlinear. A supplier's quoted price may be expressed as: P = cm + cl + co + cf + π where P is price per unit, c_m is material cost, c_l is direct labour cost, c_o is allocated or incremental overhead, c_f is freight and related costs, and π is profit and risk allowance. The terms must be defined consistently; otherwise, freight or overhead may be counted twice. Relevant cost and opportunity costA cost is relevant to a decision when it is future-oriented and differs between alternatives. Opportunity cost is the benefit sacrificed by using a scarce resource for one purpose rather than its best alternative. If a production line is full, accepting a low-margin order may displace a more profitable order; the contribution lost is economically relevant even if it does not appear as a new invoice. 3. Price Analysis MethodsA robust price analysis uses more than one method where possible. Comparison with competitionComparable competitive quotations are strong evidence when specifications, quantities, delivery points, payment terms, warranty, currency, and quality requirements are equivalent. The analyst should normalize differences before drawing conclusions. A bid that is 4% lower but excludes testing is not necessarily cheaper. Historical price comparisonPrevious price is useful only after adjustment for quantity, specification, exchange rate, commodity prices, inflation, and supplier learning. A simple index adjustment is: Ct = C0 × (It ÷ I0) C₀ is the historical cost at the base period, Cₜ is the estimated current cost, I₀ is the index in the base period, and Iₜ is the current index. Both indexes must refer to the same category, geography, and basis. The method assumes that the selected index adequately represents the cost movement. Published and market pricesCatalogues, commodity exchanges, public tenders, distributor lists, and independent market reports can provide benchmarks. Analysts must check whether published prices include normal discounts, minimum order quantities, channel margins, or special terms. Total price comparisonFor a standard item, a low price is not persuasive if it creates more defects, late deliveries, or emergency orders. The comparison should therefore move from unit price to landed cost and, where relevant, total cost of ownership. 4. Cost Indexes and EscalationCost indexes measure relative change over time. They are useful when current supplier data are unavailable, but they do not prove that a particular supplier's cost changed by exactly the index percentage. For a product whose cost consists of several components, a weighted index is more appropriate: Ct = C0 × [wm(Im,t ÷ Im,0) + wl(Il,t ÷ Il,0) + wo(Io,t ÷ Io,0)] Here, w_m, w_l, and w_o are the material, labour, and overhead proportions of the base cost; their sum is 1. I_m, I_l, and I_o are the corresponding indexes. The model assumes that the weights remain stable and that each index appropriately represents its component. Worked example. A component historically cost $100, consisting of 50% material, 30% labour, and 20% overhead. Material has risen by 12%, labour by 6%, and overhead by 4%. Ct = 100 × [0.50(1.12) + 0.30(1.06) + 0.20(1.04)] Ct = 100 × [0.560 + 0.318 + 0.208] = $108.60 The estimate is $108.60. It is a benchmark for investigation, not an automatic entitlement to a price increase. The analyst should ask whether productivity, design changes, supplier margins, currency effects, and volume changes offset some of the escalation. 5. Break-Even AnalysisBreak-even analysis identifies the activity level at which total revenue equals total cost. It helps a buyer evaluate supplier tooling, volume commitments, outsourcing, and quantity discounts. If selling price per unit is p, variable cost per unit is v, and fixed cost is F, the break-even quantity is: QBE = F ÷ (p − v) The denominator p − v is the unit contribution margin. The formula assumes constant price and variable cost, fixed cost within the relevant range, and all output is sold. Worked example. A supplier must invest $60,000 in dedicated tooling. The supplier's selling price is $80 per unit and variable cost is $50 per unit. QBE = 60,000 ÷ (80 − 50) = 2,000 units The supplier recovers the tooling cost after 2,000 units before considering other fixed costs and profit. If the buyer expects only 1,200 units, it may negotiate shared tooling, a tooling amortization charge, a reusable design, or an alternative manufacturing process. For a buyer comparing internal production with purchase, use the difference in fixed costs and variable costs. If internal production has fixed cost F_i and variable cost v_i, while external purchase costs p per unit and avoids the internal fixed cost only under the stated decision, the indifference quantity is: Q = Fi ÷ (p − vi) This is valid only when the alternatives have comparable quality, capacity, logistics, tax, and risk conditions. A common error is to include unavoidable fixed costs in one alternative but not the other. 