Introduction and Context

Procurement creates value not simply by obtaining a low price, but by securing the right total commercial outcome: appropriate quality, reliable delivery, manageable risk, acceptable service, and legally enforceable obligations. Negotiation, contracting, and purchase execution connect the organisation’s sourcing decision with the physical and financial flow of goods and services.

A procurement professional must therefore perform three related tasks. First, the professional prepares and conducts negotiations with suppliers. Second, the negotiated understanding is converted into a clear contract or purchase order. Third, the order is monitored, changed where necessary, and closed in a controlled manner. Weakness in any one of these stages can lead to excessive cost, delivery failure, disputes, fraud, or operational disruption.

This chapter presents a practical foundation for diploma-level procurement students. It addresses negotiation preparation, commercial terms, Incoterms, warranties, service-level agreements, basic contract law, purchase-order execution, contract changes, ethical conduct, and technology-enabled control.

Learning Objectives

After studying this chapter, you should be able to:

  1. Prepare a negotiation strategy based on requirements, supplier information, and risk.
  2. Explain price, payment, delivery, warranty, Incoterms, and service-level provisions.
  3. Distinguish a contract from a purchase order and identify basic elements of enforceability.
  4. Execute a purchase order through acknowledgement, delivery, inspection, receipt, and payment.
  5. Control contract amendments, claims, variations, and close-out activities.
  6. Apply ethical, legal, and governance principles to supplier negotiations and contracting.

1. Procurement Negotiation as a Value-Creation Process

Negotiation is a structured process through which parties seek agreement on matters such as price, quantity, quality, delivery, payment, risk allocation, and future cooperation. It is not necessarily adversarial. A successful negotiation produces an agreement that both parties can perform and that supports the buying organisation’s objectives.

The purchasing organisation normally has several objectives:

  • continuity of supply;
  • acceptable total cost of ownership;
  • conformance to specifications;
  • delivery reliability;
  • protection against operational, legal, financial, and reputational risks;
  • flexibility when demand or technology changes; and
  • a fair and sustainable supplier relationship.

The supplier also has objectives, including a profitable price, predictable demand, prompt payment, reasonable liability, and protection of intellectual property. Understanding these interests helps the buyer identify trades rather than treating price as the only negotiable issue.

Position, interest, and issue

A position is what a party says it wants, such as “the price must be $100 per unit.” An interest is the reason behind that position, such as the supplier’s need to recover a special tooling investment. An issue is a matter to be resolved, such as unit price, tooling ownership, or order quantity. Exploring interests can reveal alternative solutions—for example, a lower unit price in return for a longer commitment or a scheduled volume.

Distributive and integrative negotiation

In distributive negotiation, parties divide a limited value, often focusing on price. A concession by one party appears to benefit the other. Integrative negotiation seeks to expand value by trading across issues. For example, a buyer may offer forecast visibility and faster invoice approval in exchange for improved lead time and a stronger warranty. Most professional procurement negotiations contain both distributive and integrative elements.

2. Preparing for a Supplier Negotiation

Preparation is usually more influential than conversational skill. A negotiation file should contain the following information:

  1. Requirement definition: specification, quantity, quality standards, delivery location, required date, and expected service.
  2. Market intelligence: alternative suppliers, capacity, commodity trends, technology, and switching costs.
  3. Supplier analysis: financial condition, performance history, capabilities, dependencies, and risk profile.
  4. Cost information: quoted price, freight, duties, taxes, inspection, inventory, installation, maintenance, and disposal implications.
  5. Authority limits: approved budget, delegation of authority, and matters requiring legal or management approval.
  6. Negotiation plan: objectives, priorities, concessions, questions, participants, and walk-away conditions.

Targets, reservation points, and alternatives

A target is the preferred outcome. A reservation point is the least acceptable outcome for the buyer. The reservation point should be based on the value of the best available alternative, commonly called the BATNA—best alternative to a negotiated agreement. If a buyer has a qualified alternative supplier, its bargaining position is usually stronger than if no alternative exists.

The reservation point should not be disclosed casually. However, the buyer should understand it internally so that negotiators do not accept a deal that is worse than an available alternative.

