Cost Estimation, Budgeting and Financial ControlIntroductionCost management is the process of estimating, allocating, authorizing, monitoring and controlling the financial resources required to deliver a project. In operations-intensive projects, cost performance affects more than profit. It influences production capacity, service reliability, working capital, investment decisions, supplier relationships and organizational credibility. A project budget is not merely a list of expected expenditure. It is a time-phased managerial baseline against which actual performance and forecasts are evaluated. Effective cost management therefore connects scope, schedule, resources, risk, procurement and financial governance. A technically attractive project can still fail if its cost estimate is optimistic, its cash requirements are misunderstood, or emerging variances are detected too late. This chapter examines four major estimation approaches—analogous, parametric, bottom-up and three-point estimation—and then develops the related ideas of cost baselines, contingency, reserves, cash flow, life-cycle cost and earned value forecasting. Emphasis is placed on managerial judgment, transparent assumptions and disciplined control rather than on false precision. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Explain the relationship between estimates, budgets, baselines and forecasts.
- Select and apply analogous, parametric, bottom-up and three-point estimation methods.
- Construct a cost baseline with appropriate contingency and management reserve.
- Analyze project cash flow and life-cycle cost.
- Apply earned value measures to diagnose cost and schedule performance.
- Forecast final cost and required funding using appropriate assumptions.
- Evaluate governance, ethical and technological issues in project financial control.
1. The Architecture of Project Cost ManagementProject financial planning normally progresses through five connected stages: - Resource planning: determining the labour, equipment, materials, facilities, technology and services required.
- Cost estimating: developing expected costs for work packages, activities or deliverables.
- Budget formulation: aggregating estimates, adding authorized contingency and aligning expenditure with time.
- Cost authorization: establishing spending authority, funding limits and approval rules.
- Cost control: comparing actual and forecast performance with the approved baseline and taking corrective action.
Several terms must be distinguished. | Term | Meaning | Primary use |
|---|
| Cost estimate | Prediction of the resources and money required | Planning and decision-making | | Budget | Authorized allocation of money to planned work | Funding and accountability | | Cost baseline | Time-phased approved budget used for performance measurement | Control and variance analysis | | Funding limit | Amount and timing of cash made available | Treasury and liquidity management | | Forecast | Revised estimate of future cost based on current evidence | Management action | | Reserve | Money set aside for uncertainty or authorized unknowns | Risk and governance |
The budget and the funding profile are related but not identical. A project may have an approved budget of $10 million but require only $1 million in the first quarter. Conversely, contractual payment terms may require cash before the related work is complete. Financial control must therefore address both total cost and timing of cash requirements. Cost classificationsCosts may be classified in several ways. Direct costs can be traced readily to a project, such as project engineers or purchased equipment. Indirect costs support several projects and require an allocation basis, such as corporate information technology or shared facilities. Fixed costs do not vary substantially with a relevant activity level, while variable costs change with output or usage. Recurring costs arise repeatedly, whereas non-recurring costs occur once, such as initial design or commissioning. These classifications are not mutually exclusive. A project manager may face a direct, variable labour cost; a corporate allocation may be indirect and relatively fixed. The classification should be consistent with the organization’s accounting policy and useful for decision-making. 2. Estimating Cost: Methods and JudgmentNo estimating method is universally superior. Method selection depends on the maturity of scope definition, availability of historical data, project uniqueness, required accuracy, time available and consequences of error. Estimates should state their basis, assumptions, exclusions, data date, confidence range and level of detail. 2.1 Analogous estimationAnalogous estimation uses the cost of a completed or sufficiently similar project as a reference. A simple form is: Cn = Cr × I × A Here, Cn is the estimated cost of the new project, Cr is the reference-project cost in comparable monetary terms, I is an adjustment factor for inflation or price movement, and A represents other combined adjustments for scale, complexity, location or productivity. All costs must use the same currency, price basis and scope boundary. For example, a previous warehouse automation project cost $4.0 million. A proposed project is assessed as 10% more complex, and relevant prices have increased by 5%. If the adjustments are applied multiplicatively, the estimate is: Cn = 4.0 × 1.10 × 1.05 = 4.62 million dollars. Analogous estimation is fast and useful in early feasibility studies. Its weakness is dependence on genuine comparability. Differences in scope, technology, regulatory requirements, market conditions or project capability may be hidden by a superficial similarity. The estimator should document why the reference is comparable rather than simply selecting the most convenient historical project. 