Cost, Financial, and Commercial RiskIntroductionProject risk is often discussed as if it were a technical probability of delay or failure. In practice, many of the most consequential risks appear through money: estimates prove unreliable, payments arrive late, prices increase, currencies move unfavourably, lenders impose conditions, suppliers fail, or contractual interpretations generate claims. Cost, financial, and commercial risks are therefore interconnected rather than isolated categories. Cost risk concerns uncertainty in the resources required to deliver scope. Financial risk concerns the effect of timing, funding, liquidity, interest rates, taxation, inflation, and foreign exchange. Commercial risk concerns how obligations, rewards, liabilities, and remedies are distributed among the project owner, contractor, consultants, lenders, suppliers, and other parties. Sound project risk management must examine both the size of a possible loss and the party best positioned to control it. A useful principle is that a risk should generally be allocated to the party that can best anticipate, control, insure, or diversify it—provided that the allocation is explicit, priced, enforceable, and not likely to create dysfunctional behaviour. Learning objectivesBy the end of this chapter, the reader should be able to: - Distinguish cost, financial, and commercial risk and explain their interactions.
- Model uncertain costs using ranges, probability distributions, sensitivity analysis, and Monte Carlo simulation.
- Estimate contingency and management reserve without confusing them with one another.
- Analyse cash-flow exposure, inflation, interest rates, exchange rates, financing, and supplier dependence.
- Evaluate contractual risk allocation, payment mechanisms, incentives, variations, and claims.
- Integrate cost and schedule uncertainty in decision-making.
- Recommend governance controls that preserve transparency, solvency, and ethical commercial conduct.
1. The architecture of financial exposureA project budget is not the same as a project financial model. The budget records expected expenditure, while the financial model also represents timing, receipts, funding, taxation, financing cost, working capital, residual value, and risk. A project may have an acceptable final cost but still fail because it cannot meet payroll or supplier obligations during a period of negative cash flow. 1.1 Categories of risk| Risk category | Typical source | Principal consequence |
|---|
| Estimate risk | Incomplete design, uncertain quantities, productivity | Cost overrun | | Scope and change risk | Ambiguous requirements, client changes | Rework, claims, delay | | Market risk | Commodity, labour, transport price movements | Margin erosion | | Liquidity risk | Late certification or payment | Insolvency or work interruption | | Financing risk | Interest rates, covenant breach, refinancing | Higher funding cost or loss of funding | | Foreign-exchange risk | Currency mismatch between receipts and costs | Translation or transaction loss | | Counterparty risk | Weak client, contractor, or supplier | Default and replacement cost | | Commercial risk | Poor allocation of liability or incentive | Disputes and opportunistic behaviour | | Regulatory and tax risk | Legal change, duties, withholding tax | Unplanned cash outflow |
The exposure can be represented conceptually as: Net financial exposure = uncertain costs + financing costs + losses − risk-adjusted receipts This is not a valuation formula unless all terms are defined consistently over time. For investment decisions, future cash flows should normally be discounted. For project control, nominal cash flows may be more useful when the focus is on actual payment dates. 1.2 Cost baseline, contingency, and reserveThe cost baseline is the time-phased, authorised budget used to measure performance. Contingency reserve is budget assigned for identified or otherwise foreseeable uncertainty within the approved scope and normally included in the cost baseline. Management reserve is budget held by management for unknown-unknowns or unforeseen work within the project’s scope; it is controlled separately and is not normally part of the performance measurement baseline. Terminology differs among standards and organisations. Consequently, the project governance document should specify: - what risks each reserve may fund;
- who may approve a drawdown;
- whether unused reserve is returned;
- how reserve consumption is reported; and
- whether reserve is included in the contract price.
A contingency is not a licence to conceal poor estimating. It should be traceable to risk evidence and updated as uncertainty changes. 2. Estimating uncertain cost2.1 From point estimates to probabilistic estimatesA point estimate such as $10 million implies more precision than is usually justified during early development. A defensible estimate identifies cost components, estimating methods, assumptions, quantity uncertainty, rate uncertainty, correlation, and the maturity of design information. Common approaches include: - Analogous estimating: uses actual results from comparable projects, adjusted for scale, location, complexity, and time.
- Parametric estimating: applies a statistically supported cost relationship, such as cost per kilometre or labour-hours per unit.