Total cost rather than quoted price

A quoted unit price may exclude freight, insurance, duties, installation, inspection, maintenance, energy, and disposal. A basic total-cost model is:

TCO = P + F + I + D + Q + O + M + E + X − V

Where:

  • TCO = estimated total cost of ownership, in currency;
  • P = purchase price;
  • F = freight and transport cost;
  • I = insurance cost;
  • D = duties and non-recoverable taxes;
  • Q = quality, inspection, and testing cost;
  • O = ordering, receiving, and administration cost;
  • M = maintenance and support cost;
  • E = operating or energy cost; and
  • X = end-of-life, disposal, or switching cost;
  • V = residual or recovery value.

The formula is a planning model, not an accounting standard. It applies when the listed cost components can be estimated consistently and when alternatives are compared over the same period, volume, currency, and tax basis. If costs occur at different times, a discounted cash-flow method may be more appropriate.

Worked example. Supplier A quotes $48,000. Freight is $2,000, insurance $300, duties $1,700, inspection $500, maintenance $6,000, and disposal cost $1,000. There is no residual value. The estimated total cost is:

TCO = 48,000 + 2,000 + 300 + 1,700 + 500 + 6,000 + 1,000 = $59,500

A supplier quoting $50,000 may therefore be economically preferable if its comparable total cost is lower.

Negotiation agenda and concession planning

A practical agenda may proceed as follows:

  1. confirm participants, authority, and objectives;
  2. establish shared understanding of the requirement;
  3. discuss quality, capacity, and delivery capability;
  4. explore cost drivers and commercial assumptions;
  5. negotiate price and payment;
  6. negotiate risk, warranty, liability, and performance remedies;
  7. record open points and responsibilities; and
  8. confirm the next approval and documentation steps.

Concessions should be conditional rather than automatic. “If the supplier provides a 24-month warranty, the buyer can consider a longer forecast commitment” is stronger than an unexplained price concession. Every concession should be recorded, valued, and exchanged for something meaningful.

3. Commercial Terms and Pricing Structures

Fixed price

A fixed-price contract establishes a price for defined goods or services. It gives the buyer budget certainty but may lead suppliers to include risk premiums. The contract should state whether the price includes packaging, freight, taxes, installation, testing, and other charges.

Cost-reimbursable pricing

Under a cost-reimbursable arrangement, the buyer pays allowable costs plus an agreed fee or margin. This can suit uncertain development work but requires strong cost verification, audit rights, and controls against unnecessary expenditure.

Time and materials

Time-and-materials contracts pay agreed rates for labour and actual or agreed material charges. They are useful when scope cannot be fully defined, but they require approval limits, time-sheet controls, and a ceiling or review mechanism.

Escalation and indexation

Long-term contracts may allow price adjustment for defined changes in labour, materials, energy, or exchange rates. An escalation clause should identify:

  • the reference index and publication source;
  • the base date;
  • the review frequency;
  • the portion of price subject to adjustment;
  • the calculation method;
  • any cap, floor, or notice requirement; and
  • treatment when the index is discontinued.

Ambiguous escalation language creates disputes. A buyer should not accept an unrestricted right to increase prices merely because a supplier’s costs have changed.

Payment terms

Payment clauses should state the invoice requirements, currency, due date, tax treatment, bank charges, retention, advance-payment conditions, and dispute process. A common control is three-way matching: the purchase order, receiving record, and supplier invoice must agree before payment is released. Exceptions should be authorised and documented.

4. Delivery Terms and Incoterms

Incoterms® are standardised international commercial terms published by the International Chamber of Commerce. They allocate specified responsibilities, costs, and risks between seller and buyer. They do not by themselves determine ownership transfer, payment, product specifications, warranty, governing law, or dispute resolution.

An Incoterm should be written with the named place and version, for example, “CIP Nairobi, Incoterms® 2020.” The named place matters because it determines where delivery, cost, or risk obligations operate.

Term or groupGeneral implicationBuyer’s main concern
EXWBuyer takes extensive responsibility from the seller’s premisesExport clearance and loading responsibilities may be unsuitable for an inexperienced buyer
FCASeller delivers to the agreed carrier or place and handles export formalitiesThe exact delivery point must be specified
CPT/CIPSeller pays carriage; under CIP the seller also arranges insurance to the required levelRisk may transfer earlier than arrival
DAPSeller delivers to the named destination, generally ready for unloadingBuyer normally handles import clearance and duties
DPUSeller delivers and unloads at the named destinationDestination must be operationally suitable
DDPSeller bears extensive delivery responsibility, including import clearance in principleLocal legal and tax capability must be verified
FOB/CFR/CIFMaritime terms for appropriate port-to-port shipmentsThey should not be used indiscriminately for containerised or multimodal transport

A frequent mistake is assuming that the party paying for transport also bears transit risk until arrival. Under many terms, cost and risk transfer at different points. Procurement staff must read the relevant Incoterm together with the contract’s insurance, claims, and delivery provisions.

