Project and Temporary Operations ManagementIntroduction and ContextProjects are temporary systems established to create a unique product, service, capability, or change. Unlike repetitive operations, which emphasize stability, projects operate under a defined beginning and end, a specified scope, constrained resources, and an intended outcome. Examples include implementing an enterprise-resource-planning system, constructing a plant, launching a product, relocating a distribution centre, developing a software platform, and executing a major maintenance shutdown. Project management is therefore a central concern of production and operations management. It converts strategic intentions into coordinated work while balancing scope, time, cost, quality, risk, resources, and stakeholder expectations. Temporary operations management extends this perspective to the design and control of short-lived operating systems, such as event operations, emergency response, commissioning, turnaround maintenance, and transformation programmes. A project is not simply a large task list. It is a socio-technical system involving interdependent activities, decision rights, information flows, suppliers, users, regulators, and organizational learning. Effective managers must plan sufficiently to provide direction while remaining adaptable when assumptions change. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Distinguish projects, programmes, portfolios, and temporary operations.
- Develop a work breakdown structure and a logically valid network schedule.
- Calculate the critical path, project duration, float, and PERT estimates.
- Evaluate crashing decisions and allocate scarce resources.
- Apply earned-value management to monitor cost and schedule performance.
- Select predictive, agile, or hybrid delivery approaches.
- Design practical risk-management and project-governance systems.
- Critically evaluate project performance, ethics, and contemporary technology.
1. The Nature of Projects and Temporary OperationsA project has five defining attributes: - Temporariness: It has an approved start and a planned or condition-based finish.
- Uniqueness: Its output or context is not entirely repetitive.
- Progressive elaboration: Understanding of requirements and methods becomes more detailed over time.
- Constraints: Time, cost, scope, quality, resources, risk, and benefits must be balanced.
- Stakeholder dependence: Success is judged by multiple parties, not only by the project team.
A project may produce a deliverable, whereas a programme coordinates related projects to obtain benefits that individual projects cannot achieve independently. A portfolio contains projects, programmes, and operational work selected to support organizational strategy. Governance determines how these entities are authorized, controlled, and reviewed. Temporary operations share project characteristics but usually emphasize the design and operation of a temporary service or capacity. For example, a sports event requires temporary facilities, workforce rosters, safety controls, ticketing, transport, and contingency arrangements. The event is temporary, but its operational performance must be managed in real time. The traditional “iron triangle” of scope, time, and cost is useful but incomplete. Quality, safety, benefits realization, sustainability, resilience, and stakeholder legitimacy may be more important than finishing cheaply. A project can be delivered on time and within budget yet fail if customers do not adopt its output or if the expected benefits do not materialize. 2. Project Life Cycle and Delivery LogicA generic life cycle comprises initiation, planning, execution, monitoring and control, and closure. These are not always strictly sequential. Agile projects revisit planning and execution repeatedly, while regulated projects may require formal stage gates. InitiationInitiation establishes the business need, sponsor, high-level scope, expected benefits, constraints, assumptions, and authority to proceed. The business case should identify alternatives, costs, benefits, risks, and the consequences of not acting. A project charter converts this rationale into a formally authorized mandate. PlanningPlanning defines deliverables, work packages, activities, dependencies, estimates, resources, procurement, quality criteria, communications, risks, and baselines. Planning is not a one-time administrative exercise; it is a mechanism for exposing uncertainty before resources are committed. Execution and controlExecution produces deliverables. Control compares actual performance with approved baselines, manages changes, resolves issues, forecasts outcomes, and protects quality and safety. A baseline is a formally approved reference plan; changes should be traceable rather than silently absorbed. Closure and transitionClosure confirms acceptance, transfers the output to the operating owner, closes contracts, releases resources, captures lessons, and evaluates whether benefits are likely to be realized. Operational readiness is especially important: training, maintenance, data migration, support, and ownership must be in place before handover. 3. Work Breakdown StructuresA work breakdown structure (WBS) is a hierarchical decomposition of the total project scope into progressively smaller components. The lowest useful components are work packages. A WBS is deliverable-oriented: it describes what must exist, not merely the departments that will perform the work. A sound WBS follows the 100-percent rule: the hierarchy should represent all approved project scope, and each lower level should collectively represent the complete scope of its parent. Work should not be counted twice, and exclusions should be explicit. For example, a warehouse-automation project might be decomposed as follows: | Level | WBS element |
