Chapter 14
Risk Technology, AI, and Future Practice
Post Graduate Program in Project Management
Project Risk Management & Modeling
•
Post Graduate
Risk Technology, AI, and Future Practice
Introduction
Project risk management is increasingly a data, technology, and governance discipline. Projects generate information through schedules, cost systems, sensors, contracts, collaboration platforms, inspection records, satellite observations, and stakeholder communications. The managerial challenge is not simply to collect more data. It is to convert heterogeneous information into timely, trustworthy decisions while preserving human accountability.
Digital technologies can improve risk identification, forecasting, simulation, control, and learning. They can also create new risks: biased models, cyberattacks, privacy violations, opaque recommendations, automation overconfidence, unreliable data, and concentration of decision power in technology vendors. Consequently, advanced risk practice requires both analytical capability and institutional judgment.
This chapter examines risk information systems, digital twins, predictive analytics, machine learning, natural-language processing, generative artificial intelligence, automated sensing, and scenario intelligence. It then develops governance requirements for model risk, explainability, privacy, bias, security, and human oversight, before considering climate, geopolitical, supply-chain, and resilience requirements.
Learning Objectives
By the end of this chapter, the reader should be able to:
Evaluate the architecture and usefulness of project risk information systems.
Distinguish descriptive, diagnostic, predictive, and prescriptive analytics.
Explain how digital twins, machine learning, NLP, generative AI, and automated sensing support risk decisions.
Construct and interpret basic risk metrics and predictive-model measures.
Govern model risk, explainability, privacy, bias, cybersecurity, and human oversight.
Apply scenario intelligence to climate, geopolitical, supply-chain, and resilience risks.
Design a proportionate technology roadmap for project organizations.
1. From Risk Registers to Risk Intelligence
A conventional risk register records a risk statement, cause, event, consequence, owner, response, due date, and status. It remains valuable, but it is usually episodic and dependent on human reporting. A risk intelligence system extends this foundation by connecting structured and unstructured data to decisions.
A useful distinction is:
Information level
Central question
Typical output
Descriptive
What has happened?
Dashboard of incidents and variance
Diagnostic
Why did it happen?
Root-cause analysis
Predictive
What may happen?
Forecast, probability, warning
Prescriptive
What should be done?
Ranked interventions or optimized actions
Adaptive
How should the system learn?
Updated model, policy, or control
Technology does not eliminate uncertainty. It changes how uncertainty is represented, updated, communicated, and acted upon. A forecast is not a fact; it is a conditional statement based on data, assumptions, and a model.
1.1 Risk information system architecture
A project risk information system commonly contains five layers:
Source layer: schedules, estimates, enterprise-resource-planning systems, quality records, contracts, weather feeds, equipment telemetry, geospatial data, surveys, and text documents.
Integration layer: application programming interfaces, data pipelines, master-data management, and identity controls.
Data layer: validated storage, metadata, lineage, access rights, retention rules, and version control.
Decision layer: alerts, dashboards, approval workflows, risk responses, escalation, and audit records.
The central design principle is traceability: a decision-maker should be able to determine where a critical data point originated, how it was transformed, which model used it, and who approved the resulting action.
A technologically sophisticated system can still fail because of poor definitions. If “schedule variance,” “critical activity,” or “approved change” is defined differently across projects, aggregation creates an illusion of comparability. Data governance therefore precedes advanced analytics.
2. Quantitative Foundations for Digital Risk Analysis
2.1 Expected loss and expected value
For a discrete set of mutually exclusive outcomes, expected loss is:
EL = ∑ᵢ pᵢLᵢ
where pi is the probability of outcome i, Li is its loss, and the probabilities sum to 1. Expected loss is measured in the same monetary or operational units as the loss. It is an average over repeated comparable situations, not a prediction that the average loss will occur in one project.
For a risk event with probability p and consequence C, the special case is:
EL = pC
This calculation assumes that probability and consequence are defined over the same time horizon and that consequence is represented consistently. It does not capture risk appetite, timing, correlation, catastrophic thresholds, or distribution shape.
2.2 Bayesian updating
Evidence can change a prior assessment. Bayes’ theorem is:
P(H|E) = [P(E|H)P(H)] ÷ P(E)
Here, H is a hypothesis, E is evidence, P(H) is the prior probability, P(E|H) is the likelihood of observing the evidence if the hypothesis is true, and P(H|E) is the posterior probability. The denominator P(E) is the total probability of the evidence.
