Introduction

Facility location, layout and material flow are closely connected decisions in production management. Location determines where an organisation performs its activities; layout determines how departments, workstations, equipment, storage areas and services are arranged within that location; and material flow determines how materials, components, people and information move through the system. Together, these decisions influence cost, throughput, quality, safety, flexibility, employee performance and customer service.

A poor location may create high transport, labour or regulatory costs for many years. A poor layout may cause excessive movement, congestion, waiting, work-in-process inventory and unsafe conditions even when the factory has modern equipment. Effective production managers therefore treat location and layout as strategic, cross-functional decisions rather than merely engineering or property decisions.

The appropriate solution depends on product characteristics, process technology, demand volume and variety, supply-chain structure, labour requirements, environmental obligations and future growth. This chapter develops methods for assessing these factors and for designing product, process, cellular, fixed-position and hybrid layouts. It also explains load–distance analysis, relationship charts, line balancing, material-handling principles and workplace safety requirements.

Learning objectives

After studying this chapter, the learner should be able to:

  1. Explain the strategic significance of facility-location decisions.
  2. Evaluate qualitative and quantitative location factors.
  3. Distinguish product, process, cellular, fixed-position and hybrid layouts.
  4. Apply load–distance analysis and relationship-chart techniques.
  5. Calculate basic production-line balance measures.
  6. Design material flows using recognised handling and safety principles.
  7. Recommend an integrated facility solution and identify its limitations.

1. Facility location as a production decision

A facility may be a factory, warehouse, distribution centre, service centre, repair depot or administrative-support site. Location decisions are normally long-term because buildings, utilities, transport links and local employment relationships are costly to change. They should therefore be based on total life-cycle performance rather than land price alone.

1.1 Strategic and operational levels

Location analysis is commonly conducted at three levels:

  • Country or region level: political stability, market access, taxation, trade rules, labour availability, infrastructure and environmental regulation.
  • Community or city level: local labour markets, wage rates, education, housing, public services, quality of life and municipal incentives.
  • Site level: plot size, soil and drainage, access roads, utilities, expansion potential, zoning, neighbouring land uses and internal transport distances.

The decision should also distinguish between a new facility, relocation, expansion of an existing facility and the use of multiple facilities. A network with several plants may reduce delivery distance but increase coordination, duplicated equipment and inventory.

1.2 Principal location factors

FactorQuestions for analysis
Market proximityHow quickly and economically can customers be served?
Supplier proximityAre inbound materials bulky, fragile, perishable or time-sensitive?
TransportAre road, rail, port and air connections reliable and affordable?
LabourAre required skills available, and what are wage and turnover patterns?
UtilitiesAre electricity, water, fuel, telecommunications and waste services adequate?
Land and buildingsIs the site affordable, suitable and expandable?
RegulationWhat planning, labour, environmental, safety and tax requirements apply?
RiskIs the site exposed to flood, fire, earthquake, political disruption or cyber-related dependency?
CommunityWill the facility receive social acceptance and a reliable local workforce?
SustainabilityCan emissions, energy use, water use and transport impacts be controlled?

The importance of each factor depends on the operation. A food-processing plant may prioritise water quality, agricultural supply and hygiene regulation. An electronics plant may prioritise skilled technicians, stable electricity and clean-room requirements. A heavy engineering plant may require high floor loading, large transport access and distance from dense residential areas.

1.3 Qualitative factor-rating method

When alternatives differ across factors that cannot be expressed in comparable monetary units, a weighted-factor model is useful. Let the score of site j be:

Sj = ∑(wi rij), i = 1, 2, …, n

where wᵢ is the weight of factor i, with all weights summing to 1; rᵢⱼ is the rating of site j on factor i; and Sⱼ is the total weighted score. Ratings must use the same scale, such as 1 to 10, for all sites. The method assumes that factor preferences can be represented by additive scores and that the weights reflect management priorities.

Worked example. Three possible sites are rated from 1 to 10 on labour, market access, utilities and regulation. The weights are 0.30, 0.25, 0.25 and 0.20 respectively.

SiteLabourMarketUtilitiesRegulationWeighted score
A87687.25
B79867.65
C96777.40

For site B, the calculation is 0.30(7) + 0.25(9) + 0.25(8) + 0.20(6) = 7.65. Site B has the highest score, but the result is not automatically decisive. Sensitivity analysis should test whether reasonable changes in weights alter the ranking. A site with a lower score may still be preferred if it avoids a critical legal, safety or supply risk.