6. Learning CurvesLearning curves describe the reduction in average labour time or cost as cumulative production increases. Repetition, improved methods, better tooling, training, and process stabilization can increase productivity. Learning is not guaranteed; automation, staff turnover, design changes, and interruptions may alter the pattern. The cumulative-average learning model is: Y = aXb Y is the average labour time or cost per unit for the first X cumulative units, a is the time or cost for the first unit, and b is the learning exponent. If the learning rate is r, expressed as a decimal such as 0.80, then: b = log(r) ÷ log(2) The model assumes that each doubling of cumulative output multiplies cumulative average time by r. It applies to a reasonably stable product and process, and should not be extrapolated beyond observed experience without validation. Worked example. The first unit requires 100 labour-hours and the learning rate is 80%. For 2 units, average time is 100 × 0.80 = 80 hours, so cumulative time is 160 hours. For 4 units, average time is 80 × 0.80 = 64 hours, so cumulative time is 256 hours. The second batch of two units therefore requires 96 hours, not 128 hours. This distinction between average and incremental time is essential in quotation analysis. Learning curves may support negotiation of future prices, labour standards, and ramp-up schedules. They should not be used to demand unrealistic reductions where the supplier is already mature or where material, energy, and purchased-component costs dominate. 7. Should-Cost EstimationA should-cost estimate is the buyer's reasoned estimate of what a product or service ought to cost under specified assumptions. It is not a claim that the supplier's actual accounting cost must equal the estimate. Its purpose is to reveal cost drivers, test quotations, identify negotiation opportunities, and support design decisions. A basic manufacturing should-cost model may contain: - Material quantity × standard material price.
- Direct labour hours × labour rate.
- Machine hours × machine rate.
- Setup, tooling, and testing.
- Scrap and yield losses.
- Logistics and packaging.
- Appropriate overhead and profit assumptions.
For material with yield loss: Material cost per good unit = (Input quantity × Material price) ÷ Yield Yield is the proportion of input that becomes acceptable output and must be expressed as a decimal. If input is 2 kg, material price is $5/kg, and yield is 95%: Material cost = (2 × 5) ÷ 0.95 = $10.53 Illustrative should-cost example. A fabricated bracket requires 3 kg of steel at $4/kg, 0.4 labour-hours at $25/hour, 0.2 machine-hours at $30/hour, $1.50 packaging, and $2.00 inspection. Yield is 98%. The direct material cost is: (3 × 4) ÷ 0.98 = $12.24 The estimated conversion and other costs are: $12.24 + (0.4 × 25) + (0.2 × 30) + 1.50 + 2.00 = $30.74 If an agreed overhead and profit allowance is 15% of this subtotal: Should-cost = 30.74 × 1.15 = $35.35 The estimate must state whether the 15% is a markup on cost or a margin on sales. These are not equivalent. A 15% markup gives price = cost × 1.15; a 15% margin means price = cost ÷ 0.85. Should-cost models require controlled data. Labour rates should identify skill and geography; material prices should identify grade and delivery basis; machine rates should avoid double-counting labour or overhead. Sensitivity analysis is valuable: if steel price rises 10%, the model should show the effect on the total rather than hiding it in an unexplained adjustment. 8. Landed Cost and Total Cost of OwnershipLanded costLanded cost is the cost of bringing an item to the buyer's specified location and condition. A general structure is: Landed cost = Purchase price − Discounts + Freight + Insurance + Duties + Taxes + Brokerage + Handling + Inspection Whether taxes are included depends on recoverability. A recoverable value-added tax is usually excluded from economic cost; a nonrecoverable tax is included. Currency conversion must use a stated exchange rate and date or hedging basis. Example. A shipment contains 1,000 units at $20 each. Freight is $800, insurance $100, duty is 5% of invoice value, and handling is $300. A recoverable tax is excluded. Invoice value = 1,000 × $20 = $20,000. Duty = 0.05 × 20,000 = $1,000 Landed cost = 20,000 + 800 + 100 + 1,000 + 300 = $22,200 Landed cost per unit = 22,200 ÷ 1,000 = $22.20 The customs valuation basis may differ from the simplified example; actual classification and regulations must be checked. Total cost of ownershipTotal cost of ownership (TCO) considers costs across the acquisition and use life of an item: TCO = Ca + Ct + Co + Cm + Cq + Cr + Cd − R C_a is acquisition cost, C_t transaction and implementation cost, C_o operating cost, C_m maintenance cost, C_q quality and failure cost, C_r risk-related expected cost, C_d disposal cost, and R residual value or recoverable benefit. The terms must cover the same time horizon and quantity. For multi-year assets, cash flows should normally be discounted. Present value is: PV = CFt ÷ (1 + i)t CF_t is cash flow at period t, i is the discount rate per period, and t is the number of periods. If costs occur at different dates, TCO is the sum of their present values. Discounting assumes a chosen rate and reasonably estimable timing; it should not be used to conceal uncertain operational risks. TCO example. Supplier A offers equipment for $50,000, installation $4,000, annual energy $6,000 for three years, maintenance $3,000 per year, and disposal $2,000. Supplier B offers equipment for $58,000, installation $2,000, annual energy $3,500, maintenance $2,000 per year, and disposal $1,000. Ignoring discounting for simplicity: A: 50,000 + 4,000 + 3(6,000 + 3,000) + 2,000 = $83,000. B: 58,000 + 2,000 + 3(3,500 + 2,000) + 1,000 = $77,500. Although B's purchase price is $8,000 higher, its three-year TCO is $5,500 lower. The conclusion depends on equal capacity, reliability, service scope, and operating assumptions. 9. Procurement Savings and BaselinesSavings are meaningful only when the baseline, timing, volume, and quality conditions are explicit. Common measures include: Purchase price savings = (Baseline unit price − Actual unit price) × Actual quantity Savings percentage = Savings ÷ (Baseline unit price × Actual quantity) × 100 A baseline may be the previous valid price, approved budget, competitive alternative, or should-cost estimate. Each has a different interpretation. Avoided cost, cost reduction, cost avoidance, and negotiated savings should not be mixed in one figure. Example. The baseline is $12 per unit, the negotiated price is $11.20, and actual quantity is 5,000 units. Savings = (12.00 − 11.20) × 5,000 = $4,000 Savings percentage = 4,000 ÷ 60,000 × 100 = 6.67% If freight increases by $0.30 per unit after negotiation, the net landed saving is only ($12.00 − $11.20 − $0.30) × 5,000 = $2,500. Savings claims should also account for changed specifications, lower service levels, inventory carrying cost, supplier development cost, and implementation expenditure. 10. Applied Case: Selecting a Compressed-Air SystemThe following is an illustrative case designed for learning purposes. BackgroundA medium-sized manufacturer needs a compressed-air system for a five-year operating period. Two suppliers submit offers. Supplier A has a lower acquisition price; Supplier B proposes a more efficient system with higher installation cost. | Item | Supplier A | Supplier B |
|---|
| Equipment price | $42,000 | $50,000 | | Installation | $3,000 | $5,000 | | Annual energy | $12,000 | $8,000 | | Annual maintenance | $4,000 | $3,000 | | Expected annual failure cost | $2,000 | $800 | | Disposal cost at year 5 | $2,000 | $1,500 | | Residual value at year 5 | $3,000 | $5,000 |
ProblemThe engineering department initially recommends A because it is cheaper to purchase. Procurement must test whether that conclusion remains valid over the equipment life. AnalysisUsing undiscounted TCO for a preliminary comparison: TCOA = 42,000 + 3,000 + 5(12,000 + 4,000 + 2,000) + 2,000 − 3,000 TCOA = $144,000 TCOB = 50,000 + 5,000 + 5(8,000 + 3,000 + 800) + 1,500 − 5,000 TCOB = $115,500 Supplier B costs $28,500 less over five years under the stated assumptions. The annual operating advantage is partly responsible: energy, maintenance, and expected failure costs are $6,200 lower per year for B. A sensitivity test should examine whether B remains preferable if its energy saving is overstated. The annual difference excluding energy is $3,200. B's energy advantage is $4,000 per year. Even if only half the energy advantage is achieved, B's annual operating benefit remains $5,200 ($2,000 energy plus $3,000 maintenance/failure benefit), so the direction of the result is robust in this simple model. A formal evaluation should use measured demand, tariff assumptions, discounting, service response, warranty terms, and capacity verification. Approach and solutionThe procurement team should: - Confirm that both systems meet air-quality, pressure, flow, safety, and regulatory requirements.
- Validate energy estimates using expected load profile rather than nameplate capacity alone.
- Request a warranty covering performance and failure response.
- Include commissioning, operator training, spare parts, and disposal responsibilities in the contract.
- Record the TCO assumptions in the award recommendation.
- Establish post-award measurement of energy use, downtime, and maintenance cost.
