Construction Method Selection and Integrated Project ApplicationIntroductionConstruction method selection is the disciplined process of choosing the most suitable way to plan, produce, assemble and control a constructed facility. It is not simply a choice between traditional and modern construction. It involves matching a construction system to the project’s geometry, function, site, resources, programme, budget, quality requirements, environmental objectives and risk profile. A technically attractive method may be unsuitable because it requires unavailable equipment. A low-cost method may create unacceptable safety exposure or delay. Similarly, a rapid prefabricated system may fail when transport restrictions, tolerances or design changes have not been adequately controlled. The professional task is therefore to compare alternatives systematically and convert the preferred alternative into an integrated construction proposal. This chapter presents a practical framework for method selection at diploma level. It combines constructability review, productivity analysis, cost and schedule evaluation, quality assurance, safety, sustainability, risk management, technical drawings, data interpretation and professional reporting. Learning ObjectivesAfter studying this chapter, a student should be able to: - Explain the purpose and stages of construction method selection.
- Compare conventional, mechanised, prefabricated and hybrid construction methods.
- Apply constructability, productivity, cost, schedule, quality, safety, sustainability and risk criteria.
- Prepare a basic method-selection matrix using weighted criteria.
- Develop a realistic sequence, resource plan and quality-control approach.
- Interpret technical drawings and site data when proposing a construction method.
- Present an integrated construction proposal in a professional format.
- Recognise the limitations, ethical duties and uncertainties associated with method-selection decisions.
1. Construction Method Selection as a Professional DecisionA construction method is the organised procedure by which work is performed. It includes labour, plant, materials, temporary works, logistics, sequencing, inspection and control activities. A construction method statement describes how a particular activity will be undertaken safely and correctly; a construction method-selection study determines which overall approach is most appropriate. Method selection commonly occurs at several levels: - Project level: traditional construction, modular construction, precast concrete, steel framing or a hybrid system.
- Element level: cast-in-place slab versus precast slab; brick masonry versus blockwork; tower crane versus mobile crane.
- Activity level: manual excavation versus excavator-based excavation; conventional formwork versus flying formwork.
- Process level: alternative procurement, logistics, inspection or digital-control procedures.
The decision should be based on project requirements rather than personal preference. Important inputs include architectural and structural drawings, specifications, geotechnical information, site restrictions, programme milestones, labour availability, supplier capacity, statutory requirements and client priorities. 1.1 The decision hierarchyA sound decision follows a hierarchy: - Mandatory requirements: legal compliance, structural adequacy, fire performance, access, environmental permits and client constraints.
- Feasible alternatives: methods that can actually be built with available technology, resources and site access.
- Comparative assessment: evaluation against cost, time, quality, safety, sustainability and risk.
- Integration: development of drawings, sequence, resources, controls and responsibilities.
- Verification: review by competent personnel and revision as project information changes.
A low score in a desirable category must not compensate for failure in a mandatory requirement. For example, a method cannot be selected because it is cheap if it violates a safety regulation or cannot satisfy structural design requirements. 2. Main Construction Method Families2.1 Conventional or in-situ constructionConventional construction uses materials and components assembled largely on site. Reinforced-concrete buildings may use site-built reinforcement, formwork and concrete placement, while masonry walls are constructed progressively. Advantages include flexibility, widespread familiarity, relatively low dependence on specialised suppliers and suitability for irregular geometry. Limitations include greater site labour, exposure to weather, variable workmanship, material storage and potentially longer duration. 2.2 Mechanised constructionMechanised construction uses equipment to increase output or reduce manual handling. Examples include excavators, concrete pumps, tower cranes, automated rebar cutting and mechanical lifting systems. Mechanisation is advantageous when work quantities are large, repetitive and accessible. It may be uneconomic for small quantities because of mobilisation, fuel, maintenance and operator costs. Equipment selection must consider capacity, reach, ground bearing, access, interference and backup arrangements. 2.3 Prefabricated and off-site constructionPrefabrication transfers part of production from the site to a controlled factory or yard. Components may include precast beams, columns, wall panels, bathroom pods, reinforcement cages and modular rooms. Potential benefits include improved production control, reduced site labour, shorter installation time, less waste and reduced exposure to weather. Risks include transport damage, lifting constraints, dimensional tolerances, supplier dependency, early design freeze and complex interfaces between components. 2.4 Steel and dry constructionSteel framing and dry-wall systems can reduce wet trades and provide rapid erection. They are particularly useful where lightweight construction, long spans or future adaptability is important. Fire protection, corrosion protection, acoustic performance, connection detailing and supply-chain reliability require careful control. 2.5 Hybrid constructionA hybrid method combines systems, such as a reinforced-concrete core with steel framing, precast floors with cast-in-place connections, or conventional foundations with modular upper floors. Hybrid systems can balance flexibility and speed but create interface risks. Responsibility for tolerances, waterproofing, fire stopping and load transfer must be clearly assigned. 3. Constructability ReviewConstructability is the extent to which a design permits efficient, safe and high-quality construction using available resources. Constructability review should begin before site work and continue through design development. A review asks: - Can materials and equipment reach the work area?
