Production Planning & Control

Chapter 5
Sales and Operations Planning and Aggregate Planning

Advance Diploma in Operations management
Production Planning & Control   •   Advance Diploma

Sales and Operations Planning and Aggregate Planning

Introduction and Context

Production Planning and Control connects market requirements with the organisation’s capacity to supply products and services. At the medium-term level, the principal coordinating mechanism is Sales and Operations Planning (S&OP), supported by aggregate planning. S&OP converts forecasts, customer commitments and strategic priorities into an agreed plan for production, procurement, inventory, workforce and capacity over a planning horizon commonly ranging from 3 to 18 months.

The central challenge is that demand and productive capacity rarely match naturally. Demand may be seasonal, uncertain or promotion-driven, while capacity is constrained by labour availability, equipment, supplier capability, regulations and finance. A sound plan therefore balances customer service, operating cost, workforce stability, inventory investment and risk.

S&OP is not merely a production meeting. It is a cross-functional decision process involving sales, marketing, operations, procurement, finance, logistics and senior management. Aggregate planning provides the quantitative analysis needed to compare alternatives such as:

  • maintaining a stable workforce and using inventory to absorb demand variation;
  • varying workforce or production rates to follow demand;
  • using overtime, temporary labour or subcontracting;
  • accepting planned backlogs or lost sales; and
  • combining these approaches in a hybrid strategy.

The objective is not necessarily to find the mathematically cheapest plan. The preferred plan must also be feasible, robust, ethically acceptable and consistent with the organisation’s strategic commitments.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Explain the purpose, process and governance of S&OP.
  2. Distinguish aggregate planning from master production scheduling and detailed scheduling.
  3. Formulate and interpret a medium-term aggregate-planning model.
  4. Compare level, chase and hybrid strategies.
  5. Evaluate workforce, inventory, overtime, outsourcing and backlog trade-offs.
  6. Prepare and communicate a cross-functional S&OP recommendation.
  7. Recognise the limitations, risks and ethical implications of aggregate plans.

1. Planning Hierarchy and Time Horizons

Production planning is hierarchical. Decisions made at one level constrain decisions at lower levels.

Planning levelTypical horizonMain decisionTypical output
StrategicSeveral yearsFacilities, technology, supply-network structureCapacity and network strategy
Aggregate planning/S&OP3–18 monthsOverall output, workforce, inventory and capacityAggregate production and sales plan
Master production schedulingWeeks to several monthsSpecific end items and delivery timingMaster production schedule
Material requirements planningDays to monthsComponents and purchased materialsPlanned orders and release dates
Detailed scheduling and controlHours to weeksSequence, dispatching and shop-floor prioritiesWork schedules and control actions

Aggregate planning uses product families rather than individual stock-keeping units. For example, a manufacturer may plan “commercial refrigerators” as one family even though several models exist. This reduces complexity while retaining the information needed for capacity and financial decisions.

The plan is usually expressed in time buckets such as months. Monthly buckets are appropriate for medium-term capacity decisions, but they conceal weekly variation. Consequently, an aggregate plan must later be translated into a feasible master schedule and detailed schedule.

2. Sales and Operations Planning

2.1 Purpose of S&OP

S&OP creates one organisational view of expected demand and the resources required to meet it. Its purposes include:

  • reconciling sales forecasts with operational capability;
  • identifying capacity, material and labour constraints early;
  • aligning the operating plan with financial budgets;
  • making trade-offs visible to decision makers;
  • improving customer-service reliability; and
  • coordinating functions that otherwise optimise locally.

A sales department may prefer high availability and aggressive promotions. Operations may prefer stable production and long runs. Finance may emphasise working-capital reduction. S&OP provides a forum in which these competing priorities are evaluated against common assumptions and agreed performance measures.

2.2 The S&OP cycle

A practical monthly S&OP cycle normally contains the following stages:

  1. Data gathering and statistical forecasting. Actual sales, orders, inventory, open capacity, supplier information and forecast accuracy are assembled.
  2. Demand review. Sales and marketing review the baseline forecast, promotions, new products, customer intelligence and known risks.
  3. Supply review. Operations and procurement test whether the demand plan can be supported by labour, equipment, materials, suppliers, inventory and logistics.
  4. Reconciliation and scenario analysis. Cross-functional teams quantify alternatives and identify gaps between demand and supply.
  5. Executive S&OP. Senior managers select priorities, approve assumptions, resolve conflicts and authorise exceptions.
  6. Implementation and measurement. The agreed plan is communicated, converted into operational schedules and monitored through the next cycle.