|---|
| 1 | Warehouse automation project | | 2 | Design; equipment; software; facility preparation; training and launch | | 3 | Under equipment: conveyors; sensors; controls; testing | | 4 | Under testing: factory acceptance; site acceptance; performance trial |
A work package should have a clear owner, deliverable, acceptance criteria, estimate, planned start and finish, dependencies, and budget. The WBS should be linked to a responsibility assignment matrix, often a RACI matrix: responsible, accountable, consulted, and informed. The WBS, schedule, cost plan, risk register, and procurement plan should use consistent codes so that performance can be integrated. Common WBS errors include organizing only by organizational departments, omitting project management work, decomposing to excessive detail, mixing deliverables and activities at the same level, and failing to include transition or benefits activities. 4. Network Scheduling and the Critical Path MethodA network diagram represents logical relationships among activities. In an activity-on-node representation, each node is an activity and arrows show precedence. Typical relationships are finish-to-start, start-to-start, finish-to-finish, and start-to-finish, although finish-to-start should not be used automatically when overlap is operationally possible. The critical path method (CPM) uses deterministic activity durations. For each activity, the forward pass calculates earliest times: EFi = ESi + di where ESi is the earliest start of activity i, EFi is its earliest finish, and di is its duration. For an activity with predecessors, its earliest start is the maximum earliest finish of its immediate predecessors: ESi = max(EFj) where j represents each immediate predecessor. The project duration is the earliest finish of the final activity or the maximum earliest finish among terminal activities. The backward pass calculates latest allowable times without delaying the project: LSi = LFi − di For an activity with successors, its latest finish is the minimum latest start of its immediate successors: LFi = min(LSk) where k represents each immediate successor. Total float is: TFi = LSi − ESi = LFi − EFi Activities with zero total float form at least one critical path. Criticality can change when durations, logic, calendars, or constraints change. A critical activity is not necessarily the most important activity; safety-critical or legally constrained work may have substantial float but still require close control. Worked example: CPMConsider the following activities: | Activity | Duration (days) | Immediate predecessor |
|---|
| A | 3 | — | | B | 4 | A | | C | 5 | A | | D | 2 | B | | E | 3 | C | | F | 2 | D, E |
The paths are A-B-D-F = 3 + 4 + 2 + 2 = 11 days and A-C-E-F = 3 + 5 + 3 + 2 = 13 days. Therefore, the project duration is 13 days and the critical path is A-C-E-F. Activity B-D has two days of path slack relative to the critical path. This result assumes the stated dependencies, uninterrupted work, fixed calendars, and unlimited availability of the required resources. CPM is valuable because it reveals schedule sensitivity and supports what-if analysis. Its limitations include deterministic durations, difficulty representing resource constraints, and the risk that managers focus narrowly on the calculated path while ignoring emerging risks and near-critical paths. 5. PERT and Schedule UncertaintyThe Program Evaluation and Review Technique (PERT) models uncertain activity duration using three estimates: optimistic a, most likely m, and pessimistic b. The expected duration is: te = (a + 4m + b) ÷ 6 The commonly used activity variance is: σ² = ((b − a) ÷ 6)² Here, σ² is variance in squared time units. PERT is based on a beta-like approximation and assumes the three estimates are meaningful, the activity’s uncertainty is represented by them, and dependencies are correctly specified. It should not be treated as a guarantee or as proof that project duration is normally distributed. For a path, expected duration is the sum of expected activity durations. If activity durations are treated as independent, path variance is the sum of activity variances: σ²path = ∑σ²i and path standard deviation is σpath = √(σ²path). A rough probability that a path will finish by deadline D can be estimated using a normal approximation: Z = (D − μpath) ÷ σpath where μpath is expected path duration. This approximation becomes unreliable when paths merge, activity durations are strongly correlated, or the critical path changes under uncertainty. Simulation, such as Monte Carlo analysis, is preferable for complex schedules. Suppose an activity has a = 2, m = 5, and b = 8 days. Its expected duration is (2 + 4×5 + 8) ÷ 6 = 5 days, and its variance is ((8 − 2) ÷ 6)2 = 1 day². The estimates are useful only if the optimistic and pessimistic values reflect credible operating conditions rather than arbitrary optimism and pessimism. 