Outcome and learning pointsB is the economically preferred option in the illustrative model despite its higher initial price. The case demonstrates that acquisition price is only one component of value. It also demonstrates the importance of expected failure cost: a risk estimate should be evidence-based, using historical failure rates and credible consequence costs rather than arbitrary allowances. 11. Governance, Ethics and Contemporary PracticeCost and price analysis involves commercially sensitive information. Procurement staff should protect supplier data, avoid sharing one supplier's confidential cost breakdown with another, and comply with competition, public procurement, tax, customs, and record-retention rules. A buyer must not manipulate a should-cost model to force an unfair price or use a false competitive quotation as leverage. Supplier cost transparency should be proportionate to risk. Open-book costing may be justified for a sole-source defence item or long-term strategic contract, while a catalogue purchase normally does not require disclosure of internal labour rates. Audit rights, confidentiality clauses, approved cost classifications, and change-control procedures make open-book arrangements workable. Digital procurement systems can compare quotations, normalize landed cost, monitor indexes, and identify unusual price movements. Artificial intelligence may assist with classification, spend analysis, and anomaly detection, but its outputs require human validation. Risks include poor master data, biased historical prices, confidential-data leakage, unexplained recommendations, and false precision. The accountable procurement professional remains responsible for assumptions, approvals, and decisions. Contemporary value analysis increasingly includes carbon cost, circularity, repairability, energy consumption, labour practices, and supply-chain resilience. These factors should be translated into clear requirements or evaluated criteria rather than inserted as vague preferences. A low-cost supplier that creates unacceptable environmental, social, safety, or continuity risk is not a low-value supplier. 12. Common Errors and Best PracticesFrequent errors include comparing unlike price bases, treating allocated overhead as avoidable cost, double-counting freight, applying a general inflation index to a specialized component, confusing markup with margin, ignoring learning-curve maturity, and claiming savings without a documented baseline. Best practice is to: - define the decision, time horizon, quantity, currency, and delivery basis;
- separate facts, estimates, and assumptions;
- use price analysis before demanding detailed supplier cost data;
- reconcile should-cost models with engineering and operational evidence;
- test major assumptions through sensitivity and scenario analysis;
- evaluate TCO where operating or failure costs are material;
- document baseline and savings ownership before negotiation;
- maintain an audit trail for formulas, sources, approvals, and revisions; and
- review actual results after award to improve future estimates.
Chapter SummaryCost is the resource consumed, price is the transaction amount, and value is the benefit obtained relative to total resources and risk. Price analysis tests reasonableness through market and historical comparisons; cost analysis reconstructs the supplier's cost structure; value analysis examines whether required functions can be delivered more economically. Cost structures distinguish fixed, variable, direct, indirect, relevant, sunk, and opportunity costs. Break-even analysis links fixed investment and contribution margin to volume. Learning curves estimate productivity improvement but require stable processes and careful separation of average from incremental time. Cost indexes update historical values, while weighted indexes reflect different material, labour, and overhead movements. Should-cost models provide a transparent buyer benchmark based on material, labour, machine, yield, logistics, overhead, and profit assumptions. Landed cost adds the expenditure required to receive an item; TCO adds operating, maintenance, quality, risk, and disposal costs over the relevant life. Procurement savings are credible only when the baseline, actual quantity, scope, and quality conditions are documented. Ethical governance, data quality, sensitivity analysis, and post-award verification are essential for evidence-based procurement decisions. Key TermsCost: Economic resource consumed to produce, acquire, use, or dispose of an item. Price: Amount charged or paid in a transaction. Value analysis: Examination of function, performance, cost, and risk to improve economic value. Price analysis: Evaluation of price reasonableness using market or comparative evidence. Cost analysis: Examination of the elements that build a supplier's cost and price. Direct cost: Cost traceable economically to a specific item or activity. Indirect cost: Cost supporting several items or activities and allocated by a method. Fixed cost: Cost that remains constant within a relevant range and period. Variable cost: Cost that changes with activity or output. Relevant cost: Future cost that differs between decision alternatives. Opportunity cost: Benefit sacrificed by using a resource for its next-best alternative. Break-even point: Activity level at which total revenue equals total cost. Learning curve: Model of productivity improvement with cumulative production. Cost index: Measure of relative cost movement over time. Should-cost estimate: Buyer-developed estimate of economically reasonable cost. Landed cost: Cost of bringing an item to the required destination and condition. Total cost of ownership: Life-cycle cost of acquiring, using, maintaining, and disposing of an item. Baseline: Agreed reference against which a price or saving is measured. Markup: Addition to cost used to determine price. Margin: Profit expressed as a proportion of selling price. Review QuestionsShort Answer Questions- Distinguish price analysis from cost analysis.