- Bottom-up estimating: estimates work packages and aggregates them; it is detailed but sensitive to omissions.
- Three-point estimating: uses optimistic, most-likely, and pessimistic values to express uncertainty.
- Reference-class forecasting: uses the distribution of outcomes from a relevant external class of projects, reducing optimism bias.
For a three-point activity estimate, the triangular expected value is: E[X] = (a + m + b) ÷ 3 where a is the minimum or optimistic cost, m is the most-likely cost, and b is the maximum or pessimistic cost. This is appropriate when the three values are treated as the vertices of a triangular distribution and no stronger distributional evidence is available. The beta-PERT approximation is: E[X] = (a + 4m + b) ÷ 6 and its commonly used approximate variance is: Var(X) = ((b − a) ÷ 6)² These are approximations, not universal laws. They should not be used when the tails are asymmetric in a way the selected distribution cannot represent, or when the three estimates are merely arbitrary management targets. Worked example: three-point estimateA work package has a = $0.80 million, m = $1.00 million, and b = $1.60 million. The PERT expected cost is: E[X] = (0.80 + 4(1.00) + 1.60) ÷ 6 = $1.067 million The approximate standard deviation is: σ = (1.60 − 0.80) ÷ 6 = $0.133 million The result does not mean that actual cost must lie within one standard deviation. It is an input to a larger model, and the tail probability depends on the assumed distribution. 2.2 Aggregation and correlationIf uncertain cost components are independent, the variance of their sum is: Var(ΣXᵢ) = Σ Var(Xᵢ) For two correlated components: Var(X + Y) = Var(X) + Var(Y) + 2ρσₓσᵧ where ρ is the correlation coefficient, and σₓ and σᵧ are standard deviations. Positive correlation increases aggregate uncertainty; ignoring it can materially understate contingency. For example, steel and transport costs may rise together because both are affected by energy prices. Correlation should be based on historical evidence, expert elicitation, or scenario logic—not inserted merely to make a model appear sophisticated. 2.3 Sensitivity and scenario analysisSensitivity analysis changes one assumption while holding others constant. It identifies cost drivers but does not represent joint uncertainty. Scenario analysis changes a coherent set of assumptions—for example, a high-inflation scenario combined with currency depreciation and delayed procurement. Tornado charts, break-even analysis, and stress tests are useful governance tools because senior decision-makers can understand them without inspecting simulation code. 3. Contingency and management reserveA probability-based contingency may be set as: Contingency at confidence level p = Qₚ(Total uncertain cost) − Expected total cost where Qₚ is the p-quantile of the simulated or empirically estimated total-cost distribution. If the expected total cost is $100 million and the P80 outcome is $112 million, the risk-based contingency is $12 million, subject to governance and scope rules. This approach is preferable to applying an arbitrary percentage when a credible risk model exists. However, a quantile is not automatically a management decision. The chosen confidence level depends on risk appetite, funding constraints, contract strategy, estimate maturity, and the consequences of failure. Management reserve should not be used to make an unapproved scope increase appear affordable. A reserve drawdown should identify the event, amount, owner, decision authority, revised forecast, and remaining reserve. If a risk is realised, the risk register, cost forecast, schedule forecast, and change log should be updated together. 4. Cash flow, working capital, and liquidity4.1 Timing mattersA simple project cash-flow forecast for period t is: Net cash flowₜ = Cash receiptsₜ − Cash disbursementsₜ Cumulative cash position is: Cumulative cashₜ = Opening cash + Σ(Net cash flowᵢ), for i = 1 to t The minimum cumulative cash position indicates the funding requirement before considering financing fees, reserve policy, and lender requirements. A profitable project can therefore require substantial working capital. Consider a contractor with monthly certified receipts of $2 million, but payment 60 days after certification. Labour and supplier payments total $1.6 million monthly. If work starts with no cash and the first two months generate no receipts, the contractor must fund $3.2 million before the first payment, excluding tax and financing cost. A project manager should therefore track forecast receipts by contractual entitlement and by realistic collection date. Relevant indicators include days sales outstanding, payable days, retention balances, advance-payment recovery, committed cost, unbilled work, and cash-at-risk. These are not substitutes for a dated cash forecast. 4.2 Discounted cash flow and financing costFor an investment appraisal, net present value is commonly calculated as: NPV = Σ [CFₜ ÷ (1 + r)ᵗ] − I₀ where CFₜ is net cash flow in period t, r is the discount rate per period, and I₀ is the initial investment. Cash flows and the discount rate must use consistent periods, currency, inflation basis, and tax treatment. If nominal cash flows include expected inflation, a nominal discount rate should be used. If cash flows are expressed in real purchasing-power terms, a real discount rate is appropriate. The Fisher relationship is approximately: 1 + rₙ = (1 + rᵣ)(1 + π) where rₙ is the nominal rate, rᵣ is the real rate, and π is inflation. Mixing nominal and real assumptions creates systematic valuation error. 