Foundations of Project Cost ManagementIntroduction and ContextProject cost management is the disciplined process of estimating, allocating, authorizing, monitoring, controlling, and learning from the financial resources required to achieve a project’s objectives. It is not limited to producing a budget. A credible cost-management system connects scope, schedule, resources, risk, procurement, organizational strategy, governance, and benefits realization. Cost decisions are made throughout the project life cycle, although their influence is usually greatest early in the project. A design decision may determine material quantities, construction methods, maintenance requirements, energy consumption, and disposal costs for many years. Consequently, cost management must begin before detailed estimates are available and must continue after project delivery when operating and life-cycle costs are evaluated. In professional practice, the terms cost, price, value, budget, estimate, forecast, funding, and contingency are sometimes used interchangeably. They are not interchangeable. Clear definitions are essential because poor terminology can produce poor decisions, conceal uncertainty, and create disputes between sponsors, project teams, suppliers, and finance functions. This chapter establishes the conceptual foundation for later study of estimating methods, cost baselines, earned value, risk allowances, and budget control. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Define and distinguish fundamental project cost-management terminology.
- Explain the project cost life cycle from early concept through closeout and operations.
- Distinguish cost, price, value, budget, funding, and financial performance.
- Classify direct and indirect, fixed and variable, sunk and opportunity costs.
- Explain the relevance and limits of PMI, ISO 21502/ISO 21508, and AACE International guidance.
- Apply cost classifications to managerial decisions and project scenarios.
- Identify governance, ethical, data, and uncertainty issues affecting cost decisions.
1. The Meaning and Scope of Project Cost ManagementA project cost is a measured sacrifice of economic resources attributable to project work or to decisions made because of the project. The resource may be cash, labor time, materials, equipment capacity, information, facilities, or management attention. In accounting practice, costs are often recorded in monetary units, but the underlying resource consumption is broader than cash expenditure. Project cost management normally includes five connected activities: - Cost planning: deciding how costs will be estimated, classified, authorized, reported, and controlled.
- Cost estimating: developing an approximation of the resources and monetary amounts required.
- Budgeting: aggregating approved estimates into a time-phased cost baseline and identifying funding requirements.
- Cost control: comparing actual and forecast performance with the approved baseline and managing changes.
- Cost learning and closeout: reconciling accounts, evaluating performance, capturing lessons, and improving future estimates.
The activities are iterative. A risk event, design change, market shock, or productivity discovery can require a revised forecast. Revision does not necessarily mean that the original estimate was negligent; it may reflect the legitimate reduction of uncertainty as knowledge improves. The governance question is whether the revision is transparent, authorized, traceable, and based on defensible evidence. Important terminology| Term | Meaning in project cost management |
|---|
| Cost estimate | An assessment of the resources and monetary cost required to perform defined work. | | Budget | An authorized, time-phased plan for expected project costs. | | Cost baseline | The approved version of the time-phased budget used for performance comparison, normally excluding management reserve. | | Funding | Money made available to the project or organization to pay for authorized work. | | Forecast | A current estimate of future cost or financial outcome using actual information and assumptions. | | Actual cost | The cost recorded for work performed or resources consumed. | | Commitment | A contractual or otherwise authorized obligation to incur cost in the future. | | Contingency reserve | A provision for identified uncertainty or risk within the approved scope and cost baseline, according to the organization’s rules. | | Management reserve | A separately controlled allowance for unforeseen work or unknown-unknowns; its treatment varies by governance system. | | Cost variance | The difference between a relevant planned, earned, or forecast amount and another comparison amount. Its meaning depends on the selected performance method. | | Life-cycle cost | The total cost associated with an asset or solution over acquisition, operation, maintenance, renewal, and disposal. |
A useful distinction is that an estimate is a prediction, whereas a budget is an authorized management commitment. An estimate may exist before approval. Once approved and time-phased, selected estimate elements form a baseline against which performance can be assessed. 2. The Project Cost Life CycleCost management follows the logic of the project life cycle but does not stop at the point of technical completion. Four overlapping stages are especially useful for analysis. 2.1 Concept and feasibilityAt concept stage, scope is incomplete and uncertainty is high. Estimates may use analogous projects, parametric relationships, expert judgment, market benchmarks, or broad order-of-magnitude ranges. The purpose is often to support strategic screening, option selection, affordability analysis, and a preliminary business case—not to authorize detailed procurement. At this stage, decision makers should ask: - What problem is the project intended to solve?