6. Time–Cost Trade-offs and CrashingCrashing reduces activity duration by applying additional resources, overtime, alternative methods, or premium suppliers. It should be considered only when the activity lies on the current critical path or when the reduction creates a strategically valuable outcome. Crashing a non-critical activity may produce no project-level benefit. For an activity, the cost slope is: Cost slope = (Crash cost − Normal cost) ÷ (Normal time − Crash time) The units are cost per unit of time saved. The usual procedure is to identify the critical path, select the lowest-cost crashable activity on that path, reduce its duration within feasible limits, recalculate the network, and repeat until the target is met or further crashing is uneconomic or infeasible. Suppose an activity normally takes 10 days and costs $40,000; it can be reduced to 7 days at $52,000. Its cost slope is ($52,000 − $40,000) ÷ (10 − 7) = $4,000 per day saved. This calculation assumes a reasonably linear cost-duration relationship between the stated normal and crash points. In real projects, overtime may create nonlinear costs, rework, fatigue, safety exposure, or quality loss. A rational decision compares incremental crash cost with the value of earlier completion, contractual damages avoided, capacity released, or strategic benefit gained. Crashing should never bypass safety, regulatory approval, testing, or quality acceptance. 7. Resource Allocation and Resource-Constrained SchedulingA time-feasible schedule may be resource-infeasible. If two activities require the same scarce engineer, machine, or specialist at the same time, precedence logic alone does not solve the conflict. Resource management includes capacity planning, skills analysis, procurement, cross-training, leveling, smoothing, subcontracting, and prioritization. Resource smoothing adjusts activities within available float to reduce peaks while preserving the target completion date. Resource leveling resolves over-allocation even when the completion date must move. Managers should distinguish a genuine capacity constraint from a planning assumption that can be changed through hiring, outsourcing, shift design, or technology. Useful heuristics include prioritizing activities with low float, high downstream impact, safety significance, or contractual importance. However, heuristic decisions should be tested against the whole network because locally efficient choices can increase total makespan. Resource-constrained project scheduling is computationally difficult for large networks, so optimization software, simulation, and expert judgment are commonly combined. Resource allocation also has a behavioural dimension. Excessive multitasking increases switching costs, hides delays, and reduces throughput. A focused team with explicit priorities may deliver faster than a nominally larger team whose members are continuously interrupted. 8. Earned-Value ManagementEarned-value management (EVM) integrates scope, schedule, and cost. At a measurement date, three quantities are required: - Planned value (PV): budgeted value of work scheduled to be completed.
- Earned value (EV): budgeted value of work actually completed.
- Actual cost (AC): actual cost incurred for the completed work.
The principal variances and indices are: SV = EV − PV CV = EV − AC SPI = EV ÷ PV CPI = EV ÷ AC Schedule variance SV and cost variance CV are expressed in monetary value, not calendar time. SPI < 1 indicates less earned work than planned at the measurement point, while CPI < 1 indicates cost inefficiency. These indices are dimensionless because the numerator and denominator use the same value units. If BAC is the budget at completion, a simple estimate at completion is: EAC = BAC ÷ CPI This assumes current cost efficiency will continue. Other forecasts may use actual cost plus a revised estimate of remaining work: EAC = AC + ETC where ETC is the estimate to complete. The appropriate formula depends on whether past variance is expected to recur, whether scope has changed, and whether remaining work has been independently re-estimated. Worked EVM exampleAssume PV = $100,000, EV = $90,000, AC = $120,000, and BAC = $300,000. Then: - SV = 90,000 − 100,000 = −$10,000;
- CV = 90,000 − 120,000 = −$30,000;
- SPI = 90,000 ÷ 100,000 = 0.90;
- CPI = 90,000 ÷ 120,000 = 0.75;
- EAC = 300,000 ÷ 0.75 = $400,000.
The project is behind the planned value curve and spending $1.33 for every dollar of budgeted work earned. The forecast is not a certainty; management should investigate scope definition, accounting timing, productivity, procurement, and quality-related rework before accepting it. 9. Predictive, Agile, and Hybrid DeliveryPredictive approaches define substantial scope and sequence before execution. They are appropriate when requirements are stable, interfaces are known, change is costly, and regulatory or contractual evidence is required. Stage gates, design reviews, baselines, and formal change control are prominent. Agile approaches deliver small increments, obtain frequent feedback, and reprioritize a transparent backlog. Scrum, Kanban, and related methods emphasize collaboration, short feedback cycles, visual flow, and adaptation. Agile is not an absence of planning: product goals, release planning, capacity, architecture, quality criteria, and governance remain necessary. A hybrid approach combines predictive and adaptive elements. For example, a pharmaceutical facility may use predictive controls for validation, construction, and regulatory submissions while using agile teams for software configuration and user-interface development. The key question is not whether one method is fashionable, but which elements of scope, uncertainty, risk, and compliance require which control logic. Agile metrics must be interpreted carefully. Velocity is a local planning indicator, not a universal productivity measure. A team should not inflate story points to appear faster. Flow measures such as cycle time, work-in-progress, throughput, and blocked time often provide more useful operational insight. 10. Risk Management and UncertaintyA risk is an uncertain event or condition that may affect objectives positively or negatively. An issue is a condition that has already occurred. Risk management is a continuous process: - Establish context and risk criteria.
