Project Risk Management & Modeling

Chapter 7
Schedule Risk Analysis

Post Graduate Program in Project Management
Project Risk Management & Modeling   •   Post Graduate

Schedule Risk Analysis

Introduction and Context

A project schedule is not a single forecast date; it is a model of how uncertain activities, dependencies, resources, and external conditions combine to produce possible completion outcomes. Schedule risk analysis (SRA) makes this uncertainty explicit. It supports decisions such as setting a credible completion commitment, sizing time contingency, identifying activities that deserve management attention, and evaluating whether acceleration investments are worthwhile.

Traditional critical path method (CPM) uses one duration estimate for each activity and identifies the longest path through a network. This is useful for planning, but it can create false confidence. Activity durations are uncertain, the critical path may change from one scenario to another, and activities with substantial schedule influence may not be critical in the deterministic baseline. Probabilistic schedule analysis addresses these limitations by modelling duration uncertainty and repeatedly evaluating the project network.

SRA is therefore not simply a more complicated CPM calculation. It is a decision-support discipline combining network logic, probability modelling, simulation, statistical interpretation, and governance judgment.

Learning Objectives

By the end of this chapter, the reader should be able to:

  1. Explain activity-duration uncertainty and distinguish aleatory variability from epistemic uncertainty.
  2. Construct and evaluate probabilistic activity-duration models.
  3. Explain critical-path volatility, merge bias, criticality indices, and schedule sensitivity.
  4. Use network simulation to estimate probabilistic completion dates and time contingency.
  5. Interpret simulation results responsibly, including assumptions, correlation, and model limitations.
  6. Apply SRA to a project case and make defensible managerial recommendations.

1. The Network Foundation

A precedence network represents activities as nodes or arrows and dependencies as directed links. For an activity i, let:

  • di = activity duration;
  • ESi = earliest start;
  • EFi = earliest finish;
  • LSi = latest start consistent with the specified completion date;
  • LFi = latest finish;
  • TFi = total float.

For a finish-to-start relationship with no lag:

EFi = ESi + di

For an activity with predecessors Pi:

ESi = max(EFj : j ∈ Pi)

Total float is:

TFi = LSi − ESi = LFi − EFi

These equations assume a correctly specified acyclic network, deterministic durations, and the stated relationship types. Durations and floats must use the same unit, such as working days. The deterministic project duration is the earliest finish of the final activity or the maximum earliest finish among terminal activities.

The deterministic critical path is the path with zero total float under the selected baseline durations. In a probabilistic model, however, “the critical path” is a scenario-specific result. A path can be critical in one simulated outcome and noncritical in another.

2. Sources and Types of Schedule Uncertainty

Schedule uncertainty arises from several sources:

  • Duration variability: the same work may take different amounts of time because of productivity, weather, defects, or learning.
  • Event uncertainty: an event such as regulatory approval or a supplier failure may occur or not occur.
  • Epistemic uncertainty: limited knowledge about scope, design maturity, or conditions creates uncertainty that may be reduced through investigation.
  • Aleatory uncertainty: inherent variation remains even with excellent knowledge, such as random processing time.
  • Network uncertainty: missing, incorrect, or changing dependencies alter the structure of the schedule.
  • Resource uncertainty: limited shared resources create competition, queuing, or reassignment.
  • Correlation: activities may be jointly affected by a common cause, such as a late design package or severe weather.

A schedule model should distinguish uncertainty in the activity duration from uncertainty in the network logic. If a required predecessor is omitted, simulation of durations alone may produce precise but invalid results.

2.1 Three-Point Duration Estimates

Three-point estimating commonly uses optimistic, most-likely, and pessimistic values:

  • a: optimistic duration under favourable but credible conditions;
  • m: most-likely duration;
  • b: pessimistic duration under adverse but credible conditions.

The triangular distribution is defined directly by these three values and is useful when the estimator can describe a lower bound, mode, and upper bound. Its expected value is:

E[D] = (a + m + b) / 3

Its variance is:

Var(D) = (a² + m² + b² − am − ab − mb) / 18

These formulas apply to a triangular distribution with minimum a, mode m, and maximum b, where a ≤ m ≤ b. Duration units are squared in the variance.