1.4 Cost–volume analysis

When fixed and variable costs differ among locations, total annual cost for site j may be expressed as:

TCj = Fj + vj Q

where TCⱼ is total cost per period, Fⱼ is fixed cost per period, vⱼ is variable cost per unit and Q is expected output. This model assumes a linear variable cost, a known output level and no capacity discontinuities. It excludes qualitative risks unless they are separately assessed.

The crossover quantity between sites A and B is obtained by setting their total costs equal:

QAB = (FB − FA) ÷ (vA − vB)

provided the denominator is not zero. The formula identifies the volume at which the two alternatives have equal cost; it does not prove that either site is feasible.

Example. Site A has fixed cost of $400,000 and variable cost of $18 per unit. Site B has fixed cost of $700,000 and variable cost of $12 per unit. The crossover is (700000 − 400000) ÷ (18 − 12) = 50000 units. Below 50,000 units, A is cheaper; above 50,000 units, B is cheaper, assuming both have adequate capacity.

1.5 Centre-of-gravity method

For a distribution facility, a rough geographical starting point can be found using weighted coordinates:

x* = ∑(wi xi) ÷ ∑wi, y* = ∑(wi yi) ÷ ∑wi

Here, xi and yi are the coordinates of customer or supply point i, and wi is its shipment volume, demand or transport weight. The method assumes transport cost is approximately proportional to volume and distance and that roads, terrain, traffic and legal restrictions do not significantly distort straight-line distance. It is a screening tool, not a final site-selection method.

2. Layout strategy and process choice

Layout design begins with the relationship between product volume and variety. High-volume, low-variety products generally support flow-oriented layouts. Low-volume, high-variety products generally require functional departments and flexible routing. Intermediate conditions often suit cellular layouts.

Product process matrix showing volume and variety relationships Increasing volume → Increasing variety → Job shop / process Cellular Product / line Low volume High volume
Product process matrix showing volume and variety relationships
Figure: Product process matrix showing volume and variety relationships

Figure: The product–process relationship guides the choice of layout type.

The matrix is a guide rather than a law. Automation, modular equipment, postponement and digital production control can make a facility economically viable outside the traditional relationship.

3. Major layout types

3.1 Product layout

In a product layout, workstations are arranged according to the sequence of operations required for a product or product family. Examples include assembly lines, bottling lines and continuous-process plants.

Advantages include high throughput, short travel distance, low work-in-process, simple visual control and relatively low unit handling cost. Limitations include low flexibility, vulnerability to breakdowns, repetitive work, difficult product changes and the possibility that one bottleneck stops the entire line.

Product layouts require accurate demand forecasts, stable product design, balanced workstations, reliable equipment and disciplined quality control.

3.2 Process layout

A process, or functional, layout groups similar resources together, such as all lathes, milling machines, inspection equipment or painting facilities. It is suitable for low-volume, high-variety production and job-shop work.

Its flexibility permits different routings and specialist supervision. However, jobs may travel long and varying distances, queues may develop before busy departments, scheduling is complex and work-in-process may be high. Routing data, dispatching rules and visible capacity information are especially important.

3.3 Cellular layout

A cellular layout groups dissimilar machines into a cell that can manufacture a family of parts with similar processing requirements. Group technology, part-family coding and production-flow analysis are usually used to identify families.

Cells can reduce setup time, travel, queueing and supervisory complexity while retaining more variety than a dedicated line. Risks include duplicated equipment, imbalance between cells, unsuitable family assignments and underutilised resources when product mix changes. Periodic review of part families is therefore necessary.

3.4 Fixed-position layout

In a fixed-position layout, the product remains stationary and workers, materials, tools and equipment move to it. Shipbuilding, aircraft assembly, construction and major equipment installation are typical examples.

The layout supports very large or fragile products but requires rigorous staging, access planning, lifting control, coordination and schedule management. Congestion around the product can create serious safety risks. A location plan should identify zones for materials, personnel, cranes, emergency access and temporary work.

3.5 Hybrid layout

Most modern facilities use a hybrid. For example, receiving and fabrication may be process-oriented, subassembly may use cells, final assembly may use a product line, and large modules may be built in fixed-position zones. Hybrid design allows the organisation to match layout to product families and process constraints rather than forcing the whole plant into one pattern.