5. Inflation, escalation, and foreign exchange5.1 Inflation and escalationGeneral inflation does not necessarily equal project cost escalation. Labour, cement, fuel, specialist equipment, and freight may each follow different indices. A cost component escalated from a base date can be represented as: Future cost = Base cost × (Index at future date ÷ Index at base date) The index must be appropriate to the cost category, published consistently, and linked to the contractual measurement date. Escalation clauses should define the index, base date, lag, treatment of negative movement, caps, floors, and exceptional events. 5.2 Exchange-rate exposureForeign-exchange risk arises when the currency of a cost differs from the currency of revenue or funding. Exposure should be measured by currency and date, not merely as a total project value. A payable of €5 million due in six months creates a different risk from the same payable due in three years. Possible responses include natural hedging, currency matching, forward contracts, options, currency clauses, early procurement, and supplier pricing in the revenue currency. Hedging should be approved under treasury policy and documented against an underlying exposure; speculative trading is not project risk management. For a foreign-currency cost, home-currency cost can be expressed as: Home-currency cost = Foreign-currency amount × Spot exchange rate The exchange-rate quotation must be defined—for example, home currency per euro—and used consistently. A hedge may reduce uncertainty but can create fees, collateral requirements, accounting complexity, and opportunity cost if the exposure changes. 6. Financing and financial structureFunding risk includes inability to obtain required finance, covenant breach, interest-rate increases, refinancing failure, and restrictions on drawdown. Project finance commonly depends on debt-service coverage, completion tests, reserve accounts, insurance, security packages, and lender step-in rights. A basic debt-service coverage ratio is: DSCR = Cash available for debt service ÷ Debt service due The definition of cash available and debt service must follow the financing agreement. A ratio of 1.20 does not have a universal meaning unless the period, accounting adjustments, and covenant threshold are known. Fixed-rate debt reduces interest-rate uncertainty but may involve break costs. Floating-rate debt may be cheaper initially but exposes the project to rate increases. Interest-rate swaps can hedge this exposure but introduce counterparty and basis risk. The project manager should understand these mechanisms sufficiently to challenge assumptions, while specialist treasury and legal advice remains essential. 7. Commercial models and contractual allocationThe contract type influences behaviour and risk distribution: | Contract model | Owner exposure | Contractor exposure | Appropriate use |
|---|
| Lump sum/fixed price | Lower price uncertainty if scope is mature | High quantity, productivity, and price risk | Defined scope and stable conditions | | Cost reimbursable | High cost uncertainty | Lower cost risk, subject to control | Uncertain scope or urgent start | | Target cost with pain/gain share | Shared overrun and underrun | Shared | Collaborative delivery with open-book control | | Unit price/remeasurement | Quantity risk | Rate and productivity risk | Quantities uncertain but rates estimable | | Time and materials | High owner exposure | Lower commercial risk | Specialist or emergency work | | Design-build | Single-point coordination advantage | Greater design responsibility | Integrated design and construction |
No contract eliminates risk. A fixed-price contract may transfer price risk on paper while increasing tender prices, claims, conservative behaviour, or contractor failure. Risk allocation should consider capability, information asymmetry, insurability, transaction cost, and market power. Important clauses address scope definition, payment and certification, retention, security, advance payment, indexation, variations, extensions of time, differing site conditions, force majeure, limitation of liability, indemnity, intellectual property, termination, dispute resolution, audit rights, subcontracting, sanctions, and data obligations. Incentives and moral hazardPoorly designed incentives can create adverse selection or moral hazard. For example, a very aggressive lowest-price award may attract a bidder that underprices risk and later pursues claims. Conversely, an uncapped cost-reimbursable model may weaken cost discipline. Open-book target-cost arrangements can align parties when baseline assumptions, allowable costs, audit rights, pain/gain bands, and decision rights are clear. 