A beta-PERT distribution is often used when the three estimates are intended to describe a smoother, bounded distribution. A common PERT mean approximation is:

E[D] = (a + 4m + b) / 6

A commonly used approximate standard deviation is:

σD = (b − a) / 6

The PERT approximation is a modelling convention rather than a universal law. It gives greater weight to the most-likely estimate and assumes that the optimistic and pessimistic estimates represent approximately six standard deviations across the practical range. The analyst should document whether the values are true distribution parameters or expert elicitation points.

Worked Example 1: Estimating an Activity Distribution

Suppose system testing has estimates of 8, 12, and 22 working days for a, m, and b. Using the PERT approximation:

E[D] = (8 + 4×12 + 22) / 6 = 78 / 6 = 13 days
σD = (22 − 8) / 6 = 2.33 days

The expected duration is 13 working days, not 12 days. The most-likely value is the mode, whereas the expected value is the probability-weighted average. Confusing these two values systematically biases a schedule model toward the mode.

3. From Activity Uncertainty to Project Uncertainty

For a serial chain of activities, project duration is the sum of activity durations:

T = D1 + D2 + … + Dn

If the durations are independent:

E[T] = ∑ E[Di]
Var(T) = ∑ Var(Di)

If durations are correlated, the general variance is:

Var(T) = ∑ Var(Di) + 2∑i<j Cov(Di,Dj)

where Cov(Di,Dj) is covariance. Positive covariance increases project uncertainty; negative covariance reduces it. Independence must not be assumed merely because activities have different names. Common suppliers, weather, design quality, labour markets, and management decisions can create material dependence.

For parallel activities, the relevant completion time is a maximum, not a sum. If two branches feed a merge node:

Tmerge = max(TA, TB)

Consequently, the expected project duration is generally not equal to the duration of the path formed by separately expected activity durations. In general:

E[max(TA,TB)] ≠ max(E[TA],E[TB])

This distinction is central to simulation-based SRA.

4. Critical-Path Volatility and Merge Bias

4.1 Critical-Path Volatility

Critical-path volatility is the tendency for the critical path to change across plausible project outcomes. It occurs when competing paths have similar expected durations or when their uncertainties differ substantially. A deterministic schedule may show Path A as critical, while simulated outcomes may frequently show Path B or Path C as controlling completion.

Volatility has managerial implications. A team that monitors only the baseline critical path may overlook a near-critical path that becomes controlling after modest delay. Risk responses should therefore consider criticality and sensitivity across the distribution of outcomes.

4.2 Merge Bias

A merge point is a node where two or more predecessor branches must finish before downstream work can start. Because the successor waits for the latest predecessor, delays on several branches can accumulate in the project outcome even when each branch individually appears unlikely to be late.

This effect is sometimes called merge bias. It does not imply that the mathematical network is biased; rather, a deterministic schedule based on mean or most-likely durations can understate the expected waiting time at merges. If two independent branches have equal expected duration but variability, the expected maximum is greater than that common expected duration.

For two normally distributed branch durations, X and Y, the expected maximum can be expressed as:

E[max(X,Y)] = μX Φ(k) + μY Φ(−k) + σZ φ(k)

where:

k = (μX − μY) / σZ

and σZ = √(σX² + σY² − 2ρσXσY). Here μX and μY are means, σX and σY are standard deviations, ρ is correlation, and Φ and φ are the standard normal cumulative distribution and density functions. This expression assumes jointly normal branch durations and is mainly illustrative; bounded or skewed activity distributions are usually better represented directly through simulation.

4.3 Simple Merge Illustration

Suppose two independent branches each have a mean duration of 10 days and a standard deviation of 2 days. Their merge completion is the maximum of the two. Although each branch has mean 10 days, the maximum will generally have an expected value above 10 days because one branch often exceeds 10 days while the other may not. A model that simply uses 10 days for each branch and takes the maximum reports 10 days and therefore misses this uncertainty effect.

5. Monte Carlo Network Simulation

Monte Carlo simulation repeatedly samples uncertain durations, propagates them through the network, and records project outcomes. A basic iteration is:

  1. Sample a duration for every uncertain activity.
  2. Apply network logic using the sampled durations.
  3. Calculate project completion time.
  4. Calculate floats and identify the controlling or critical path.
  5. Store relevant outputs.
  6. Repeat for a sufficiently large number of iterations.

A simplified pseudocode representation is:

for iteration = 1 to N:
    for each activity i:
        sample d_i from its specified distribution
    perform forward pass through the network
    record project finish T
    perform backward pass using the sampled finish date
    record activity float and critical-path membership
summarise T and activity statistics

The simulated completion-date distribution produces percentiles. If T is project duration, the p-th percentile tp satisfies:

P(T ≤ tp) = p

Thus, a P80 date is a date that the model estimates will be achieved with probability 0.80, subject to model assumptions. It is not a guarantee.