4. Layout-design methods

4.1 From-to and load–distance analysis

Load–distance analysis estimates the effort associated with movement between departments. For a layout with departments i and j:

LD = ∑∑ lij dij

where lij is the number of loads moved between departments i and j per planning period, and dij is the distance moved per load. The result is expressed in load-distance units, such as pallet-metres per day. If loads have different weights or handling costs, a weighted form may be used:

LDc = ∑∑ lij cij dij

where cij is cost per load-distance unit. The method assumes that distance is a reasonable proxy for movement effort and that the movement data represent a normal planning period. It does not capture congestion, vertical movement, risk, damage or handling-time differences unless these are added explicitly.

Worked example. Three departments have the following daily movements: A–B, 20 loads; A–C, 10 loads; B–C, 15 loads. In layout 1, the distances are 5 m, 12 m and 7 m respectively. Thus:

LD1 = 20(5) + 10(12) + 15(7) = 325 load-m/day.

An alternative layout has distances of 8 m, 6 m and 5 m. Therefore:

LD2 = 20(8) + 10(6) + 15(5) = 295 load-m/day.

Layout 2 reduces the movement index by 30 load-metres per day, or approximately 9.2%. The manager should then check aisle width, fire exits, equipment access, utilities and future changes before selecting it.

4.2 Relationship charts

A relationship chart records the desired closeness between departments, including non-material relationships. A common rating scale is:

  • A: absolutely necessary
  • E: especially important
  • I: important
  • O: ordinary closeness acceptable
  • U: unimportant
  • X: undesirable

Reasons should be recorded, such as “frequent material movement,” “shared supervision,” “noise,” “contamination risk” or “emergency access.” The chart prevents designers from relying only on shipment counts. For example, a laboratory may need to be near quality control despite low material flow, while a noisy compressor room may need separation from offices.

A relationship chart is not a final drawing. It is converted into a relationship diagram, then into block layouts that are tested using load–distance, safety and capacity criteria.

4.3 Space requirements and adjacency

Space planning must include machines, operator working areas, material presentation, maintenance access, aisles, columns, utilities, inspection points, waste handling, offices and expansion. The net footprint of equipment is therefore not the required facility area. Allowances must also reflect forklift turning radii, pedestrian routes, emergency evacuation and safe separation from hazards.

A good layout distinguishes primary flow, support flow and reverse flow. Scrap, returns and maintenance materials should not cross high-volume finished-product routes unnecessarily.

5. Product-layout line balancing

Line balancing assigns tasks to workstations so that precedence requirements are obeyed and station workloads are as even as practicable.

5.1 Takt time and cycle time

Takt time is the available production time divided by customer demand:

Takt time = Available production time per period ÷ Required customer units per period

If a line must produce 420 units during a 7-hour shift, with no planned breaks included in available time, available time is 7 × 60 = 420 minutes and takt time is 420 ÷ 420 = 1 minute per unit. If a station requires more than one minute per unit, it cannot meet demand without parallel capacity, task redesign or additional time.

The theoretical minimum number of stations is:

Nmin = ⌈∑ti ÷ C⌉

where ti is the time of task i, C is the allowable cycle time and ⌈ ⌉ means round upward to the next whole station. This is a lower bound; precedence constraints may require more stations.

5.2 Efficiency and balance delay

For N stations:

Line efficiency = ∑ti ÷ (N C) × 100%

This assumes every station has the same cycle-time limit and that task times are measured in the same units. Balance delay is:

Balance delay = 100% − Line efficiency

Example. Total task time is 8.4 minutes, cycle time is 2.0 minutes and four stations are used. Efficiency is 8.4 ÷ (4 × 2.0) × 100% = 105%, which is impossible because the proposed staffing capacity is only 8.0 minutes per cycle. At least five stations are required: efficiency becomes 8.4 ÷ (5 × 2.0) × 100% = 84%. The example demonstrates why arithmetic and feasibility checks are essential.

5.3 Balancing procedure

A practical procedure is to list tasks and predecessors, calculate cycle time, identify eligible tasks, assign tasks without exceeding the cycle time, and evaluate idle time and precedence feasibility. Heuristics such as largest-candidate rule or ranked positional weight can provide an initial solution, but managers should compare alternatives and validate them under realistic variation.

Line balancing should not optimise only labour utilisation. Excessively tight balance may reduce resilience, leave no recovery time and increase operator stress. Quality checks, ergonomic rotation, micro-stoppages and planned maintenance must be included in the design.

6. Material flow and handling

Material flow includes raw materials, purchased parts, work-in-process, finished goods, packaging, waste, returns and sometimes information. The objective is not simply to move material quickly; it is to move the correct material safely, without damage, contamination, loss of identification or unnecessary handling.