2.2 Parametric estimationParametric estimation applies a statistical or operational relationship between cost and measurable project characteristics. A basic model is: C = q × r where q is the quantity of a cost-driving unit and r is the validated cost per unit. For a 12,000-square-metre facility with a benchmark construction cost of $1,800 per square metre, the base estimate is $21.6 million. More sophisticated models may include several drivers: C = a + b1x1 + b2x2 + … + bkxk Here, a is an intercept, bi is the estimated cost coefficient for driver xi, and k is the number of drivers. Such a model is useful only when the data set is relevant, the variables are measured consistently and the relationship remains valid for the proposed project. Parametric models require calibration. The estimator should examine sample size, outliers, confidence intervals, changes in technology, scale effects and possible correlation among drivers. A model that predicts cost well for routine projects may be unreliable for a novel project outside the historical data range. Unit consistency is essential: a cost per square metre cannot be multiplied by a quantity measured in square feet without conversion. 2.3 Bottom-up estimationBottom-up estimation develops estimates for detailed activities or work packages and aggregates them. If work-package costs are independent components, the total direct estimate is: Ctotal = ∑_(i=1)n Ci where Ci is the estimate for component i and n is the number of components. In practice, the aggregation may also include indirect costs, risk allowances and approved reserves, but these should be shown separately rather than hidden inside activity estimates. For labour, a common calculation is: Clabour = h × r where h is planned labour hours and r is the fully burdened hourly rate. The rate may include wages, benefits, payroll taxes and approved overhead. Equipment cost may be estimated from hours multiplied by an ownership or rental rate, while materials may be estimated from quantity multiplied by purchase price plus applicable logistics costs. Bottom-up estimates are generally more defensible when scope is well defined. They support responsibility assignment and later control at work-package level. Their limitations include high effort, false precision, omission of integration activities and the possibility that every small estimate is optimistic. Independent review and reconciliation with an analogous or parametric estimate can expose such problems. 2.4 Three-point estimationThree-point estimation explicitly recognizes uncertainty by using three values: - optimistic estimate, a;
- most likely estimate, m; and
- pessimistic estimate, b.
The triangular expected value is: ET = (a + m + b) ÷ 3 The beta-PERT expected value, often used when the most likely value deserves greater weight, is: EP = (a + 4m + b) ÷ 6 For the beta-PERT form, a commonly used approximate standard deviation is: σ = (b − a) ÷ 6 The estimates must refer to the same scope, currency and conditions. For a = 80, m = 100 and b = 160 thousand dollars: EP = (80 + 4(100) + 160) ÷ 6 = 106.67 thousand dollars, and σ = (160 − 80) ÷ 6 = 13.33 thousand dollars. These formulas are approximations, not guarantees of a normal distribution or a 90% confidence interval. They are most useful for structured discussion of uncertainty. If activity risks are correlated—for example, several activities depend on the same delayed permit—simply adding standard deviations understates aggregate uncertainty. Simulation or scenario analysis may then be appropriate. Choosing and combining methodsA professional estimate often triangulates methods. A parametric estimate may provide a top-down reasonableness check; a bottom-up estimate may provide control detail; analogous evidence may reveal whether the total is plausible; and three-point analysis may represent uncertainty. Differences should be investigated, not averaged mechanically. 3. From Estimates to the Cost BaselineThe cost baseline is a time-phased version of the approved budget. A useful formulation is: BAC = PV1 + PV2 + … + PVn where BAC is the budget at completion and PVt is the planned value scheduled for period t. In earned value management, planned value means the authorized budget for work scheduled by a particular date—not cash paid and not actual physical progress. A practical budget structure is: - Control accounts: management points where scope, schedule and cost are integrated.
- Work packages: measurable portions of control accounts that receive budget.
- Planning packages: future work not yet decomposed into detailed work packages.
- Undistributed budget: authorized budget not yet assigned to control accounts.
- Contingency reserve: budget for identified risks whose responses are within the approved project scope.
- Management reserve: budget held by authorized management for unforeseen work within the project’s overall scope, subject to governance rules.