- Identify threats and opportunities.
- Analyse probability, impact, proximity, and interdependence.
- Prioritize using qualitative or quantitative methods.
- Select responses.
- Assign owners and trigger indicators.
- Monitor, communicate, and escalate.
Threat responses include avoid, mitigate, transfer, and accept. Opportunity responses include exploit, enhance, share, and accept. Contingency reserves address identified risks, whereas management reserves are held for unforeseen work subject to governance authority. A probability–impact matrix is useful for screening but can create false precision. A risk rated “high” because of a multiplied score may deserve less attention than a low-probability event with catastrophic safety consequences. Quantitative analysis may use expected monetary value: EMV = ∑(pi × impacti) where pi is the probability of outcome i and impacti is its monetary impact. EMV supports portfolio decisions under uncertainty but should not be interpreted as a guaranteed financial result. Safety, legal, human, and reputational impacts should not be reduced to money alone. Risk owners must possess authority and resources. A risk register without actions, triggers, dates, and accountable owners is merely a list. Common risk sources include immature requirements, optimistic estimates, supplier failure, integration defects, cyber threats, labour shortages, regulatory change, weather, stakeholder resistance, and benefits that depend on behaviour after handover. 11. Project Governance, Ethics, and ControlProject governance defines who decides, who is accountable, what information is required, and how exceptions are escalated. A practical governance structure may include a sponsor, project manager, steering committee, product or business owner, technical authority, assurance function, and operational owner. A governance framework should establish: - decision rights and delegated authority;
- approval thresholds for scope, cost, schedule, and risk;
- stage-gate criteria and independent assurance;
- change-control procedures;
- reporting cadence and data definitions;
- procurement and contract controls;
- quality, safety, privacy, and cybersecurity requirements;
- escalation routes and records of decisions;
- transition and benefits ownership.
Ethical project management requires truthful reporting, protection of workers and users, fair procurement, respect for privacy, avoidance of conflicts of interest, and willingness to stop unsafe work. “Green” claims should be supported by evidence, and artificial schedule optimism should not be used to secure authorization. Governance should create psychological safety so that team members can report defects, risks, harassment, or misconduct without retaliation. Digital dashboards and artificial intelligence can support estimating, anomaly detection, document search, schedule risk analysis, resource forecasting, and predictive maintenance. However, data may be incomplete, biased, commercially sensitive, or generated under inconsistent definitions. AI outputs should be explainable enough for the decision context, checked by competent professionals, and governed for privacy, cybersecurity, intellectual property, and accountability. Automation should strengthen—not replace—responsible judgment. 12. Contemporary Practice and Best PracticesProjects increasingly operate in volatile environments characterized by supply disruption, climate exposure, geopolitical uncertainty, distributed teams, and rapid digital change. Useful contemporary practices include modular design, scenario planning, digital twins, integrated planning tools, collaborative contracting, product operating models, and benefits tracking after delivery. Best practice is less about applying every tool than about maintaining coherence among objectives, scope, schedule, resources, risk, and governance. Managers should: - Define the value and acceptance criteria before optimizing the schedule.
- Build the WBS with delivery and operational stakeholders.
- Validate dependencies and resource assumptions with the people doing the work.
- Baseline only a credible plan and record approved changes.
- Monitor leading indicators such as blocked work, unresolved decisions, defect trends, and risk triggers—not only lagging cost data.
- Protect critical-path and near-critical activities while managing resource bottlenecks.
- Use independent estimates and challenge optimism bias.
- Integrate suppliers early where interfaces create system risk.
- Treat safety, quality, cybersecurity, and sustainability as design requirements.
- Close the learning loop by measuring adoption and benefits after handover.