In practice, Bayesian reasoning helps a project team update the probability of defective work after inspection results, or the probability of delay after a supplier reports a capacity problem. The quality of the update depends on the reliability and independence of the evidence. Repeatedly counting the same information as independent evidence produces overconfidence.
2.3 Forecast error and uncertainty
For observed values yt and forecasts hat{y}t over n periods, mean absolute error is:
MAE = (1/n)∑ₜ |yₜ − ŷₜ|
MAE is expressed in the units of the target variable and treats errors linearly. Root mean square error is:
RMSE = √[(1/n)∑ₜ(yₜ − ŷₜ)²]
RMSE gives greater influence to large errors. Neither metric alone establishes that a model is useful; evaluation must reflect the decision, baseline performance, data drift, and costs of false alarms and missed events.
For probabilistic forecasts, calibration asks whether events assigned probability 0.7 occur approximately 70 percent of the time over a sufficiently large and comparable set of cases. A calibrated model may still be uninformative if it gives nearly the same probability for every case. Discrimination and calibration should therefore be assessed separately.
3. Digital Twins and Automated Sensing
A digital twin is a maintained digital representation of a physical, organizational, or project system, connected to the represented system through data and defined update processes. A three-dimensional model alone is not necessarily a digital twin. The twin must have a purpose, a data relationship, a model of relevant behavior, and governance for updating and use.
In construction, a twin may connect building information, schedule, cost, equipment, environmental conditions, and inspection results. In manufacturing, it may represent assets, production states, maintenance history, and process constraints. In infrastructure, it may combine structural condition, traffic, weather, and deterioration models.
Automated sensing can include temperature, vibration, pressure, location, imagery, acoustic signals, machine status, and worker-worn safety devices. Sensors can provide earlier evidence than periodic inspections, but they introduce calibration, connectivity, battery, tampering, and interpretation risks.
A practical sensing workflow is:
Automated sensing and digital twin risk workflow
Figure: Automated sensing and digital twin risk workflow
Figure: A governed sensing-to-decision loop for a digital twin.
The twin should not be treated as an unquestionable copy of reality. It is a model with boundaries. It may omit informal work, undocumented changes, unusual failure modes, or social conditions. Its outputs should be tested against physical inspections and expert judgment.
4. Predictive Analytics and Machine Learning
Predictive analytics estimates future outcomes from historical and current data. Common methods include regression, time-series models, classification, survival analysis, anomaly detection, and simulation. Machine learning differs less by a single algorithm than by an emphasis on learning patterns from data, often with flexible models.
A supervised learning workflow includes problem definition, target specification, data preparation, training, validation, testing, deployment, monitoring, and retirement. Data must be split in a manner consistent with time and project structure. Randomly mixing future observations into training data creates leakage and falsely optimistic performance.
Examples of project applications include:
forecasting cost or duration at completion;
classifying change orders likely to become disputes;
identifying equipment conditions associated with failure;
detecting unusual procurement or quality patterns;
estimating the probability of safety incidents;
prioritizing inspections.
A confusion matrix supports classification evaluation. For a positive class, precision is:
Precision = TP ÷ (TP + FP)
Recall is:
Recall = TP ÷ (TP + FN)
TP is true positives, FP false positives, and FN false negatives. Precision answers, “Of the flagged cases, how many were genuinely positive?” Recall answers, “Of the genuinely positive cases, how many were flagged?” In safety applications, a high-recall system may be preferred, but excessive false alarms can cause alert fatigue. Thresholds should therefore be selected with decision costs, not accuracy alone.
Machine learning risks include nonrepresentative training data, proxy discrimination, unstable relationships, concept drift, adversarial manipulation, and poor transfer from one project type to another. A model trained on large commercial buildings may not generalize to tunnels, remote infrastructure, or a different regulatory environment.
5. Natural-Language Processing and Generative AI
Project risk evidence is heavily textual: contracts, claims, meeting minutes, inspection reports, correspondence, permits, lessons learned, and safety narratives. Natural-language processing can classify documents, extract entities and obligations, identify topics, compare clauses, detect sentiment cautiously, and retrieve similar historical events.
NLP is especially useful for triage. It can identify a clause mentioning notice periods, extract a date, and route the document to a contract specialist. It should not silently make a legal determination where wording, jurisdiction, and factual context require professional interpretation.