Contingency is not a license to inflate every activity estimate. It should be connected to identified uncertainty, risk exposure or an explicit estimating policy. Management reserve should not conceal poor performance or be used to make an unauthorized scope change appear affordable. A change that alters the approved scope normally requires formal change control and possibly a revised baseline. Deterministic and probabilistic budgetsA deterministic budget presents a single approved value. A probabilistic estimate presents a distribution or range, such as a percentile-based estimate. For investment decisions, management may compare a base estimate with P50 and P80 values, where the percentile indicates the probability that actual cost will not exceed the stated amount under the model assumptions. Percentiles are meaningful only when the risk model, input quality and correlations are credible. 4. Cash Flow and Funding RequirementsCost, expenditure and cash flow are related but different. A cost may be recognized when goods or services are received, while cash may be paid earlier or later. Retentions, milestone payments, advance payments, tax obligations and foreign exchange movements can create substantial timing differences. For period t, net cash flow is: NCFt = CashInt − CashOutt Cumulative cash balance is: CBt = CB_(t−1) + NCFt where CB0 is the opening cash balance. If project-specific funding is being evaluated, the minimum cumulative balance indicates the potential funding requirement, subject to organizational cash policies and financing costs. Worked cash-flow exampleAn illustrative project has the following monthly cash outflows and inflows, in thousands of dollars: | Month | Cash inflow | Cash outflow | Net cash flow | Cumulative balance |
|---|
| 1 | 0 | 120 | −120 | −120 | | 2 | 100 | 180 | −80 | −200 | | 3 | 250 | 160 | 90 | −110 | | 4 | 300 | 140 | 160 | 50 |
Assuming zero opening balance, the maximum cumulative deficit is $200,000 at the end of month 2. The project therefore requires at least $200,000 of funding before considering a liquidity buffer, financing charges or uncertainty. A project can be within its total budget and still experience financial distress if this funding need is not planned. Cash-flow forecasts should be updated for procurement commitments, revised payment terms, actual invoices, retention releases, tax timing and approved changes. Finance and project controls teams should agree on the distinction between committed cost, accrued cost, invoiced cost and paid cash. 5. Life-Cycle Cost and Economic EvaluationProject decisions should not be based only on acquisition cost. Life-cycle cost includes costs incurred from concept through disposal. A generic undiscounted expression is: LCC = Cinitial + Cimplementation + ∑_(t=1)T (Coperation,t + Cmaintenance,t + Cdisposal,t) where Cinitial is initial acquisition or design cost, Cimplementation is deployment and commissioning cost, Coperation,t and Cmaintenance,t are operating and maintenance costs in period t, Cdisposal,t is disposal or decommissioning cost, and T is the analysis horizon. Because money has a time value, future costs may be discounted. The present value of a future cost is: PVt = Ct ÷ (1 + r)t where Ct is the cost in period t, r is the discount rate per period and t is measured in consistent periods. The net present cost is the sum of all discounted costs, adjusted for residual value where appropriate. The rate and treatment of inflation must be consistent: nominal cash flows should generally use a nominal discount rate, while real cash flows should use a real rate. Life-cycle costing supports decisions such as whether to purchase a cheaper machine with high energy consumption or a more expensive machine with lower maintenance requirements. It should include downtime, training, energy, cybersecurity, compliance, environmental liabilities and exit costs where material. Estimates remain sensitive to utilization, asset life, discount rate and technological obsolescence; sensitivity analysis is therefore essential. 6. Cost Control and Earned Value AnalysisCost control is a forward-looking management process. It involves collecting reliable data, explaining deviations, forecasting the likely outcome and deciding whether corrective or preventive action is required. Merely reporting that actual spending differs from budget does not explain whether the project has produced the planned value. Earned value management uses three core measures at a status date: - Planned Value (PV): authorized budget for work scheduled.
- Earned Value (EV): authorized budget for work actually performed.
- Actual Cost (AC): realized cost incurred for work performed.