5.1 Number of Iterations and Sampling Error

Simulation results are estimates. More iterations generally reduce Monte Carlo sampling error, but they do not correct a poor network or unrealistic distributions. The standard error of the estimated sample mean is approximately:

SE(ȳ) = s / √N

where s is the sample standard deviation of simulated project duration and N is the number of iterations. Percentile estimates may require more iterations than mean estimates, particularly in the tails. Analysts should examine convergence by comparing percentiles across successive simulation batches.

Latin hypercube sampling can improve coverage of input distributions with fewer iterations than simple random sampling. It does not remove modelling error and must be used consistently with the treatment of correlation.

6. Criticality, Sensitivity, and Schedule Drivers

6.1 Criticality Index

The criticality index of activity i is:

CIi = Ci / N

where Ci is the number of simulations in which activity i is on the controlling critical path and N is the total number of simulations. A criticality index of 0.70 means that the activity was critical in 70% of simulated scenarios under the chosen definition.

Criticality index is a frequency measure, not a direct measure of delay impact. An activity can be critical frequently but have little duration variability, while another activity can be critical less often yet create large delays when it is long.

6.2 Schedule Sensitivity

Schedule sensitivity measures how strongly an activity’s uncertainty is associated with project completion uncertainty. Common measures include rank correlation between sampled activity duration and project duration, standardized regression coefficients, and sensitivity indices based on variance decomposition.

A rank correlation is useful when distributions are non-normal or relationships are nonlinear. A high positive correlation indicates that longer activity durations tend to accompany longer project durations. Correlation does not prove that changing the activity will cause the observed project change; the network and other variables may mediate the relationship.

A useful managerial classification is:

PatternInterpretationResponse implication
High CI, high sensitivityFrequent and influential driverPrioritise active management and response planning
High CI, low sensitivityOften critical but relatively stableProtect logic and monitor execution
Low CI, high sensitivityInfrequent but consequential driverPrepare contingency or targeted mitigation
Low CI, low sensitivityLimited current influenceAvoid disproportionate management effort

6.3 Criticality Is Not Sufficient

A deterministic zero-float activity is not automatically the greatest risk. Conversely, a high criticality index does not establish that mitigation is cost-effective. Decisions should combine probability, impact, controllability, response cost, and strategic consequence.

7. Probabilistic Completion Dates and Time Contingency

A schedule commitment should distinguish at least three dates:

  1. Expected date: the mean or another central estimate of simulated completion.
  2. Target or committed date: a date selected through governance and risk appetite.
  3. Contingency allowance: time between a planning date and the selected confidence date.

If the deterministic baseline date is t0 and the selected percentile date is tp, a simple schedule contingency allowance is:

Cp = tp − t0

The units are time, such as working days or calendar weeks. This calculation is meaningful only when the baseline and percentile are defined on a comparable calendar and include equivalent scope, calendars, constraints, and milestones.

A percentile is not automatically the correct management target. A high-confidence date may be unnecessarily conservative if it delays benefits or creates idle capacity. A low-confidence date may be unacceptable for a regulatory or contractual milestone. Confidence selection should reflect risk appetite, contractual exposure, cost of delay, and the quality of the underlying model.

Contingency should be governed rather than hidden. A project may maintain an approved time reserve, define who can consume it, record causes of consumption, and periodically reforecast the remaining distribution.

8. Worked Network Example

Consider the following activities, measured in working days:

ActivityPredecessorOptimisticMost likelyPessimistic
A: Requirements—81016
B: ArchitectureA6814
C: ProcurementA101424
D: BuildB182436
E: InstallationC121830
F: IntegrationD, E81220
G: AcceptanceF5713

Using PERT means, the expected durations are approximately:

  • A: (8+4×10+16)/6 = 10.67 days;
  • B: (6+4×8+14)/6 = 8.67 days;
  • C: (10+4×14+24)/6 = 15.00 days;
  • D: (18+4×24+36)/6 = 25.00 days;
  • E: (12+4×18+30)/6 = 19.00 days;
  • F: (8+4×12+20)/6 = 12.67 days;
  • G: (5+4×7+13)/6 = 8.00 days.