Generative AI systems produce text, code, summaries, images, or structured outputs from prompts. They can support risk workshops by proposing categories, summarize large document sets, draft response options, translate technical language, and act as an interface to approved knowledge repositories. Retrieval-augmented generation can ground responses in selected organizational documents, but retrieval does not guarantee that the source is correct or that the generated answer accurately represents it.
Material risks include hallucinated facts, fabricated citations, disclosure of confidential information, prompt injection, copyright concerns, inconsistent outputs, and automation bias. Controls should include approved use cases, data classification, private or enterprise-controlled environments, source citation, output verification, logging, human approval, and a prohibition on treating generated content as evidence without checking the original source.
6. Scenario Intelligence and Decision Support
Scenario intelligence links external signals, causal assumptions, and plausible futures. It is not the same as forecasting one most-likely future. Scenario analysis is valuable when uncertainty is deep, structural change is possible, or historical data are poor guides.
A robust process is:
Define the decision and time horizon.
Identify drivers, constraints, and early indicators.
Separate predictable trends from uncertain forces.
Construct a small set of distinct, internally coherent scenarios.
Stress-test plans, contracts, schedules, and capacity against each scenario.
Identify no-regret actions, contingent actions, and trigger thresholds.
Monitor indicators and update the decision record.
For example, a supply-chain project may examine combinations of demand volatility and supplier concentration. A climate scenario may combine increasing heat exposure with water restrictions and insurance repricing. A geopolitical scenario may consider sanctions, border delays, export controls, and cyber disruption.
Scenario intelligence should avoid false precision. A scenario is a disciplined representation of possibility, not a claim that the future will follow a plotted line. Its value lies in revealing vulnerabilities, options, dependencies, and signals.
7. Model Risk and Responsible Governance
Model risk is the possibility that a model produces harmful decisions because of incorrect specification, unsuitable data, implementation error, misuse, or changing conditions. Model risk exists in a spreadsheet, a simulation, a machine-learning classifier, and a generative AI service.
A proportionate model-governance lifecycle includes:
Stage
Governance question
Initiation
What decision will the model influence, and who owns it?
Design
Are assumptions, variables, boundaries, and alternatives documented?
Validation
Does independent testing challenge data, logic, performance, and limitations?
Deployment
Are access, version, thresholds, and approval rules controlled?
Monitoring
Are drift, errors, incidents, overrides, and subgroup performance tracked?
Change or retirement
When must the model be recalibrated, suspended, or withdrawn?
Explainability
Explainability has several meanings. A global explanation describes overall model behavior; a local explanation describes why a particular case received an output; a process explanation identifies data, version, threshold, and approval steps. Feature importance is not automatically causation. A variable may correlate with risk without causing it.
For high-consequence decisions, a useful explanation should state the output, key evidence, uncertainty, limitations, alternatives considered, and human decision rights. If a model cannot provide an adequate explanation for a decision affecting safety, employment, access, or legal rights, its use should be restricted or supplemented by a more interpretable method.
Privacy and data protection
Risk systems may process worker locations, health-related information, identity records, supplier pricing, and communications. Privacy governance should apply purpose limitation, data minimization, lawful and transparent processing, retention controls, role-based access, encryption, secure deletion, and rights appropriate to the applicable jurisdiction. Sensitive data should not be collected merely because technology makes collection possible.
Anonymization is difficult when datasets can be linked. Pseudonymized data may still be personal data if re-identification is reasonably possible. Privacy impact assessments should be completed before deploying intrusive monitoring or combining datasets.
Bias and fairness
Bias may arise from historical underreporting, sample imbalance, proxy variables, measurement differences, labeling practices, or unequal access to technology. A model can be statistically accurate overall while performing poorly for a smaller group or project type. Testing should therefore examine relevant subgroups, error rates, missingness, and consequences. Fairness cannot be reduced to one universal metric; the appropriate standard depends on the decision, law, and affected parties.
Security and resilience
AI-enabled risk systems expand the attack surface. Threats include stolen credentials, poisoned training data, manipulated sensors, ransomware, model extraction, prompt injection, data exfiltration, and denial of service. Controls include least privilege, network segmentation, secure software development, multifactor authentication, backups, incident response, vendor assessment, immutable logs, and manual fallback procedures.
