Project Management & Tracking

Chapter 10
Stakeholder Engagement, Communication and Project Leadership

Post Graduate Program in Operations Management
Project Management & Tracking   •   Post Graduate

Stakeholder Engagement, Communication and Project Leadership

Introduction

Projects are temporary organizational systems whose success depends not only on schedules, budgets and deliverables, but also on relationships. A technically sound project can fail when a regulator is ignored, a sponsor loses confidence, a user rejects the product, or a geographically dispersed team stops sharing information. Stakeholder engagement, communication and leadership therefore form an integrated managerial capability.

Stakeholder engagement concerns the deliberate development of productive relationships with individuals and groups affected by, able to influence, or responsible for a project. Communication provides the information flows through which expectations, decisions, risks and learning are coordinated. Project leadership gives these activities direction by creating purpose, enabling collaboration and making responsible decisions under uncertainty.

At postgraduate level, these topics should not be treated as soft skills in opposition to technical project management. They are mechanisms through which authority, knowledge, commitment and organizational change are mobilized.

Learning Objectives

By the end of this chapter, learners should be able to:

  1. Identify stakeholders and analyse their power, legitimacy, urgency, interests and likely responses.
  2. Design differentiated communication and engagement strategies.
  3. Lead diverse, cross-functional and virtual project teams.
  4. Diagnose and manage conflict, negotiation and resistance.
  5. Build motivation and psychological safety while maintaining accountability.
  6. Interpret the effects of culture and organizational change on project performance.
  7. Evaluate ethical, governance and technology-related issues in stakeholder communication.

1. Stakeholders and the Project System

A stakeholder is an individual, group or organization that can affect, be affected by, or perceive itself to be affected by a project, its decisions or its outcomes. This definition is broader than the project team. It may include the sponsor, customer, end users, suppliers, regulators, local communities, unions, shareholders, senior executives, partner organizations and future maintenance personnel.

Stakeholders differ in at least four ways:

  • Position: their formal role or relationship to the project.
  • Interests: the benefits, risks, values or outcomes they care about.
  • Influence: their capacity to shape decisions, resources, approvals or public opinion.
  • Response: their current and anticipated level of support, neutrality or resistance.

A stakeholder is not necessarily powerful because of hierarchy alone. A community group may have limited formal authority but substantial reputational influence. An operational employee may have little decision power but possess essential tacit knowledge. A regulator may intervene only occasionally but have decisive legal authority.

Stakeholder analysis is consequently a political and interpretive activity. It requires evidence, dialogue and continuous reassessment rather than a one-time register completed at project initiation.

Stakeholder salience

The stakeholder-salience perspective evaluates stakeholders through three attributes:

  • Power: the ability to influence project decisions or outcomes.
  • Legitimacy: the perceived appropriateness or validity of the stakeholder’s relationship with the project.
  • Urgency: the degree to which a claim requires immediate attention.

Stakeholders possessing one attribute may be latent; those possessing two may demand active management; and those possessing all three are highly salient. Salience can change rapidly. A previously peripheral stakeholder may become central after a safety incident, legal challenge or media investigation.

Power-interest analysis is a useful practical simplification. Stakeholders with high power and high interest require close management. High-power, low-interest stakeholders should be kept satisfied without unnecessary information overload. Low-power, high-interest stakeholders should be kept informed and given credible channels to contribute. Low-power, low-interest stakeholders should be monitored because their status may change.

Stakeholder positionAppropriate managerial emphasis
High power, high interestFrequent dialogue, joint decisions where appropriate, escalation access
High power, low interestConcise assurance, milestone reporting, exception-based communication
Low power, high interestInclusion, transparent information, feedback and impact management
Low power, low interestPeriodic monitoring and accessible public information

The matrix is a prioritization device, not a substitute for judgement. It can conceal vulnerable groups if “power” is defined only as formal authority. Ethical analysis should therefore consider whose interests are underrepresented and who bears project risks without receiving corresponding benefits.

Stakeholder register and influence network

A useful stakeholder register records the stakeholder’s role, interests, influence, current attitude, desired attitude, information needs, engagement owner, risks and planned actions. It should also record assumptions and evidence, because stakeholder classifications often reflect managerial perceptions rather than verified facts.