- Can workers safely install, inspect and maintain the work?
- Are dimensions, tolerances and connection details buildable?
- Is there adequate space for storage, temporary works and access?
- Can work be sequenced without rehandling or obstruction?
- Are design interfaces coordinated?
- Can completed work be protected from damage?
- Are inspection and testing requirements practical?
A constructability register is useful. Each issue should identify the drawing or specification reference, proposed action, responsible person, required date and residual risk. Examples include insufficient crane access, reinforcement congestion, uncoordinated service openings and a façade detail that cannot be safely installed from the proposed access system. 3.1 Drawing and data requirementsMethod selection should use, at minimum: - site location and access plan;
- architectural plans, elevations and sections;
- structural framing and foundation drawings;
- utility and service information;
- geotechnical and groundwater data;
- project specifications and quality requirements;
- quantities and schedule constraints;
- labour, plant and supplier information; and
- applicable legislation, codes and permits.
Drawings must be read as a coordinated set. A foundation method based only on an architectural plan may overlook groundwater, existing services or structural loads. Revision status is essential: a method based on superseded information can produce costly rework. 4. Evaluation Criteria and Decision Models4.1 Mandatory screeningBefore scoring alternatives, screen them against non-negotiable conditions. A method may be rejected if it: - cannot meet planning, building or occupational-safety requirements;
- exceeds site boundary or access limitations;
- requires unavailable specialist equipment or materials;
- cannot satisfy required fire, acoustic, durability or structural performance; or
- creates an unacceptable environmental or community impact.
4.2 Weighted decision matrixWhen several feasible methods remain, a weighted matrix provides a transparent comparison. For criterion i, define a weight wi and a score si for each method. The weights should sum to 1, and the score scale should be defined before scoring. Sj = ∑(i=1 to n) wi sij Here, Sj is the total score for method j, wi is the weight of criterion i, sij is the score of method j under criterion i, and n is the number of criteria. This is an additive model: it assumes that criteria can reasonably be represented on a common scale and that the selected weights express their relative importance. It should not override a mandatory requirement. A practical scoring scale is 1 to 5: 1 = very poor, 2 = poor, 3 = acceptable, 4 = good and 5 = very good. The scoring definitions must be recorded because a score without evidence is only an opinion. | Criterion | Typical question | Example weight |
|---|
| Constructability | Can the work be safely and practically built? | 0.15 | | Productivity | What output can be achieved with available resources? | 0.15 | | Cost | What is the whole-life and construction cost? | 0.15 | | Schedule | Can milestones be achieved reliably? | 0.15 | | Quality | How consistent and verifiable is the result? | 0.12 | | Safety | How effectively are hazards eliminated or controlled? | 0.12 | | Sustainability | What are the resource, waste and environmental effects? | 0.08 | | Risk | How exposed is the method to uncertainty? | 0.08 |
The weights in this table are illustrative, not universal. A hospital project may give greater weight to quality and infection control, while an emergency facility may emphasise schedule. Worked example: selecting a floor systemAn illustrative project compares cast-in-place reinforced concrete (Method A), precast concrete planks (Method B) and a steel-composite floor (Method C). Scores are assigned after reviewing drawings, supplier quotations and site access. | Criterion | Weight | A | B | C |
|---|
| Constructability | 0.15 | 4 | 3 | 4 | | Productivity | 0.15 | 3 | 5 | 4 | | Cost | 0.15 | 4 | 3 | 3 | | Schedule | 0.15 | 3 | 5 | 4 | | Quality | 0.12 | 4 | 4 | 4 | | Safety | 0.12 | 3 | 4 | 4 | | Sustainability | 0.08 | 3 | 4 | 4 | | Risk | 0.08 | 4 | 3 | 3 |
For Method B: SB = (0.15×3)+(0.15×5)+(0.15×3)+(0.15×5)+(0.12×4)+(0.12×4)+(0.08×4)+(0.08×3) = 3.88 The corresponding totals are 3.46 for Method A and 3.68 for Method C. Method B ranks first in this illustrative comparison, but its transport and lifting risks must be controlled. The result is a decision aid, not a substitute for engineering approval. 4.3 Sensitivity testingA decision is more credible when it remains acceptable under reasonable changes in assumptions. Increase the schedule weight, for example, if delay has severe contractual consequences. If the preferred method changes under a small change in weights, the decision is sensitive and should receive further investigation, additional quotations or a risk allowance. 