Agile and Hybrid Delivery Platforms

Post Graduate Program in Project Management
Project Management Tools Bootcamp   •   Post Graduate

Agile and Hybrid Delivery Platforms

Introduction and Context

Project delivery platforms are the operational environments in which teams plan, prioritize, execute, monitor, and govern work. In contemporary project management, these platforms commonly support Scrum, Kanban, or a hybrid of predictive and adaptive practices. They are not merely digital task lists. Properly configured, they create a shared system of work that links strategy, requirements, delivery activity, evidence of completion, risk management, and stakeholder decision-making.

Agile platforms are particularly valuable where requirements evolve, users need early feedback, and delivery can be organized into increments. Hybrid platforms are appropriate where adaptive delivery must coexist with fixed contractual milestones, regulatory approvals, budget controls, architectural governance, or portfolio reporting.

The central managerial challenge is not selecting a fashionable tool. It is designing a workflow whose boards, backlogs, metrics, permissions, and governance rules accurately represent how value is created and controlled. A poorly designed board can encourage multitasking, conceal blocked work, distort progress, and generate misleading reports. A well-designed platform makes work visible, establishes decision rights, supports empiricism, and provides reliable evidence for intervention.

Learning Objectives

By the end of this chapter, learners should be able to:

  1. Explain the purposes and relationships among Scrum boards, Kanban boards, backlogs, releases, and roadmaps.
  2. Configure workflow states, policies, issue types, ownership, and permissions for an agile delivery platform.
  3. Apply relative estimation using story points and interpret velocity responsibly.
  4. Design and use work-in-progress limits and flow metrics.
  5. Integrate agile delivery with predictive governance in a hybrid workflow.
  6. Evaluate platform data critically, including its ethical, managerial, and reporting limitations.
  7. Recommend an appropriate platform configuration for a complex project context.

1. Agile Delivery as a System of Empirical Control

Scrum and Kanban are different but compatible approaches to managing complex work. Scrum establishes a timeboxed cadence, defined accountabilities, a product backlog, a sprint goal, a potentially usable increment, and recurring inspection and adaptation events. Kanban emphasizes visualization, explicit policies, flow, pull, limiting work in progress, and continuous improvement. Neither approach is simply a set of software features.

A platform should support three empirical controls:

  • Transparency: stakeholders can see the state, ownership, priority, dependencies, and evidence associated with work.
  • Inspection: the team regularly examines progress, quality, flow, risks, and outcomes.
  • Adaptation: plans, priorities, workflow policies, or resourcing change in response to evidence.

A digital board is therefore a model of a delivery system. Models are useful because they simplify reality, but they can also misrepresent it. For example, a single “In Progress” column may hide analysis, development, testing, security review, and deployment. Conversely, excessive columns may create administrative burden without improving decisions.

2. Core Platform Objects

Most delivery platforms use a hierarchy similar to the following:

ObjectPurposeTypical example
Initiative or outcomeConnects delivery to strategic intentReduce customer onboarding time
EpicRepresents a substantial body of value or capabilityDigital identity verification
FeatureGroups related capabilitiesAutomated document validation
User story or work itemDescribes a user or operational needAs a customer, I can verify my identity online
TaskRepresents implementation activityConfigure validation service
Bug or defectRecords a deviation from expected behaviorValidation rejects valid passports
SpikeTime-limited investigation or learning activityCompare two identity providers
Release or versionGroups work intended for a deployable outcomeRelease 2.1
Sprint or iterationTimebox for planning and inspectionSprint 14

Hierarchies should be used carefully. A work item should have one clear purpose, one accountable owner at the relevant level, and traceability to its parent outcome where such traceability adds value. Excessive decomposition creates fragmented reporting and encourages teams to optimize task completion rather than customer outcomes.

Backlogs

A backlog is an ordered inventory of potential work. It is not a requirements warehouse or a promise that every item will be delivered. The product backlog expresses what may be needed; the sprint backlog expresses the selected work and the team’s plan for achieving the sprint goal.

A healthy backlog has:

  • an explicit ordering policy;
  • concise descriptions of value and scope;
  • acceptance criteria;
  • appropriate estimates or sizing;
  • dependencies and risks where material;
  • a clear indication of uncertainty;
  • regular refinement; and
  • obsolete or superseded items removed or archived.