A mature process has clear ownership, a fixed calendar, version-controlled data and documented decisions. It also separates assumptions from decisions. For example, “demand will increase by 12%” is an assumption; “use overtime in months 5 and 6” is a decision.

2.3 Forecasts, orders and demand consensus

The demand plan should distinguish among statistical forecasts, firm customer orders, contractual commitments, promotional uplifts and speculative opportunities. A forecast is not the same as demand certainty. Forecasts should be accompanied by ranges, confidence information or scenario labels where possible.

Forecast bias is particularly important. A consistently optimistic forecast creates excess inventory and capacity reservations; a consistently pessimistic forecast causes shortages and expediting. S&OP should therefore review forecast error and bias, not only forecast totals.

Useful measures include forecast error, forecast bias, service level, inventory turns, schedule adherence, overtime and plan stability. No single metric is sufficient. For example, high service achieved through excessive overtime may be inferior to slightly lower service with sustainable capacity.

3. Aggregate Planning Concepts

An aggregate plan specifies, for each period:

  • expected demand;
  • regular-time production;
  • overtime production;
  • subcontracted or outsourced production;
  • beginning and ending inventory;
  • workforce level;
  • hiring and layoffs;
  • backlog or shortages, if permitted; and
  • relevant costs.

The plan must satisfy conservation of flow: beginning inventory plus all available supply must equal demand, ending inventory and any permitted backlog. For a plan that permits positive inventory and positive backlog as separate quantities, the balance for period t is:

It-1 + Rt + Ot + St = Dt + It + Bt

where It-1 is beginning inventory in units, Rt regular-time production, Ot overtime production, St subcontracted production, Dt demand, It ending inventory and Bt ending backlog. All quantities must use the same unit and time period. The equation assumes that inventory and backlog are not simultaneously used to represent the same unmet demand; in a more rigorous model, complementary constraints or a net-inventory formulation may be required.

If backlog is represented as a signed net inventory, let Nt be positive for inventory and negative for backlog. Then:

Nt = Nt-1 + Rt + Ot + St - Dt

This formulation is compact, but separate inventory and backlog variables are often clearer for costing and reporting.

3.1 Cost components

An aggregate-planning cost model may include:

  • regular production cost;
  • overtime premium;
  • hiring and training cost;
  • layoff or severance cost;
  • inventory holding cost;
  • shortage or backlog cost;
  • subcontracting cost;
  • recruitment of temporary labour;
  • expediting and transportation cost; and
  • penalties for missed contractual service.

A simplified total-cost expression is:

TC = ∑t=1T (cR Rt + cO Ot + cS St + h It + p Bt + cH Ht + cL Lt)

Here, TC is total relevant cost; T is the number of periods; cR, cO and cS are unit costs for regular, overtime and subcontract production; h is holding cost per unit per period; p is backlog cost per unit per period; cH and cL are hiring and layoff costs; and Ht and Lt are hires and layoffs. Costs must be stated on a consistent basis, such as currency per unit or currency per worker.

This expression is a decision model, not a universal accounting identity. It is appropriate when costs are approximately linear and known over the planning horizon. It may be inadequate when there are fixed charges, quantity discounts, nonlinear learning effects, labour laws, minimum subcontract quantities or multiple capacity bottlenecks.

3.2 Workforce relationships

If each worker produces at units during period t, regular production is often represented by:

Rt = at Wt

where Wt is the number of workers assigned to regular production. If a worker is available for only a fraction ut of the period because of absenteeism, training or planned downtime, effective production may instead be:

Rt = at ut Wt

The productivity coefficient must be defined carefully. It may mean units per worker-month, standard hours per worker, or good units after yield loss. These interpretations must not be mixed.

Workforce continuity is represented by:

Wt = Wt-1 + Ht - Lt

where Ht and Lt are non-negative hires and layoffs. If the model assumes integer workers, integrality constraints are required. A linear model may produce fractional workers, which is acceptable only as a planning approximation or where a pooled labour force makes fractional full-time equivalents meaningful.

4. Level, Chase and Hybrid Strategies

4.1 Level strategy

A level strategy maintains a relatively constant workforce and regular production rate. Demand variation is absorbed through inventory, backlog, overtime or subcontracting.