5. Productivity, Cost and Schedule Analysis5.1 ProductivityProductivity is commonly expressed as output per unit of resource or resource-hours per unit of output. For labour productivity: P = Q/H where P is productivity, Q is completed quantity and H is labour-hours. If 240 m² of formwork is completed using 120 labour-hours, productivity is 2.0 m² per labour-hour. The calculation is meaningful only when quantity definitions, crew composition, working conditions and quality acceptance are consistent. A duration estimate based on productivity is: T = Q/(p × N) where T is working time, Q is quantity, p is output per crew per time period and N is the number of equivalent crews. This assumes reasonably stable production and no major interruption. Allowances for mobilisation, inspection, curing, weather, access and learning should be considered separately. 5.2 Cost comparisonConstruction cost should include direct and indirect components. Direct costs include labour, materials, plant and subcontractors. Indirect costs include supervision, site facilities, temporary works, insurance, testing, permits and time-related overheads. A simple total-cost expression is: Ctotal = Cdirect + Cindirect + Crisk + Clife-cycle The terms must not be double-counted. Crisk may represent quantified expected risk allowances, while Clife-cycle includes relevant operation, maintenance, replacement and disposal costs when the decision is intended to consider more than initial construction cost. For a risk event with probability p and financial consequence I, the expected monetary value is: EMV = p × I This is an average decision-support value, not a prediction that the exact average loss will occur on one project. Probabilities and consequences should be supported by historical data or expert assessment. 5.3 Schedule logicA construction schedule should show activities, durations, dependencies, resources, inspections and milestones. A network’s critical path is the sequence of activities controlling the earliest project completion under the stated logic. Delaying a critical activity generally delays completion unless mitigation changes the network. Method selection should consider not only nominal duration but reliability. A method with a shorter planned duration may be inferior if it depends on a single supplier, specialised equipment or perfect weather. Include procurement, approvals, trial installation, delivery, erection, inspection, testing and remedial work in the programme. 6. Quality, Safety and Sustainability Integration6.1 Quality planningQuality must be designed into the method rather than inspected only at completion. A quality plan should identify: - approved drawings and specifications;
- materials approval and traceability;
- inspection and test plans;
- hold points requiring approval before proceeding;
- tolerances and acceptance criteria;
- test records and nonconformance procedures; and
- protection of completed work.
For prefabricated work, factory inspection does not eliminate site inspection. Connections, alignment, lifting damage, seals, fire stopping and interfaces must still be checked. 6.2 Safety by design and methodThe preferred method should eliminate hazards where possible and otherwise apply the hierarchy of controls: elimination, substitution, engineering controls, administrative controls and personal protective equipment. A method statement should address lifting, temporary stability, work at height, excavation collapse, plant movement, electrical energy, traffic, dust, noise and emergency response. Risk assessment should be activity-specific. “Use personal protective equipment” is not an adequate control for an unstable excavation or an uncontrolled lifting operation. Temporary works require competent design, checking, inspection and controlled modification. 6.3 SustainabilitySustainability assessment should examine material consumption, waste, energy, transport, water, emissions, durability and adaptability. Construction waste can be reduced through accurate take-off, standardisation, off-site fabrication, returnable packaging, segregation and reuse. A basic material-intensity indicator is: Im = M/Q where Im is material intensity, M is material mass and Q is a defined functional quantity, such as floor area. The result is meaningful only when the functional unit and system boundary are the same for all alternatives. It should not be interpreted as a complete environmental assessment. Life-cycle thinking prevents shifting impacts from construction to operation or disposal. For example, a cheaper façade may require more maintenance and replacement, while a durable system may have higher initial embodied impact but lower total resource demand. 7. Developing the Integrated Construction ProposalAn integrated proposal converts the selected method into an executable plan. It should normally contain the following sections: - Executive summary: project, recommended method, principal benefits and major conditions.