5. Contract Formation and Basic Contract Law

Specific legal rules vary by jurisdiction, and legal advice should be obtained for material or unusual contracts. Nevertheless, most contracts require recognisable elements such as:

  • offer or proposal;
  • acceptance;
  • consideration or exchange of value, where required by applicable law;
  • intention to create legal relations;
  • capacity and authority of the parties;
  • certainty of important terms; and
  • legality of purpose.

A written contract reduces uncertainty but does not automatically make poor terms enforceable or fair. The buyer must know which document controls when terms conflict. A typical order of precedence might be: signed agreement, negotiated statement of work, purchase order, and supplier quotation—but the organisation’s approved terms should specify the actual hierarchy.

Purchase order and contract

A purchase order (PO) is a formal instruction to buy specified goods or services. It commonly contains supplier, item, quantity, price, delivery date, ship-to address, tax information, terms, and approval details. A PO may itself form a contract when properly issued and accepted, or it may operate under a framework or master agreement. Its legal effect depends on applicable law, the parties’ conduct, and the documents exchanged.

A requisition is an internal request for procurement; it is not normally an offer to the supplier. A quotation is a supplier’s commercial proposal, although its legal status varies. A contract is the legally binding arrangement created by the applicable documents and conduct.

Essential drafting principles

Good contract drafting is:

  • specific: quantities, standards, dates, locations, and responsibilities are measurable;
  • consistent: terms do not conflict across the specification, quotation, PO, and agreement;
  • complete: assumptions, exceptions, and dependencies are addressed;
  • balanced: risk is allocated to the party best able to control it; and
  • operational: users can understand how to administer the obligation.

Important clauses may include scope and specifications, price, delivery, inspection, acceptance, payment, warranty, intellectual property, confidentiality, data protection, insurance, liability, indemnity, termination, force majeure, dispute resolution, governing law, audit, anti-bribery, sanctions, and subcontracting.

6. Warranties, Acceptance, and Remedies

A warranty is a contractual assurance concerning quality, performance, condition, or conformity. It should state:

  • the warranty period and when it begins;
  • what is covered and excluded;
  • the buyer’s notice procedure;
  • the supplier’s remedy, such as repair, replacement, refund, or re-performance;
  • response and resolution times; and
  • treatment of repaired or replaced items.

Warranty protection is meaningful only if the buyer can demonstrate the defect, preserve evidence, and notify the supplier within the required period. Receiving goods without objection does not necessarily mean the buyer has waived latent-defect rights, but the legal effect depends on the contract and governing law.

Acceptance should be linked to objective tests or documents. A buyer may accept goods after inspection, after successful commissioning, or automatically after a defined period unless defects are notified. The contract should distinguish delivery from acceptance: delivery is physical or contractual tender; acceptance is confirmation that the goods or service meet agreed requirements.

Possible remedies include repair, replacement, re-performance, price reduction, service credits, liquidated damages where legally valid, termination, and damages. Remedies should be proportionate and drafted carefully. A liquidated-damages amount intended as a genuine pre-estimate of loss may be treated differently from a punitive penalty, depending on jurisdiction.

7. Service-Level Agreements

A service-level agreement (SLA) defines measurable service commitments and the method for monitoring them. It is especially important for logistics, maintenance, information technology, facilities, and outsourced operations.

An effective SLA identifies:

  1. service scope and service hours;
  2. definitions of incidents, response, restoration, and resolution;
  3. performance indicators and measurement method;
  4. target and minimum performance levels;
  5. exclusions and customer dependencies;
  6. reporting frequency and data ownership;
  7. escalation contacts and review meetings; and
  8. remedies, service credits, corrective action, or termination rights.

For example, “high availability” is weak unless the contract defines the measurement period, planned-maintenance exclusions, downtime calculation, and evidence source. A service credit should not be treated as the only remedy where failure could create safety, regulatory, or major operational consequences.