Cybersecurity is part of project risk management, not merely an information-technology concern. A compromised schedule or sensor stream can produce apparently credible but false risk signals.
Human oversight
Human oversight must be substantive rather than ceremonial. The responsible person needs authority, competence, sufficient time, access to evidence, and the ability to reject or escalate a recommendation without penalty. Automation should generally support, not conceal, accountability. High-impact decisions require documented review, exception handling, and an audit trail showing what the system recommended and what the human decided.
8. Contemporary Risk Requirements
Climate risk
Climate risk includes acute hazards such as floods, storms, heatwaves, and wildfires, and chronic changes such as sea-level rise, heat stress, water scarcity, and changing precipitation. Project analysis should consider hazard, exposure, vulnerability, adaptation capacity, asset life, interdependencies, and transition effects such as regulation or carbon pricing. Historical averages may be insufficient where climate conditions are nonstationary.
Responses can include climate-resilient design, changed construction seasons, redundancy, emergency access, supplier diversification, insurance review, and monitoring thresholds. Climate claims should distinguish physical risk from transition risk and avoid treating uncertain projections as precise predictions.
Geopolitical risk
Geopolitical risk may affect permits, sanctions, currency, borders, labor availability, technology access, security, and stakeholder legitimacy. Scenario planning should include legal and compliance review, not only probability scoring. Contractual rights, alternative suppliers, inventory policies, local partnerships, and evacuation or continuity plans may be more valuable than a single probability estimate.
Supply-chain risk
Supply-chain exposure is shaped by concentration, substitutability, lead time, financial health, transport dependency, visibility beyond tier one, and common-cause hazards. A supplier map should identify critical nodes and shared dependencies. Resilience may require dual qualification, strategic inventory, modular design, local alternatives, and collaborative information sharing. Redundancy has cost; the appropriate level depends on consequence, recovery time, and risk appetite.
Organizational resilience
Resilience is the capacity to anticipate, absorb, adapt, recover, and learn. It is not equivalent to maintaining a large buffer everywhere. Resilient project organizations combine preventive controls with adaptive capacity: cross-training, decision rights, modular plans, realistic exercises, trusted communication, financial headroom, and lessons-learned mechanisms. Recovery objectives should be explicit. For a critical process, the recovery time objective is the maximum acceptable time before restoration; the recovery point objective is the maximum acceptable data-loss interval. These are governance requirements, not merely technical settings.
9. Illustrative Case: The Northbank Transit Extension
Background. The Northbank Transit Extension is an illustrative case involving a 12-kilometre urban rail project. It includes a tunnel, elevated stations, imported electrical equipment, and construction near a flood-prone river. The project has a complex alliance of public and private participants.
Problem. The project team relied on monthly risk meetings and a spreadsheet register. Schedule updates were late, supplier correspondence was dispersed across email systems, and flood warnings were not connected to work planning. Senior management wanted an AI dashboard, but the project director was concerned about privacy, cyber risk, and unjustified confidence in forecasts.
Analysis. A diagnostic review found inconsistent activity codes, missing baseline versions, duplicate supplier records, and sensor readings without calibration metadata. Historical projects differed substantially in geology and procurement strategy, so a model trained on all records would have produced misleading comparisons. The team also found that worker-location data could reveal individual behavior.
Approach. The project adopted a staged design. First, it created a common data dictionary, version-controlled baselines, and role-based access. Second, a digital twin linked the approved schedule, asset locations, flood forecasts, equipment telemetry, and inspection records. Third, an interpretable duration model was tested against a simple historical baseline. Fourth, NLP classified supplier notices and extracted possible contractual deadlines, but a contract specialist approved every material interpretation. Fifth, scenarios were developed for flood disruption, a six-week electrical-equipment delay, and a cyber outage.
The project established thresholds: an alert could be automated, but a change to the critical-path recovery plan required human approval. Model performance was monitored by work package, and the model was suspended when data quality fell below a defined standard. Sensor data were aggregated where individual identification was unnecessary.
Outcome. The system detected a combination of rising river levels, restricted site access, and a vulnerable sequence of outdoor activities. The team resequenced work and protected equipment before the event. It also identified that the apparent supplier-risk signal was largely a documentation delay rather than production failure. The result was not a claim that AI prevented all risk; rather, integrated evidence improved timing, challenged assumptions, and supported proportionate action.