- Which alternatives have been evaluated?
- What assumptions drive the estimate?
- What benefits, risks, and life-cycle costs are associated with each option?
- What level of estimate uncertainty is acceptable for the decision being made?
A low initial estimate can be strategically misleading if it excludes enabling works, escalation, taxes, design development, commissioning, operations, or disposal. 2.2 Definition and planningDuring definition, the work breakdown structure, requirements, quantities, resource strategy, procurement approach, schedule, risk register, and estimating basis become more detailed. Cost accounts are established, estimates are refined, and a budget is developed. The result should be a coherent relationship among scope, schedule, resource loading, estimate assumptions, and funding profile. Time-phasing matters because the timing of expenditure affects cash requirements, financing costs, escalation exposure, and performance interpretation. A project can be within its total budget while experiencing a short-term funding shortage. 2.3 Execution and controlDuring execution, actual costs, commitments, progress, changes, and forecasts are recorded. Control involves more than comparing invoices with budget. The project team must determine whether expenditure has produced the planned physical progress and whether the remaining work can be completed within the remaining resources. Controls should integrate: - approved scope and change control;
- schedule status and productivity;
- procurement commitments and claims;
- labor, material, and equipment usage;
- risk occurrence and reserve consumption;
- actual costs and accruals; and
- forecast cost at completion.
A favorable cash variance can conceal poor performance if invoices are delayed or work is incomplete. Similarly, an unfavorable early variance may be temporary if major planned purchases occur before progress is measured. Interpretation requires context. 2.4 Closeout, operations, and learningAt closeout, the organization reconciles commitments, accruals, invoices, approved changes, claims, retained amounts, and remaining liabilities. It compares final cost with the approved baseline and explains material variances. Lessons should address estimating assumptions, market conditions, productivity, design maturity, risk responses, contract behavior, and data quality. For assets such as hospitals, software platforms, energy systems, and manufacturing facilities, project delivery cost may be only one component of economic performance. Operating, maintenance, energy, downtime, renewal, and disposal costs may dominate the asset’s life-cycle cost. Therefore, project decisions should be evaluated against the period relevant to the intended benefit, not solely against the construction or implementation budget. 3. Cost, Price, Value, Budget, and FundingCost and priceCost is the resource sacrifice incurred by a party. Price is the amount charged or paid in an exchange. A supplier’s price may include direct cost, indirect cost, profit, risk allowance, financing cost, taxes, and commercial strategy. A client’s project cost may include the supplier price plus internal project management, land, permits, financing, integration, training, and other costs. Thus, supplier price and owner cost can differ substantially. The price paid for a software license, for example, may not include internal configuration, data migration, cybersecurity testing, training, and future support. ValueValue is the worth of an outcome to a stakeholder in a particular context. It may include financial return, service quality, safety, resilience, environmental performance, regulatory compliance, reputation, or social benefit. Value is not identical to low cost. A higher-cost option may create greater value if it produces larger benefits or materially reduces risk. A simple economic comparison may use a benefit–cost ratio: BCR = PV(Benefits) ÷ PV(Costs) Here, BCR is the benefit–cost ratio, and PV denotes present value calculated using an appropriate discount rate. The ratio is meaningful only when benefits and costs are defined consistently, valued over the same analysis period, and treated with comparable assumptions. It should not be used as the sole decision criterion where benefits are non-monetary or distributional effects are important. For a cash-flow stream, present value can be represented as: PV = Σ[t=0 to n] CFt ÷ (1 + r)t where CF_t is the net cash flow in period t, r is the discount rate per period, and n is the final period. The units of PV are monetary units. This formula assumes that cash flows are defined consistently, the discount rate corresponds to the time period, and timing conventions are known. Budget and fundingA budget is an approved plan; funding is the financial capacity made available to pay for that plan. A project may have an approved budget but delayed funding, or adequate funding but an unapproved scope increase. Confusing these concepts can lead to unauthorized commitments or unrealistic schedules. Estimate, baseline, and forecastAn estimate expresses expected cost under stated assumptions. A baseline is the approved reference plan. A forecast updates expected final cost using current evidence. Forecasting should not be treated as an admission of failure; it is a control function that enables timely action. 