Project Documentation & Control

Chapter 3
Documentation Governance and Standards

Certificate in Software Project Management
Project Documentation & Control   •   Certificate

Documentation Governance and Standards

Introduction

Software projects generate a large body of information: business requirements, project plans, schedules, risk registers, architecture descriptions, source-code documentation, test evidence, release notes, procurement records, and acceptance approvals. These artefacts support decision-making, coordination, accountability, compliance, and organizational learning. However, documentation creates value only when it is trustworthy, accessible, current, and managed throughout its life cycle.

Documentation governance is the system of policies, roles, controls, standards, and decision rights used to manage project documents. It answers practical questions such as:

  • Who owns a document?
  • Who may approve or change it?
  • Which version is authoritative?
  • What information must be recorded about the document?
  • Where must it be stored?
  • How long must it be retained?
  • When may it be archived or destroyed?

In software project management, governance must achieve a balance. Excessive control can slow delivery and encourage informal workarounds; insufficient control creates conflicting versions, undocumented decisions, weak audit evidence, and operational risk. Effective governance is therefore risk-based, proportionate, and integrated with the project life cycle.

Learning Objectives

By the end of this chapter, a learner should be able to:

  1. Explain the purpose and principles of documentation governance.
  2. Define document ownership, stewardship, authorship, and approval authority.
  3. Design practical policies for document creation, review, approval, change, retention, and disposal.
  4. Apply naming conventions, templates, and metadata standards.
  5. Distinguish between working, approved, superseded, archived, and obsolete documents.
  6. Relate project documentation controls to organizational policies and industry standards.
  7. Identify governance risks and recommend proportionate controls.

1. The Purpose and Scope of Documentation Governance

Documentation governance is not simply filing. It is a management framework that establishes how documented information is created, controlled, used, protected, and retired. It applies to both formal documents and controlled records. A document is generally information that may be revised, such as a draft requirements specification. A record is evidence of an event, decision, transaction, or completed activity, such as an approved acceptance certificate or signed change authorization. A document may become a record when it is formally approved or used as evidence.

A sound governance system supports six outcomes:

  1. Reliability: stakeholders can trust that information is accurate and approved.
  2. Traceability: users can determine who created, reviewed, approved, and changed information.
  3. Availability: authorized users can locate information when needed.
  4. Consistency: similar documents follow common structures and terminology.
  5. Protection: confidential, personal, commercially sensitive, and security-related information is appropriately controlled.
  6. Disposition: documents are retained for an appropriate period and securely disposed of when no longer required.

Documentation governance covers the whole life cycle:

Plan → Create → Review → Approve → Publish → Use → Revise → Supersede → Retain or Dispose

The life cycle is iterative. A document may return from use to revision, but it should not bypass required review and approval controls merely because a change is urgent.

Governance and Document Management

Document management concerns the practical handling of files and information, including storage, search, versioning, and access. Documentation governance is broader. It establishes the rules under which document management operates and assigns accountability for those rules. A project may use a document-management platform, but technology alone does not create governance. A repository cannot decide whether a business requirement has been approved or whether a privacy-sensitive document should be retained.

Documentation as a Control Mechanism

Project documents are controls because they define expectations and provide evidence. A baseline schedule controls agreed timing; a risk register controls risk visibility; a decision log controls the memory of important choices; test evidence supports quality claims; and an approved change record supports scope control. Poor documentation weakens these controls even when the underlying project work is competent.

2. Principles of Effective Documentation Governance

Accountability

Every controlled document should have a named owner. Accountability must not be assigned only to a department or vague group. A role such as “Project Manager” may own a document type, but the current individual responsible should be identifiable in the project records.

Authority

The person who writes a document is not necessarily the person who may approve it. Approval authority should reflect the document’s impact. For example, a team lead may approve an internal working procedure, whereas a sponsor or product owner may approve a scope baseline.

Fitness for Purpose

Documentation should be sufficient for its intended use, audience, risk, and life span. A small internal enhancement may need a concise change record; a safety-critical or regulated system may need formal requirements traceability, independent verification, and long-term evidence preservation.

Single Source of Truth

A project should identify the authoritative location for each document. Copies may be circulated for convenience, but users must know which repository or controlled record is definitive. Email attachments are generally poor authoritative sources because they multiply uncontrolled copies.