- What is the difference between a fixed cost and a variable cost?
- Why must a historical price be adjusted before it is used as a benchmark?
- Define landed cost and identify four components that may be included in it.
- Why is a savings baseline necessary?
Long Answer Questions- Explain how cost structures assist a procurement professional in negotiating a complex manufactured item.
- Describe the assumptions and limitations of break-even analysis and learning-curve analysis.
- Explain the construction of a should-cost model, including material yield, labour, overhead, and profit.
- Compare acquisition price, landed cost, and total cost of ownership using a suitable procurement example.
- Discuss ethical, confidentiality, and governance issues in supplier cost analysis.
Analytical / Application Questions- A component had a historical cost of $80. Material represented 60%, labour 25%, and overhead 15%. Material, labour, and overhead indexes have increased by 10%, 5%, and 8%, respectively. Calculate the indexed estimate and explain two reasons why the supplier's quoted price might differ.
- A buyer compares an item at $18 per unit with a landed cost of $2 per unit against an alternative at $19.20 with a landed cost of $0.50 per unit. For 10,000 units, calculate each total delivered cost and recommend an option, stating any assumptions that require checking.
- A supplier quotes $100,000 for equipment, $10,000 installation, and annual operating and maintenance costs of $22,000 for four years. Disposal is $4,000 and residual value is $6,000. Calculate undiscounted TCO and identify at least three additional factors that could change the decision.
Multiple Choice Questions with AnswersQuestion 1Which statement best distinguishes price analysis from cost analysis? A. Price analysis examines supplier labour hours only. B. Price analysis tests price reasonableness using comparative evidence, while cost analysis examines cost elements. C. Cost analysis is used only for catalogue purchases. D. Price analysis always requires complete supplier open-book records. Correct Answer: B. Price analysis tests price reasonableness using comparative evidence, while cost analysis examines cost elements. Question 2A product has fixed cost of $30,000, selling price of $50, and variable cost of $35 per unit. What is the break-even quantity? A. 600 units B. 857 units C. 2,000 units D. 15,000 units Correct Answer: C. 2,000 units Question 3A historical cost is $200. The relevant cost index was 120 then and is 132 now. What is the indexed estimate? A. $181.82 B. $212.00 C. $220.00 D. $332.00 Correct Answer: C. $220.00 Question 4In a cumulative-average learning curve, an 80% learning rate means that when cumulative output doubles, the average time per unit becomes: A. 80% of its previous average B. 20% of its previous average C. 80 hours regardless of the first-unit time D. Twice its previous average Correct Answer: A. 80% of its previous average Question 5Which item is normally excluded from economic landed cost when it is fully recoverable by the buyer? A. Freight B. Import duty C. Recoverable value-added tax D. Insurance Correct Answer: C. Recoverable value-added tax Question 6An item costs $15 each, freight is $500, duty is $250, and handling is $250 for a shipment of 100 units. What is the landed cost per unit? A. $15.00 B. $20.00 C. $25.00 D. $25.50 Correct Answer: C. $25.00 Question 7Which expression represents a basic total cost of ownership concept? A. Purchase price only B. Purchase price plus life-cycle operating, maintenance, risk, and disposal costs less residual value C. Quoted price minus supplier profit D. Annual maintenance cost divided by quantity Correct Answer: B. Purchase price plus life-cycle operating, maintenance, risk, and disposal costs less residual value Question 8A buyer's baseline is $10 per unit, negotiated price is $9.40, and actual quantity is 2,000 units. What is the purchase price saving? A. $600 B. $1,200 C. $18,800 D. $20,000 Correct Answer: B. $1,200 Question 9Which statement about a should-cost estimate is correct? A. It is necessarily the supplier's actual accounting cost. B. It is a buyer's reasoned benchmark based on stated technical and commercial assumptions. C. It excludes material yield losses. D. It replaces the need to verify specifications. Correct Answer: B. It is a buyer's reasoned benchmark based on stated technical and commercial assumptions. Question 10A 15% markup on a cost of $40 produces what price? A. $34.00 B. $40.15 C. $46.00 D. $47.06 Correct Answer: C. $46.00
|