Quality Control and Statistical MethodsIntroductionQuality control (QC) is the systematic examination of project work and deliverables to determine whether they conform to approved requirements, standards, specifications, and stakeholder expectations. In project quality management, quality assurance asks whether appropriate processes are being used; quality control asks whether the resulting outputs actually meet defined criteria. QC therefore provides evidence for corrective action, acceptance, rework, prevention, and continual improvement. Project environments create particular difficulties for statistical control. Processes may be temporary, data may be limited, requirements may change, and measurements may be affected by suppliers, technology, human judgement, and environmental conditions. Nevertheless, statistical methods help project teams distinguish ordinary process variation from unusual or assignable causes. They also support decisions when inspecting every item is costly, destructive, or impossible. This chapter develops an integrated toolkit comprising sampling, check sheets, Pareto analysis, histograms, scatter diagrams, cause-and-effect analysis, run charts, control charts, process capability, measurement system analysis, and acceptance sampling. The tools are most effective when used as part of a defined quality-management system rather than as isolated graphical techniques. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Explain common and special causes of variation in project processes.
- Design practical sampling plans and data-collection instruments.
- Select and interpret basic statistical quality tools.
- Construct and interpret run charts and control charts.
- Assess process capability and distinguish it from process stability.
- Evaluate measurement-system adequacy.
- Apply acceptance sampling while recognizing its risks and limitations.
- Integrate statistical evidence into project decisions, governance, and improvement.
1. Quality Control as an Evidence-Based ProcessA quality-control system normally follows a closed loop: Define → Measure → Compare → Diagnose → Act → Verify The project team first translates requirements into measurable characteristics. It then collects valid data, compares results with specifications or control limits, investigates deviations, implements action, and verifies whether the action was effective. Two forms of limits must be distinguished: - Specification limits are externally defined requirements. They may be a lower specification limit (LSL), an upper specification limit (USL), or both.
- Control limits are statistically calculated boundaries describing expected process behaviour. They are not customer requirements and should not be confused with specification limits.
A process can be stable but incapable: its results may consistently fall outside customer specifications. Conversely, a process may appear capable over a short period but be unstable because special causes have not been removed. Sound decisions require both stability and capability analysis. Variation in project processesCommon-cause variation results from the normal interaction of many factors built into a process—for example, ordinary variation in programming time, equipment precision, or material properties. It is reduced by redesigning or improving the process. Special-cause variation results from identifiable, abnormal influences, such as a failed instrument, an untrained operator, a defective batch, or an unusual environmental event. It should be investigated and removed or deliberately incorporated into the process if it represents a beneficial change. Overreacting to common-cause variation creates tampering: unnecessary adjustments increase instability. Ignoring special causes allows abnormal performance to continue. Statistical control is therefore partly a discipline of interpreting evidence before acting. 2. Sampling and Data Collection2.1 Why sampling is usedA census examines every unit. Sampling examines a selected subset and uses it to infer or decide something about the wider population. Sampling is appropriate when inspection is expensive, destructive, time-consuming, or operationally disruptive. It is also useful for continuous monitoring, where a small rational subgroup is measured periodically. The central sampling question is not simply “How many observations can we collect?” It is “What population, decision, precision, and risk must the sample support?” A sample must be representative of the process or lot relevant to the decision. 2.2 Sampling approaches| Method | Principle | Typical project use | Main risk |
|---|
| Simple random | Each unit has a known, equal chance of selection | Selecting records for audit | Incomplete sampling frame | | Systematic | Select every kth unit after a random start | Inspecting every 20th transaction | Hidden periodic pattern | | Stratified | Divide population into relevant groups and sample each | Comparing regions, suppliers, or work packages | Incorrect strata or allocation | | Cluster | Select naturally occurring groups, then inspect units within them | Auditing project sites or teams | Greater sampling error within clusters | | Judgmental | Select based on expert assessment | Targeting high-risk activities | Subjective selection bias | | Sequential | Inspect progressively and stop when evidence is sufficient | Acceptance decisions | Requires a defined stopping rule |
For a proportion estimate, a commonly used large-sample planning relationship is: n₀ = (Z² p(1 − p)) / e² Here, n₀ is the initial required sample size, Z is the standard-normal critical value for the selected confidence level, p is the anticipated population proportion, and e is the desired maximum margin of error. The formula assumes an approximately random sample, independent observations, and a sufficiently large population. If no prior estimate of p exists, p = 0.5 is conservative because it produces the largest variance. When the population is finite and sampling is a substantial fraction of it, a finite-population correction may be used: n = n₀ / (1 + (n₀ − 1)/N) where N is the population size. The result should be rounded upward and adjusted for nonresponse, missing data, or design effects. Formal sample-size planning should reflect the actual decision, confidence, power, and cost requirements; the formulas above are planning approximations, not universal rules. 2.3 Rational subgroupsA rational subgroup contains observations produced under approximately homogeneous conditions, such as units made by one machine during a short interval or defects recorded for one work package in one reporting period. Within-subgroup variation helps estimate short-term process variation; between-subgroup patterns reveal shifts over time. Poor subgroup design can conceal important changes or create false signals. 2.4 Operational definitions and check sheetsBefore collecting data, define: - the unit of analysis;
- the characteristic and unit of measurement;
- the defect or nonconformity criteria;
- who records the data and when;
- the instrument and calibration status;
- the coding scheme;
- the treatment of missing, repeated, or disputed observations.