The two primary variances are: CV = EV − AC SV = EV − PV Cost variance CV is expressed in currency. A positive value indicates that the value of completed work exceeds its actual cost. Schedule variance SV is also expressed in budget currency; it is a schedule-performance indicator, not a direct measure of elapsed days. The efficiency indices are: CPI = EV ÷ AC SPI = EV ÷ PV A CPI below 1 indicates that cost efficiency is worse than planned; an SPI below 1 indicates that less budgeted work has been completed than scheduled. These interpretations assume consistent measurement rules and reliable EV data. Forecasting final costThe simplest forecast at completion is: EAC = AC + (BAC − EV) This assumes the remaining work will be completed at the original budget rate. If current cost efficiency is expected to continue, a commonly used forecast is: EAC = BAC ÷ CPI If both cost and schedule performance are expected to influence remaining cost, one possible form is: EAC = AC + (BAC − EV) ÷ (CPI × SPI) The third equation is not universally appropriate. It should be used only when schedule delay is demonstrably producing cost consequences and the organization’s forecasting policy supports the assumption. The estimate to complete is: ETC = EAC − AC and variance at completion is: VAC = BAC − EAC The to-complete performance index can be stated as: TCPI = (BAC − EV) ÷ (BAC − AC) when the original budget is the performance target, or: TCPI = (BAC − EV) ÷ (EAC − AC) when the revised estimate at completion is the target. The first denominator represents remaining budget; the second represents remaining forecast cost. A very high TCPI may indicate that the target is unrealistic. Worked earned-value exampleSuppose a project has BAC = $1,000,000. At the status date, PV = $500,000, EV = $450,000 and AC = $480,000. Then: CV = 450,000 − 480,000 = −30,000. The project is $30,000 unfavourable on cost performance. SV = 450,000 − 500,000 = −50,000. Work worth $50,000 less than planned has been completed. CPI = 450,000 ÷ 480,000 = 0.9375. Each dollar spent has generated approximately $0.9375 of budgeted value. SPI = 450,000 ÷ 500,000 = 0.90. Progress is 90% of planned progress on the chosen measurement basis. If current cost efficiency continues, EAC = 1,000,000 ÷ 0.9375 = 1,066,667 approximately. The forecast overrun is therefore about $66,667. Management should not treat this calculation as a prediction independent of judgment. It should examine causes, remaining risk, procurement commitments, schedule recovery plans and whether the observed performance is transient or systemic. 7. Integrated Case: Regional Distribution-Centre AutomationThe following is an illustrative case, created for educational purposes. BackgroundA logistics company approved a project to automate a regional distribution centre. The scope included conveyors, scanning equipment, warehouse-control software, installation, staff training and a three-month stabilization period. The approved budget at completion was $8.00 million, excluding corporate expansion beyond the facility. ProblemDuring implementation, equipment prices increased, software integration took longer than expected and the supplier requested milestone payments earlier than planned. Senior management initially focused on the fact that total invoices were below the approved budget. The project controls manager argued that both forecast cost and cash timing indicated a significant threat. AnalysisThe team conducted a bottom-up re-estimate and reconciled it with a parametric benchmark based on throughput capacity. The bottom-up estimate identified omitted cybersecurity testing and additional commissioning labour. A three-point analysis was applied to integration and commissioning activities. Identified risks were quantified and a contingency reserve was established, while management reserve remained subject to executive approval. At the review date, the project data were PV = $3.60 million, EV = $3.20 million and AC = $3.50 million. Thus, CPI = 3.20 ÷ 3.50 ≈ 0.914 and SPI = 3.20 ÷ 3.60 ≈ 0.889. If the cost efficiency continued, the forecast at completion would be EAC = 8.00 ÷ 0.914 ≈ $8.75 million. Cash-flow analysis showed a $1.1 million deficit before customer milestone receipts, while the original treasury plan provided only $0.7 million of short-term funding. The immediate issue was therefore liquidity as well as budget overrun. Approach and solutionManagement approved five actions: - Freeze nonessential scope and route all additions through formal change control.
- Negotiate supplier milestones to align payments with tested deliverables.
- Establish a dedicated integration work package with measurable acceptance criteria.
- Use reserve only for documented uncertainty, not to erase unfavorable variance.
- Update the forecast monthly using actual commitments, earned value and risk exposure.