8. Supplier and counterparty riskSupplier risk is both operational and financial. Assessment should cover financial statements, liquidity, leverage, order book, bonding capacity, production capacity, quality history, cyber controls, geographic concentration, sanctions exposure, critical-subcomponent dependence, and business continuity. Practical controls include dual sourcing, approved alternates, framework agreements, long-lead procurement, performance security, parent guarantees, escrow of critical designs, step-in rights, inspection and testing, milestone payments tied to evidence, and rights to recover tooling or materials. Excessive transfer of risk to small suppliers can increase prices and systemic fragility; ethical procurement considers fair payment and realistic obligations. A supplier risk score should not be treated as an objective probability unless its calibration has been demonstrated. Governance should distinguish expert judgement, verified financial data, and model output. 9. Claims, variations, and dispute managementA claim is an asserted entitlement, not necessarily a valid entitlement. Claims commonly arise from changed scope, delay, disruption, defective information, differing conditions, acceleration, payment failure, and contract interpretation. Effective claims management begins before the dispute. The project should maintain contemporaneous records of instructions, notices, programme updates, labour and equipment records, costs, correspondence, approvals, and causation. A sound claim generally requires analysis of: - contractual entitlement;
- factual event and notice compliance;
- causation;
- measured time or cost effect;
- mitigation; and
- valuation under the contract.
A cost claim should avoid double recovery—for example, claiming the same labour inefficiency as both direct cost and disruption overhead. Delay analysis should use a method suited to the facts and available records; a sophisticated method applied to poor data does not produce reliable causation. Early negotiation, dispute boards, adjudication, mediation, arbitration, and litigation each have different cost, speed, confidentiality, and enforceability characteristics. Escalation should be governed by a dispute-resolution ladder rather than personal relationships. 10. Integrated cost–schedule risk modellingCost and schedule risks interact. Extended duration may increase site overhead, supervision, financing cost, escalation, and exposure to weather or currency changes. A schedule model can therefore drive cost outcomes. A basic integrated simulation repeatedly samples uncertain activity durations and cost drivers, applies logical schedule relationships, and calculates completion date, direct cost, indirect cost, and financing effects. The output is a joint distribution rather than a single forecast. Important outputs include: - probability of completing by a required date;
- probability of staying within budget;
- probability of meeting both constraints;
- cost at selected confidence levels;
- schedule drivers of cost exposure; and
- correlations between completion date and final cost.
The probability of meeting both budget and date is not generally equal to the product of separate probabilities because the outcomes may be correlated. A model should represent common drivers, such as a delayed imported component that causes both currency exposure and site overhead. Simulation results are conditional on the model. They can be distorted by omitted risks, unrealistic distributions, false independence, double counting, inadequate data, or unjustified precision. Validation should include back-testing where possible, expert review, sensitivity analysis, and comparison with reference-class evidence. 11. Illustrative case: the Northbank Water Treatment ProjectBackgroundThe fictional Northbank project is a two-year design-and-build water treatment plant. The contract value is $120 million. Major equipment is priced in euros, construction labour in local currency, and debt is floating-rate. The owner wants 80% confidence that the plant will be operational within the approved budget and date. ProblemThe initial estimate used a 10% contingency. However, design maturity was low, imported equipment represented 30% of cost, the payment cycle was 60 days, and the selected contractor relied on one specialist membrane supplier. The project team also treated schedule and cost analysis separately. AnalysisThe team decomposed uncertainty into design quantities, productivity, equipment price, exchange rate, inflation, supplier delay, and commissioning duration. Historical data and structured expert elicitation were used to define distributions. Supplier delay was modelled as correlated with commissioning duration; exchange rate was correlated with imported equipment cost. A monthly cash-flow model included retention, tax, debt drawdown, interest, and payment lag. The model showed a 50% probability of remaining below $120 million and only a 58% probability of meeting both budget and operational date. The P80 cost was $132 million. The minimum cash requirement was $18 million higher than the original funding plan because delayed certification coincided with peak procurement payments. Approach and solutionThe owner adopted several measures: - design gates were introduced before release of major packages;
- a target-cost arrangement with pain/gain sharing replaced a rigid transfer of poorly understood risks;
- the membrane supplier was required to provide a recovery plan and approved alternate source;
- euro exposure was hedged progressively against confirmed commitments;
- the payment process was shortened through electronic certification;
- an integrated risk model was updated monthly;
- $12 million was established as risk-based contingency, with a separately governed management reserve; and
- a dispute board and contemporaneous-record protocol were established.