- Project basis: location, scope, drawings, assumptions, exclusions and constraints.
- Alternative methods: description of options and reasons for shortlisting.
- Evaluation: decision matrix, evidence, sensitivity and rejected alternatives.
- Construction sequence: site establishment, temporary works, main activities, inspections and commissioning.
- Resources: labour, plant, materials, suppliers, storage and logistics.
- Technical drawings: method sketches, access plans, lifting layouts, temporary works and sequencing diagrams.
- Quality plan: inspections, tests, hold points, tolerances and records.
- Health and safety plan: hazards, controls, responsibilities and emergency arrangements.
- Environmental plan: waste, dust, noise, water, energy and community controls.
- Programme and cost: baseline schedule, quantities, rates, assumptions and allowances.
- Risk register: probability, consequence, owner, response and residual risk.
- Conclusions and approvals: recommendation, conditions and review requirements.
7.1 Method drawingsA method drawing is not a replacement for a design drawing. It explains how construction will occur. It should show scale or key dimensions, access, working platforms, plant position, exclusion zones, temporary supports, load paths, sequence arrows, interfaces and notes. Drawings must carry a title, number, revision, date, author and checker. A lifting layout should identify crane location, load path, landing area and exclusion zone. A formwork drawing should show supports, access, pour sequence and striking requirements. A logistics plan should show delivery routes, storage, pedestrian segregation and emergency access. 8. Applied Case: Illustrative Community Health CentreBackgroundThe following is a fictional illustrative case. A two-storey community health centre has a 1,200 m² floor area, repetitive room layouts and a six-month construction target. The constrained urban site has one road frontage, limited storage and nearby occupied buildings. The client requires low disruption, durable finishes and documented quality. ProblemThe initial concept used fully cast-in-place construction. The contractor identified that extensive formwork storage, wet trades and restricted delivery space could threaten the programme. Three alternatives were considered: - A: conventional in-situ reinforced concrete and masonry;
- B: precast floor and stair components with in-situ columns, beams and walls; and
- C: light steel framing with composite floors and prefabricated service modules.
AnalysisThe team reviewed structural drawings, site access, supplier capacity, crane reach, fire requirements and programme logic. Method C offered rapid erection but required early coordination of fire protection, acoustic details and service interfaces. Method B reduced site formwork and provided repetitive factory production, but delivery and lifting had to be carefully scheduled. A weighted assessment gave Method A a score of 3.41, Method B 4.02 and Method C 3.67 on a five-point scale. Method B ranked first because it balanced programme, quality and site constraints. The score was not accepted automatically: the team required confirmation of supplier capacity, lifting studies and connection details before approval. Approach and solutionThe integrated proposal selected Method B with the following sequence: - establish hoarding, welfare, traffic separation and survey controls;
- complete excavation, foundations and ground-floor columns;
- install precast stairs and floor units using a mobile crane positioned within the approved hardstanding;
- complete temporary bracing and connection works before releasing lifting controls;
- cast structural toppings and in-situ beams where specified;
- erect masonry and service partitions after structural survey approval;
- install prefabricated service modules and complete fire stopping;
- inspect finishes, commission systems and complete handover documentation.