Advantages include stable employment, lower hiring and layoff activity, predictable learning effects, improved quality from experienced workers and smoother utilisation of equipment. Disadvantages include inventory carrying cost, risk of obsolescence, storage requirements and possible backlog during demand peaks.

A level strategy is attractive when products are stable, inventory is not highly perishable, workforce skills are scarce and employment stability has strategic value.

4.2 Chase strategy

A chase strategy adjusts production approximately to demand. This may be achieved through hiring and layoffs, variable hours, temporary workers or flexible capacity.

Advantages include low finished-goods inventory and reduced risk of obsolescence. Disadvantages include recruitment and severance cost, training time, quality risk, employee stress, industrial-relations concerns and loss of organisational knowledge.

A pure chase strategy is rarely feasible when demand changes faster than the labour market or when capacity has significant setup and qualification requirements.

4.3 Hybrid strategy

A hybrid strategy combines stable core capacity with selected flexibility. An organisation may maintain a level workforce, build inventory before a predictable peak, use overtime for moderate deviations and subcontract only exceptional demand.

Hybrid plans are common because they recognise that costs and constraints are not symmetric. Hiring and layoffs may be slow and disruptive, while overtime may be fast but expensive. Similarly, inventory may be inexpensive for standard products but unacceptable for short-life or customised products.

StrategyMain balancing mechanismStrengthPrincipal risk
LevelInventory and capacity buffersStability and workforce retentionExcess inventory or backlog
ChaseWorkforce or output variationLow inventoryLabour instability and quality risk
HybridCombination of buffersFlexibility and balanceMore complex coordination

5. A Worked Aggregate-Planning Example

The following illustrative example uses a simplified single-product family. Demand is known for four months. One worker produces 100 units per month. Beginning inventory is 100 units, and the initial workforce is 10 workers. Backlog is not permitted. Regular production costs £20 per unit, overtime costs £30 per unit, and inventory holding cost is £2 per unit carried at the end of a month. The analysis ignores hiring and layoff costs so that the inventory and overtime trade-off can be seen clearly.

MonthDemand (units)
1900
21,300
31,100
4700

Level plan

The initial workforce produces 1,000 units per month. With beginning inventory of 100 units:

  • Month 1 ending inventory = 100 + 1,000 − 900 = 200.
  • Month 2 ending inventory = 200 + 1,000 − 1,300 = −100.

The level plan therefore fails the no-backlog condition in month 2 unless overtime or additional capacity is added. Suppose 300 overtime units are produced in month 2. The resulting inventory is 200 units. Month 3 ending inventory is 200 + 1,000 − 1,100 = 100 units, and month 4 ending inventory is 100 + 1,000 − 700 = 400 units.

Regular production is 4,000 units. Overtime is 300 units. Total demand is 4,000 units, and the initial 100 units of inventory are carried into the plan; the final inventory is 400 units. The flow balance is verified as:

100 + 4,000 + 300 = 4,000 + 400.

The relevant production cost is 4,000 × £20 = £80,000, overtime cost is 300 × £30 = £9,000, and ending-inventory holding charges, if charged on each month’s ending inventory, are £2 × (200 + 200 + 100 + 400) = £1,800. Total stated cost is therefore £90,800, excluding the cost of beginning inventory.

A chase-oriented alternative

A chase-oriented plan could produce 800 units in month 1, 1,300 in month 2, 1,100 in month 3 and 700 in month 4, using workforce changes and no overtime or ending inventory. At 100 units per worker-month, the required workforce levels are 8, 13, 11 and 7 workers respectively. This plan demonstrates the operational burden of chasing demand: the workforce changes from 10 to 8, then 13, 11 and 7. Whether it is cheaper depends on hiring, layoff, training, employment-protection and productivity costs.

The comparison cannot be completed responsibly without those costs. If hiring and layoff costs are high, the level or hybrid plan may be preferable. If inventory is expensive or products become obsolete quickly, the chase plan may be preferable. The correct conclusion is therefore conditional, not that one strategy is universally superior.

6. Capacity, Inventory and Workforce Trade-offs

Workforce flexibility

Workforce decisions should consider more than headcount. Relevant factors include skill certification, legal working-time limits, absenteeism, learning curves, cross-training and the time required to recruit. A nominal capacity of 1,000 units per month may be unrealistic if new workers are initially only 60% productive.

Overtime

Overtime is useful for temporary peaks and short-term recovery. Its disadvantages include premium cost, fatigue, safety risk, absenteeism and quality deterioration. Overtime should not be treated as unlimited capacity. Maximum hours, collective agreements and health-and-safety regulation must be respected.