The two principal paths are A–B–D–F–G and A–C–E–F–G. Based on expected durations, their sums are approximately:

A−B−D−F−G = 10.67 + 8.67 + 25 + 12.67 + 8 = 65.01 days
A−C−E−F−G = 10.67 + 15 + 19 + 12.67 + 8 = 65.34 days

The paths are nearly equal. A deterministic conclusion that the procurement path is permanently critical would therefore be weak. Simulation is appropriate because the merge at F takes the later of the two branches. In a model, each activity would receive a sampled duration, the forward pass would calculate the later predecessor finish at F, and the resulting completion date would be recorded. The analyst would then report the completion-date percentiles, path frequencies, activity criticality indices, and sensitivity measures rather than only one “critical path.”

9. Applied Case: Illustrative Data-Centre Migration

Background

The following is a fictional illustrative case. A financial-services organisation plans to migrate a customer-facing application to a new data centre. The contractual service transition date is important, but the organisation also faces uncertainty in network configuration, security testing, vendor equipment delivery, and operational acceptance.

Problem

The baseline CPM schedule forecasts completion in 20 weeks. The project board observes that two technical branches converge before integrated testing. The infrastructure branch has a slightly shorter baseline duration but greater delivery uncertainty. Executives ask whether 20 weeks is a credible commitment and how much time reserve is justified.

Analysis

The project controls team validates the work breakdown structure and identifies several model risks:

  • a vendor approval dependency was missing from an early draft;
  • infrastructure delivery and installation durations share a supplier-risk factor;
  • security testing duration is affected by the maturity of the configuration;
  • the two major technical branches merge before integrated testing.

The team elicits three-point estimates, uses bounded skewed distributions for activity durations, and models supplier-related durations with positive correlation. It runs 50,000 Latin hypercube iterations and checks percentile stability using independent batches. It records completion dates, path membership, criticality indices, and rank correlations.

The results indicate an expected completion of 20.8 weeks, a P50 of 20.6 weeks, a P80 of 22.4 weeks, and a P90 of 23.3 weeks. The baseline 20-week date has an estimated probability below 0.50. The infrastructure branch is critical in 46% of simulations, the application branch in 39%, and mixed or changing paths account for the remainder. Security testing has a lower criticality index than the main construction activities but one of the highest duration-to-completion sensitivity measures.

Approach and Solution

The board rejects the assumption that the baseline critical path alone defines exposure. It adopts 22.4 weeks as the planning commitment for internal capacity and retains a separate management reserve for exceptional supplier events. Actions include:

  1. early supplier design review;
  2. a prototype configuration before full installation;
  3. reserved security-test capacity;
  4. a decision gate before committing to the final migration weekend;
  5. weekly updating of distributions using actual progress and remaining work.

Outcome

The project completes in 21.9 weeks. The infrastructure branch becomes critical during installation, but the prototype reduces rework. The project does not consume the full time reserve. More importantly, the board’s decision was based on an explicit confidence level and a transparent model rather than an unsupported promise.

Learning Points

The case demonstrates that:

  • critical paths can change;
  • merge points can increase completion exposure;
  • correlation can matter materially;
  • a percentile date is a decision choice, not a discovered certainty;
  • model validation and governance are as important as simulation software.

10. Model Governance, Ethics, and Technology

10.1 Data and Expert Judgment

Historical duration data should be segmented by comparable work type, team capability, technology, scale, and environmental conditions. Combining unlike projects can create a misleading distribution. Expert estimates should record rationale, evidence, confidence, and potential incentives. Estimates that are intentionally optimistic to secure approval are a governance failure, not a modelling assumption.

10.2 Correlation and Double Counting

Risk events should not be added independently when they share a cause. For example, a design defect may lengthen redesign, testing, and training. Modelling the common cause once and then separately adding full duration impacts can double count exposure. Conversely, ignoring common causes can understate tail risk.

10.3 Constraints and Resources

A precedence-only simulation may be inadequate where resources are scarce. Resource levelling, calendars, shifts, weather windows, and contractual milestones can materially change results. If the real schedule is resource constrained, the simulation engine should model resource logic or the results should be explicitly labelled as a precedence-network approximation.

10.4 AI and Contemporary Practice

AI-assisted forecasting can identify patterns in historical schedules, text-based risk registers, issue logs, and progress data. It can support anomaly detection and estimate updating, but it should not be treated as an objective oracle. Important controls include data lineage, explainability, validation against out-of-sample projects, bias testing, human review, and protection of confidential information. Generative systems may produce plausible but unsupported dependencies or estimates; every AI-generated input requires professional verification.