Backlog ordering should reflect value, risk reduction, learning, urgency, regulatory need, dependency, and effort—not merely the loudest stakeholder request. A useful prioritization discussion distinguishes importance from readiness. A highly important item may remain below the “ready” threshold until its assumptions, acceptance criteria, or dependencies are sufficiently understood.

Definition of Ready and Definition of Done

A Definition of Ready is an optional team policy describing conditions that normally make an item suitable for selection. It may include a clear objective, acceptance criteria, known dependencies, and an appropriately small scope. It should not become a bureaucratic gate that prevents discovery.

A Definition of Done is a quality and completion policy. It may require implemented code, peer review, automated tests, security checks, updated documentation, and deployment to a specified environment. “Developer says finished” is not a reliable completion policy. The Definition of Done should apply consistently to comparable increments and should be visible in the platform.

3. Configuring Scrum Boards

A Scrum board generally represents the work selected for a sprint. A practical configuration might include:

Selected for Development → In Development → In Review → In Test → Ready for Release → Done

The exact states depend on the team’s actual workflow. A column should exist when it supports a meaningful decision, exposes a constraint, or expresses a policy. States such as “Blocked” are often better represented by a visible flag or reason code in addition to the item’s actual workflow state. Moving a blocked item into a separate column can make the board look less accurate if the item remains, for example, in testing.

Important configuration decisions include:

  • whether sub-tasks count toward board progress;
  • whether work can move backward;
  • how rejected or reopened work is recorded;
  • whether testing is performed by the delivery team or a separate group;
  • how work crossing the sprint boundary is treated;
  • which statuses qualify as complete;
  • how defects discovered after release are classified; and
  • who may change priority or alter sprint scope.

A sprint should have a coherent goal. A board filled with unrelated items may show activity while providing little evidence of progress toward a meaningful outcome. Scope changes during a sprint should be transparent. If a new item is added, the team should explain whether capacity is reduced elsewhere, whether the sprint goal remains viable, and who authorized the change.

4. Configuring Kanban Boards

A Kanban system visualizes demand as it flows through a process. Unlike Scrum, Kanban does not require fixed-length iterations or a particular set of roles. Its essential mechanisms are visualization, explicit policies, pull, work-in-progress limits, and feedback loops.

A Kanban board should distinguish at least:

  1. work that is waiting to be selected;
  2. work currently being performed;
  3. work awaiting review, approval, or validation; and
  4. completed work.

A useful configuration might be:

Ready → Analysis → Build → Review → Validate → Deploy → Done

Each state should have an entry policy and an exit policy. For example, an item may enter “Validate” only when a test environment is available, test data is prepared, and the acceptance criteria are testable. It may leave “Validate” only when the relevant evidence is recorded.

Kanban uses a pull principle: downstream capacity creates the condition for upstream work to move. If the review column is full, developers should help clear review work or address the constraint rather than continuously starting new development items.

Work-in-Progress Limits

A work-in-progress limit caps the number of items permitted in a state or group of states. The purpose is not to make the team appear less busy. It is to reduce multitasking, expose bottlenecks, shorten feedback loops, and improve flow.

Limits should be based on observed demand, capacity, and bottlenecks. A limit of one may be appropriate for a specialist approval step; a larger limit may be necessary for a broad development stage. Limits should be treated as policies to inspect, not permanent truths. If a limit is repeatedly exceeded, the team should investigate the reason rather than silently increasing it.

Common anti-patterns include setting one limit per person, using limits to punish teams, and counting every tiny sub-task as independent work. The unit of flow should normally be a customer- or operationally meaningful work item.

5. Story Points, Estimation, and Velocity

Story points are a relative measure of the size of a backlog item. They commonly combine considerations such as effort, complexity, uncertainty, and the amount of work involved. They are not hours, days, financial values, or a direct measure of individual productivity.

Teams often use a sequence such as 1, 2, 3, 5, 8, 13, and 21. The increasing gaps reflect growing uncertainty. A team may estimate by comparing a new item with reference items already understood. Planning poker or another structured discussion can reduce anchoring and reveal different assumptions.

Story points are meaningful only within the team and its stable estimation system. Comparing points between teams is generally invalid because teams use different reference stories, scales, definitions of size, and quality policies.

Velocity is the amount of estimated work completed in a timebox, usually expressed in story points. If a team completes 18, 22, 20, and 24 points over four comparable sprints, its average historical velocity is:

V̄ = (18 + 22 + 20 + 24) ÷ 4 = 21 points per sprint

Here, V̄ is the arithmetic mean velocity. The calculation assumes comparable sprint lengths, a stable team, consistent estimation, and a consistent Definition of Done. Completed means meeting the completion policy; partially complete items should not normally be counted as complete.