Traceability

A reader should be able to connect a document to its origin, related documents, decisions, changes, and approvals. Traceability may be established through document identifiers, version histories, requirement IDs, links, change records, and approval records.

Transparency with Appropriate Confidentiality

Documentation should be accessible to those who need it, while access must be limited where information contains personal data, security details, legal advice, or commercial secrets. Transparency does not mean unrestricted access.

Proportionality

Controls should be commensurate with risk. Applying a complex approval board to every minor formatting correction wastes resources. Conversely, treating a change to a security design as a routine edit is dangerous.

Accessibility and Usability

Documents should be readable, searchable, available in appropriate formats, and usable by authorized people with disabilities. Accessibility includes meaningful headings, alternative text for informative diagrams, sufficient contrast, logical reading order, and avoidance of information conveyed only by colour.

Integrity and Immutability of Records

Once a document serves as formal evidence, its content and approval history should be protected from unauthorized alteration. Corrections should create a new controlled version or an auditable amendment rather than silently overwriting the record.

3. Roles, Ownership, and Approval Authority

A governance model becomes practical when responsibilities are explicit. The following roles are commonly used in software projects.

RoleMain responsibility
Document ownerAccountable for content, usefulness, review cycle, and controlled status
AuthorDrafts or updates the document according to the approved structure
Technical reviewerEvaluates technical correctness and feasibility
Business reviewerChecks business alignment, requirements, and operational implications
ApproverGrants formal authority for use or baseline status
Document controller or repository administratorMaintains identifiers, metadata, access, version history, and filing rules
Records or compliance officerAdvises on retention, legal holds, privacy, and regulatory obligations
Reader or userUses the current approved information and reports errors

One person may hold several roles in a small project, but the arrangement should not undermine independence. For high-risk documents, the author should not be the sole approver. Separation of duties is particularly important for security controls, financial authorization, compliance evidence, and production release approval.

RACI as a Governance Tool

A responsibility assignment matrix can clarify whether a role is Responsible, Accountable, Consulted, or Informed. For example, for a requirements baseline, the business analyst may be Responsible for preparation, the product owner Accountable for business approval, the technical lead Consulted, and the project team Informed. RACI is useful for clarifying involvement, but it does not replace a clear approval rule. “Accountable” must be connected to a specific decision right and evidence of approval.

Approval Authority Matrix

An organization should define approval thresholds. A simple example is shown below.

Document or decisionDrafting roleRequired reviewApproval authority
Project charterProject managerSponsor, key stakeholdersProject sponsor
Requirements baselineBusiness analystProduct owner, technical lead, QA leadProduct owner or steering authority
Architecture decisionTechnical leadSecurity and operations representativesArchitecture authority or delegated technical authority
Project schedule baselineProject managerTeam leads and sponsorProject sponsor or project board
Test exit reportTest managerProduct owner, technical leadRelease authority
Change request affecting scope or budgetRequestor and project managerImpacted ownersChange authority defined in the governance plan

The matrix should state what happens when the named approver is unavailable. Delegation should be documented, time-limited where appropriate, and within the delegate’s authority.

4. Documentation Policies

A documentation policy is a formally approved statement of required practices. It should be short enough to be usable and specific enough to be enforceable. A project-level documentation plan may translate organizational policy into operational procedures.

A practical policy normally addresses:

  • Scope: which projects, document types, and records are covered.
  • Classification: public, internal, confidential, restricted, or another approved scheme.
  • Repository: the authoritative storage location.
  • Roles: ownership, authorship, review, approval, and administration.
  • Required templates and metadata.
  • Naming and numbering conventions.
  • Version and status controls.
  • Access permissions and sharing rules.
  • Review frequency and triggers.
  • Retention, legal holds, and disposition.
  • Exceptions and escalation.
  • Monitoring, audit, and corrective action.

Policies should distinguish mandatory requirements from guidance. Words such as “must” and “shall” should be reserved for obligations; “should” can indicate recommended practice; “may” identifies an option.

Policy Exceptions

Exceptions are sometimes necessary, particularly during incidents, urgent regulatory responses, or tool outages. An exception should record the reason, affected documents, approving authority, duration, compensating controls, and required follow-up. A permanent informal exception is usually a governance failure rather than a valid exception.

5. Naming Conventions and Document Identification

Naming conventions allow users to understand and retrieve files without opening them. A useful convention is predictable, concise, and stable. It should avoid characters that cause problems across operating systems and repositories, including uncontrolled use of slashes, quotation marks, or very long names.