10.5 Model Risk

Model risk is the possibility that decisions are harmed by an incorrect, incomplete, or misused model. A robust SRA should maintain:

  • a version-controlled network;
  • documented distribution rationale;
  • assumptions and exclusions;
  • correlation rationale;
  • validation and sensitivity tests;
  • clear definitions of critical path and percentile;
  • reproducible simulation settings;
  • change control and approval records.

11. Limitations and Best Practices

SRA does not predict the future with certainty. Its outputs are conditional on the network, distributions, calendars, correlations, and behavioural assumptions. Common limitations include optimistic three-point estimates, false precision, omitted scope, unstable logic, inadequate iteration counts, and misuse of percentile dates as guarantees.

Best practice is to:

  1. validate the network before fitting distributions;
  2. separate uncertainty from identifiable risk events where appropriate;
  3. use evidence-based estimates and document expert judgment;
  4. test dependence and common-cause risks;
  5. analyse both criticality and sensitivity;
  6. examine percentile stability and tail behaviour;
  7. include resources, calendars, and constraints when material;
  8. communicate confidence levels in plain language;
  9. update the model as actual performance changes;
  10. link mitigation decisions to measurable changes in the distribution.

A useful response is not merely “add ten days.” It is to explain which date has what confidence, what assumptions support it, what risks consume the reserve, and what actions could shift the distribution leftward or reduce its spread.

Chapter Summary

Schedule risk analysis extends CPM by representing uncertain activity durations, uncertain path selection, dependence, and merge behaviour. Three-point distributions such as triangular and beta-PERT models provide practical ways to translate expert judgment into probability models, but their assumptions must be documented. In serial networks, expected durations and variances may be combined under stated independence assumptions; in parallel networks, completion depends on the maximum of branch durations.

Critical-path volatility means that the controlling path can change across scenarios. Merge bias arises because a successor waits for the latest predecessor, so deterministic use of central estimates can understate expected completion exposure. Monte Carlo simulation samples activity durations, propagates them through the network, and produces completion-date distributions. Percentiles such as P80 support confidence-based commitments, while contingency can be expressed as the difference between a selected percentile date and a baseline date.

Criticality indices show how frequently activities appear on the controlling path, whereas sensitivity measures show how strongly activity uncertainty relates to project completion uncertainty. Neither measure alone is sufficient for prioritising responses. Effective SRA depends on sound network logic, realistic distributions, correlation analysis, resource awareness, model governance, and transparent communication. Simulation is a disciplined aid to judgment, not a substitute for it.

Key Terms

Schedule risk analysis: Quantitative analysis of uncertainty in project completion and schedule performance.

Activity-duration uncertainty: Variability or lack of knowledge concerning the time required for an activity.

Aleatory uncertainty: Inherent random variability that is not eliminated by additional knowledge.

Epistemic uncertainty: Uncertainty caused by incomplete knowledge that may be reduced through investigation.

Critical path: The path controlling project completion under a specified scenario and set of assumptions.

Critical-path volatility: Variation in the controlling path across plausible scenarios.

Merge point: A network node requiring two or more predecessor branches to finish.

Merge bias: Understatement of completion exposure caused by treating uncertain converging branches as deterministic central values.

Triangular distribution: A bounded distribution defined by minimum, mode, and maximum values.

Beta-PERT distribution: A bounded, smoothed distribution commonly parameterised from three-point estimates.

Monte Carlo simulation: Repeated random sampling and network evaluation used to estimate an outcome distribution.

Criticality index: Proportion of simulations in which an activity is on the controlling critical path.

Schedule sensitivity: Degree to which activity uncertainty is associated with project completion uncertainty.

Percentile completion date: Date by which the model estimates completion will occur with a specified probability.

Time contingency: Deliberate time allowance held to address schedule uncertainty.

Correlation: Statistical association between uncertain variables.

Covariance: A measure of joint variation between two random variables.

Model risk: Risk arising from an incorrect, incomplete, or misused analytical model.

Latin hypercube sampling: Stratified sampling method that improves distribution coverage in simulation.

Management reserve: Controlled allowance held for uncertain or unforeseen project exposure.