The project manager should supplement the register with an influence network. This identifies informal relationships, trusted intermediaries, professional communities and communication pathways. In complex projects, influence may flow through technical experts, procurement officers, community leaders or informal team networks rather than through the formal organizational chart.

2. From Communication to Engagement

Communication is the exchange and interpretation of information. Engagement is broader: it includes participation, relationship quality, mutual adaptation and the development of commitment. Sending a weekly report is communication; involving users in prototype testing and responding to their concerns is engagement.

A communication strategy should answer six questions:

  1. Who needs information?
  2. What decision, action or understanding is required?
  3. Why is the information important?
  4. When and how frequently is it needed?
  5. Through which channel should it be delivered?
  6. How will understanding and response be verified?

The communication channel should match message complexity and sensitivity. Routine status data may be handled through a dashboard. Ambiguous design trade-offs require dialogue. Conflict, performance concerns and ethical issues generally require private, high-richness interaction rather than impersonal messages.

Communication planning

A communication management plan commonly specifies:

  • audience and stakeholder owner;
  • purpose and decision rights;
  • message content and level of technical detail;
  • frequency and trigger events;
  • channel and format;
  • language, accessibility and cultural requirements;
  • document control and confidentiality;
  • feedback and escalation mechanisms; and
  • measures of communication effectiveness.

Communication effectiveness should not be measured only by the volume of messages sent. More meaningful indicators include decision-cycle time, unresolved questions, rework caused by misunderstanding, response rates, stakeholder sentiment and the percentage of decisions whose owners and deadlines are clear.

Push, pull and interactive communication

Push communication sends information to recipients, for example through email or formal reports. It is efficient but does not guarantee comprehension. Pull communication makes information available for stakeholders to retrieve, such as a project portal or knowledge repository. It is scalable but depends on stakeholder initiative. Interactive communication involves real-time exchange, such as workshops, interviews, negotiation and retrospectives. It is resource-intensive but essential for ambiguity, learning and commitment.

A mature project uses all three. It also distinguishes information from knowledge. A dashboard may display schedule variance, but only conversation may reveal that a supplier is technically incapable of meeting the next milestone.

Listening and sensemaking

Effective project communication is two-way. Active listening involves attention to content, emotion, assumptions and unspoken concerns. Project leaders should paraphrase important statements, ask exploratory questions, test interpretations and document agreed actions. Sensemaking is the collective process through which stakeholders interpret uncertain events. During a crisis, inconsistent explanations can create rumours and defensive behaviour even when the underlying technical problem is manageable.

3. Engagement Strategy Across the Project Life Cycle

Stakeholder engagement changes as the project moves from concept to closure.

During initiation, the emphasis is on legitimacy, strategic alignment, sponsorship and a shared problem definition. During planning, stakeholders help define requirements, constraints, risks, governance and acceptance criteria. During execution, engagement focuses on coordination, issue resolution, change control and maintaining confidence. During monitoring, stakeholders validate performance and emerging impacts. During closure and transition, users, operators and sponsors assess benefits realization, operational readiness and lessons learned.

Engagement should be designed at three levels:

  • Inform: provide accurate, timely and accessible information.
  • Consult: seek views and explain how they influence decisions.
  • Involve or collaborate: share problem solving, design and selected decisions.

A common failure is symbolic consultation: stakeholders are asked for views after major decisions have already been made. This damages trust. Participation should occur early enough to affect outcomes, and the project should disclose which constraints limit stakeholder choice.

4. Project Leadership in Complex Environments

Management coordinates plans, resources and controls; leadership creates direction, meaning and conditions for collective performance. Project leadership is not confined to the formally appointed project manager. Technical leads, work-package managers and stakeholder representatives may exercise leadership through expertise and credibility.

Leadership approaches

No single leadership style is universally effective. A directive approach may be appropriate in a safety emergency or when rapid compliance is legally required. A participative approach is valuable when knowledge is distributed and commitment matters. Coaching leadership develops capability, while transformational leadership helps people connect project work to a meaningful future state. Situational leadership adapts the degree of direction and support to competence, confidence, task uncertainty and risk.

Authentic leadership requires consistency between stated values and observed behaviour. Ethical leadership requires attention to consequences, fairness, rights, transparency and accountability. Charisma without governance can produce excessive dependence on one individual and suppress dissent.