6.1 Flow principles

Important principles are:

  1. Minimise movement: eliminate unnecessary transfers and storage points.
  2. Use a logical sequence: arrange operations to support a forward flow where possible.
  3. Avoid backtracking and cross-flow: separate inbound, production, outbound and waste routes.
  4. Use unit loads: move suitable quantities in standard containers or pallets.
  5. Provide point-of-use supply: present materials close to the workstation without obstructing work.
  6. Control visibility: use labels, barcodes, RFID or other identification systems.
  7. Design for replenishment: define supermarket, kanban, milk-run or direct-delivery rules.
  8. Protect quality: control temperature, moisture, cleanliness, shock and electrostatic discharge where relevant.
  9. Plan reverse logistics: include scrap, reusable packaging, returns and quarantine.
  10. Allow controlled flexibility: routes should support product changes and emergency access.

6.2 Handling-equipment selection

Forklifts, pallet trucks, conveyors, cranes, automated guided vehicles, autonomous mobile robots, hoists and manual handling each have different capacities and risks. Selection should consider load size, frequency, travel distance, floor condition, aisle width, lifting height, battery or fuel requirements, maintenance, operator competence and interaction with pedestrians.

Automation is beneficial when flow is repetitive, volumes justify investment and interfaces are stable. It can be unsuitable where product variety is high, routes change frequently or safety controls are immature. Automated equipment does not remove risk; it changes the risk profile to include collision, entrapment, sensor failure, software error and cyber or network dependency.

6.3 Safety and regulatory requirements

Facility design must comply with applicable occupational health and safety, fire, building, environmental, lifting and electrical requirements. Specific legal provisions vary by jurisdiction, so managers must consult current national regulations and competent safety professionals.

Core controls include:

  • segregated pedestrian and vehicle routes;
  • marked aisles, crossings and restricted zones;
  • adequate lighting, ventilation and housekeeping;
  • guarding and interlocks for machinery;
  • emergency stops and accessible isolation points;
  • safe stacking and rack-load limits;
  • inspection and certification of lifting equipment;
  • manual-handling assessment and ergonomic workstation design;
  • emergency exits, alarms, fire equipment and evacuation plans;
  • training, supervision, incident reporting and near-miss learning.

The hierarchy of controls should guide risk reduction: eliminate the hazard where possible, substitute a safer alternative, apply engineering controls, establish administrative controls and use personal protective equipment as the final layer rather than the only control. Layout decisions should be reviewed through formal risk assessment before operation and after significant change.

7. Integrated design approach

A robust project normally follows these stages:

  1. Define products, volumes, demand variation, routings and service requirements.
  2. Screen regional and site alternatives using strategic, cost, risk and sustainability criteria.
  3. Map current and proposed material, people, information and waste flows.
  4. Establish activity relationships and space requirements.
  5. Generate alternative block layouts.
  6. Test alternatives with load–distance, line-balance, capacity, safety and ergonomic analyses.
  7. Model variability, breakdowns, queues and future expansion where necessary.
  8. Select equipment, handling systems, utilities and control technology.
  9. Validate the design with operators, maintenance, quality, safety, logistics and finance personnel.
  10. Implement in stages, measure performance and revise the design.

Relevant performance indicators include throughput, lead time, work-in-process, distance travelled, handling cost, on-time delivery, space utilisation, changeover time, first-pass yield, accidents, near misses and energy use. No single indicator is sufficient. A layout that reduces distance but increases accidents or quality defects is not an improvement.

Illustrative case: relocation and hybrid layout at Meridian Components

Background

Meridian Components, a fictional medium-sized manufacturer of industrial pump modules, produces three product families. Annual demand has increased, but the existing plant contains a functional machine shop, separate welding and painting departments, and a distant final-assembly area. Parts frequently travel back through the machine shop for rework. Forklifts share narrow aisles with pedestrians, and work-in-process is stored in unmarked areas.

Problem

Management is considering a new site and must decide whether to copy the existing process layout or introduce a hybrid arrangement. The principal objectives are to reduce lead time and unsafe movement without losing the ability to manufacture customised orders.

Analysis

A factor-rating study gives greatest weights to supplier access, skilled labour, expansion space, utilities and safety compliance. The selected site scores highest because it has reliable power, a trained labour pool, two-sided vehicle access and room for expansion. A cost–volume analysis shows that its higher lease cost is justified at the forecast production volume, although sensitivity analysis is required if demand falls.