8. Purchase-Order Execution

After approval and supplier selection, execution should follow a controlled sequence:

  1. confirm budget, authority, supplier status, and required approvals;
  2. convert the approved requirement into an accurate PO;
  3. issue the PO through an authorised channel;
  4. obtain supplier acknowledgement, including exceptions;
  5. monitor production, dispatch, transport, and required documents;
  6. receive and inspect the goods or verify service completion;
  7. record receipt, discrepancies, and acceptance status;
  8. match the invoice to the PO and receipt;
  9. resolve claims, shortages, or defects; and
  10. close the order and retain records according to policy.

The supplier’s acknowledgement is important. If it changes quantity, price, delivery, or terms, the buyer should treat the response as a proposed amendment rather than silently accepting it. Informal instructions by email or telephone can create uncontrolled commitments. Changes should be issued by authorised personnel and linked to the original PO.

Receiving and discrepancy control

Receiving staff should check quantity, packaging damage, identification, documents, and visible conformity. Inspection may be sampling-based or 100 percent, depending on risk. A discrepancy report should identify the PO, item, quantity affected, evidence, date, and requested corrective action. Photographs, test results, transport records, and signed delivery documents can be important in claims.

9. Managing Contract Changes

Changes are common because demand, specifications, regulations, technology, and supplier capability can change. A controlled change process prevents scope creep and disputes.

A change request should describe:

  • the proposed change and its reason;
  • impact on price, delivery, quality, risk, and resources;
  • effect on existing milestones and dependencies;
  • revised documents or specifications;
  • required approvals; and
  • implementation date.

A useful principle is no work before authorised change. If urgent action is required, the emergency authority and retrospective documentation process should be clear.

A change order should identify the original contract, the exact clauses amended, the revised commercial terms, and the terms that remain unchanged. The parties should also update forecasts, budgets, schedules, risk registers, and performance measures. Repeated small changes may indicate that the original scope was poorly defined or that a supplier is using variations to recover an inadequate price.

10. Applied Case: Emergency Packaging Procurement

Background

This illustrative case concerns FreshFields Foods, a regional food manufacturer. Its main packaging supplier suffered a production failure six weeks before a seasonal demand peak. The buyer needed 200,000 printed cartons within four weeks. The normal supplier could provide only 80,000.

Problem

The emergency supplier quoted a lower unit price than the normal supplier but proposed EXW terms, a 30 percent advance payment, no confirmed artwork approval process, and a 30-day warranty. The buyer’s production schedule required delivery to the factory, conformity to food-contact packaging standards, and replacement of defective cartons within five working days.

Analysis

The procurement team identified the following risks:

  • transport and export responsibilities under EXW;
  • quality and artwork errors;
  • financial exposure from the advance payment;
  • insufficient warranty coverage;
  • inability to recover production losses; and
  • pressure to bypass approval controls.

The team calculated comparable total cost rather than comparing unit prices. It obtained freight quotations, checked the supplier’s certifications, and contacted two alternative printers. It also separated urgent quantity from the remaining forecast so that the organisation would not make an unnecessary long-term commitment.

Approach and solution

The buyer negotiated FCA at the supplier’s loading location, with the supplier responsible for export clearance and the buyer arranging main carriage. Payment was changed to 10 percent advance, 80 percent after inspection and dispatch, and 10 percent after accepted delivery. The contract required a signed artwork proof, a pre-production sample, food-contact documentation, inspection rights, and replacement of non-conforming cartons within five working days. A service measure required at least 98 percent accepted quantity by the confirmed delivery date, with corrective action for failure.

The PO referred to the approved specification, identified the exact named place, stated Incoterms® 2020, and included an order-of-precedence clause. The buyer obtained management and quality approvals before release.

Outcome

The emergency quantity arrived three days later than planned, but production continued because the buyer used existing stock to bridge the delay. Inspection found a small colour variation in one batch; the supplier replaced the affected cartons within the agreed period. The organisation paid more for transport than initially estimated but avoided an unplanned production shutdown.

Learning points

  1. A low unit price does not establish a low total cost.
  2. Incoterms must be selected with operational capability in mind.
  3. Quality, artwork, and acceptance terms are essential for printed materials.
  4. Payment should reflect performance and risk, especially during emergencies.
  5. Speed does not eliminate the need for authority, documentation, and segregation of duties.

11. Ethics, Governance, and Regulatory Considerations

Negotiators must avoid bribery, undisclosed conflicts of interest, collusion, discrimination, and misuse of confidential supplier information. Gifts and hospitality should be handled under organisational policy. A buyer must not disclose one supplier’s confidential quotation to another without permission, even if doing so might create a lower price.