Leading diverse teams

Diversity includes profession, discipline, nationality, language, gender, age, cognitive style, experience and organizational identity. Diversity can improve creativity and risk detection, but only when inclusion allows people to influence decisions. Otherwise, it may produce fragmented subgroups and unequal voice.

Leaders should establish explicit norms for turn-taking, evidence, disagreement, meeting conduct, documentation and escalation. They should rotate visible responsibilities, ensure that technical language is explained, and distinguish confidence from competence. Inclusion also requires attention to time zones, disability access, language proficiency and caregiving responsibilities.

Virtual and hybrid teams

Virtual teams face reduced social cues, communication delay, technology dependence and weaker informal learning. Effective practice includes:

  • a team charter defining purpose, roles, working hours and response expectations;
  • a single source of truth for controlled project information;
  • purposeful meeting design with agendas and decisions recorded;
  • asynchronous updates for routine information;
  • periodic synchronous sessions for complex problem solving and relationship building;
  • explicit escalation routes; and
  • attention to workload, isolation and digital fatigue.

Leaders should manage outputs and commitments rather than equating online presence with contribution. Excessive surveillance may reduce trust and encourage performative activity rather than genuine performance.

5. Motivation, Psychological Safety and Accountability

Motivation combines intrinsic factors, such as mastery, autonomy and purpose, with extrinsic factors, such as recognition, career opportunities and compensation. Project work can weaken motivation when goals are unstable, contributions are invisible or decision rights are unclear.

A practical motivation system aligns meaningful work, achievable challenge, feedback, recognition and fairness. Goals should be sufficiently specific to guide action but adaptable when assumptions change. Recognition should reward collaboration and responsible risk reporting, not only heroic recovery of avoidable failures.

Psychological safety is a shared belief that people can ask questions, admit errors, raise concerns and disagree without humiliation or retaliation. It does not mean low standards or unrestricted agreement. High-performing teams combine psychological safety with accountability.

Leaders can strengthen psychological safety by:

  1. acknowledging uncertainty and their own fallibility;
  2. inviting dissent before decisions are finalized;
  3. responding constructively to bad news;
  4. separating learning discussions from blame-oriented investigations, except where misconduct is involved;
  5. making escalation safe and traceable; and
  6. following up on concerns so that speaking up produces visible learning.

A project that celebrates only on-time delivery may encourage concealment of risks. Governance should reward transparency, not merely favourable appearances.

6. Conflict and Negotiation

Conflict is a perceived incompatibility of interests, goals, values or interpretations. It is not automatically harmful. Task conflict can expose assumptions and improve decisions; relationship conflict can damage trust; process conflict concerns roles, methods and resource allocation.

A useful diagnostic sequence is:

  • What is the observable issue?
  • Which interests and constraints lie beneath stated positions?
  • Is the conflict about facts, values, authority, resources or identity?
  • Who is affected but absent from the discussion?
  • What is the cost of delay or escalation?

Avoidance may be suitable for trivial or temporary issues, but persistent avoidance allows conflict to become structural. Accommodation can preserve relationships but may create unfairness. Competition may be necessary for safety or compliance decisions. Collaboration seeks an integrative solution, while compromise distributes losses and benefits. The appropriate response depends on urgency, importance, power asymmetry and relationship value.

Interest-based negotiation

Interest-based negotiation separates people from problems, focuses on underlying interests, develops options and uses objective criteria. A project team negotiating with a supplier, for example, should explore capacity constraints, cash-flow timing, quality risks and future business rather than simply arguing over a missed date.

Preparation should define the desired outcome, minimum acceptable outcome, alternatives if agreement is not reached, authority limits, evidence and likely interests of the other party. Agreements should specify scope, responsibilities, assumptions, dates, acceptance criteria and consequences of non-performance. Verbal consensus without written ownership is a frequent source of renewed conflict.

7. Culture and Organizational Change

Culture consists of shared assumptions, values, symbols and patterns of behaviour. Projects often cross organizational cultures: a safety-regulated unit may prioritize formal approval, while an entrepreneurial technology team may prioritize speed and experimentation. Neither culture is universally superior; their compatibility with the project’s risk and uncertainty is what matters.

Cultural analysis should examine:

  • attitudes to hierarchy and authority;
  • tolerance for ambiguity and failure;
  • directness of communication;
  • relationship between individual and group identity;
  • attitudes to time, commitments and deadlines; and
  • treatment of disagreement and status.