A from-to study shows that machining, welding and assembly account for most movement. A relationship chart identifies quality inspection as especially important near assembly, while paint preparation should be separated from clean assembly because of contamination risk. Product-family analysis identifies three families: standard pump modules, corrosion-resistant modules and customised heavy modules.

Approach and solution

The proposed facility uses a hybrid layout:

  • a machining cell for common precision parts;
  • a welding and fabrication cell for standard frames;
  • a controlled paint area physically separated from clean assembly;
  • a paced assembly line for standard modules;
  • a fixed-position zone for heavy customised modules;
  • a central but controlled quality area near the cells and assembly;
  • one-way inbound and outbound logistics routes with pedestrian segregation.

Point-of-use racks supply small components. Larger loads move during scheduled milk runs rather than whenever an operator requests material. Barcodes identify work orders and quarantine status. The heavy-module zone has dedicated lifting equipment and marked exclusion areas.

Outcome

In a pilot implementation, average travel distance falls by 18%, visible work-in-process decreases and standard-module throughput improves. The heavy-module area remains slower because of engineering changes, but it no longer disrupts the standard assembly line. Safety review identifies the need for an additional pedestrian crossing and improved crane exclusion markings before full operation.

Learning points

The case demonstrates that a facility should not be forced into a single layout type. Quantitative distance reduction must be combined with relationship analysis, contamination control, safety, product-family logic and future capacity. Pilot testing and worker participation also reveal problems that a drawing alone may not show.

Challenges, limitations and contemporary developments

Location and layout models simplify reality. Demand may be uncertain, transport costs may be nonlinear, departments may have changing routings and the shortest route may not be the safest route. Factor ratings can conceal subjective bias; cost–volume models can ignore disruption and capacity; load–distance analysis can undervalue congestion; and line-efficiency measures can encourage local optimisation.

Sustainability is now a core design consideration. Facility decisions should evaluate energy intensity, renewable-energy access, water consumption, waste, emissions, packaging, local environmental impact and climate resilience. A site exposed to flooding may have attractive current costs but unacceptable long-term risk.

Digital tools support computer-aided facility layout, discrete-event simulation, digital twins, warehouse-management systems, real-time location systems and automated material handling. AI can assist demand forecasting, route optimisation, anomaly detection and alternative-layout evaluation. Human governance remains necessary because training data may be incomplete, recommendations may be difficult to explain, and optimisation objectives may neglect worker safety or equity. Systems should be validated, access-controlled and monitored for cyber security and operational failure.

Best practice is therefore participative and iterative. Include operators and maintainers, document assumptions, test unusual conditions, provide expansion space, protect emergency routes, measure actual flows after implementation and treat safety and legal compliance as design constraints rather than optional scoring factors.

Chapter Summary

Facility location is a long-term production decision involving markets, suppliers, labour, transport, utilities, regulation, risk, sustainability and community conditions. Weighted-factor scoring, cost–volume analysis and centre-of-gravity calculations provide useful screening tools, but they must be supported by feasibility, sensitivity and risk analysis.

Layout selection should reflect volume, variety and process requirements. Product layouts support high-volume flow; process layouts support flexibility; cellular layouts organise machines around product families; fixed-position layouts keep large products stationary; and hybrid layouts combine these arrangements. Load–distance analysis quantifies movement, while relationship charts capture qualitative closeness and separation requirements. Product-line designs additionally require takt-time analysis, precedence control and line balancing.

Effective material flow minimises unnecessary movement, backtracking, congestion, damage and handling. Safe design separates pedestrians and vehicles, controls lifting and machinery hazards, supports ergonomics and complies with applicable law. Contemporary facilities increasingly use digital identification, simulation, automated vehicles and AI-assisted analysis, but technology must remain subject to human safety, ethical and governance controls. The strongest facility designs integrate strategic location, physical layout, flow, capacity, quality, safety and future adaptability.

Key Terms

Facility location: The geographic placement of an operating facility.

Layout: The physical arrangement of resources, work areas, storage and services.

Product layout: Arrangement of workstations in the sequence of product operations.

Process layout: Arrangement that groups similar machines or functions together.

Cellular layout: Arrangement of different resources into cells serving product families.

Fixed-position layout: Layout in which the product remains stationary while resources move.

Hybrid layout: A facility combining two or more layout types.

Factor rating: Weighted evaluation of location alternatives against selected criteria.

Cost–volume analysis: Comparison of facility costs as output volume changes.

Centre of gravity: A weighted-coordinate method for identifying a preliminary facility location.