A check sheet is a structured form for recording occurrences in real time. It may classify defects by type, location, time, supplier, severity, or project phase. It is not merely a tick list: its categories should be mutually understandable, sufficiently complete, and connected to a later decision. 3. The Seven Basic Statistical Tools3.1 Pareto analysisA Pareto chart ranks categories from greatest to least frequency or cost and often overlays a cumulative-percentage line. It supports prioritisation, not proof of causation. The familiar “vital few” idea is a useful heuristic, not a law that every dataset must obey. If category frequencies are fᵢ, total frequency is: F = ∑ fᵢ The cumulative percentage through category k is: Cₖ = 100 × (∑ᵢ₌₁ᵏ fᵢ) / F Categories should be defined consistently. Combining unlike defects merely to obtain a visually attractive chart can mislead management. 3.2 HistogramA histogram groups numerical observations into intervals called bins. It reveals location, spread, skewness, multimodality, gaps, and possible outliers. It is appropriate for continuous or discrete numerical data, but the appearance depends on bin width and origin. A histogram does not show time order; a stable-looking histogram may conceal a drift or alternating pattern. 3.3 Scatter diagramA scatter diagram plots paired observations to explore association between two numerical variables—for example, ambient temperature and curing time, or review effort and defect count. Association is not causation. Confounding variables, restricted ranges, autocorrelation, and measurement error can create or hide apparent relationships. The Pearson sample correlation coefficient is: r = [∑(xᵢ − x̄)(yᵢ − ȳ)] / √[∑(xᵢ − x̄)² × ∑(yᵢ − ȳ)²] where xᵢ and yᵢ are paired observations, x̄ and ȳ are sample means, and r ranges from −1 to +1. This coefficient measures linear association under appropriate assumptions; it does not establish a causal mechanism. 3.4 Cause-and-effect analysisA cause-and-effect, or fishbone, diagram organizes possible causes under categories such as People, Methods, Machines, Materials, Measurement, and Environment. The categories are prompts, not a mandatory taxonomy. The team should move from broad hypotheses to testable causes using evidence, stratification, experiments, audits, or process observation. The “five whys” technique can deepen an inquiry, but repeated questioning should not be treated as proof that the final statement is the root cause. Complex failures often have multiple interacting causes, weak controls, and latent organizational conditions. 3.5 Run chartsA run chart plots observations in time order, usually with a median or reference line. It helps reveal shifts, trends, cycles, and long runs above or below the centre. Because run-chart rules depend on sample size and chosen conventions, the team should define the rules in advance and avoid treating every irregularity as a signal. 3.6 Check sheets and stratificationCheck sheets become more informative when data are stratified by shift, location, supplier, design version, work package, or operator. Aggregated data can hide a local problem. Stratification should be planned before collection where possible, because relevant information may be impossible to recover later. 4. Control Charts4.1 Purpose and structureA control chart displays a statistic over time with a centre line and statistically derived upper and lower control limits. The centre line often represents a process mean, average proportion, or average count. Control limits estimate the range of common-cause variation under stated assumptions. A point outside a limit is evidence of an unusual event, not automatic proof of a specific cause. Other signals include sustained shifts, trends, cycles, and unusual sequences. Rules must be selected consistently, documented, and interpreted with process knowledge. 