OutcomeAt the next approval point, the model estimated an 82% probability of meeting both constraints, subject to the stated assumptions. The result was not achieved by simply increasing budget. It came from reducing exposure, improving information, changing incentives, protecting liquidity, and making residual uncertainty visible to decision-makers. Learning points- Contractual transfer without capability or pricing discipline is not risk reduction.
- Liquidity can be the binding constraint even when expected profit is positive.
- Currency, supplier, and schedule risks may share common causes.
- Reserves should be evidence-based and governed, not hidden padding.
- A model supports judgement; it does not replace accountability.
12. Governance, ethics, technology, and contemporary practiceFinancial governance requires segregation of duties, approval limits, audit trails, transparent forecast changes, conflict-of-interest declarations, and protection for good-faith reporting. Manipulating estimates to secure approval, delaying recognition of a loss, concealing a claim, or exploiting a supplier’s weak bargaining position may be commercially tempting but is professionally indefensible and potentially unlawful. Tax, competition, anti-bribery, sanctions, public procurement, accounting, environmental, and insolvency requirements may affect commercial decisions. Contract managers should obtain jurisdiction-specific legal advice rather than assume that a clause is enforceable because it appears clear. Digital tools can connect estimating, procurement, enterprise-resource-planning, schedule, contract, and risk data. Machine-learning systems may identify abnormal invoices, predict supplier distress, or detect emerging cost trends. Their use requires data lineage, access control, explainability, protection of confidential pricing, bias testing, and human review. An AI-generated forecast should never be presented as an observed fact; assumptions, training data, uncertainty, and approval responsibility must remain visible. Best practice is to maintain a single integrated risk and forecast process: identify exposure, quantify it where credible, assign ownership, select a response, monitor leading indicators, record decisions, and update the financial consequences. Escalate when thresholds are crossed rather than waiting for a budget breach. Chapter SummaryCost, financial, and commercial risks determine whether a project can be delivered economically and remain solvent while doing so. Cost uncertainty should be decomposed and modelled using suitable estimating methods, distributions, correlations, scenarios, and reference-class evidence. Contingency can be linked to a selected confidence level, while management reserve must remain separately governed. Cash-flow timing, payment terms, working capital, interest, inflation, taxation, and exchange rates can transform an apparently profitable project into a liquidity crisis. Contract strategy allocates risk but does not eliminate it; effective allocation matches responsibility with control, capability, insurability, and information. Supplier due diligence, incentives, records, claims discipline, and dispute mechanisms protect commercial value. Integrated cost–schedule simulation is particularly valuable where delay creates escalation, overhead, financing, or revenue exposure. Yet models remain conditional representations. Professional judgement, transparent assumptions, ethical governance, and continuous validation are essential. Key TermsCost baseline: Authorised, time-phased budget used to measure performance. Contingency reserve: Budget for identified or foreseeable uncertainty within approved scope. Management reserve: Separately controlled budget for unforeseen work within project scope. Cost risk: Uncertainty in resources, rates, quantities, or productivity required for delivery. Financial risk: Exposure arising from cash timing, funding, interest, inflation, tax, or currency. Commercial risk: Exposure created by business relationships, contracts, incentives, and liabilities. Liquidity risk: Risk of insufficient cash to meet obligations when due. Working capital: Short-term funds required to finance operating activities. Three-point estimate: Estimate expressed through optimistic, most-likely, and pessimistic values. Reference-class forecasting: Forecasting based on outcomes from comparable completed projects. Correlation: Statistical association affecting the uncertainty of combined variables. Quantile: Value below which a specified proportion of outcomes falls. Escalation: Increase in a cost due to price or index movement over time. Foreign-exchange exposure: Risk caused by changes between currencies of costs, receipts, or debt. DSCR: Cash available for debt service divided by debt service due. Counterparty risk: Risk that another party fails to perform its obligation. Variation: Contractual change to scope, quantity, method, time, or price. Claim: Asserted contractual or legal entitlement requiring evaluation. Pain/gain sharing: Arrangement that shares cost underruns or overruns between parties. Integrated risk model: Model that represents interactions among cost, schedule, and financial variables. Review QuestionsShort Answer Questions- Distinguish contingency reserve from management reserve.