Learning points. Technology created value because governance preceded automation, the model had a defined decision purpose, alternatives were tested, privacy was considered, and accountable professionals retained authority. The case also demonstrates that false positives can be useful if they are affordable to investigate, whereas false negatives may be unacceptable for safety or major resilience risks.
10. Implementation Roadmap and Best Practice
Organizations should begin with decisions, not tools. A practical roadmap is:
Inventory critical risk decisions and their owners.
Assess data quality, accessibility, sensitivity, and lineage.
Establish definitions, controls, and accountability.
Select a low-risk, high-value pilot with measurable outcomes.
Compare the proposed model with a transparent baseline.
Validate independently and test unusual conditions.
Deploy with human review, logging, fallback, and user training.
Monitor performance, drift, bias, incidents, and benefits.
Scale only when governance capacity grows with technical capability.
Benefit measurement should include not only predictive accuracy but also response time, avoided disruption, quality of decisions, user adoption, false-alarm burden, equity effects, security incidents, and cost of operation. A technically accurate model that nobody trusts or uses may have little practical value.
Senior leaders should ask: What decision improves? What evidence supports the model? What happens when the model is wrong? Who can override it? What data are being collected? Which groups may be disadvantaged? How will the organization continue if the platform, supplier, network, or model becomes unavailable?
Challenges and Limitations
First, technology cannot resolve ambiguity in objectives or conflicts among stakeholders. Second, project data are often sparse, inconsistent, proprietary, and nonstationary. Third, rare catastrophic events provide little training data but demand serious attention. Fourth, predictive systems may encourage reactive management if teams neglect prevention and learning. Fifth, vendor claims may obscure lock-in, hidden subcontractors, and unclear data ownership. Sixth, explainability methods can create a persuasive narrative without proving that the model is valid. Finally, organizational incentives may reward optimistic forecasts and suppress inconvenient signals.
The appropriate response is not to reject technology. It is to match analytical sophistication to decision consequence, data quality, reversibility, and governance maturity. Simple rules, expert review, and well-designed contingencies may outperform complex models in low-data settings.
Chapter Summary
Risk technology extends traditional risk registers into connected systems that integrate operational, textual, environmental, and external data. Digital twins and automated sensing can provide timely representations of physical and project conditions, but their outputs remain model-based and require calibration, lineage, and human interpretation. Predictive analytics and machine learning support forecasting, classification, anomaly detection, and prioritization; their performance must be evaluated with metrics suited to the decision, including MAE, RMSE, precision, recall, calibration, and baseline comparison.
NLP and generative AI can organize documents, retrieve evidence, draft analyses, and support workshops. They also create risks of hallucination, confidentiality loss, prompt injection, copyright problems, and automation bias. Scenario intelligence is particularly important for climate, geopolitical, supply-chain, and resilience risks because deep uncertainty cannot always be represented by a single forecast.
Responsible practice requires model inventories, independent validation, documentation, explainability, privacy protection, bias assessment, cybersecurity, monitoring, fallback arrangements, and substantive human oversight. The central managerial principle is that technology should improve the quality and timeliness of accountable decisions rather than replace accountability.
Key Terms
Risk information system: A governed system that collects, integrates, analyzes, and communicates risk information.
Digital twin: A maintained digital representation of a physical, organizational, or project system connected to it through data and update processes.
Automated sensing: Machine-based collection of measurements from assets, environments, equipment, or activities.
Predictive analytics: Analysis used to estimate future outcomes or probabilities.
Machine learning: Computational methods that learn patterns from data for prediction, classification, or decision support.
Natural-language processing: Computational analysis and generation of human language.
Generative AI: AI that produces new text, code, images, or other outputs from learned patterns and instructions.
Scenario intelligence: Structured analysis of signals, drivers, and plausible alternative futures.
Expected loss: Probability-weighted average consequence across defined outcomes.
Bayesian updating: Revision of a probability assessment using new evidence.
Calibration: Agreement between stated probabilities and observed frequencies.
Model risk: Potential harm arising from model error, misuse, implementation failure, or changing conditions.
Explainability: The ability to communicate how a model or process produced an output.
Data lineage: A record of data origin, transformation, movement, and use.
Data drift: Change in input-data characteristics over time.
Concept drift: Change in the relationship between inputs and the outcome being predicted.
Prompt injection: Manipulation of an AI system through crafted instructions or content.