An illustrative pattern is:

ProjectID_DocumentType_Subject_Version_Status_YYYY-MM-DD.ext

For example:

ALPHA_REQ_PaymentProcessing_v1.2_Approved_2025-04-18.docx

The organization may instead use a unique document ID and keep descriptive information in metadata. Both approaches can work. The essential requirement is consistency and unambiguous identification.

Good conventions typically include:

  • a stable project or product identifier;
  • a controlled document type code;
  • a concise subject or workstream;
  • a version or revision identifier;
  • a status indicator where the repository does not provide one;
  • a date in an unambiguous format such as YYYY-MM-DD;
  • a file extension appropriate to the purpose.

Avoid names such as final.docx, final-final.docx, or new version2.docx. “Final” describes an intention, not a reliable status. A controlled status field such as Approved or Superseded is more dependable.

Naming conventions should be documented with examples and applied consistently across folders, records, diagrams, and exports. If a repository automatically manages versions, duplicating version numbers in filenames may create confusion unless policy requires both.

6. Templates and Document Structures

Templates improve completeness and reduce the cognitive effort required to create recurring documents. They should guide authors without encouraging meaningless text. A template for a project decision record might contain:

  1. Decision identifier and title.
  2. Date and status.
  3. Decision owner and approver.
  4. Context or problem statement.
  5. Options considered.
  6. Decision and rationale.
  7. Consequences and assumptions.
  8. Related requirements, risks, or changes.
  9. Review date.

A requirements template might include purpose, scope, stakeholders, functional requirements, non-functional requirements, assumptions, constraints, acceptance criteria, traceability, and approval history.

Templates should be version-controlled themselves. When a template changes, the organization should decide whether existing documents need migration. A change to a mandatory field may justify a controlled update; a cosmetic change may not.

Templates must not replace professional judgment. A completed template can still contain ambiguous requirements, unsupported claims, or inadequate evidence. Reviewers must assess content, not merely whether all fields contain text.

7. Metadata and Classification

Metadata is structured information about a document. It improves search, sorting, access control, reporting, and retention. Common metadata fields include:

Metadata fieldPurpose
Document IDUniquely identifies the item
TitleProvides a human-readable description
Document typeSupports classification and workflow
OwnerIdentifies accountability
AuthorIdentifies originator or contributors
StatusShows whether the item is draft, approved, or superseded
VersionIdentifies the current revision
ClassificationIndicates sensitivity and handling requirements
Created and modified datesSupports history and review
Approval dateShows when authority was granted
Review dateIndicates when currency must be reconsidered
Retention categoryLinks the item to a retention rule
Related itemsSupports traceability

Metadata values should use controlled vocabularies wherever practical. If one user enters “Approved,” another enters “approved,” and a third enters “Accepted,” searching and reporting become unreliable. Drop-down lists, validation rules, and repository workflows can improve consistency.

Classification should be based on consequences of unauthorized disclosure, alteration, or loss. Classification levels must be defined in organizational policy; labels without handling rules are ineffective. A document labelled “Confidential” should have associated access, sharing, storage, and disposal requirements.

8. Version, Status, and Change Control

Version control prevents users from relying on obsolete information. A project should define how versions are assigned and what changes require review. One practical approach is to use major and minor revisions:

  • A major revision indicates a substantive change in purpose, scope, requirements, design, or approved direction.
  • A minor revision indicates a limited change that does not alter the approved intent, such as clarification or correction.

The exact numbering system may vary. The important point is that its meaning is documented.

Typical document statuses include:

  • Draft: being prepared and not authorized for formal reliance.
  • In review: submitted for defined review but not yet approved.
  • Approved: authorized for its stated purpose.
  • Baselined: approved and protected as a reference point against which change is controlled.
  • Superseded: replaced by a newer approved version.
  • Withdrawn: removed from intended use for a documented reason.
  • Archived: retained for historical, legal, contractual, or learning purposes.
  • Destroyed: disposed of in accordance with approved rules.

A minor typographical correction to an approved record should not be made invisibly. Depending on policy, it may require a new revision, correction note, or controlled amendment. The method should preserve the original history and make the correction auditable.

Baselines

A baseline is a formally reviewed and agreed version used as a reference for control. Common baselines include scope, requirements, schedule, cost, architecture, and release configuration. A baseline does not mean that change is impossible. It means that change must follow an authorized process, with impact assessment and recorded approval.