Outsourcing and subcontracting

Outsourcing provides scalable capacity and may reduce capital requirements. However, it can introduce longer lead times, quality variation, intellectual-property exposure, supplier dependence and loss of internal capability. Supplier capacity should be validated rather than assumed. The apparent subcontracting unit price may exclude inspection, transport, coordination, warranty and switching costs.

Inventory

Inventory decouples production from demand and protects service against uncertainty. Its costs include capital, storage, insurance, deterioration, obsolescence, handling and shrinkage. Safety stock should not be confused with inventory created by an aggregate plan. Safety stock protects against uncertainty; cycle or anticipation inventory may be deliberately built for batch economics or seasonality.

Backlog and lost sales

A backlog may be acceptable for a make-to-order industrial product but unacceptable for emergency medical supplies or a major retail promotion. Backlog cost should include customer dissatisfaction, cancellation, contractual penalties, reputation and future lost business. In many markets, “no backlog” is an unrealistic assumption because shortage is transformed into lost sales rather than recorded orders.

7. Scenario Analysis and Decision Quality

Aggregate planning should compare scenarios rather than rely on one forecast. Typical scenarios include:

  • base demand;
  • optimistic and pessimistic demand;
  • supplier disruption;
  • labour shortage;
  • promotion success or failure; and
  • reduced equipment availability.

Sensitivity analysis changes one assumption at a time, such as demand, overtime cost or subcontract capacity. Scenario analysis changes a coherent set of assumptions, such as a demand surge combined with supplier shortage. Both methods reveal whether a plan is robust or dependent on a fragile forecast.

A useful decision table may compare total cost, service, workforce change, inventory peak, capacity risk and implementation difficulty. The lowest-cost scenario is not necessarily best if it has unacceptable service or operational risk.

8. Cross-Functional Governance and Performance Measures

Effective S&OP requires governance. The organisation should define:

  • the executive owner of the process;
  • decision rights and escalation thresholds;
  • the data source for demand, inventory and capacity;
  • the planning horizon and time buckets;
  • the approved assumptions;
  • the treatment of exceptions; and
  • the measures used to evaluate performance.

Measures should be balanced. Examples include:

PerspectivePossible measures
CustomerFill rate, on-time delivery, promise-date adherence
OperationsSchedule adherence, capacity utilisation, yield
WorkforceTurnover, absenteeism, overtime, training completion
InventoryDays of supply, inventory turns, obsolescence
FinanceRelevant plan cost, working capital, margin impact
Planning qualityForecast bias, forecast error, plan stability

A measure can create undesirable behaviour if used in isolation. For example, maximising utilisation may encourage overproduction and inventory accumulation. Minimising inventory may increase shortages and expedite costs. Measures should therefore be interpreted as a system.

9. Technology and Contemporary Developments

Enterprise-resource-planning systems provide transaction data, while advanced-planning systems can optimise scenarios across capacity, materials and demand. Digital S&OP increasingly uses near-real-time order data, supplier visibility, cloud collaboration and control-tower dashboards.

Artificial intelligence can support demand sensing, anomaly detection, forecast segmentation and scenario generation. However, AI-generated forecasts do not remove the need for managerial judgement. Structural breaks, new products, promotions, geopolitical disruption and ethical constraints may not be represented adequately in historical data. Models should be monitored for bias, data leakage, unexplained recommendations and deteriorating accuracy.

A sound technology implementation includes data ownership, access control, audit trails, model validation, human approval of material decisions and clear separation between forecast generation and plan authorisation. Technology should reduce decision latency and improve transparency, not conceal assumptions behind an apparently precise number.

10. Ethical, Legal and Sustainability Considerations

Aggregate plans affect people and communities. Repeated hiring and layoffs can transfer demand volatility to workers. Managers should consider fair notice, consultation, retraining, non-discrimination and legal employment requirements. Overtime planning must protect health and safety rather than treating fatigue as a cost-free resource.

Outsourcing decisions should consider labour standards, environmental compliance, modern-slavery risks and supplier governance. Sustainability may require evaluating carbon emissions from expedited transport, energy-intensive overtime, waste from obsolete inventory and the social consequences of unstable employment.

The relevant objective is therefore broader than short-term cost minimisation. A responsible plan balances economic performance with legal compliance, worker welfare, customer obligations and environmental impact.