Load–distance analysis: Evaluation of movement volume multiplied by travel distance.

Relationship chart: A diagrammatic record of required closeness or separation between activities.

Takt time: Available production time divided by required customer demand.

Cycle time: Maximum allowable time between completed units on a line.

Line balancing: Assignment of tasks to stations while satisfying precedence and capacity limits.

Material flow: Movement of materials, products, waste and related information through an operation.

Unit load: A quantity of material moved as one handling entity.

Point-of-use storage: Material presentation close to the workstation where it is consumed.

Hierarchy of controls: Ordered approach to reducing hazards from elimination through PPE.

Work-in-process: Items that have entered production but are not yet finished.

Review Questions

Short Answer Questions

  1. Why are facility-location decisions considered strategic and long term?
  2. State two advantages and two limitations of a product layout.
  3. What information does a relationship chart provide?
  4. Define takt time and explain its relationship to customer demand.
  5. List four principles of safe material flow.

Long Answer Questions

  1. Explain the principal factors that should be evaluated when selecting a manufacturing-facility location.
  2. Compare product, process, cellular, fixed-position and hybrid layouts, including suitable applications.
  3. Describe how load–distance analysis and relationship charts can be used together to develop alternative layouts.
  4. Explain the line-balancing procedure and discuss why efficiency alone is not an adequate performance criterion.
  5. Discuss how workplace safety, sustainability and digital technology influence modern facility design.

Analytical / Application Questions

  1. Two sites have fixed and variable costs of $500,000 and $16 per unit, and $800,000 and $10 per unit respectively. Calculate the crossover volume and explain which site is preferred above that volume, subject to capacity and risk constraints.
  2. A facility records 30 loads per day between A and B at 6 m, 20 loads between A and C at 10 m, and 15 loads between B and C at 8 m. Calculate the total load–distance value and identify what additional factors should be checked before changing the layout.
  3. A proposed assembly line has total task time of 14.5 minutes and a cycle time of 3 minutes. Calculate the theoretical minimum number of stations and line efficiency if five stations are used. Interpret the result and identify practical issues that may prevent implementation.

Multiple Choice Questions with Answers

Question 1

Which layout is most appropriate for high-volume, low-variety production with a stable sequence of operations?

A. Product layout

B. Process layout

C. Fixed-position layout

D. Random layout

Correct Answer: A. Product layout

Question 2

A facility has fixed costs of $300,000 and variable cost of $20 per unit. A second site has fixed costs of $450,000 and variable cost of $15 per unit. What is the crossover volume?

A. 15,000 units

B. 30,000 units

C. 45,000 units

D. 60,000 units

Correct Answer: B. 30,000 units

Question 3

In load–distance analysis, the load term normally represents:

A. The physical floor area of a department

B. The number or weight of movements between locations

C. The number of employees in a department

D. The operating hours of a machine

Correct Answer: B. The number or weight of movements between locations

Question 4

Which relationship-chart rating indicates that closeness is undesirable?

A. A

B. E

C. I

D. X

Correct Answer: D. X

Question 5

Available production time is 360 minutes per shift and demand is 240 units per shift. What is the takt time?

A. 0.67 minute per unit

B. 1.0 minute per unit

C. 1.5 minutes per unit

D. 2.0 minutes per unit

Correct Answer: C. 1.5 minutes per unit

Question 6

A cellular layout primarily groups resources according to:

A. The colour of the equipment

B. Product or part families with similar processing requirements

C. The seniority of employees

D. The accounting department responsible for them

Correct Answer: B. Product or part families with similar processing requirements

Question 7

Which layout keeps the main product stationary while workers, materials and equipment move to it?

A. Product layout

B. Process layout

C. Fixed-position layout

D. Cellular layout

Correct Answer: C. Fixed-position layout

Question 8

If total task time is 9 minutes, cycle time is 2 minutes and five stations are used, what is line efficiency?

A. 80%

B. 90%

C. 110%

D. 45%

Correct Answer: B. 90%

Question 9

Which control is generally higher in the hierarchy of controls than personal protective equipment?

A. Ignoring the hazard

B. Engineering control

C. Reducing inspection frequency

D. Removing warning signs

Correct Answer: B. Engineering control

Question 10

Which is a major purpose of pedestrian–vehicle segregation in a facility?

A. To increase product variety

B. To reduce collision risk between people and handling equipment

C. To eliminate the need for maintenance

D. To increase variable labour cost

Correct Answer: B. To reduce collision risk between people and handling equipment