9. Retention, Archiving, and Disposition

Retention rules specify how long categories of documents or records must be kept. The retention period may be determined by law, contract, regulation, tax requirements, organizational policy, litigation risk, warranty obligations, or business value. There is no universally correct retention period for every software project.

A retention schedule should identify:

  • record category;
  • retention trigger, such as project closure or contract expiry;
  • retention duration;
  • responsible owner;
  • storage and protection requirements;
  • disposal method;
  • legal-hold treatment.

A legal hold or investigation notice suspends ordinary disposal for affected information. Staff must not destroy or alter relevant records after being notified of such a hold. Personal data should not be retained indefinitely merely because storage is inexpensive; retention must have a legitimate and documented basis.

Archiving is not the same as keeping uncontrolled copies. Archived information should remain identifiable, protected against unauthorized alteration, and retrievable by authorized users. Disposal should be documented, and sensitive media should be securely destroyed or rendered unrecoverable according to organizational requirements.

10. Standards and Organizational Alignment

Documentation governance should align with the organization’s broader management system and the obligations relevant to the project. Relevant reference points may include:

  • organizational records-management and information-security policies;
  • quality-management procedures;
  • privacy and data-protection requirements;
  • contractual deliverable requirements;
  • internal audit rules;
  • software life-cycle and project-management standards;
  • sector-specific regulatory requirements.

International standards can provide useful principles, but an organization should not claim compliance merely because it uses a template or repository. Compliance requires meeting the applicable requirements and retaining evidence. Standards should be interpreted in context: a small internal application and a safety-critical public service may require very different levels of documentation rigor.

A project initiation process should identify applicable obligations and produce a documentation compliance matrix. The matrix can map each obligation to an owner, required evidence, repository location, review frequency, and verification method. This makes compliance operational rather than aspirational.

11. Technology, Automation, and Artificial Intelligence

Modern repositories can automate document numbering, approval workflows, access permissions, version history, reminders, retention labels, and audit reporting. Automation reduces routine errors but can also propagate incorrect rules at scale. Workflow design therefore requires testing, ownership, and periodic review.

Artificial intelligence may assist with classification, duplicate detection, summarization, search, and extraction of metadata. Its use requires controls for confidentiality, accuracy, bias, explainability, and human accountability. AI-generated summaries should not replace the authoritative source, particularly for contractual, legal, safety, financial, or security decisions. Sensitive project information should not be entered into an AI service unless the organization has approved the service and established suitable data protections.

A practical rule is that AI may support documentation work, but responsibility for approval, accuracy, classification, and retention remains with authorized human roles. Generated content should be checked against source material, and the use of AI should be recorded where policy or risk warrants disclosure.

12. Worked Application: Establishing Governance for the Orion Project

The following is an illustrative case.

Background

Orion is a medium-sized software project developing an online service for business customers. The project includes an external supplier, an internal security team, and a product owner. During early development, team members store documents in personal folders, email attachments, and several collaboration channels.

Problem

The project has three versions of the requirements document. A security review used an outdated architecture diagram, and the supplier claims that a scope change was approved in an email. No one can determine which schedule is authoritative. The project also contains customer contact data that is being copied into uncontrolled spreadsheets.

Analysis

The immediate problem is not simply poor filing. The project lacks:

  • a repository designated as the single source of truth;
  • named owners and approval rights;
  • a status and version model;
  • classification and access rules;
  • a change and decision trail;
  • retention and disposal instructions;
  • a mechanism for communicating approved updates.

The risks include incorrect implementation, unauthorized disclosure, contractual dispute, rework, and weak audit evidence.

Approach and Solution

The project manager establishes a documentation governance plan with the following controls:

  1. The approved project repository becomes the authoritative location.
  2. Each document type receives an owner and approval authority.
  3. Requirements, architecture, schedule, risks, decisions, changes, and test evidence receive controlled templates.
  4. Metadata fields include document ID, owner, status, version, classification, approval date, and review date.
  5. Draft, In Review, Approved, Superseded, and Archived statuses are configured.
  6. Requirements and architecture are baselined after product, technical, security, and quality review.
  7. A change request is required for scope, budget, architecture, or contractual changes.
  8. Email approvals are accepted only when captured in the formal decision or change record.
  9. Customer data is removed from working examples and access is restricted according to classification.
  10. A weekly report identifies documents overdue for review and documents with missing owners or approval evidence.