Core governance controls include:

  • segregation between requesting, approving, ordering, receiving, and paying roles;
  • documented evaluation criteria;
  • competitive bidding or a justified exception;
  • approval thresholds;
  • supplier due diligence;
  • conflict-of-interest declarations;
  • audit trails for changes; and
  • retention of contracts, quotations, approvals, receipts, and correspondence.

Regulatory requirements may include public procurement rules, competition law, sanctions and export controls, modern-slavery obligations, environmental requirements, data protection, product safety, and tax regulations. The buyer should identify which rules apply before solicitation and should obtain specialist advice for cross-border or high-value transactions.

12. Technology and Contemporary Practice

E-procurement systems can connect requisitions, approvals, sourcing events, purchase orders, receipts, invoices, and supplier performance records. Electronic catalogues and guided buying reduce maverick spending. Digital signatures and contract repositories improve version control, while dashboards can monitor delivery, quality, invoice exceptions, and SLA performance.

Artificial intelligence can assist with clause comparison, spend classification, supplier-risk screening, and anomaly detection. However, AI outputs require human review. Risks include inaccurate summaries, biased supplier evaluation, exposure of confidential information, and unexplained recommendations. Organisations should define approved data sources, access controls, auditability, and human approval requirements.

Contemporary procurement also places greater emphasis on resilience, sustainability, cyber risk, and responsible sourcing. Contracts increasingly include carbon reporting, recycled-content requirements, business-continuity plans, cybersecurity controls, and rights to audit supply-chain practices. These provisions are useful only when they are measurable, proportionate, and monitored.

13. Challenges and Limitations

Procurement professionals face several recurring difficulties:

  • incomplete specifications create ambiguity and variations;
  • excessive focus on price can damage quality and resilience;
  • unequal bargaining power can produce impractical obligations;
  • international transactions create currency, transport, tax, and legal complexity;
  • performance data may be incomplete or manipulated;
  • urgent purchases can weaken competition and segregation of duties; and
  • contract language may be legally sound but operationally difficult to administer.

No contract can remove all uncertainty. Good procurement combines careful drafting with supplier relationship management, performance monitoring, contingency planning, and timely escalation.

Chapter Summary

Negotiation, contracting, and purchase execution form one connected procurement process. Effective negotiation begins with a clear requirement, market knowledge, supplier analysis, total-cost evaluation, targets, reservation points, and a credible alternative. Professional negotiators trade across price, delivery, quality, payment, warranty, flexibility, and risk rather than pursuing price alone.

Commercial terms must be documented precisely. Incoterms allocate defined delivery responsibilities, costs, and risks but do not replace clauses on ownership, payment, warranty, governing law, or dispute resolution. Contracts and purchase orders should contain clear scope, price, delivery, acceptance, payment, remedies, change, and termination provisions. Warranties and SLAs are useful only when performance, measurement, evidence, and remedies are defined.

Purchase execution requires authorised issue, supplier acknowledgement, delivery monitoring, inspection, receiving, three-way matching, discrepancy management, and close-out. Contract changes should be documented, approved, priced, and implemented before work proceeds. Ethical conduct, segregation of duties, auditability, legal compliance, and responsible use of technology protect both the organisation and its suppliers.

Key Terms

Negotiation: A process through which parties seek agreement on commercial and operational matters.

BATNA: Best alternative to a negotiated agreement.

Reservation point: The least acceptable outcome a party will accept.

Total cost of ownership: The purchase and lifecycle costs associated with acquiring, using, and disposing of an item or service.

Fixed-price contract: A contract with a stated price for a defined scope.

Cost-reimbursable contract: A contract under which allowable costs are reimbursed, usually with an agreed fee.

Incoterms®: Internationally standardised trade terms allocating specified delivery responsibilities, costs, and risks.

Purchase order: An authorised document instructing a supplier to provide specified goods or services.

Requisition: An internal request to obtain goods or services.

Acceptance: Confirmation that delivered goods or services meet agreed requirements.

Warranty: A contractual assurance concerning quality, condition, or performance.

Service-level agreement: A document defining measurable service obligations and remedies.

Three-way match: Comparison of the purchase order, receipt record, and supplier invoice.

Variation: An authorised change to contractual scope, price, time, or other terms.

Liquidated damages: A pre-agreed financial remedy for specified breach, subject to applicable law.

Force majeure: A contractual provision addressing specified events beyond a party’s reasonable control.