13. Illustrative Case: Regional Hospital Digital-Operations ProjectBackgroundA regional hospital decides to replace paper-based medication administration with an integrated electronic medication-management system. The project includes software configuration, barcode devices, wireless upgrades, pharmacy integration, staff training, data migration, clinical testing, and a controlled launch. ProblemThe hospital initially proposes a six-month deadline. Clinical leaders want rapid implementation, while the information-technology team identifies uncertain interfaces and limited availability of nurses for testing. A supplier offers an accelerated configuration at additional cost, but the safety team warns that insufficient user testing could create medication errors. AnalysisThe project team constructs a deliverable-oriented WBS. The network schedule shows that wireless upgrades, interface testing, clinical validation, and training are linked. Although software configuration has a short nominal duration, interface testing is on the critical path. Resource analysis reveals that the same senior nurses are needed for clinical validation and training development. The team therefore levels the schedule rather than assuming unlimited clinical capacity. A risk workshop identifies risks involving data-quality defects, downtime, user resistance, cyber compromise, supplier delay, and unsafe workarounds. The highest-priority risk is not given a monetary score alone: medication safety requires mandatory clinical acceptance criteria and a go/no-go decision by the clinical governance committee. The project adopts a hybrid model. Predictive controls govern cybersecurity, procurement, validation evidence, and the hospital-wide cutover. Agile teams configure screens and workflows in short iterations with pharmacists and nurses. A pilot ward provides feedback before wider deployment. Approach and solutionThe sponsor approves a revised nine-month plan. The project uses a WBS-linked schedule, weekly risk review, two formal stage gates, a change-control board, and EVM for cost monitoring. The team establishes acceptance criteria: barcode scanning reliability, interface accuracy, response time, training completion, incident thresholds, and downtime procedures. A contingency plan allows rollback to the previous process if safety indicators deteriorate. OutcomeThe pilot launches two weeks later than the original target but meets the revised clinical acceptance criteria. Early EVM reporting identified configuration rework and prevented premature expansion. Post-launch measurement shows improved medication-record completeness and reduced transcription errors, while benefits ownership remains with hospital operations rather than the temporary project team. Learning pointsThe case illustrates that schedule acceleration is not automatically valuable; safety and readiness may dominate calendar objectives. Critical-path analysis must be combined with resource analysis. Hybrid delivery is effective when different work components have different uncertainty and compliance needs. Finally, project success includes safe adoption and benefits realization, not merely technical installation. Challenges and LimitationsProject methods can create an illusion of control. A precise schedule may conceal uncertain estimates; a risk matrix may conceal severe but rare events; and EVM may report favourable performance when scope has been reduced or quality has been deferred. Network models also simplify human relationships, negotiation, learning, and political behaviour. Projects may fail through weak sponsorship, unstable requirements, fragmented accountability, poor integration, unrealistic deadlines, inadequate operational ownership, or incentives that reward reporting good news rather than solving problems. Standard methods must therefore be adapted to organizational maturity, industry regulation, project complexity, and stakeholder capability. Methodological discipline is valuable, but professional judgment remains indispensable. Chapter SummaryProject and temporary operations management coordinates unique, time-bounded work under constraints while protecting value, quality, safety, and stakeholder interests. The WBS defines complete scope through deliverables and work packages. Network scheduling and CPM identify precedence, earliest and latest times, float, and critical paths. PERT incorporates duration uncertainty, while crashing evaluates the cost of reducing activity durations. Resource allocation recognizes that a logically feasible schedule may be impossible with available people or equipment. Earned-value management integrates scope, cost, and schedule through PV, EV, AC, variances, performance indices, and forecasts. Predictive, agile, and hybrid approaches should be selected according to uncertainty, compliance, interfaces, and the cost of change. Risk management requires active owners, response strategies, triggers, and escalation, not merely a register. Governance establishes authority, assurance, change control, ethical conduct, and benefits accountability. Contemporary project leadership combines analytical tools with transparency, safety, learning, stakeholder engagement, and responsible use of digital and AI technologies. Key TermsProject: A temporary endeavour undertaken to create a unique deliverable, service, or result. Temporary operation: A short-lived operating system designed to deliver a service or capability. Programme: Related projects and activities managed together to realize broader benefits. Portfolio: Projects, programmes, and operational investments aligned with strategy. Work breakdown structure: Hierarchical decomposition of total project scope. Work package: The lowest manageable WBS component with defined scope, owner, and estimate. Network diagram: Graphical representation of activity dependencies. Critical path: The longest-duration path through a schedule network, determining minimum project duration under stated assumptions. Float: Time an activity may be delayed without violating a defined schedule constraint. PERT: A technique using optimistic, most-likely, and pessimistic duration estimates. Crashing: Shortening activity duration by applying additional or more costly resources. Resource leveling: Adjusting a schedule to resolve resource over-allocation, potentially changing completion date. Planned value: Budgeted value of work scheduled by a measurement date. Earned value: Budgeted value of work actually completed by a measurement date. Actual cost: Cost incurred for completed work. Risk: An uncertain event or condition that can affect objectives. Issue: A problem or condition that has already occurred. Hybrid delivery: Combination of predictive and adaptive management practices. Stage gate: Formal decision point at which continuation, revision, or termination is considered. Project governance: Framework of authority, accountability, controls, and decision processes. Review QuestionsShort Answer Questions- What distinguishes a project from repetitive operations?