4. Cost Classifications for Project DecisionsCost classifications are analytical tools. The same cost can be classified differently for different decisions. For example, an engineer’s salary may be direct to a project, fixed over a short period, variable over a long period, and an opportunity cost when assigned to one project rather than another. 4.1 Direct and indirect costsDirect costs can be traced economically and practically to a specific project, work package, product, or activity. Examples include project-specific labor, materials installed in a facility, equipment rented exclusively for the project, and subcontract prices attributable to defined work. Indirect costs support several projects or organizational activities and cannot be assigned economically to one cost object without an allocation method. Examples include corporate finance, human resources, shared information technology, office rent, enterprise insurance, and general administration. Allocation methods should be causal, consistent, transparent, and fit for purpose. A simple percentage allocation may be convenient but can distort decisions when projects consume shared resources differently. The project manager should understand whether an indirect charge is controllable by the project and whether it is included in the approved estimate. 4.2 Fixed and variable costsA fixed cost remains approximately constant over a specified relevant range and time period as activity volume changes. Examples may include a monthly project office lease or a fixed-price design package. A variable cost changes with an activity driver such as labor hours, units produced, distance transported, or quantity installed. The qualification “over a relevant range” is essential. A project office lease may be fixed until the team outgrows the facility; then a step increase occurs. Labor may be variable with work quantity but fixed for a short salaried period. Cost behavior must therefore be modeled with respect to time, capacity, and the decision horizon. A basic cost model is: C(Q) = F + vQ where C(Q) is total cost for activity level Q, F is fixed cost, and v is variable cost per unit. The model assumes a linear relationship within a relevant range, constant unit variable cost, and clearly defined units. It is a simplification, not a universal law. 4.3 Sunk and opportunity costsA sunk cost has already been incurred and cannot be recovered by the current decision. It should not determine whether to continue, redesign, or abandon a project, although it remains relevant for accountability, learning, and financial reporting. An opportunity cost is the value of the best alternative forgone. If a scarce engineering team is assigned to Project A, the contribution that could have been obtained from the best rejected use may be an opportunity cost of Project A. Opportunity cost is often absent from invoices but important in portfolio prioritization. The relevant cost for a decision is generally a future, incremental, and decision-dependent cost. Past costs are relevant only if they create future consequences, such as an unavoidable remediation liability or a recoverable asset value. 4.4 Recurring, non-recurring, and life-cycle costsNon-recurring costs occur once or infrequently, such as design, setup, commissioning, and initial training. Recurring costs arise repeatedly, such as support, energy, subscriptions, inspections, and maintenance. A narrow project budget may emphasize non-recurring delivery costs, whereas investment appraisal should usually examine both. 5. Estimating Logic and Cost AggregationA project estimate is built by defining the cost object, identifying resources, quantifying work, applying rates or prices, documenting assumptions, and aggregating cost elements. A generic aggregation is: Ctotal = Σ[i=1 to m] qi ri + Cindirect + Cother where q_i is the quantity of resource or work item i, r_i is its applicable unit rate, m is the number of items, C_indirect represents allocated indirect costs, and C_other includes relevant costs such as permits, taxes, escalation, or specialist allowances. The terms must use compatible units and avoid double counting. The estimate should include an estimating basis that records: - scope definition and exclusions;
- measurement rules and quantity sources;
- labor, material, equipment, and subcontract rates;
- productivity assumptions;
- location, currency, and price date;
- escalation and exchange-rate assumptions;
- taxes, duties, insurance, and overhead treatment;
- risk and contingency methodology;
- schedule assumptions and calendar;
- estimate classification and expected accuracy range; and
- data quality, limitations, and approval status.