Leaders should avoid stereotyping national or professional groups. Culture is dynamic and exists at multiple levels: national, organizational, occupational, team and project.

Projects frequently deliver organizational change rather than merely physical outputs. Change adoption depends on whether people understand the case for change, believe leadership is committed, have the capability to work differently and see reinforcement for new behaviour. Resistance is not always irrational. It may reveal loss of status, workload concerns, inadequate training, poor design or legitimate ethical objections.

A responsible change strategy combines impact assessment, sponsor coalition, affected-user involvement, training, transition support, feedback loops and benefit measurement. Communication should explain not only what will change, but also what will remain stable and how concerns will be handled.

8. Governance, Ethics and Technology

Stakeholder engagement raises ethical questions about representation, transparency, privacy and fairness. Projects should disclose material risks, avoid manipulative consultation, protect confidential information and provide reasonable access to participation. Decisions affecting communities or vulnerable users require impact assessment beyond the interests of the funding sponsor.

Governance should define escalation rights, decision authority, conflict-of-interest declarations, records management and assurance. A stakeholder with commercial influence should not control acceptance evidence without independent review.

Digital collaboration platforms and artificial intelligence can support stakeholder management by summarizing meetings, identifying unanswered questions, analysing sentiment and translating routine content. However, automated summaries may omit dissent or misattribute statements. Sentiment analysis can reproduce cultural and linguistic bias. Sensitive project data may also be exposed through inappropriate tools.

Use of AI should therefore include human review, data minimization, access controls, disclosure where appropriate, auditability and a prohibition on treating generated text as authoritative evidence without verification. Technology should improve inclusion, not replace meaningful dialogue.

9. Applied Case: The Northbridge Health Information Project

The following is a fictional illustrative case.

Background

Northbridge Regional Health Authority initiated a project to replace fragmented hospital scheduling systems with a shared digital platform. The intended benefits were fewer appointment errors, better capacity visibility and improved patient communication. Stakeholders included clinicians, administrative staff, patients, a software supplier, privacy officers, unions, hospital executives and a regional regulator.

Problem

The project met its early technical milestones but encountered growing resistance. Clinicians argued that the workflow increased documentation time. Administrative staff feared job redesign. The supplier reported that requirements were changing, while the project board believed users were indecisive. A pilot revealed that patient representatives had not understood how appointment data would be used. In addition, virtual meetings were dominated by senior voices, and frontline staff rarely raised concerns.

Analysis

The original stakeholder register classified the supplier and executives as high power and high interest, but treated patients and frontline administrators mainly as “informed” stakeholders. This underestimated legitimacy, operational knowledge and reputational risk. Communication was predominantly push-based: monthly reports and recorded demonstrations. The project had no explicit psychological-safety norms and no structured route for anonymous escalation.

A revised analysis identified four critical gaps:

  1. requirements were being gathered as feature requests rather than underlying workflow needs;
  2. privacy communication described compliance but not practical data use;
  3. the project measured technical progress but not adoption readiness; and
  4. decision rights between the hospitals and supplier were ambiguous.

Approach and solution

The project sponsor created a stakeholder coalition including a clinician, administrator, patient advocate, privacy officer and supplier lead. The team conducted workflow observations and short interviews across shifts. Workshops used anonymous digital input before open discussion, reducing status effects. The communication plan was redesigned so that each major decision included its rationale, affected groups, owner and appeal route.

The project adopted a differentiated strategy:

  • executives received exception-based benefit and risk reports;
  • clinicians participated in scenario-based design reviews;
  • administrative staff received training and role-transition support;
  • patients received plain-language privacy explanations and consent choices; and
  • the regulator received traceable evidence of control design and testing.

The project manager introduced a team charter, a decision log and a “bad news early” norm. The supplier contract was amended to clarify change-control thresholds and joint acceptance criteria. A pilot was repeated in two departments with different operating conditions rather than relying on a single demonstration site.

Outcome

The second pilot required more time but revealed usability problems before full deployment. Several unnecessary data fields were removed, training was redesigned around real tasks, and privacy notices were clarified. Adoption improved in the pilot departments, while unresolved issues were escalated to the steering committee with documented alternatives. The project did not eliminate disagreement; it made disagreement more visible, structured and actionable.