- Explain the 100-percent rule in a work breakdown structure.
- Define total float and explain its relationship to the critical path.
- What are planned value, earned value, and actual cost?
- Distinguish a project risk from a project issue.
Long Answer Questions- Explain how a WBS, responsibility assignment matrix, schedule, cost plan, and risk register should be integrated.
- Describe the CPM forward-pass and backward-pass calculations and discuss their assumptions.
- Compare predictive, agile, and hybrid delivery approaches, including circumstances in which each is appropriate.
- Explain how governance and ethics influence project performance beyond the iron triangle.
- Discuss the strengths and limitations of earned-value management as a project-control method.
Analytical / Application Questions- A project contains two paths: A–B–D–F with durations 3, 4, 2, and 2 days, and A–C–E–F with durations 3, 5, 3, and 2 days. Identify the critical path and explain the effect of reducing activity B by one day.
- A project has PV = $160,000, EV = $144,000, and AC = $180,000. Calculate SV, CV, SPI, and CPI, then interpret the results.
- Design a hybrid delivery and governance model for a regulated organization implementing a customer-facing digital service with uncertain user requirements and strict cybersecurity obligations.
Multiple Choice Questions with AnswersQuestion 1Which statement best describes a work breakdown structure? A. A hierarchy of the total project scope into manageable deliverables and work packages B. A list of employees ranked by organizational seniority C. A financial statement showing project profitability D. A register containing only project risks Correct Answer: A. A hierarchy of the total project scope into manageable deliverables and work packages Question 2For an activity with ES = 6 days and duration = 4 days, what is its earliest finish? A. 2 days B. 6 days C. 10 days D. 24 days Correct Answer: C. 10 days Question 3Which activities form the critical path in the worked network example in the chapter? A. A–B–D–F B. A–C–E–F C. B–C–D–E D. A–B–C–F Correct Answer: B. A–C–E–F Question 4Using PERT, if a = 2, m = 5, and b = 8 days, what is the expected activity duration? A. 3 days B. 4 days C. 5 days D. 8 days Correct Answer: C. 5 days Question 5An activity has a normal cost of $40,000 for 10 days and a crash cost of $52,000 for 7 days. What is its cost slope? A. $1,200 per day B. $3,000 per day C. $4,000 per day D. $12,000 per day Correct Answer: C. $4,000 per day Question 6Which action is most characteristic of resource smoothing? A. Moving activities within available float to reduce resource peaks B. Ignoring resource constraints until project closure C. Reducing all activity durations simultaneously D. Changing the project objective without approval Correct Answer: A. Moving activities within available float to reduce resource peaks Question 7If EV = $90,000 and AC = $120,000, what is the cost performance index? A. 0.75 B. 0.90 C. 1.20 D. 1.33 Correct Answer: A. 0.75 Question 8Which response is appropriate for a project threat? A. Exploit B. Enhance C. Transfer D. Share Correct Answer: C. Transfer Question 9What is a defining characteristic of a hybrid delivery approach? A. It prohibits formal governance B. It combines predictive and adaptive practices according to the work context C. It requires all requirements to remain unknown D. It eliminates the need for acceptance criteria Correct Answer: B. It combines predictive and adaptive practices according to the work context Question 10Which statement about schedule variance in earned-value management is correct? A. It is calculated as AC − EV and is always expressed in calendar days B. It is calculated as EV − PV and is expressed in value units C. It is calculated as PV − AC and measures quality defects D. It is calculated as EV ÷ AC and is dimensionless Correct Answer: B. It is calculated as EV − PV and is expressed in value units
|