For forecasting, a range is generally more honest than a single-point estimate. In the example, the observed range is 18–24 points per sprint. If a remaining backlog contains 84 points, a simple forecast using the mean is:

Number of sprints ≈ Remaining points ÷ Average velocity = 84 ÷ 21 = 4 sprints

This is not a guarantee. A range-based interpretation using the observed velocities would suggest approximately 84 ÷ 24 = 3.5 sprints at the high end of throughput and 84 ÷ 18 ≈ 4.7 sprints at the low end, before accounting for uncertainty, scope change, holidays, defects, or dependencies. Monte Carlo forecasting can improve probabilistic forecasting when sufficient historical throughput data exists, but it does not remove the need for sound backlog definition and stable measurement.

Velocity should support planning and conversation, not performance ranking. If management rewards higher velocity, teams may inflate estimates, split work artificially, or lower quality standards. Such gaming destroys the metric’s usefulness.

6. Flow Metrics and Little’s Law

Kanban platforms commonly report cycle time, lead time, throughput, work in progress, blocked time, aging work items, and cumulative flow. These measures answer different questions:

MetricQuestion answered
Lead timeHow long from request to delivery?
Cycle timeHow long from start of active work to completion?
ThroughputHow many items are completed per unit of time?
WIPHow many items are currently active?
AgingHow long has an unfinished item been in progress?
Blocked timeHow much time is work unable to progress?

A foundational relationship is Little’s Law:

L = λW

L is average work in progress, λ is average throughput, and W is average flow time. Units must be consistent. For example, if average throughput is 10 items per week and average flow time is 1.5 weeks, average WIP is 15 items.

L = 10 items/week × 1.5 weeks = 15 items

The relationship assumes a sufficiently stable system over the period analyzed, with average inflow and outflow broadly balanced and a meaningful definition of the system boundary. It is not a promise that every individual item will take exactly W time. If leadership demands shorter cycle time while preserving throughput, reducing WIP or increasing effective capacity may be necessary. Simply urging people to work faster often creates defects and rework.

A cumulative flow diagram shows the amount of work in each state over time. Widening bands indicate accumulation; a widening “Review” band may reveal a review bottleneck. The diagram should be interpreted with changes in policy, item size, and scope in mind.

7. Releases, Roadmaps, and Dependencies

A release is a planned deployment or externally meaningful package of capability. It may contain several sprints or a continuous flow of work. A release should have an objective, quality criteria, target date or window, and a clear statement of what is included and excluded.

A roadmap communicates intended direction over time. It is not necessarily a fixed promise of detailed features. At postgraduate level, it is important to distinguish:

  • Output roadmap: what capabilities may be delivered;
  • Outcome roadmap: what measurable change is expected;
  • Technology roadmap: what platforms, architecture, or technical enablers are required; and
  • Governance roadmap: what approvals, audits, or regulatory milestones must occur.

Roadmaps should use appropriate uncertainty language, such as “now,” “next,” and “later,” or confidence ranges rather than false precision. A feature-level roadmap twelve months into a volatile project can create commitment bias and encourage teams to defend obsolete assumptions.

Dependencies should be represented explicitly. A dependency record should identify the supplying and receiving work, the needed date, responsible owners, and escalation path. Merely adding a label called “dependency” does not manage a dependency. Cross-team dependencies may require a dependency board, integration events, architectural decision records, or a release train plan.

8. Hybrid Delivery and Governance Workflows

Hybrid delivery combines adaptive development with predictive planning or control. It is appropriate when different parts of a project have different uncertainty profiles. For example, software discovery and development may use Scrum, while procurement, construction, regulatory approval, and financial authorization follow stage-gate controls.

A robust hybrid design separates three related questions:

  1. How is work performed? Scrum, Kanban, engineering practices, or another delivery method.
  2. How is value and scope prioritized? Product strategy, business cases, portfolio decisions, and release planning.
  3. How is risk and accountability governed? Funding approvals, quality assurance, legal review, audit, safety, security, and executive decision rights.

These questions should be integrated but not confused. A governance gate should not require every team to abandon iterative delivery. Instead, the platform can connect adaptive work to evidence-based gate criteria.