The project team also introduced an assumptions register. Each major estimate recorded its productivity rate, price basis, exchange-rate assumption, tax treatment and confidence range. OutcomeThe project completed at a revised authorized budget of $8.55 million after approved scope clarification and risk response. Although the final cost exceeded the original baseline, the organization avoided an uncontrolled overrun, secured temporary working capital and achieved operational handover within the revised schedule. Post-project review found that the original estimate had omitted integration complexity and had treated vendor quotations as fixed despite material escalation clauses. Learning pointsThe case demonstrates that cost control is not equivalent to restricting expenditure. It requires understanding what value has been produced, what remains, when cash is needed and which assumptions are failing. A low invoice total can coexist with poor performance if work is incomplete or commitments are not yet invoiced. Transparent reserves and disciplined change control protect both decision quality and organizational trust. 8. Governance, Ethics and Contemporary PracticeCost estimates influence investment approval, contracts, staffing and public accountability. Deliberately understating an estimate to secure authorization—sometimes called strategic misrepresentation—creates ethical and governance risk. Professional practice requires disclosure of assumptions, uncertainty, exclusions and known optimism bias. Estimates should be independently challenged for high-value or high-risk projects. Important controls include segregation of duties, documented approval thresholds, audit trails, version control, procurement compliance, change logs and reconciliation between project systems and the general ledger. Managers should not shift costs between periods or work packages merely to improve reported performance. Performance measures must avoid rewarding the concealment of bad news. Digital project-control platforms can integrate schedules, purchase orders, timesheets, invoices, risk registers and forecasts. Artificial intelligence can assist with anomaly detection, cost classification, supplier-price analysis and probabilistic forecasting. However, AI outputs depend on data quality and historical patterns. A model may reproduce past estimating bias, misinterpret a scope change or create false confidence through precise-looking predictions. Human review, explainability, access controls, privacy protection and model validation remain necessary. Contemporary practice increasingly emphasizes carbon and environmental cost, total-cost-of-ownership analysis, resilience, supply-chain volatility and scenario planning. These factors should be incorporated when material to the decision, but they must be defined consistently. For example, a carbon price used in an option analysis should be stated explicitly rather than hidden in an unexplained contingency. 9. Best-Practice FrameworkA robust cost-management system follows these principles: - Define the scope boundary: state what is included, excluded and assumed.
- Use an appropriate estimating method: match method to data maturity and project complexity.
- Triangulate: compare bottom-up, analogous and parametric results where possible.
- Separate base estimate, contingency and management reserve: preserve transparency.
- Time-phase the budget: connect expenditure plans to the schedule and funding needs.
- Use consistent measurement rules: especially for earned value and percent complete.
- Forecast early: investigate trends before a variance becomes irreversible.
- Integrate risk and cost: model important uncertainty and correlation.
- Control changes formally: do not use reserves to bypass authorization.
- Record assumptions and revise them: an estimate is a managed hypothesis, not a fact.
- Reconcile project and accounting data: distinguish commitments, accruals, invoices and cash.
- Learn systematically: compare estimates with actual outcomes and update organizational data.
Chapter SummaryCost management integrates estimating, budgeting, funding and control. Analogous estimates are rapid but depend on genuine comparability; parametric estimates use validated cost drivers; bottom-up estimates provide detailed accountability; and three-point estimates represent uncertainty through optimistic, most likely and pessimistic values. These methods should be selected according to scope maturity, data quality and decision purpose. The cost baseline is an approved, time-phased budget. Contingency addresses identified uncertainty within scope, while management reserve is governed separately for unforeseen in-scope work. Cash-flow analysis is essential because the timing of receipts and payments may create liquidity problems even when total budget remains adequate. Life-cycle costing expands analysis beyond acquisition to operation, maintenance, disposal and the time value of money. Earned value compares planned value, earned value and actual cost. CV, SV, CPI and SPI help diagnose performance, while EAC, ETC, VAC and TCPI support forecasting. These indicators require reliable data and informed interpretation. Ethical governance requires transparent assumptions, independent challenge, disciplined change control and honest reporting. Digital tools and AI can improve visibility and prediction, but they do not replace professional judgment. Key TermsCost estimate: A prediction of resources and money required to perform defined project work. Analogous estimation: Estimation based on the cost of a comparable historical project. Parametric estimation: Estimation using a validated quantitative relationship between cost and project drivers. Bottom-up estimation: Estimation developed by aggregating detailed activity or work-package estimates. Three-point estimation: Estimation using optimistic, most likely and pessimistic values. Contingency reserve: Budget allocated for identified uncertainty within approved scope. Management reserve: Governed budget held for unforeseen in-scope work. Cost baseline: Approved, time-phased budget used for performance measurement. Budget at completion: Total approved performance-measurement budget. Planned value: Authorized budget for work scheduled by a specified date. Earned value: Authorized budget for work actually performed. Actual cost: Cost incurred for completed work. Cost variance: Earned value minus actual cost. Cost performance index: Earned value divided by actual cost. Estimate at completion: Forecast of total project cost at completion. Cash flow: Timing of cash receipts and payments. Life-cycle cost: Total cost from acquisition or concept through operation and disposal. Committed cost: Cost associated with authorized obligations, even if not yet invoiced. Change control: Formal process for evaluating and approving modifications to scope, cost or schedule. Optimism bias: Systematic tendency to underestimate cost, duration or risk. Review QuestionsShort Answer Questions- Distinguish between a cost estimate, a budget and a cost baseline.