Privacy by design: Incorporation of privacy protections throughout system design.
Resilience: Capacity to anticipate, absorb, adapt, recover, and learn.
Human oversight: Competent, authorized human review and control of technology-supported decisions.
Review Questions
Short Answer Questions
What distinguishes predictive analytics from prescriptive analytics?
Why is a three-dimensional model not necessarily a digital twin?
Define model risk and give two sources of it.
What do precision and recall measure in classification?
Why should a project maintain a transparent baseline when evaluating a machine-learning model?
Long Answer Questions
Explain the architecture of a project risk information system and discuss why data lineage is important.
Compare the benefits and limitations of automated sensing and digital twins in project risk management.
Discuss governance requirements for generative AI used in contract and risk analysis.
Explain how climate, geopolitical, and supply-chain risks can be integrated through scenario intelligence.
Develop a model-governance lifecycle for a high-consequence project prediction system.
Analytical / Application Questions
A classification model flags 80 supplier records as high risk. Of these, 60 are genuinely high risk. There are 15 additional high-risk records that were not flagged. Calculate precision and recall, and explain which metric would be prioritized if missed high-risk suppliers could cause major safety consequences.
A project is considering a disruption with probability 0.25 and consequence $4 million. Calculate expected loss, then explain why the result should not be the sole basis for accepting or rejecting the risk.
Design a technology and governance plan for a major infrastructure project exposed to flooding, imported equipment delays, worker privacy concerns, and cyberattack. Identify data sources, analytical methods, human approval points, and fallback arrangements.
Multiple Choice Questions with Answers
Question 1
Which statement best describes a digital twin?
A. A static three-dimensional drawing of an asset
B. A maintained digital representation connected to a represented system through data and update processes
C. A spreadsheet containing only historical costs
D. An automated decision system that requires no physical validation
Correct Answer: B. A maintained digital representation connected to a represented system through data and update processes
Question 2
A model produces 60 true positives and 20 false positives. What is its precision?
A. 60%
B. 75%
C. 80%
D. 90%
Correct Answer: B. 75%
Question 3
Which practice most directly reduces data leakage during time-based project forecasting?
A. Randomly mixing all historical and future observations
B. Using future observations in the training set
C. Separating training and testing in a manner consistent with time
D. Removing all validation procedures
Correct Answer: C. Separating training and testing in a manner consistent with time
Question 4
What is the primary purpose of Bayesian updating?
A. To replace all expert judgment with a fixed average
B. To revise probability assessments in light of evidence
C. To guarantee that a forecast is correct
D. To convert qualitative risks into legal obligations
Correct Answer: B. To revise probability assessments in light of evidence
Question 5
Which is a characteristic risk of generative AI in project risk work?
A. It cannot produce text
B. It always cites the correct source
C. It may generate plausible but unsupported information
D. It eliminates confidentiality concerns
Correct Answer: C. It may generate plausible but unsupported information
Question 6
Which statement about recall is correct?
A. It is the proportion of flagged cases that are truly positive
B. It is the proportion of actual positive cases that are identified
C. It is the average monetary loss per project
D. It measures the number of model parameters
Correct Answer: B. It is the proportion of actual positive cases that are identified
Question 7
Which control is most relevant to model risk governance?
A. Deploying every model without documentation
B. Independent validation, monitoring, and defined retirement criteria
C. Allowing only vendors to approve model outputs
D. Removing audit logs to protect privacy
Correct Answer: B. Independent validation, monitoring, and defined retirement criteria
Question 8
Why are scenarios useful for deep uncertainty?
A. They prove which future will occur
B. They replace all monitoring and contingency planning
C. They test plans against several plausible futures
D. They make probability estimates unnecessary in every decision
Correct Answer: C. They test plans against several plausible futures
Question 9
Which principle supports responsible collection of worker-location data?
A. Collect all available data indefinitely
B. Use data minimization and purpose limitation
C. Publish individual data by default
D. Ignore access controls if sensors are accurate
Correct Answer: B. Use data minimization and purpose limitation
Question 10
A disruption has probability 0.2 and consequence $5 million. What is its expected loss under the simple probability-times-consequence model?
A. $0.2 million
B. $1 million
C. $2.5 million
D. $5.2 million
Correct Answer: B. $1 million
Project Risk Management & Modeling
Chapter 14
of 14