4.2 Variable control chartsFor individual measurements with a stable moving range, an Individuals–Moving Range chart may be used. Let x̄ be the average of individual observations and MR̄ the average moving range, where each moving range is typically MRᵢ = |xᵢ − xᵢ₋₁|. A common estimate of the process standard deviation is: σ̂ = MR̄ / d₂ where d₂ is a control-chart constant dependent on moving-range length; for a two-observation moving range, d₂ is approximately 1.128. The individuals-chart limits are: UCL = x̄ + 3σ̂ LCL = x̄ − 3σ̂ These limits assume an appropriate stable process and approximately independent observations. For subgroup means, X̄ charts are commonly paired with R or S charts. Constants vary with subgroup size, so published or software-provided constants must match the chosen chart design. 4.3 Attribute control chartsFor the fraction nonconforming in a sample of constant size n, a p chart uses: p̄ = (total nonconforming units) / (total units inspected) UCL = p̄ + 3√[p̄(1 − p̄)/n] LCL = p̄ − 3√[p̄(1 − p̄)/n] Limits below zero are set to zero. These relationships assume binomial-type counting, a defined inspection unit, and independence sufficiently appropriate for the application. For varying sample sizes, the standard error and limits must be calculated for each sample. A c chart monitors counts of defects per constant inspection unit; a u chart monitors defects per unit when the opportunity or sample size varies. A defect is not necessarily a defective unit: one unit may contain several defects. 4.4 Building and using a control chart- Define the characteristic, unit, sampling frequency, and subgrouping.
- Verify the measurement system.
- Collect baseline data under normal operating conditions.
- Calculate the centre line and limits using the correct chart type.
- Investigate signals using contemporaneous records and process knowledge.
- Remove special causes where justified, documenting evidence.
- Recalculate limits only when a genuine, sustained process change has occurred.
- Continue monitoring and link signals to action responsibilities.
Control limits should not be recalculated simply to make a point appear in control. Nor should specification limits be substituted for control limits. In automated systems, alerts need escalation rules, response times, and a method for preventing repeated false alarms. 5. Process CapabilityCapability compares the natural spread and centring of a stable process with specification requirements. It is meaningful only after process stability has been demonstrated and the measurement system is adequate. For a normally distributed characteristic with two-sided specifications: Cₚ = (USL − LSL) / (6σ) Cₚₖ = min[(USL − μ)/(3σ), (μ − LSL)/(3σ)] Here, USL and LSL are specification limits, μ is the process mean, and σ is the within-process standard deviation. Cₚ measures potential capability if centred; Cₚₖ also accounts for off-centre performance. A commonly used organisational benchmark is 1.33 or higher, but the required threshold depends on risk, industry, contract, and consequences of failure. Worked example: capabilitySuppose a stable shaft-diameter process has USL = 10.10 mm, LSL = 9.90 mm, μ = 10.02 mm, and σ = 0.03 mm. Then: Cₚ = (10.10 − 9.90)/(6 × 0.03) = 0.20/0.18 = 1.11 Cₚₖ = min[(10.10 − 10.02)/(3 × 0.03), (10.02 − 9.90)/(3 × 0.03)] = min[0.08/0.09, 0.12/0.09] = min[0.89, 1.33] = 0.89 The process spread is potentially moderate, but the mean is closer to the upper specification limit; actual capability is therefore governed by Cₚₖ = 0.89. Management should first investigate centring and variation rather than assume that more inspection will solve the process problem. Capability indices can be misleading when data are non-normal, autocorrelated, mixed across different conditions, or affected by special causes. Percentile-based or non-normal capability methods may be more appropriate, provided their assumptions and estimation methods are documented. 6. Measurement System AnalysisA measurement system includes the instrument, software, method, environment, operator, and calibration process. Poor measurement can produce false alarms, conceal defects, and distort capability estimates. Important properties include: - Bias: systematic difference between the average measurement and a reference value.
- Repeatability: variation when the same operator measures the same item repeatedly with the same equipment.
- Reproducibility: variation between operators or measurement conditions.
- Stability: change in measurement performance over time.
- Linearity: change in bias across the measurement range.
- Resolution: the smallest meaningful measurement increment.