- State one advantage and one limitation of analogous estimation.
- What do contingency reserve and management reserve represent?
- Define planned value, earned value and actual cost.
- Why can a project with an adequate total budget still face a cash crisis?
Long Answer Questions- Compare analogous, parametric, bottom-up and three-point estimation. Explain when each method is most appropriate.
- Explain how an approved cost estimate is transformed into a time-phased cost baseline.
- Discuss the importance of life-cycle costing in equipment or infrastructure investment decisions.
- Explain earned value analysis and the interpretation of CV, SV, CPI, SPI and EAC.
- Evaluate the ethical and governance risks associated with optimistic project estimates.
Analytical / Application Questions- A project has a = $120,000, m = $150,000 and b = $240,000. Calculate the beta-PERT expected estimate and approximate standard deviation. Explain what the spread implies for management.
- At a status date, BAC = $2,000,000, PV = $900,000, EV = $800,000 and AC = $850,000. Calculate CV, SV, CPI, SPI and EAC using EAC = BAC ÷ CPI. Interpret the results.
- Design a cost-control and funding approach for a project in which supplier payments occur before customer milestone receipts. Identify the data, controls, reserves and forecasts required.
Multiple Choice Questions with AnswersQuestion 1Which estimation method uses the cost of a comparable completed project as its primary reference? A. Analogous estimation B. Bottom-up estimation C. Three-point estimation D. Variance analysis Correct Answer: A. Analogous estimation Question 2A project has an optimistic estimate of $80,000, a most likely estimate of $100,000 and a pessimistic estimate of $160,000. Using beta-PERT, what is the expected estimate? A. $100,000 B. $106,667 C. $113,333 D. $160,000 Correct Answer: B. $106,667 Question 3Which item is normally included in a cost baseline? A. Unapproved scope requested by a stakeholder B. Time-phased approved budget C. All possible future projects D. Only invoices already paid Correct Answer: B. Time-phased approved budget Question 4If earned value is $450,000 and actual cost is $480,000, what is the cost variance? A. $30,000 favourable B. $30,000 unfavourable C. $930,000 favourable D. $480,000 unfavourable Correct Answer: B. $30,000 unfavourable Question 5A cost performance index of 0.80 indicates that the project is producing approximately: A. $0.80 of earned value per dollar spent B. $1.20 of earned value per dollar spent C. 80% more value than planned D. No measurable cost information Correct Answer: A. $0.80 of earned value per dollar spent Question 6Which formula represents the simple forecast at completion when current cost efficiency is expected to continue? A. EAC = BAC × CPI B. EAC = BAC ÷ CPI C. EAC = EV ÷ AC D. EAC = PV − EV Correct Answer: B. EAC = BAC ÷ CPI Question 7What is the principal purpose of a contingency reserve? A. To hide unfavorable cost variance B. To fund identified uncertainty within approved scope C. To authorize unrelated scope expansion D. To replace the project baseline every month Correct Answer: B. To fund identified uncertainty within approved scope Question 8Why is life-cycle costing more informative than acquisition-cost comparison alone? A. It excludes maintenance costs B. It considers costs over the asset’s relevant life C. It guarantees the cheapest option will be selected D. It eliminates the need for assumptions Correct Answer: B. It considers costs over the asset’s relevant life Question 9If cash inflow is $100,000 and cash outflow is $180,000 in a period, the net cash flow is: A. $280,000 B. $80,000 C. −$80,000 D. −$280,000 Correct Answer: C. −$80,000 Question 10Which practice best supports ethical project cost control? A. Suppressing unfavorable forecasts until completion B. Moving costs between work packages to improve indicators C. Documenting assumptions, uncertainty and approved changes D. Using management reserve without authorization Correct Answer: C. Documenting assumptions, uncertainty and approved changes
|