The project also publishes a short “how to use project documents” guide. Team members receive a briefing, and the project manager conducts a sample audit after two weeks.

Outcome

The project gains a dependable reference set. The supplier’s alleged scope change is found to be an unapproved proposal rather than an authorized change. The security review is repeated against the current architecture baseline. The project reduces duplicate documents and can demonstrate who approved its major deliverables.

Learning Points

The case illustrates that governance is both preventive and corrective. The most valuable controls were not complex technical features; they were clear authority, an authoritative repository, controlled status, and visible traceability. Governance also exposed a privacy issue that ordinary version control would not have solved.

13. Challenges and Limitations

Excessive Bureaucracy

Too many forms, approvals, or mandatory fields can encourage staff to bypass the system. Controls should be risk-based and periodically simplified.

Shadow Documentation

Teams may maintain unofficial spreadsheets, chat decisions, or local notes because official processes are slow. These sources should be assessed rather than ignored. Important information should be transferred into controlled records.

Repository Migration

Moving documents between tools can break links, lose metadata, or create duplicate versions. Migration requires inventory, mapping, validation, access testing, and communication.

Distributed and Agile Teams

Agile delivery produces rapidly changing information. Governance should support lightweight decision records, living documentation, automated checks, and frequent approval points rather than relying only on large documents produced at the end.

Human Error

Users may misclassify files, approve without reading, or continue using an old download. Training, clear status labels, notifications, and periodic audits reduce but do not eliminate this risk.

Conflicting Obligations

Contractual, legal, privacy, security, and business requirements may conflict. Escalation to legal, compliance, security, or records specialists is appropriate when the project cannot resolve the conflict confidently.

14. Best-Practice Implementation Checklist

A project beginning or improving its governance should:

  1. Inventory major document and record types.
  2. Identify applicable organizational, contractual, legal, and regulatory obligations.
  3. Assign an owner and approval authority to each important type.
  4. Select the authoritative repository.
  5. Define naming, numbering, status, version, and metadata rules.
  6. Publish templates for recurring deliverables.
  7. Configure access according to need and classification.
  8. Establish review, baseline, change, and exception procedures.
  9. Define retention triggers and legal-hold controls.
  10. Train users with realistic examples.
  11. Monitor missing metadata, overdue reviews, unauthorized access, and obsolete copies.
  12. Review the governance system after major delivery phases and lessons-learned activities.

Chapter Summary

Documentation governance establishes the accountability, authority, standards, and controls needed to manage project information throughout its life cycle. It identifies owners, authors, reviewers, approvers, administrators, and users, while ensuring that approval authority matches the impact of a document or decision. Policies should define repositories, classification, templates, metadata, naming conventions, status, version control, exceptions, retention, and disposal.

A reliable governance system creates a single source of truth, supports traceability, protects sensitive information, and preserves evidence of decisions and approvals. Baselines provide controlled reference points, while change management permits necessary evolution without losing accountability. Templates and metadata improve consistency and retrieval, but they do not replace professional review. Retention must reflect legal, contractual, regulatory, privacy, and business requirements, including legal holds.

Technology and AI can automate routine controls and improve discovery, but human roles remain responsible for accuracy, approval, confidentiality, and compliance. Effective governance is proportionate: it applies stronger controls where the consequences of error, alteration, disclosure, or loss are greater. Ultimately, documentation governance is a practical project-control discipline rather than an administrative burden.

Key Terms

Documentation governance: The framework of policies, roles, standards, and controls governing documented information.

Document owner: The person accountable for a document’s content, currency, and controlled use.

Author: The person who prepares or updates document content.

Approver: The authorized person who grants formal approval for a document or decision.

Document controller: The person who administers identifiers, metadata, workflows, and repository controls.

Record: Evidence of an activity, decision, transaction, or completed event.

Metadata: Structured information describing a document, such as owner, status, version, and classification.

Naming convention: A defined pattern for identifying files or records consistently.

Template: A controlled structure that guides creation of a recurring document type.

Single source of truth: The designated authoritative location for current information.

Version: A distinct controlled revision of a document.

Status: An indicator of a document’s state, such as Draft, Approved, or Superseded.

Baseline: A formally approved reference version managed through change control.