The quality plan included delivery inspection, lifting-point checks, dimensional survey, connection inspection, concrete testing, fire-stopping records and hold points before concealment. The safety plan established exclusion zones, a lift supervisor, weather limits, tag-line controls and a no-person-under-suspended-load rule. The environmental plan used just-in-time delivery, waste segregation, reusable protection and noise restrictions. OutcomeIn the illustrative outcome, the revised programme achieved the structural frame two weeks earlier than the original baseline. Site storage demand reduced substantially, but the project remained dependent on reliable supplier deliveries and accurate surveys. A minor dimensional discrepancy at one stair connection was corrected before surrounding finishes were installed because the inspection hold point was effective. Learning pointsThe case demonstrates that method selection is an integrated decision. The highest productivity option is not automatically best. Supplier reliability, temporary stability, quality interfaces, community impact and risk response must be incorporated into the proposal. It also demonstrates the importance of reviewing the method before procurement and again after detailed design information becomes available. 9. Risk, Governance and Professional ResponsibilityA risk register should distinguish hazards, events, causes, consequences, controls and owners. Typical method-selection risks include inaccurate quantities, incomplete design, late approvals, supply interruption, equipment breakdown, adverse weather, ground uncertainty, labour shortage, interface failure and public disruption. Risk responses include avoidance, reduction, transfer and acceptance. Transfer through a contract does not remove the physical risk; the project team must still verify competence and controls. Residual risks should be communicated clearly to the client, designer, contractor and affected workers. Professional reporting requires traceable evidence. Assumptions must be labelled, estimates must identify their basis, and uncertainty must not be hidden behind excessive numerical precision. Conflicts of interest, supplier influence and manipulated scoring undermine the integrity of the decision. Environmental and community impacts must be considered even when they do not appear as direct project costs. Regulatory requirements vary by jurisdiction, but proposals should be checked against building regulations, occupational health and safety law, environmental permits, traffic requirements, lifting regulations, labour rules and contract obligations. Competent persons must approve structural temporary works, lifting plans and specialist systems where required. 10. Digital Tools and Contemporary PracticeBuilding information modelling can support method selection by coordinating geometry, identifying clashes, simulating sequence and linking quantities to programme activities. Four-dimensional models add time; five-dimensional workflows connect quantities and cost. They are useful only when model information is accurate, coordinated and governed by revision control. Field technologies such as mobile inspection forms, drones, laser scanning and sensors can improve progress measurement and dimensional verification. Artificial intelligence may assist with quantity extraction, schedule-risk identification, image classification and document search. However, AI outputs require competent human review because drawings may be incomplete, image conditions may be misleading and generated recommendations may lack engineering context. Responsibility remains with the authorised professional and project organisation. 11. Limitations and Best PracticeNo decision matrix eliminates judgement. Scores can be subjective, criteria may overlap and weights can favour a preferred outcome. Productivity data may not transfer between sites because of different access, weather, crews or supervision. Cost estimates are uncertain before design and procurement are complete. Schedule logic may omit commissioning or approval delays. Sustainability indicators may use different system boundaries. Best practice is therefore to: - define project objectives before comparing methods;
- screen mandatory requirements first;
- use current drawings and verified site information;
- involve design, construction, safety, quality and environmental personnel;
- use evidence-based scores and record assumptions;
- test sensitivity to weights and uncertain quantities;
- assess whole-life consequences where appropriate;
- develop method drawings and a realistic sequence;
- assign owners to risks and hold points; and
- update the proposal at design, procurement and construction gateways.
Chapter SummaryConstruction method selection is a structured professional decision that matches project requirements with feasible construction systems. Conventional, mechanised, prefabricated, steel, dry and hybrid methods each offer benefits and limitations. Constructability review connects design information with site reality, resources, access, sequence and temporary works. A robust comparison begins with mandatory screening and then evaluates constructability, productivity, cost, schedule, quality, safety, sustainability and risk. A weighted decision matrix can make assumptions visible, but it cannot replace engineering judgement. Productivity and duration calculations require consistent quantities and clearly stated assumptions. Cost evaluation should distinguish direct, indirect, risk and life-cycle components. The selected method must be developed into an integrated proposal containing technical drawings, construction sequence, resources, programme, cost basis, quality controls, safety measures, environmental arrangements and risk ownership. Digital tools can improve coordination and evidence, while AI requires human verification. Ethical, regulatory and professional responsibilities remain central to a defensible construction decision. Key TermsConstructability: The degree to which a design can be built efficiently, safely and to the required quality. Construction method: An organised procedure for executing construction work using defined resources and controls. Method statement: A document explaining how a specific construction activity will be performed safely and correctly. Prefabrication: Production of components away from their final installation location. Hybrid construction: A system combining two or more construction methods or material systems. Productivity: Output achieved per unit of resource, such as square metres per labour-hour. Critical path: The sequence of activities controlling the earliest possible project completion. Weighted decision matrix: A comparison tool that combines criterion weights and alternative scores. Mandatory requirement: A condition that must be satisfied before an alternative can be considered feasible. Constructability register: A record of buildability issues, actions, owners and due dates. Temporary works: Temporary structures or systems supporting construction operations or partially completed work. Hold point: A specified stage at which work cannot proceed without inspection or approval. Quality assurance: Planned procedures that provide confidence that requirements will be met. Quality control: Operational inspection and testing used to verify conformity. Residual risk: Risk remaining after controls have been applied. Whole-life cost: Cost considered across construction, operation, maintenance, replacement and disposal. Material intensity: Material quantity relative to a defined functional output. Constructability drawing: A drawing showing the practical arrangement and sequence of construction operations. Sensitivity analysis: Testing how a decision changes when assumptions or weights vary. Expected monetary value: Probability multiplied by the financial consequence of a risk event. Review QuestionsShort Answer Questions- What is meant by construction method selection?