A typical hybrid workflow is:

Business case approved → Discovery backlog → Iterative delivery → Integration evidence → Assurance review → Release decision → Operational transition → Benefits review

At each gate, the project should specify entry evidence, decision authority, possible decisions, and consequences. A gate may result in approval, conditional approval, rework, deferral, or termination. Governance is stronger when it evaluates outcomes, risk exposure, quality, and evidence rather than the superficial appearance of complete task lists.

Example Hybrid Configuration

A regulated financial-services project may use:

  • an initiative record linked to strategic objectives;
  • epics for customer, compliance, and platform capabilities;
  • Scrum sprints for product development;
  • a Kanban lane for urgent production defects;
  • mandatory security and privacy review states;
  • a release record containing test evidence and approval records;
  • a change-control workflow for material scope or budget changes; and
  • a benefits dashboard measuring adoption, processing time, and error reduction.

The platform should preserve team autonomy over day-to-day execution while establishing non-negotiable controls for security, data protection, financial authority, and regulatory compliance.

9. Worked Application: Northstar Claims Modernization

Background

The following is an illustrative case. Northstar Mutual, a fictional insurer, is modernizing its claims process. The organization has a fixed regulatory reporting date in nine months, but the user experience and integration requirements are uncertain. The project includes internal software development, an external identity-verification provider, information-security review, and operational training.

Problem

The initial project board contains 146 tasks, a single “In Progress” column, no WIP limits, and a roadmap listing detailed features for all nine months. Executives report that 70 percent of tasks are complete, yet the first usable claims journey has not been demonstrated. Testing is performed near the end, and external-provider dependencies are frequently discovered late.

Analysis

The board measures activity rather than flow or outcomes. The absence of explicit workflow states conceals the testing bottleneck. The task count mixes different levels of work, making the 70 percent figure misleading. The detailed roadmap gives a false impression of certainty. The regulatory date is a genuine constraint, but not every feature must be delivered before that date.

Approach

The project team redesigns the platform as follows:

  1. Create an initiative linked to the regulatory and customer outcomes.
  2. Decompose the work into epics, features, user stories, defects, and spikes.
  3. Establish a product backlog ordered by regulatory necessity, customer value, risk reduction, and learning value.
  4. Use two-week Scrum sprints for product development.
  5. Create explicit states: Ready, Build, Review, Test, Security Review, Ready for Release, and Done.
  6. Apply WIP limits of 4 in Build, 3 in Review, and 3 in Test, initially based on observed team capacity.
  7. Add a separate Kanban service lane for urgent production defects, with an explicit expedite policy.
  8. Define the Definition of Done to include automated testing, peer review, security evidence, documentation, and deployment readiness.
  9. Use releases for regulatory and operational increments rather than for every sprint.
  10. Maintain a roadmap at outcome and capability level, marking later items as low-confidence.
  11. Link external-provider dependencies to owners and required dates.
  12. Establish a governance review at the end of every second sprint, using evidence from demonstrations, quality reports, risk status, and forecast ranges.

Outcome

After three sprints, the team identifies that the Test column is regularly at its WIP limit. Instead of starting more development, developers assist with test automation and clarify acceptance criteria. The average cycle time falls from 18 to 12 working days over the next six weeks, while the number of reopened defects declines. The team also discovers that the external provider cannot support one proposed feature by the regulatory date. Because the roadmap distinguishes mandatory capability from optional enhancement, the steering group removes the feature from the first release without jeopardizing the regulatory outcome.

The project does not become risk-free. Its improved platform makes uncertainty visible earlier and gives governance a better basis for decisions. The organization learns that “more tasks completed” was not equivalent to “more value delivered.”

Learning Points

  • Configure the board around decisions and flow, not organizational convenience.
  • Use WIP limits to expose constraints rather than to restrict people arbitrarily.
  • Link releases to usable outcomes and evidence.
  • Preserve uncertainty in the roadmap instead of disguising it as precision.
  • Hybrid governance works when controls are connected to evidence and decision rights.

10. Platform Governance, Ethics, and Data Quality

Platform data increasingly influences funding, performance reviews, supplier assessments, and executive decisions. This creates governance and ethical responsibilities.

First, teams should know how metrics are defined. A dashboard that labels an item “done” when it has merely reached development completion creates a material reporting risk. Second, metric data should be traceable and auditable, particularly in regulated settings. Third, managers should avoid surveillance practices that infer individual productivity from card movements, keyboard activity, or story points. Such measures are weak proxies for value and can damage psychological safety.