Order of precedence: The rule identifying which document controls if contract documents conflict.

Maverick spending: Purchasing conducted outside approved procurement processes or contracts.

Review Questions

Short Answer Questions

  1. What is the difference between a negotiation position and an underlying interest?
  2. Why should a buyer compare total cost rather than unit price alone?
  3. What information should be included when citing an Incoterm?
  4. What is the purpose of three-way matching?
  5. Identify four elements that should appear in an effective service-level agreement.

Long Answer Questions

  1. Explain how a procurement professional should prepare for a supplier negotiation, including targets, reservation points, alternatives, and concession planning.
  2. Compare fixed-price, cost-reimbursable, and time-and-materials contracts. State an appropriate application and major control for each.
  3. Explain the distinction between delivery and acceptance and discuss how warranty and remedy clauses should support both.
  4. Describe the complete purchase-order execution process from internal approval through contract close-out.
  5. Discuss the governance and ethical controls required for emergency procurement.

Analytical / Application Questions

  1. A supplier offers a lower unit price under EXW terms, while another offers a higher price under DAP terms. What information should the buyer collect before selecting an option?
  2. A supplier acknowledges a PO but changes the delivery date and payment terms in its email. How should the buyer respond, and why?
  3. A service provider reports 99 percent availability, but users experience repeated outages during business hours. Analyse what may be wrong with the SLA and propose improvements.

Multiple Choice Questions with Answers

Question 1

Which item is most directly associated with a buyer’s BATNA?

A. The supplier’s invoice format

B. The buyer’s best alternative if no agreement is reached

C. The legal name of the supplier

D. The inspection sampling percentage

Correct Answer: B. The buyer’s best alternative if no agreement is reached

Question 2

Which cost is normally included in a total-cost-of-ownership comparison?

A. Only the quoted unit price

B. Only the supplier’s profit margin

C. Maintenance and disposal costs

D. The buyer’s unrelated office expenses

Correct Answer: C. Maintenance and disposal costs

Question 3

What does an Incoterm primarily allocate?

A. Product ownership in every circumstance

B. Responsibilities, costs, and specified risks in delivery

C. The supplier’s profit margin

D. The governing law of every contract

Correct Answer: B. Responsibilities, costs, and specified risks in delivery

Question 4

Under three-way matching, which records are compared?

A. Quotation, bank statement, and tax return

B. Purchase order, receipt record, and invoice

C. Contract, employee timesheet, and budget

D. Supplier catalogue, forecast, and insurance policy

Correct Answer: B. Purchase order, receipt record, and invoice

Question 5

Which is the strongest example of a conditional concession?

A. The buyer immediately reduces its price requirement

B. The buyer gives a concession without recording it

C. The buyer offers a longer forecast in exchange for shorter lead time

D. The buyer ends the negotiation without discussion

Correct Answer: C. The buyer offers a longer forecast in exchange for shorter lead time

Question 6

What should a warranty clause normally specify?

A. Only the supplier’s company history

B. The warranty period, coverage, notice process, and remedy

C. The buyer’s unrelated future purchases

D. The names of all competing suppliers

Correct Answer: B. The warranty period, coverage, notice process, and remedy

Question 7

What is the main purpose of an order-of-precedence clause?

A. To determine which document controls if terms conflict

B. To calculate customs duty automatically

C. To replace inspection procedures

D. To eliminate the need for supplier acknowledgement

Correct Answer: A. To determine which document controls if terms conflict

Question 8

Which action best controls a contract change?

A. Allowing the supplier to begin work on an informal request

B. Approving and documenting the change’s scope, cost, and schedule impact

C. Deleting the original purchase order

D. Ignoring changes below a chosen monetary amount

Correct Answer: B. Approving and documenting the change’s scope, cost, and schedule impact

Question 9

Which statement about Incoterms is correct?

A. They automatically determine governing law

B. They always transfer risk when the goods arrive at the buyer’s site

C. They do not by themselves settle every issue such as warranty or payment

D. They are used only for domestic employment contracts

Correct Answer: C. They do not by themselves settle every issue such as warranty or payment

Question 10

Which control most directly supports segregation of duties?

A. Allowing one person to request, approve, receive, and pay for an order

B. Separating requesting, approving, receiving, and payment responsibilities

C. Removing all approval thresholds

D. Accepting invoices without receipt evidence

Correct Answer: B. Separating requesting, approving, receiving, and payment responsibilities