- State four questions that should be asked during a constructability review.
- Distinguish between a method statement and a method-selection study.
- What is the purpose of a hold point in a quality plan?
- Why should mandatory requirements be screened before weighted scoring?
Long Answer Questions- Compare conventional, mechanised, prefabricated and hybrid construction methods, including their principal advantages and limitations.
- Explain how a weighted decision matrix can be prepared and used responsibly in construction method selection.
- Discuss the relationship between productivity, cost and schedule reliability.
- Describe the contents of an integrated construction proposal.
- Explain how safety, quality and sustainability should influence method selection from the earliest design stage.
Analytical / Application Questions- A contractor must choose between in-situ slabs and precast slabs on a restricted urban site. Develop suitable evaluation criteria, assign justified weights and explain what evidence would be required before making a recommendation.
- A prefabricated system has a shorter planned duration but depends on one supplier and a mobile crane. Analyse the risks and propose controls, contingency measures and decision-review points.
- Prepare a conceptual sequence and method-drawing checklist for constructing a two-storey reinforced-concrete building with limited storage and adjacent occupied premises.
Multiple Choice Questions with AnswersQuestion 1Which condition should be checked before applying a weighted decision matrix? A. Whether the alternative satisfies mandatory legal and technical requirements B. Whether the alternative has the lowest labour cost C. Whether the alternative uses the newest technology D. Whether the alternative has the largest equipment fleet Correct Answer: A. Whether the alternative satisfies mandatory legal and technical requirements Question 2In the expression P = Q/H, what does H represent? A. Material quantity B. Labour-hours or another defined resource input C. Project overhead cost D. Planned building height Correct Answer: B. Labour-hours or another defined resource input Question 3If 300 m² of work is completed using 150 labour-hours, the labour productivity is: A. 0.5 m² per labour-hour B. 2 m² per labour-hour C. 150 m² per labour-hour D. 450 m² per labour-hour Correct Answer: B. 2 m² per labour-hour Question 4What is a principal risk of prefabricated construction? A. It always produces lower quality B. It eliminates the need for site inspection C. It can create transport, lifting and interface risks D. It cannot be used for repetitive buildings Correct Answer: C. It can create transport, lifting and interface risks Question 5For a risk event with probability 0.2 and consequence of $10,000, the expected monetary value is: A. $500 B. $2,000 C. $10,200 D. $50,000 Correct Answer: B. $2,000 Question 6Which document normally explains how a particular activity will be performed safely and correctly? A. Method statement B. Land survey certificate C. Payment certificate D. Completion certificate Correct Answer: A. Method statement Question 7Which control is higher in the hierarchy of controls than personal protective equipment? A. Ignoring the hazard B. Engineering control C. Increasing paperwork only D. Removing warning signs Correct Answer: B. Engineering control Question 8What is the main purpose of sensitivity analysis in method selection? A. To hide uncertainty from the client B. To determine whether the decision changes when assumptions vary C. To replace all technical drawings D. To guarantee the final cost Correct Answer: B. To determine whether the decision changes when assumptions vary Question 9A hold point means that: A. Work must stop permanently B. Work cannot proceed until specified inspection or approval occurs C. Only the client may design the work D. Materials may be used without inspection Correct Answer: B. Work cannot proceed until specified inspection or approval occurs Question 10Which item is most appropriate for a lifting-layout method drawing? A. Crane position, load path and exclusion zone B. Only the building’s colour schedule C. The contractor’s payroll information D. A list of unrelated suppliers Correct Answer: A. Crane position, load path and exclusion zone
|