Review Questions

Short Answer Questions

  1. Why can the critical path change during probabilistic schedule simulation?
  2. State the PERT approximation for expected activity duration and define its three inputs.
  3. What does a criticality index of 0.65 mean?
  4. Why is the expected maximum of two uncertain branches generally greater than the maximum of their expected durations?
  5. Distinguish aleatory uncertainty from epistemic uncertainty.

Long Answer Questions

  1. Explain how Monte Carlo simulation converts activity-duration uncertainty into a project completion-date distribution. Include the principal steps and assumptions.
  2. Compare criticality index and schedule sensitivity. Explain why a project manager should use both measures.
  3. Discuss merge bias, including its network cause and its implications for schedule contingency.
  4. Evaluate the strengths and limitations of triangular and beta-PERT duration models.
  5. Explain the governance requirements for using AI-assisted schedule forecasting in a major project.

Analytical / Application Questions

  1. A project has two independent branches feeding a common integration activity. Each branch has a mean of 15 days, but one has a standard deviation of 1 day and the other 5 days. Explain why a deterministic mean-based schedule may understate the expected integration start and propose an appropriate analysis.
  2. A simulation reports a P50 completion of 30 weeks, a P80 of 34 weeks, and a P90 of 38 weeks. The sponsor demands a 30-week commitment. Analyse the decision using risk appetite, cost of delay, governance, and contingency concepts.
  3. An activity has a criticality index of 0.25 but the highest rank correlation with project completion. Another has a criticality index of 0.85 but low sensitivity. Recommend how the project manager should investigate and prioritise responses.

Multiple Choice Questions with Answers

Question 1

Which statement best describes a criticality index of 0.70?

A. The activity has 70% schedule sensitivity.

B. The activity is critical in 70% of simulated scenarios.

C. The activity has 70 days of float.

D. The project has a 70% probability of finishing early.

Correct Answer: B. The activity is critical in 70% of simulated scenarios.

Question 2

Using the PERT approximation, what is the expected duration when a = 8, m = 12, and b = 22 days?

A. 10 days

B. 12 days

C. 13 days

D. 14 days

Correct Answer: C. 13 days

Question 3

At a merge point with no lags, the successor can start when:

A. The shortest predecessor finishes.

B. The average predecessor finishes.

C. The most-likely predecessor finishes.

D. The latest predecessor finishes.

Correct Answer: D. The latest predecessor finishes.

Question 4

What is the principal purpose of Monte Carlo network simulation?

A. To eliminate all schedule uncertainty.

B. To calculate only the deterministic critical path.

C. To estimate a distribution of possible schedule outcomes.

D. To replace the project network with a risk register.

Correct Answer: C. To estimate a distribution of possible schedule outcomes.

Question 5

If an activity’s duration and project duration have a high positive rank correlation, this usually indicates that:

A. Longer activity durations tend to accompany longer project durations.

B. The activity is always on the critical path.

C. The activity has no uncertainty.

D. The project duration is independent of the activity.

Correct Answer: A. Longer activity durations tend to accompany longer project durations.

Question 6

If the baseline completion date is 20 weeks and the selected P80 date is 22.4 weeks, the simple percentile-based contingency is:

A. 1.2 weeks

B. 2.0 weeks

C. 2.4 weeks

D. 4.4 weeks

Correct Answer: C. 2.4 weeks

Question 7

Which condition generally increases the variance of a serial project duration?

A. Negative covariance among activity durations.

B. Positive covariance among activity durations.

C. Removing all uncertain activities.

D. Replacing durations with their modes.

Correct Answer: B. Positive covariance among activity durations.

Question 8

Why can a deterministic critical path be an inadequate basis for risk response?

A. The deterministic path is always longer than every other path.

B. The critical path can change across plausible scenarios.

C. Float cannot be calculated in a deterministic schedule.

D. Deterministic schedules contain no dependencies.

Correct Answer: B. The critical path can change across plausible scenarios.

Question 9

The formula SE(ȳ) = s / √N describes approximately:

A. The standard error of a simulated sample mean.

B. The criticality index of an activity.

C. The covariance between two activities.

D. The expected maximum of two branches.

Correct Answer: A. The standard error of a simulated sample mean.

Question 10

Which practice is most appropriate when two activities share a common supplier risk?

A. Assume they are independent without testing.

B. Delete one activity from the network.

C. Model the common cause or an appropriate positive dependence.

D. Assign both activities zero variance.

Correct Answer: C. Model the common cause or an appropriate positive dependence.

Project Risk Management & Modeling
Chapter 7 of 14