Illustrative worked exampleAn illustrative work package requires 1,200 labor hours at 48 monetary units per hour, materials costing 32,000 monetary units, equipment costing 9,500 monetary units, and an allocated indirect cost of 12% of direct cost. Assume no tax, escalation, contingency, or double counting. Direct labor cost: 1,200 × 48 = 57,600 Direct cost: 57,600 + 32,000 + 9,500 = 99,100 Indirect cost: 0.12 × 99,100 = 11,892 Total estimated cost: 99,100 + 11,892 = 110,992 monetary units The result is an estimate, not automatically a budget. Before approval, the team should verify whether the 12% allocation includes project management, whether equipment cost overlaps with supplier pricing, and whether the work package is sufficiently defined. 6. Professional Frameworks and StandardsPMI guidanceThe Project Management Institute’s PMBOK® Guide presents project cost management as a performance domain or set of management practices concerned with planning, estimating, budgeting, financing, funding, managing, and controlling costs. PMI emphasizes tailoring: the project team should select practices appropriate to project size, complexity, delivery approach, governance, life cycle, and organizational context. Common PMI concepts include cost baseline, funding requirements, reserve analysis, earned value analysis, and change control. PMI guidance is a body of professional knowledge rather than a substitute for organizational accounting policy, contract terms, or statutory requirements. Its value lies in a coherent vocabulary and adaptable management practices. ISO guidanceISO 21502 provides guidance on project management principles and practices across project contexts. It supports integrated management of scope, schedule, resources, risk, governance, and stakeholders; cost management must therefore be connected with these areas rather than treated as an isolated finance activity. ISO 21508 provides guidance on earned value management, including the integration of scope, schedule, and cost information for performance assessment. ISO documents generally provide principles and guidance rather than a single mandatory estimating technique. Organizations must define procedures, responsibilities, thresholds, data controls, and reporting rules appropriate to their environment. AACE International guidanceAACE International publishes recommended practices and professional guidance on cost engineering, estimating, cost control, risk analysis, project controls, and estimate classification. AACE estimate classifications emphasize the relationship between the maturity of project definition and the expected use and accuracy of an estimate. Early estimates have less definition and wider uncertainty; later estimates normally have greater definition and narrower expected ranges, although market volatility and technical novelty can disrupt this pattern. AACE practices are particularly useful for developing an estimating basis, selecting methods, documenting uncertainty, conducting estimate reviews, and linking estimating with total cost management. They should be applied with awareness of the industry sector, contract structure, jurisdiction, and organization’s governance system. Comparison of the frameworks| Dimension | PMI | ISO | AACE International |
|---|
| Primary emphasis | Integrated project-management practice | International principles and guidance | Cost engineering, estimating, and project controls | | Cost contribution | Planning, estimating, budgeting, funding, control | Integration and governance; earned value guidance | Estimate development, classification, risk, and control detail | | Flexibility | Strong tailoring orientation | Context-dependent guidance | Recommended practices requiring professional judgment | | Best use | Project-management system design | Consistent organizational or international governance | Technical estimating and control procedures |
These frameworks are complementary. A mature organization may use PMI for project-management architecture, ISO for consistent governance and terminology, and AACE practices for detailed cost engineering. None eliminates the need for sound data, experienced judgment, transparent assumptions, or ethical conduct. 7. Governance, Ethics, and Contemporary PracticeCost information influences investment approval, supplier selection, public expenditure, staffing, and stakeholder trust. Ethical cost management requires honest estimates, disclosure of uncertainty, avoidance of deliberate underestimation, segregation of duties where appropriate, protection of confidential data, and prompt escalation of material deviations. Common governance failures include: - presenting a target cost as though it were an independent estimate;
- omitting known scope to obtain approval;
- hiding unfavorable information in aggregated categories;
- moving costs between projects to improve reported performance;
- recognizing progress without evidence of completed work;
- treating management reserve as untracked discretionary spending; and
- using optimistic assumptions without sensitivity analysis.
Digital tools can improve quantity take-off, rate libraries, dashboards, procurement integration, and forecast updating. Artificial intelligence can assist with anomaly detection, document classification, risk pattern recognition, and probabilistic forecasting. However, AI outputs depend on data quality, training history, model assumptions, and governance. They should be explainable enough for material decisions, independently reviewed, protected against confidential-data leakage, and never treated as authoritative merely because they are computationally sophisticated. Contemporary cost management also faces inflation, supply-chain disruption, geopolitical risk, climate-related events, cyber threats, labor scarcity, and changing regulatory requirements. Scenario analysis, sensitivity analysis, reference-class forecasting, probabilistic risk analysis, and explicit escalation assumptions can improve decision quality. The purpose is not to create false precision, but to make uncertainty visible and actionable. 8. Illustrative Case: The Northbank Health Information SystemThis is a fictional illustrative case. BackgroundA regional health authority planned a three-year digital health information system. The initial proposal stated a delivery cost of 18 million monetary units. Senior leaders viewed the figure as affordable and compared it with the capital budget. ProblemDuring detailed planning, the project team identified data migration, clinical workflow redesign, cybersecurity testing, user training, integration with laboratories, and two years of post-go-live support. Several of these items had been treated as operational concerns rather than project costs. The supplier’s proposed price was 12 million, but the authority’s internal cost forecast exceeded 18 million. AnalysisThe team separated the financial concepts: - Supplier price: 12 million.