Traceability: The ability to connect information to its origin, changes, decisions, and approvals.

Classification: A label indicating sensitivity and required handling.

Retention: The authorized period for keeping a document or record.

Disposition: The controlled action taken when retention ends, including destruction or transfer.

Legal hold: A suspension of normal disposal because information may be relevant to litigation or investigation.

Separation of duties: Distribution of responsibilities so that one person does not improperly control conflicting activities.

Review Questions

Short Answer Questions

  1. What is the difference between documentation governance and document management?
  2. Why should every controlled document have a named owner?
  3. What is the purpose of metadata?
  4. Explain the difference between an approved document and a superseded document.
  5. What information should be recorded when a policy exception is granted?

Long Answer Questions

  1. Explain the principles of effective documentation governance and discuss how proportionality prevents both excessive bureaucracy and inadequate control.
  2. Describe how an approval authority matrix can be designed for a software project. Include examples of documents with different approval levels.
  3. Discuss how naming conventions, templates, metadata, and version control work together to improve document reliability and retrieval.
  4. Explain the major considerations involved in establishing retention, archiving, legal-hold, and disposal rules.
  5. Evaluate the benefits and risks of using repository automation and artificial intelligence in documentation governance.

Analytical / Application Questions

  1. A project team stores requirements in a shared drive, architecture diagrams in email attachments, and decisions in chat messages. Analyse the governance risks and propose a prioritized improvement plan.
  2. A product owner approves a requirements baseline, but the technical lead later discovers a security defect. Explain how the project should record, assess, approve, and implement the resulting change while preserving traceability.
  3. Design a concise documentation governance model for a small software project with an external supplier. Specify the repository, roles, approval rules, metadata, naming convention, status model, and retention approach.

Multiple Choice Questions with Answers

Question 1

What is the primary purpose of documentation governance?

A. To eliminate the need for project meetings

B. To establish rules, responsibilities, and controls for managing project information

C. To ensure every document is produced by the project manager

D. To replace software testing with written evidence

Correct Answer: B. To establish rules, responsibilities, and controls for managing project information

Question 2

Who is normally accountable for the content, currency, and controlled use of a document?

A. The document owner

B. Any reader of the document

C. The repository vendor

D. The project accountant

Correct Answer: A. The document owner

Question 3

Which location should contain the authoritative version of a controlled project document?

A. The most recent email attachment

B. A team member’s local computer

C. The designated project repository or controlled record system

D. A personal messaging application

Correct Answer: C. The designated project repository or controlled record system

Question 4

Which status indicates that a document has been replaced by a newer approved version?

A. Draft

B. In Review

C. Superseded

D. Baselined

Correct Answer: C. Superseded

Question 5

What is the main purpose of a baseline?

A. To prevent all future changes

B. To provide an approved reference point against which changes are controlled

C. To identify the author’s preferred file format

D. To permit unrestricted editing

Correct Answer: B. To provide an approved reference point against which changes are controlled

Question 6

Which item is an example of metadata?

A. The document’s main argument

B. The owner, status, version, and classification

C. A stakeholder’s informal opinion

D. A deleted file with no identifier

Correct Answer: B. The owner, status, version, and classification

Question 7

Which filename best follows the illustrative convention in the chapter?

A. final-final.docx

B. newrequirements.docx

C. ALPHA_REQ_PaymentProcessing_v1.2_Approved_2025-04-18.docx

D. document latest version.docx

Correct Answer: C. ALPHA_REQ_PaymentProcessing_v1.2_Approved_2025-04-18.docx

Question 8

What should happen when a legal hold applies to records that would normally be destroyed?

A. Normal disposal should continue automatically

B. The records should be deleted by the document owner

C. Ordinary disposal should be suspended for affected information

D. The records should be copied to personal devices

Correct Answer: C. Ordinary disposal should be suspended for affected information

Question 9

Which principle requires stronger controls when the consequences of error, disclosure, or loss are greater?

A. Proportionality

B. Informality

C. Duplication

D. Anonymity

Correct Answer: A. Proportionality

Question 10

What is an appropriate governance rule for AI-generated project summaries?

A. They automatically become approved records

B. They should replace the authoritative source

C. They require human verification and should not expose sensitive data to unapproved services

D. They do not need any record of their origin

Correct Answer: C. They require human verification and should not expose sensitive data to unapproved services

Project Documentation & Control
Chapter 3 of 14