Learning points

The case illustrates that engagement is not public relations. It changes design quality, risk visibility and implementation readiness. It also shows that stakeholder power must be interpreted broadly, that psychological safety is a governance asset, and that communication quality depends on dialogue and decision traceability rather than message volume.

10. Practical Framework for Project Leaders

A project leader can use the following cycle throughout the project:

  1. Map: identify stakeholders, interests, influence and affected groups.
  2. Listen: gather evidence through interviews, observation, workshops and feedback channels.
  3. Prioritize: determine which relationships require information, consultation, collaboration or escalation.
  4. Design: select messages, channels, timing, owners and accessibility provisions.
  5. Lead: establish purpose, norms, decision rights and psychological safety.
  6. Negotiate: address interests, constraints and trade-offs using objective criteria.
  7. Monitor: review sentiment, participation, unresolved issues, adoption and emerging power shifts.
  8. Adapt: revise the strategy when assumptions, stakeholders or project conditions change.

This cycle should be integrated with risk management, change control, quality assurance and benefits realization. Stakeholder engagement is strongest when it is connected to actual decisions and measurable outcomes.

Challenges and Limitations

Stakeholder models simplify reality. Power-interest grids can privilege formal authority, while salience models can be difficult to apply consistently. Stakeholder preferences may be contradictory, and no strategy can satisfy every interest. Engagement also consumes time and can create consultation fatigue if meetings do not produce decisions.

Communication can be distorted by organizational politics, selective reporting, language barriers and information overload. Virtual tools may increase access for some people while excluding those with poor connectivity or limited digital confidence. Psychological safety cannot be manufactured through slogans if leaders punish dissent. Finally, cultural adaptation must not become an excuse for tolerating discrimination, unsafe practice or violation of legal rights.

The project leader’s task is therefore not to eliminate uncertainty or conflict, but to make them visible, legitimate and manageable while protecting the project’s purpose and affected people.

Chapter Summary

Stakeholder engagement, communication and project leadership are interdependent capabilities. Stakeholder analysis identifies interests, influence, legitimacy and urgency, but must be updated as project conditions change. Power-interest matrices, salience analysis, stakeholder registers and influence networks support prioritization while requiring ethical judgement about underrepresented groups.

Communication is more than message transmission. Effective practice matches channel and richness to purpose, combines push, pull and interactive methods, enables listening and maintains decision traceability. Engagement progresses from informing to consulting, involving and collaborating, and should occur early enough to influence outcomes.

Project leadership creates direction, trust, accountability and the conditions for diverse and virtual teams to perform. Motivation, psychological safety and inclusive norms support both learning and responsible challenge. Conflict can be productive when focused on tasks and interests; negotiation should clarify alternatives, objective criteria, authority and commitments.

Culture and organizational change shape adoption, resistance and project outcomes. Ethical governance requires transparency, representation, privacy, fair participation and accountable use of technology, including AI. The central managerial principle is that stakeholder relationships are part of project delivery itself, not an accessory to the technical plan.

Key Terms

Stakeholder: An individual, group or organization that can affect, be affected by, or perceive itself to be affected by a project.

Stakeholder salience: The relative priority of a stakeholder based on power, legitimacy and urgency.

Power-interest matrix: A tool for prioritizing stakeholders according to influence and level of concern.

Legitimacy: The perceived validity or appropriateness of a stakeholder’s relationship or claim.

Urgency: The degree to which a stakeholder claim requires immediate attention.

Stakeholder register: A controlled record of stakeholder attributes, interests, influence, attitudes and engagement actions.

Engagement: The process of developing relationships, participation and commitment around a project.

Push communication: Information sent directly to intended recipients.

Pull communication: Information made available for recipients to retrieve.

Interactive communication: Two-way communication involving dialogue and immediate feedback.

Psychological safety: A shared belief that people can speak up, ask questions and admit errors without interpersonal punishment.

Task conflict: Disagreement about ideas, evidence, methods or work content.

Relationship conflict: Interpersonal tension involving identity, trust or personal incompatibility.

Interest-based negotiation: Negotiation focused on underlying interests and objective criteria rather than fixed positions.

Virtual team: A team whose members collaborate across significant geographic or temporal distance using digital technologies.

Organizational culture: Shared assumptions, values and behavioural patterns within an organization or group.

Change adoption: The extent to which affected people accept, use and sustain new practices.