For a crossed gauge repeatability and reproducibility study, several operators measure several parts repeatedly. An analysis of variance (ANOVA) can separate part-to-part, repeatability, reproducibility, and interaction components. A simplified variance decomposition is: σ²total = σ²part + σ²repeatability + σ²reproducibility + σ²interaction The decomposition depends on the experimental design and estimation method; it is not valid to add standard deviations directly. A frequently reported percentage is: %GRR = 100 × σGRR / σtotal where σGRR is the combined measurement-system standard deviation and σtotal is the observed total standard deviation, using a clearly defined convention. Acceptance criteria vary by application. A measurement system may be acceptable for broad process monitoring but inadequate for close tolerance decisions. Calibration alone does not establish repeatability or reproducibility. 7. Acceptance SamplingAcceptance sampling determines whether to accept or reject a lot based on a sample. It is a decision procedure, not a method for improving a process and not a guarantee that every accepted lot is defect-free. A single-sampling plan is often represented by (n, c), where n is sample size and c is the maximum number of nonconforming units allowed for acceptance. If the number observed is at most c, accept the lot; otherwise reject it. For a lot with nonconforming proportion p, assuming independent sampling with a large lot approximation, the probability of accepting a lot under a single plan is: Pₐ(p) = ∑ⱼ₌₀ᶜ [n choose j] pʲ(1 − p)ⁿ⁻ʲ where j is the number of nonconforming units in the sample. For finite lots sampled without replacement, the hypergeometric distribution is more appropriate. The producer’s risk α is the probability of rejecting a lot of acceptable quality. The consumer’s risk β is the probability of accepting a lot of unacceptable quality. These risks are defined at specified quality levels: the acceptable quality level (AQL) is associated with a producer-oriented point, while the limiting quality level (LQL), often called the rejectable quality level, is associated with consumer protection. AQL is not a promise that every lot with that percentage will be accepted, and it should not be interpreted as an allowable level of defects in every delivered item. Acceptance sampling plans should specify the lot, sampling frame, inspection method, decision rule, disposition of rejected lots, traceability, and escalation. For high-consequence characteristics, 100% inspection, automated verification, supplier process control, or preventive controls may be more suitable than sampling. 8. Integrated Application: Illustrative CaseBackgroundA fictional project team is delivering a cloud-based permitting system for a public agency. During user acceptance testing, rejected transactions and data-validation errors have increased. The project manager must determine whether the problem is random, concentrated in particular modules, or caused by a change in the development process. Problem definitionA defect is defined as a failed acceptance-test condition recorded against one transaction. Duplicate reports are consolidated, and severity is recorded separately. The team collects six weeks of data by module, release, tester, and defect type. AnalysisThe check sheet shows 186 defects. A Pareto analysis finds that validation errors account for 92 defects, interface mapping for 51, and access-control issues for 24; the remaining categories account for 19. The team therefore prioritises validation and mapping rather than distributing effort equally across all categories. A histogram of correction cycle time is right-skewed, suggesting that a few complex defects require much longer resolution. A scatter diagram shows an apparent association between the number of changed database fields and defect count. The team does not treat this as causation; it stratifies the data by developer team and release. A cause-and-effect workshop identifies possible contributors under Methods, People, Technology, Requirements, and Measurement. Evidence review shows that a new schema-migration script was introduced in release 4 and that the test environment did not contain representative legacy records. The team uses a run chart of weekly validation defects. A sustained shift begins after release 4, providing stronger evidence than a single high weekly count. Because the data are counts per week with differing numbers of transactions, the team uses a u chart for defects per transaction rather than a c chart of raw counts. Approach and solutionThe team first validates the defect classification and verifies that testers use the same acceptance criteria. It then conducts a measurement-system review of defect logging and excludes duplicate tickets. A targeted test sample is drawn from each data-migration stratum, rather than selecting only recently created records. The migration script is corrected, representative legacy data are added to the test environment, and a peer review is introduced for schema changes. Control limits are retained for the pre-change baseline only as a documented reference. After sufficient post-change data demonstrate a stable new process, revised limits are calculated. Capability analysis is not applied to defect counts as if they were normally distributed measurements; instead, the team monitors the rate and uses operational targets and risk-based thresholds. OutcomeThe post-change defect rate declines and shows no further sustained shift. The team reports the evidence, assumptions, excluded data, and residual risks to the project governance board. Release approval is based not on a single favourable sample but on converging evidence: corrected process cause, stable monitoring, validated test data, and acceptable residual risk. Learning points- Data definitions and measurement integrity precede statistical interpretation.
- Counts, proportions, continuous measurements, and defect opportunities require different tools.