- Internal direct project labor and testing: 3.2 million.
- Training and change management: 1.4 million.
- Data migration and integration: 2.1 million.
- Governance, assurance, and allocated support: 1.3 million.
- Identified risk allowance: 1.8 million.
- Post-go-live support: evaluated separately as a recurring operating cost.
The team also identified a sunk cost of 0.6 million from an abandoned prototype. That amount was reported for learning and accountability but excluded from the forward-looking choice between implementation options. An opportunity cost was identified: assigning the authority’s scarce clinical analysts to the project would delay another safety-improvement initiative. Approach and solutionThe authority developed a documented estimating basis, clarified scope boundaries, separated one-time and recurring costs, and created a time-phased baseline. It used a decision gate before full implementation and required approval for reserve usage. A lower-cost alternative was rejected because its apparent savings depended on omitting migration and cybersecurity work and generated materially higher operational risk. OutcomeThe approved delivery budget was higher than the original proposal, but the decision was more credible. The project obtained staged funding, established monthly integrated cost-and-schedule reviews, and created a separate operating-cost forecast. Early disclosure allowed the authority to secure clinical capacity and reduce later disruption. Learning points- Supplier price is not necessarily the owner’s total project cost.
- Cost boundaries must include enabling and integration work.
- Sunk costs should not drive forward-looking alternatives analysis.
- Opportunity costs matter when scarce organizational resources are constrained.
- Transparent uncertainty can improve governance even when it increases the approved budget.
Challenges and LimitationsCost classifications and frameworks simplify reality. Direct and indirect boundaries may be contested; fixed and variable behavior changes with time and capacity; life-cycle forecasts depend on uncertain utilization and maintenance assumptions; and benefit estimates may be politically or ethically sensitive. Inflation and exchange-rate movements can invalidate historical rates. Contract incentives can also change supplier behavior in ways not visible in a simple cost model. A cost system can be technically accurate yet strategically inadequate if it measures the wrong cost object, ignores benefits, or rewards local optimization. Conversely, an elaborate system can impose disproportionate administrative burden on a small project. The appropriate response is disciplined tailoring: use enough structure to support reliable decisions, but no more complexity than the project’s risk and governance require. Best-Practice Principles- Define the cost object, scope boundary, currency, price date, and decision purpose.
- Integrate cost estimates with the work breakdown structure and schedule.
- Document assumptions, exclusions, sources, rates, and uncertainty.
- Separate cost, price, value, budget, funding, commitment, and actual cost.
- Distinguish delivery cost from operating and life-cycle cost.
- Use classifications consistently, while recognizing that classification depends on the decision context.
- Establish approval thresholds, change control, reserve rules, and audit trails.
- Reforecast using current evidence rather than defending obsolete assumptions.
- Use independent review or challenge for material estimates.
- Treat ethical disclosure and data integrity as core cost-management responsibilities.
Chapter SummaryProject cost management is an integrated discipline covering planning, estimating, budgeting, funding, monitoring, control, closeout, and learning. An estimate is a prediction; a budget is an authorized plan; a baseline is the approved reference for performance comparison; and a forecast is an updated view of expected outcome. Cost differs from price, and low cost does not necessarily mean high value. Direct and indirect costs describe traceability; fixed and variable costs describe cost behavior over a relevant range; sunk costs describe unrecoverable past expenditure; and opportunity costs describe the value of the best alternative forgone. These classifications are decision tools rather than permanent labels. Life-cycle thinking broadens analysis beyond delivery expenditure to include operation, maintenance, renewal, and disposal. PMI, ISO, and AACE guidance are complementary. PMI supports integrated and tailored project management, ISO supports internationally consistent principles and earned-value guidance, and AACE provides detailed cost-engineering and estimating practices. Effective application requires reliable data, explicit assumptions, ethical governance, professional judgment, and appropriate treatment of uncertainty. Key TermsCost: Economic resource sacrifice attributable to work or a decision. Price: Amount charged or paid in an exchange. Value: Worth of an outcome to a stakeholder in context. Estimate: Prediction of required resources and monetary cost. Budget: Authorized plan for expected project costs. Cost baseline: Approved time-phased reference plan for cost performance. Funding: Money made available to pay for authorized work. Forecast: Updated estimate of future cost or outcome. Actual cost: Recorded cost of work performed or resources consumed. Commitment: Authorized obligation to incur future cost. Direct cost: Cost traceable to a specific cost object. Indirect cost: Shared cost allocated across cost objects. Fixed cost: Cost approximately constant over a defined relevant range. Variable cost: Cost that changes with an activity driver. Sunk cost: Past cost that cannot be recovered by a current decision. Opportunity cost: Value of the best alternative forgone. Contingency reserve: Allowance for identified uncertainty within approved scope, subject to governance rules. Management reserve: Controlled allowance for unforeseen work or unknown-unknowns. Life-cycle cost: Total cost across acquisition, operation, maintenance, renewal, and disposal. Estimating basis: Documented assumptions, methods, sources, exclusions, and conditions underlying an estimate. Review QuestionsShort Answer Questions- Distinguish an estimate from a budget and a forecast.