11. Illustrative Case: Northstar Home Appliances

Background

Northstar Home Appliances produces a family of countertop ovens. Demand is low in the first half of the year and rises sharply before a major holiday season. The company employs trained assembly workers and has limited oven-testing capacity. Sales proposes a promotion that may increase peak demand by 25%.

Problem

The existing plan is a level plan based on average demand. Operations warns that the testing station cannot support the promotional peak without overtime or subcontract testing. Finance is concerned about inventory and working capital, while human resources is concerned about excessive temporary hiring.

Analysis

The S&OP team develops three scenarios:

  1. Level: maintain the core workforce, build inventory before the peak and use limited overtime.
  2. Chase: hire temporary workers for the peak and reduce the workforce afterwards.
  3. Hybrid: build moderate inventory, cross-train permanent workers, use overtime at the testing station and subcontract only overflow testing.

The team evaluates each scenario against forecast ranges rather than the promotional point estimate alone. It discovers that a level plan creates obsolete inventory if the promotion fails, while a pure chase plan cannot recruit and train enough qualified workers in time. Subcontracting all testing would create supplier-dependence and quality-control risk.

Approach and solution

The executive S&OP meeting approves the hybrid plan. Northstar retains a stable core workforce, produces a controlled pre-season inventory, cross-trains operators for testing support, reserves limited overtime and qualifies one external testing supplier as a contingency. The promotion is divided into two release waves so that the second wave can be adjusted using early sales results.

Outcome

The plan reduces exposure to forecast error while preserving peak capacity. Its success depends on weekly review of orders, inventory, testing throughput and supplier quality. If demand exceeds the upper scenario, the approved contingency is activated; if demand is weak, the second production wave is delayed.

Learning points

The case illustrates that S&OP is a decision process rather than a single forecast. It also demonstrates the value of postponement, cross-training, staged commitments and explicit contingency plans. Most importantly, the hybrid strategy is not simply a compromise: it is designed around the different response speeds and risks of inventory, labour and outsourcing.

12. Best-Practice Checklist

A professionally managed aggregate plan should:

  • use one agreed set of demand, inventory and capacity data;
  • distinguish forecast, order and management assumptions;
  • express constraints explicitly;
  • include workforce, inventory, overtime, outsourcing and backlog costs where relevant;
  • test at least one adverse scenario;
  • verify flow balance in every period;
  • check that the plan can be translated into a feasible master schedule;
  • document decision rights and exceptions;
  • measure both service and cost; and
  • review ethical, legal, environmental and workforce implications.

Chapter Summary

Sales and Operations Planning aligns demand, supply, finance and organisational priorities through a recurring cross-functional process. Aggregate planning converts this alignment into medium-term decisions concerning production, workforce, inventory, overtime, outsourcing and backlog. The fundamental flow balance requires beginning inventory plus available production to equal demand, ending inventory and any permitted backlog.

Level strategies provide workforce and production stability but may require inventory or backlog. Chase strategies reduce inventory but create workforce and capacity volatility. Hybrid strategies combine core capacity with selective flexibility and are often the most practical. Cost models help compare alternatives, but their assumptions, units, constraints and omitted risks must be examined carefully.

Effective plans use scenario analysis, balanced performance measures, governance and transparent assumptions. Technology and AI can improve forecasting and visibility, but they do not replace human accountability. Ethical S&OP considers worker welfare, legal compliance, supplier standards, customer commitments and environmental effects alongside cost and service.

Key Terms

Aggregate planning: Medium-term planning of production, workforce, inventory and capacity for product families.

Backlog: Demand accepted but not yet fulfilled.

Chase strategy: A strategy that varies production or workforce to follow demand.

Cross-functional planning: Joint decision making by functions such as sales, operations, finance and procurement.

Demand plan: The organisation’s agreed view of expected customer requirements.

Executive S&OP: Senior-management stage at which trade-offs and exceptions are resolved.

Forecast bias: Persistent tendency for forecasts to be above or below actual demand.

Hybrid strategy: A combination of level and chase mechanisms, often with overtime or outsourcing.

Inventory holding cost: Cost of possessing inventory over a period.

Level strategy: A strategy that maintains relatively stable workforce and production.

Master production schedule: A time-phased plan for specific end items.

Outsourcing: Obtaining production or services from an external supplier.

Overtime: Production performed beyond normal working hours, usually at a premium cost.

Plan stability: The degree to which an agreed plan remains unchanged.