- Pareto analysis prioritises investigation but does not prove root cause.
- A control chart should lead to a documented response, not merely a visual report.
- Acceptance decisions should consider consequences, not only sample results.
9. Governance, Ethics, Technology, and LimitationsQuality data influence payment, release, supplier evaluation, safety, and professional reputation. Deliberately redefining defects, suppressing inconvenient observations, changing limits without justification, or selecting only favourable samples is unethical and can create contractual or regulatory exposure. Data lineage, access control, version history, audit trails, and documented decision rules are therefore part of quality control. Software can calculate charts, estimate capability, detect patterns, and generate alerts. AI can assist with defect classification, anomaly detection, text mining of incident reports, and prioritisation of inspections. However, automated results require validated data, explainable rules, human review, protection of confidential information, and monitoring for model drift and bias. An AI system trained on historical defect labels may reproduce inconsistent or discriminatory inspection practices. It should support—not replace—engineering judgement and accountable approval. Major limitations include small samples, non-independent observations, changing specifications, autocorrelation, measurement error, non-normal distributions, selective reporting, and misuse of statistical thresholds. Statistical significance is not the same as practical significance. A small numerical improvement may be operationally irrelevant, while a rare failure may be unacceptable because its consequence is severe. Quality decisions should combine statistical evidence with risk analysis, process knowledge, contractual requirements, and stakeholder impact. Best-Practice Implementation SequenceA mature project team can apply the following sequence: - Translate stakeholder requirements into measurable acceptance criteria.
- Identify critical-to-quality characteristics and failure consequences.
- Define operational terms, sampling frames, and data ownership.
- Verify the measurement system before judging process performance.
- Use check sheets and stratification to collect traceable data.
- Select charts and analyses that match the data type and sampling design.
- Separate common-cause improvement from special-cause response.
- Use Pareto and cause-and-effect tools to focus investigation.
- Confirm suspected causes with evidence rather than intuition alone.
- Assess stability before capability and capability before relying on routine acceptance.
- Establish reaction plans, escalation thresholds, and governance records.
- Review whether the control method itself remains effective as the project changes.
Chapter SummaryQuality control uses measurement and analysis to determine whether project outputs and processes conform to requirements and remain predictable. Sampling provides efficient evidence when a census is impractical, but its validity depends on a suitable sampling frame, representative selection, and a clearly defined decision. Check sheets establish disciplined data collection; Pareto charts prioritise categories; histograms show distribution; scatter diagrams explore association; cause-and-effect diagrams structure hypotheses; and run charts reveal time-based behaviour. Control charts distinguish expected common-cause variation from signals of special causes. Their control limits are statistical boundaries, not specification limits. Process capability compares stable process variation and centring with customer specifications, while measurement-system analysis determines whether the data are trustworthy enough for such conclusions. Acceptance sampling supports lot decisions but exposes producer and consumer risks and cannot substitute for process prevention. At postgraduate level, these methods should be treated as an integrated decision system. Their value depends on operational definitions, sound assumptions, ethical data governance, appropriate chart selection, documented reaction plans, and critical interpretation. Statistical tools improve project decisions when they are connected to process knowledge, risk, and accountable management action. Key TermsAcceptance sampling: A procedure for deciding whether to accept or reject a lot from sample evidence. Assignable cause: A special, identifiable source of process variation. Capability: The degree to which a stable process can meet specification limits. Check sheet: A structured form for recording and classifying observations. Common cause: Normal variation inherent in a process system. Control chart: A time-ordered chart with a centre line and statistically calculated control limits. Control limit: A boundary describing expected process variation under stated assumptions. Defect: A nonconformity in a quality characteristic or requirement. Gauge repeatability and reproducibility (GRR): Analysis of measurement variation due to equipment and operators. Histogram: A frequency display of numerical data grouped into intervals. Measurement system analysis: Evaluation of bias, precision, stability, resolution, and related measurement properties. Pareto analysis: Ranking categories by frequency, cost, or impact to support prioritisation. Process capability index: A numerical comparison between process variation and specification width or location. Rational subgroup: A group of observations collected under sufficiently similar conditions for process analysis. Run chart: A time-ordered plot used to identify shifts, trends, and other patterns. Sampling frame: The operational list or structure from which a sample is selected. Scatter diagram: A plot of paired numerical observations used to explore association. Specification limit: A customer, contract, design, or regulatory boundary for acceptance. Stratification: Separation of data into meaningful groups to expose differences hidden in aggregated results. Variation: Differences among observations, processes, or outputs. Review QuestionsShort Answer Questions- Distinguish common-cause variation from special-cause variation.