Access permissions should follow least privilege. Sensitive requirements, security vulnerabilities, personal data, commercial information, and audit evidence may need restricted visibility. Retention and deletion policies should comply with applicable organizational and legal requirements. Integrations should be reviewed for data residency, vendor access, authentication, and incident response.

AI features can assist with summarizing work, identifying duplicate items, suggesting risks, generating draft acceptance criteria, or forecasting from historical data. However, AI-generated content requires human validation. It may reproduce bias, omit context, expose confidential information, or create an unjustified appearance of certainty. AI should support professional judgment, not replace product accountability, security review, or governance decisions.

11. Common Failure Modes and Limitations

Tool-first implementation

Selecting a platform before understanding the operating model often produces unnecessary workflows and inconsistent terminology. Begin with value streams, decision rights, and information needs.

Excessive customization

Highly customized workflows may become difficult to maintain, integrate, or explain. Configuration should be sufficient to represent important control points but simple enough for routine use.

False precision

Exact dates, detailed long-range features, and single-number forecasts can conceal uncertainty. Use confidence ranges, assumptions, and scenario planning.

Metric gaming

Velocity targets, completion percentages, and utilization goals can produce inflated estimates, premature closure, and avoidance of difficult work. Metrics should stimulate inquiry rather than determine individual rewards.

Local optimization

A team may maximize its own throughput while creating queues for testing, operations, or customers. Flow metrics should cover the whole relevant system.

Dependency blindness

Labels and comments are not substitutes for active dependency management. Dependencies require owners, dates, communication, and escalation.

Administrative overload

If updating the platform takes more time than it saves, teams will create workarounds. Automate routine updates where reliable, remove fields that do not support a decision, and review configuration periodically.

12. Best-Practice Configuration Checklist

Before launching a board or workflow, confirm that:

  • the purpose and system boundary are explicit;
  • work-item types are defined and limited;
  • each workflow state has entry and exit policies;
  • the Definition of Done is visible;
  • backlog ordering authority is clear;
  • dependencies, risks, and blockers are represented consistently;
  • WIP limits are observable and reviewed;
  • release and roadmap information distinguishes commitment from intention;
  • metrics have definitions, owners, and known limitations;
  • permissions protect sensitive information;
  • integrations and automations have been tested;
  • governance gates specify evidence and decision rights; and
  • the configuration is periodically inspected with the delivery team.

Chapter Summary

Agile and hybrid delivery platforms are socio-technical systems that make work, decisions, dependencies, risks, and evidence visible. Scrum boards support timeboxed planning and inspection; Kanban boards support continuous flow, pull, and WIP control. Backlogs should be ordered inventories of valuable possibilities rather than unexamined task repositories. Releases connect delivery to usable outcomes, while roadmaps communicate direction with an honest treatment of uncertainty.

Story points are relative team-specific sizing units, and velocity is useful for local forecasting only when estimation, team composition, sprint length, and completion standards are reasonably stable. Flow metrics such as lead time, cycle time, throughput, WIP, aging, and blocked time provide complementary evidence. Little’s Law, L = λW, connects average WIP, throughput, and flow time under stable-system assumptions.

Hybrid delivery is most effective when adaptive execution is connected to predictive controls through explicit evidence, decision rights, and governance criteria. Boards should not be designed to maximize activity or surveillance. They should support value delivery, quality, learning, ethical management, security, compliance, and informed adaptation. Platform configuration is therefore an organizational design activity, not merely an administrative or software task.

Key Terms

Agile delivery: An approach emphasizing incremental value, feedback, adaptation, and collaboration.

Backlog: An ordered inventory of potential work.

Board: A visual representation of work and its workflow states.

Cycle time: Time from active work start to completion.

Definition of Done: Shared criteria that determine whether work is complete.

Definition of Ready: Optional criteria indicating that work is sufficiently prepared for selection.

Dependency: A relationship in which one work item, team, or supplier relies on another.

Epic: A substantial body of related value or capability.

Flow time: Time an item spends within the defined delivery system.

Kanban: A method based on visualization, pull, explicit policies, flow, and WIP limits.

Lead time: Time from request or commitment to delivery.

Little’s Law: The relationship L = λW between average WIP, throughput, and flow time.

Product backlog: Ordered work that may contribute to a product or outcome.

Release: A planned deployment or meaningful package of capability.