Decision traceability: The ability to identify a decision’s rationale, owner, evidence and follow-up.

Stakeholder coalition: A coordinated group of influential or affected stakeholders supporting project dialogue and implementation.

Review Questions

Short Answer Questions

  1. What are the three attributes in the stakeholder-salience perspective?
  2. Distinguish push, pull and interactive communication.
  3. Why is psychological safety compatible with high accountability?
  4. Name two characteristics of effective virtual-team leadership.
  5. What is the difference between a stakeholder register and an influence network?

Long Answer Questions

  1. Explain how a project manager should use power-interest analysis without neglecting low-power or vulnerable stakeholders.
  2. Discuss how communication strategy should change across the project life cycle.
  3. Compare directive, participative, coaching and transformational leadership in project environments.
  4. Explain how culture can influence conflict, communication and organizational change.
  5. Evaluate the ethical and governance risks of using artificial intelligence for stakeholder communication.

Analytical / Application Questions

  1. A regulator is highly powerful but currently shows little interest in a project. Design an engagement and communication strategy, including conditions that would trigger escalation.
  2. A virtual project team reports good schedule performance, but junior members rarely challenge technical decisions. Diagnose possible causes and propose interventions that preserve accountability.
  3. A supplier and project sponsor disagree about repeated requirement changes. Analyse the conflict using interests, alternatives and objective criteria, then propose a negotiation plan.

Multiple Choice Questions with Answers

Question 1

Which combination represents the three attributes of stakeholder salience?

A. Power, legitimacy and urgency

B. Cost, quality and schedule

C. Authority, seniority and availability

D. Interest, location and tenure

Correct Answer: A. Power, legitimacy and urgency

Question 2

A low-power stakeholder has high interest in a project. Which engagement approach is generally most appropriate?

A. Ignore the stakeholder unless a problem occurs

B. Keep the stakeholder informed and provide credible feedback channels

C. Give the stakeholder complete decision authority

D. Provide only confidential executive reports

Correct Answer: B. Keep the stakeholder informed and provide credible feedback channels

Question 3

Which communication type is most suitable for resolving an ambiguous design trade-off?

A. Interactive communication

B. An automated mass email

C. A static archive with no feedback route

D. A routine dashboard only

Correct Answer: A. Interactive communication

Question 4

Psychological safety means that team members can:

A. Avoid performance standards

B. Make decisions without accountability

C. Raise concerns and admit errors without humiliation or retaliation

D. Prevent leaders from making final decisions

Correct Answer: C. Raise concerns and admit errors without humiliation or retaliation

Question 5

Which action best supports effective virtual-team leadership?

A. Equating online presence with productivity

B. Using only synchronous meetings

C. Defining working norms, documenting decisions and using asynchronous updates appropriately

D. Avoiding informal relationship building

Correct Answer: C. Defining working norms, documenting decisions and using asynchronous updates appropriately

Question 6

Interest-based negotiation primarily focuses on:

A. Underlying interests and objective criteria

B. The most powerful party’s preferred position

C. Avoiding written commitments

D. Winning through positional authority

Correct Answer: A. Underlying interests and objective criteria

Question 7

Which statement best describes task conflict?

A. Disagreement about ideas, evidence or methods

B. Personal hostility unrelated to the work

C. A legal dispute over ownership

D. A disagreement caused only by cultural differences

Correct Answer: A. Disagreement about ideas, evidence or methods

Question 8

Why should stakeholder analysis be revisited during a project?

A. Stakeholder power, urgency and interests can change

B. The original register is legally permanent

C. Only communication channels change

D. Reassessment eliminates the need for governance

Correct Answer: A. Stakeholder power, urgency and interests can change

Question 9

Which is an ethical risk in using AI-generated meeting summaries?

A. Improved searchability

B. Possible omission or misattribution of dissent

C. Reduced manual transcription

D. Faster distribution of information

Correct Answer: B. Possible omission or misattribution of dissent

Question 10

A project team asks users for opinions after all major design decisions are fixed. What is the principal engagement problem?

A. The consultation may be symbolic because participation cannot influence outcomes

B. The project is using too much collaboration

C. Users have excessive decision authority

D. The project has selected a pull communication channel

Correct Answer: A. The consultation may be symbolic because participation cannot influence outcomes

Project Management & Tracking
Chapter 10 of 15