- Why must specification limits be distinguished from control limits?
- What is the purpose of a check sheet?
- Explain the difference between repeatability and reproducibility.
- Why is process stability normally assessed before capability?
Long Answer Questions- Explain how sampling design, operational definitions, and measurement-system quality influence the validity of project quality decisions.
- Compare histograms, Pareto charts, scatter diagrams, and cause-and-effect diagrams in terms of purpose, data requirements, and limitations.
- Describe the construction and interpretation of an appropriate control chart for a project process, including reaction rules.
- Explain Cₚ and Cₚₖ, including their assumptions and managerial implications.
- Critically evaluate acceptance sampling as an alternative to process prevention and 100% inspection.
Analytical / Application Questions- A project team records 40 defects in week 1, 44 in week 2, and 60 in week 3, while the number of transactions processed is 800, 1,100, and 1,500 respectively. Should the team compare raw defect counts directly? Select an appropriate rate-based analysis and justify it.
- A stable process has USL = 52, LSL = 48, μ = 51, and σ = 0.5. Calculate Cₚ and Cₚₖ, interpret the difference, and recommend an improvement priority.
- Design a quality-control plan for a high-risk supplier deliverable. Specify the sampling approach, data-collection method, measurement-system checks, statistical tools, acceptance rule, escalation process, and ethical safeguards.
Multiple Choice Questions with AnswersQuestion 1Which statement best distinguishes a control limit from a specification limit? A. A control limit is set by the customer, whereas a specification limit is calculated from process data. B. A control limit describes expected process variation, whereas a specification limit states an acceptance requirement. C. Both terms refer to the same boundary and can be used interchangeably. D. A specification limit is used only for attribute data, whereas a control limit is used only for variable data. Correct Answer: B. A control limit describes expected process variation, whereas a specification limit states an acceptance requirement. Question 2A project team wants to identify which defect categories should receive priority. Which tool is most directly appropriate? A. Pareto chart B. Scatter diagram C. Gauge R&R study D. Histogram Correct Answer: A. Pareto chart Question 3For a stable process with USL = 10.10, LSL = 9.90, and σ = 0.03, what is Cp? A. 0.89 B. 1.11 C. 1.33 D. 1.67 Correct Answer: B. 1.11 Question 4In the capability example, why is Cpk lower than Cp? A. The process mean is not centred between the specification limits. B. The sample size is necessarily too large. C. Control limits were substituted for specification limits. D. Cpk ignores process variation. Correct Answer: A. The process mean is not centred between the specification limits. Question 5Which chart is generally suitable for monitoring the fraction of nonconforming units when sample size is constant? A. c chart B. u chart C. p chart D. X-bar chart only Correct Answer: C. p chart Question 6What is the principal purpose of measurement-system analysis? A. To increase the customer specification width B. To determine whether observed data are sufficiently trustworthy for decisions C. To replace process capability analysis in all situations D. To guarantee that every inspected unit is conforming Correct Answer: B. To determine whether observed data are sufficiently trustworthy for decisions Question 7Which statement about a scatter diagram is correct? A. It proves that the plotted variables have a causal relationship. B. It is used only for categorical data. C. It explores association between paired numerical observations. D. It automatically identifies the root cause of a defect. Correct Answer: C. It explores association between paired numerical observations. Question 8In acceptance sampling, consumer’s risk is the risk of: A. Rejecting every lot regardless of quality B. Accepting a lot of unacceptable quality C. Accepting only lots with zero defects D. Using a sample larger than the lot Correct Answer: B. Accepting a lot of unacceptable quality Question 9A process produces 100 nonconforming units out of 2,000 inspected. What is the observed nonconforming proportion? A. 0.005 B. 0.02 C. 0.05 D. 0.20 Correct Answer: C. 0.05 Question 10Why should a team avoid recalculating control limits merely to place an out-of-limit point inside the limits? A. It changes the customer’s specification limits. B. It can conceal a special cause and weaken the integrity of process monitoring. C. It always increases sample size. D. It converts a variable chart into an attribute chart. Correct Answer: B. It can conceal a special cause and weaken the integrity of process monitoring.
|