- Why can a supplier’s price differ from the project owner’s total cost?
- Define direct cost and give two examples.
- What is an opportunity cost?
- Why is time-phasing important in a project budget?
Long Answer Questions- Explain the project cost life cycle from feasibility through closeout and operations.
- Compare direct/indirect, fixed/variable, and sunk/opportunity cost classifications, including their managerial uses and limitations.
- Discuss the relationship among cost, price, value, budget, and funding.
- Compare the contributions of PMI, ISO, and AACE International guidance to project cost management.
- Explain how ethical governance and uncertainty disclosure affect the credibility of a project estimate.
Analytical / Application Questions- A project manager claims that a project is under budget because invoices are lower than planned, although physical progress is also substantially behind schedule. Analyze why this conclusion may be invalid and identify the additional information required.
- A team proposes a cheaper technology by excluding training, integration, cybersecurity testing, and five years of support. Using life-cycle cost and value concepts, evaluate the proposal.
- An organization must assign a scarce engineering team to one of two projects. Explain how direct cost, opportunity cost, strategic value, and risk should be incorporated into the decision.
Multiple Choice Questions with AnswersQuestion 1Which statement best distinguishes a budget from an estimate? A. An estimate is always more accurate than a budget. B. A budget is an authorized plan, while an estimate is an assessment of expected cost. C. A budget includes only indirect costs, while an estimate includes only direct costs. D. An estimate is recorded actual cost, while a budget is a supplier price. Correct Answer: B. A budget is an authorized plan, while an estimate is an assessment of expected cost. Question 2Which item is most likely a direct project cost? A. Corporate human-resources administration B. Enterprise office rent allocated across departments C. Materials installed specifically in the project facility D. General corporate legal services Correct Answer: C. Materials installed specifically in the project facility Question 3A past expenditure that cannot be recovered by a current decision is called a: A. Variable cost B. Sunk cost C. Opportunity cost D. Committed cost Correct Answer: B. Sunk cost Question 4In the model C(Q) = F + vQ, what does v represent? A. Total fixed cost B. Activity level C. Variable cost per unit D. Total project duration Correct Answer: C. Variable cost per unit Question 5Why can a supplier price differ from the owner’s total project cost? A. Price and cost always have identical definitions. B. The owner may incur internal, integration, training, and other costs beyond the supplier price. C. Supplier prices never include profit or risk. D. Owner costs exclude all indirect costs by definition. Correct Answer: B. The owner may incur internal, integration, training, and other costs beyond the supplier price. Question 6Which statement about fixed costs is most accurate? A. They never change under any circumstances. B. They are constant over a specified relevant range and time period. C. They are always direct costs. D. They are equivalent to sunk costs. Correct Answer: B. They are constant over a specified relevant range and time period. Question 7What is the primary purpose of a cost baseline? A. To replace the project scope statement B. To provide an approved reference for comparing cost performance C. To record only supplier invoices D. To eliminate all project uncertainty Correct Answer: B. To provide an approved reference for comparing cost performance Question 8Which framework is especially associated with detailed cost-engineering recommended practices and estimate classification? A. AACE International B. ISO 9001 only C. PMI’s stakeholder engagement guidance only D. A financial market index Correct Answer: A. AACE International Question 9An opportunity cost is best described as: A. A cost already paid and unrecoverable B. The value of the best alternative forgone C. A cost that remains constant with activity D. A supplier’s invoice total Correct Answer: B. The value of the best alternative forgone Question 10A work package has direct cost of 99,100 monetary units and indirect cost equal to 12% of direct cost. What is the total estimated cost, excluding other allowances? A. 99,100 B. 103,060 C. 110,992 D. 118,892 Correct Answer: C. 110,992
|