Product family: A group of products planned together at an aggregate level.

Sales and Operations Planning: A formal process for balancing demand and supply across functions.

Scenario analysis: Evaluation of plans under coherent alternative assumptions.

Safety stock: Inventory held to protect against demand or supply uncertainty.

Supply review: Assessment of resources and capacity available to support the demand plan.

Workforce continuity: The relationship among beginning workforce, hiring and layoffs over time.

Review Questions

Short Answer Questions

  1. What is the primary purpose of Sales and Operations Planning?
  2. Distinguish aggregate planning from master production scheduling.
  3. State two advantages and two disadvantages of a level strategy.
  4. Why must backlog cost include more than the accounting cost of an unfilled order?
  5. What is the purpose of an executive S&OP meeting?

Long Answer Questions

  1. Explain the stages of a monthly S&OP cycle and the responsibilities of the main participating functions.
  2. Compare level, chase and hybrid aggregate-planning strategies using cost, service, workforce and risk criteria.
  3. Explain the aggregate flow-balance equation and discuss the assumptions required for its use.
  4. Discuss the operational and ethical implications of relying heavily on overtime and temporary labour.
  5. Explain how technology and AI can support S&OP, and identify the governance controls required for responsible use.

Analytical / Application Questions

  1. A firm begins a month with 250 units of inventory. During the month it produces 900 regular units and 150 overtime units, while demand is 1,100 units. Calculate ending inventory and explain whether the plan is flow-balanced.
  2. A seasonal manufacturer can either build inventory using a stable workforce or hire temporary workers for the peak. Identify the information needed to compare the alternatives and recommend a suitable scenario-analysis approach.
  3. An S&OP team proposes outsourcing all peak production because the supplier’s unit price is lower. Analyse at least five hidden costs or risks that should be evaluated before approval.

Multiple Choice Questions with Answers

Question 1

Which statement best describes Sales and Operations Planning?

A. A daily machine-dispatching method

B. A cross-functional process that aligns demand, supply and financial priorities

C. A purchasing procedure limited to raw materials

D. A method for calculating product quality indices

Correct Answer: B. A cross-functional process that aligns demand, supply and financial priorities

Question 2

Which strategy normally maintains a relatively stable workforce and production rate?

A. Chase strategy

B. Level strategy

C. Pure outsourcing strategy

D. Expediting strategy

Correct Answer: B. Level strategy

Question 3

A plan begins with 200 units of inventory, produces 800 units and faces demand of 750 units. What is ending inventory if no other flows occur?

A. 50 units

B. 150 units

C. 250 units

D. 1,750 units

Correct Answer: C. 250 units

Question 4

Which item is most directly associated with a chase strategy?

A. Maintaining constant output regardless of demand

B. Using inventory as the only balancing mechanism

C. Adjusting workforce or output to follow demand

D. Eliminating all capacity decisions

Correct Answer: C. Adjusting workforce or output to follow demand

Question 5

In the aggregate flow-balance equation, what does overtime production represent?

A. Units supplied through additional working hours

B. Units held from the previous period

C. Units of ending backlog

D. Units removed through obsolescence

Correct Answer: A. Units supplied through additional working hours

Question 6

Which is a principal risk of excessive outsourcing?

A. Guaranteed improvement in internal capability

B. Supplier dependence and reduced control over quality

C. Elimination of all transport costs

D. Removal of all demand uncertainty

Correct Answer: B. Supplier dependence and reduced control over quality

Question 7

Why should S&OP use scenario analysis?

A. To ensure that only one forecast is considered

B. To avoid documenting assumptions

C. To test plans under alternative demand and capacity conditions

D. To replace all managerial judgement

Correct Answer: C. To test plans under alternative demand and capacity conditions

Question 8

A worker produces 100 units per month. How many workers are required for 1,300 units in a month, ignoring other constraints?

A. 10

B. 11

C. 12

D. 13

Correct Answer: D. 13

Question 9

Which measure is most directly a customer-service measure?

A. Fill rate

B. Recruitment cost

C. Inventory storage area

D. Training hours per employee

Correct Answer: A. Fill rate

Question 10

Why is a hybrid strategy often practical?

A. It uses only one balancing mechanism

B. It combines stable core capacity with selective flexibility

C. It eliminates the need for forecasts

D. It guarantees the lowest possible cost in every situation

Correct Answer: B. It combines stable core capacity with selective flexibility

Production Planning & Control
Chapter 5 of 15