Roadmap: A communication of intended direction, outcomes, capabilities, or milestones over time.

Scrum: An empirical framework using accountabilities, events, artifacts, and increments.

Story point: A relative measure of size incorporating effort, complexity, and uncertainty.

Velocity: Estimated work completed in a timebox.

Work in progress: Work started but not yet completed.

WIP limit: A policy restricting the quantity of active work.

Review Questions

Short Answer Questions

  1. What is the difference between a product backlog and a sprint backlog?
  2. Why should story points not normally be compared across teams?
  3. State the three empirical controls supported by Scrum and Kanban.
  4. What is the purpose of a WIP limit?
  5. Distinguish a release from a roadmap.

Long Answer Questions

  1. Explain how to configure a Scrum board for a team delivering software in a regulated environment.
  2. Compare Scrum and Kanban in terms of cadence, planning, workflow control, and metrics.
  3. Explain how velocity can support forecasting while remaining unsuitable as an individual performance measure.
  4. Discuss the role of Little’s Law in diagnosing flow problems and state its assumptions.
  5. Design a hybrid governance workflow for a project combining iterative software development with fixed regulatory milestones.

Analytical / Application Questions

  1. A team completed 16, 20, 18, and 22 story points in four comparable sprints. Calculate its average velocity and explain how you would use the result to forecast a 75-point backlog.
  2. A Kanban system averages 12 completed items per week and has average flow time of 1.25 weeks. Calculate average WIP using Little’s Law, then explain what could happen if management reduces WIP without addressing a review bottleneck.
  3. A project dashboard reports 85 percent task completion, but testing has not begun and several external dependencies are unresolved. Diagnose the measurement problem and recommend a redesigned board, metric set, and governance decision process.

Multiple Choice Questions with Answers

Question 1

Which statement best describes the purpose of a product backlog?

A. A fixed contractual list that must all be delivered

B. An ordered inventory of potential work and value

C. A record containing only completed tasks

D. A time log used to calculate individual productivity

Correct Answer: B. An ordered inventory of potential work and value

Question 2

Which practice is most directly associated with Kanban?

A. Mandatory two-week sprints

B. Fixed annual release planning

C. Limiting work in progress

D. Estimating every task in hours

Correct Answer: C. Limiting work in progress

Question 3

A team completes 18, 22, 20, and 24 story points in four comparable sprints. What is its average velocity?

A. 20 points per sprint

B. 21 points per sprint

C. 22 points per sprint

D. 84 points per sprint

Correct Answer: B. 21 points per sprint

Question 4

In the relationship L = λW, what does λ represent?

A. Average work in progress

B. Average flow time

C. Average throughput

D. Maximum WIP limit

Correct Answer: C. Average throughput

Question 5

Which condition is most important when using historical velocity for forecasting?

A. All teams use identical story-point scales

B. The team and completion standards are reasonably stable

C. Every item is estimated in person-hours

D. Management sets a higher target each sprint

Correct Answer: B. The team and completion standards are reasonably stable

Question 6

What is the primary purpose of a Definition of Done?

A. To identify who may join the project

B. To determine whether an increment meets agreed completion and quality criteria

C. To rank stakeholders by authority

D. To replace backlog ordering

Correct Answer: B. To determine whether an increment meets agreed completion and quality criteria

Question 7

A widening band for testing on a cumulative flow diagram most likely indicates:

A. A testing or downstream bottleneck

B. That all work is complete earlier than expected

C. A reduction in work entering the system

D. That WIP limits are unnecessary

Correct Answer: A. A testing or downstream bottleneck

Question 8

Which is the strongest example of hybrid governance?

A. Replacing all agile work with a single annual plan

B. Allowing all changes without approval

C. Using iterative development while requiring evidence-based regulatory release approval

D. Measuring only the number of tasks closed

Correct Answer: C. Using iterative development while requiring evidence-based regulatory release approval

Question 9

Why is comparing story-point velocity between teams generally invalid?

A. Story points are always measured in currency

B. Teams use different reference items, scales, and definitions of size

C. Velocity cannot be calculated more than once

D. Velocity applies only to Kanban systems

Correct Answer: B. Teams use different reference items, scales, and definitions of size

Question 10

A system has average throughput of 10 items per week and average flow time of 1.5 weeks. What is its average WIP under Little’s Law?

A. 6.67 items

B. 10 items

C. 15 items

D. 20 items

Correct Answer: C. 15 items