- Why can a profitable project experience a cash crisis?
- State two conditions under which a fixed-price contract may be inappropriate.
- What is the purpose of correlation in aggregate cost modelling?
- Identify four elements that should be analysed in a claim.
Long Answer Questions- Explain how inflation, exchange rates, and financing costs should be incorporated into a project financial model.
- Compare lump-sum, cost-reimbursable, target-cost, and unit-price contracts, including suitable applications and behavioural risks.
- Describe a defensible process for estimating contingency using probabilistic cost analysis.
- Explain how supplier financial weakness can become a project schedule, cost, and liquidity problem.
- Critically evaluate the benefits and limitations of integrated cost–schedule Monte Carlo modelling.
Analytical / Application Questions- A project has expected cost of $100 million and a simulated P80 cost of $114 million. Explain what contingency this implies, what assumptions must be checked, and why the result should not automatically be approved.
- A contractor receives payment 60 days after certification but must pay labour monthly and equipment suppliers on delivery. Design a cash-flow risk response plan, including contractual, operational, and financing measures.
- An imported component accounts for 25% of project cost and its delivery delay would extend commissioning by three months. Develop an integrated response addressing currency, supplier, schedule, commercial, and governance risks.
Multiple Choice Questions with AnswersQuestion 1Which statement best distinguishes contingency reserve from management reserve? A. Contingency is for identified or foreseeable uncertainty within approved scope; management reserve is separately controlled for unforeseen work within scope. B. Contingency is always outside the project budget; management reserve is always paid to suppliers. C. Contingency is a profit margin; management reserve is a tax allowance. D. There is no practical distinction between them. Correct Answer: A. Contingency is for identified or foreseeable uncertainty within approved scope; management reserve is separately controlled for unforeseen work within scope. Question 2For a three-point PERT estimate with a = $0.8 million, m = $1.0 million, and b = $1.6 million, what is the approximate expected cost? A. $0.800 million B. $1.000 million C. $1.067 million D. $1.600 million Correct Answer: C. $1.067 million Question 3What is the principal purpose of modelling correlation between uncertain cost components? A. To eliminate all uncertainty from the estimate B. To represent common drivers that affect components together C. To convert nominal costs into real costs D. To determine contractual liability automatically Correct Answer: B. To represent common drivers that affect components together Question 4A project has cash receipts of $5 million and disbursements of $6.5 million in one month. What is its net cash flow for that month? A. $11.5 million B. $6.5 million C. $1.5 million positive D. $1.5 million negative Correct Answer: D. $1.5 million negative Question 5Which contract form generally shares cost overruns and underruns through agreed pain/gain mechanisms? A. Target-cost contract B. Pure fixed-price contract C. Time-and-materials contract without a target D. Unpriced purchase order Correct Answer: A. Target-cost contract Question 6If a project cost is denominated in euros but revenue is in the home currency, which risk is directly created? A. Foreign-exchange risk B. Only scope risk C. Only quality risk D. No risk if the contract is signed Correct Answer: A. Foreign-exchange risk Question 7What does DSCR measure? A. The ratio of total project cost to contingency B. Cash available for debt service divided by debt service due C. Debt service divided by foreign-currency cost D. Revenue divided by contract duration Correct Answer: B. Cash available for debt service divided by debt service due Question 8Which practice most strengthens a potential delay claim? A. Waiting until project completion to reconstruct events from memory B. Avoiding written notices to preserve flexibility C. Maintaining contemporaneous records linking event, entitlement, causation, and effect D. Claiming every possible cost without checking for double recovery Correct Answer: C. Maintaining contemporaneous records linking event, entitlement, causation, and effect Question 9Why may a project with an acceptable expected final cost still require substantial additional funding? A. Because expected cost is always higher than cash cost B. Because payment timing can create a temporary liquidity shortfall C. Because contingency cannot be included in any budget D. Because exchange rates never affect cash flow Correct Answer: B. Because payment timing can create a temporary liquidity shortfall Question 10In an integrated cost–schedule simulation, why is the probability of meeting both budget and date not generally the product of the separate probabilities? A. Because budget and schedule outcomes may be correlated B. Because probabilities cannot be used for projects C. Because cost is never affected by duration D. Because the P50 is always the same as the P80 Correct Answer: A. Because budget and schedule outcomes may be correlated
|