Material Requirements Planning

Chapter 12
MRP in Contemporary Production Environments

Post Graduate Program in Production Management
Material Requirements Planning   •   Post Graduate

MRP in Contemporary Production Environments

Introduction

Material Requirements Planning (MRP) was originally developed for environments in which a production organization converts a master production schedule into time-phased requirements for components and raw materials. Its central logic remains powerful: independent demand for finished products is translated through bills of material into dependent demand for lower-level items, while inventory records and lead times determine when supplies must be available.

Contemporary production, however, is more diverse than the traditional repetitive assembly factory for which many early MRP systems were designed. Organizations may simultaneously operate make-to-stock (MTS), make-to-order (MTO), assemble-to-order (ATO), engineer-to-order (ETO), process, repetitive, and project operations. They may also combine MRP with lean production, just-in-time (JIT), Kanban, Theory of Constraints (TOC), and demand-driven MRP (DDMRP).

The managerial challenge is therefore not to choose one universal planning method. It is to understand the conditions under which each method is appropriate, define the boundaries between them, and integrate them without creating contradictory signals. MRP is best viewed as a planning and coordination logic within a broader production-control architecture.

Learning Objectives

After completing this chapter, the reader should be able to:

  1. Distinguish the application of MRP across major production environments.
  2. Explain how demand decoupling points, bills of material, routings, and lead times affect planning.
  3. Adapt MRP for MTS, MTO, ATO, ETO, process, repetitive, and project production.
  4. Evaluate the complementary and conflicting features of MRP, lean, JIT, Kanban, TOC, and DDMRP.
  5. Design practical control policies, metrics, and governance arrangements for hybrid environments.
  6. Diagnose common implementation failures and recommend corrective action.

1. MRP as a Contingent Production-Planning System

MRP uses three primary inputs:

  • the master production schedule (MPS), which states what end items are required and when;
  • the bill of material (BOM), which defines parent–component relationships and usage quantities; and
  • inventory status records, including on-hand balances, scheduled receipts, open orders, lot sizes, and lead times.

For an item, the basic net-requirements relationship is:

NRt = max(0, GRt − OHt − SRt + BOt)

where NRt is net requirement in period t, GRt is gross requirement, OHt is projected available on-hand inventory before the planned receipt, SRt is scheduled receipt available in the period, and BOt represents backorders or other confirmed shortages. All quantities must use the same unit of measure. The expression assumes that inventory records, requirements, and receipts are correctly dated and that negative projected inventory is treated as a shortage rather than as a valid stock balance.

A planned order receipt is usually sized according to a lot-sizing rule, such as lot-for-lot, fixed quantity, economic order quantity, or a minimum order quantity. A planned order release is then offset by the relevant lead time:

PORLt−L = PORt

where PORt is the planned order receipt in period t, PORLt−L is its release, and L is the effective lead time in periods. The relationship assumes deterministic lead time; in practice, safety lead time or buffer inventory may be required when lead time is variable.

MRP is highly sensitive to data quality. A technically sophisticated system cannot compensate for inaccurate BOM quantities, obsolete engineering revisions, incorrect inventory balances, unrealistic lead times, or an unstable MPS. Consequently, contemporary MRP requires not only computation but also disciplined master data governance, cross-functional ownership, and exception management.

2. The Decoupling Point and Production-Environment Choice

A useful way to adapt MRP is to identify the customer-order decoupling point: the location in the material flow at which a customer order changes the planning logic. Before the decoupling point, demand is forecast-driven; after it, activity is usually order-driven.

EnvironmentTypical decoupling pointDominant demand signalMRP emphasis
Make-to-stockFinished-goods inventoryForecast and replenishmentMPS, safety stock, service level
Assemble-to-orderCommon modules or subassembliesForecasted modules plus customer ordersModular BOMs, configuration control
Make-to-orderRaw material or common componentsCustomer orderOrder pegging, due-date feasibility
Engineer-to-orderBasic materials or project procurementContract and design releaseProject structure, engineering milestones
Process productionIngredients, bulk materials, recipesForecast, contracts, or batch ordersFormula management, yields, co-products
Repetitive productionLine-side and component inventoriesRate-based scheduleTakt, mixed-model sequencing, replenishment
Project productionProject-specific procurement and work packagesContract milestonesNetwork schedule, resource coordination

The decoupling point is not necessarily fixed. A firm may stock generic modules for a high-volume product but engineer specialized options only after an order. Such hybrid arrangements are often more competitive than a pure MTS or pure MTO strategy.

3. Adapting MRP to Different Production Environments

3.1 Make-to-Stock

In MTS, products are completed before customer orders arrive. The MPS is therefore forecast-dependent, and the principal planning risk is the mismatch between anticipated and actual demand. MRP converts the MPS into requirements for components, packaging, and raw materials.

Important practices include:

  • use aggregate forecasts at product-family level before disaggregating to stock-keeping units;
  • maintain safety stock or safety time for demand and supply uncertainty;
  • review forecast bias, not only forecast accuracy;
  • use service-level targets to differentiate high-value or critical items;
  • coordinate MRP with distribution requirements planning when multiple warehouses are involved.

For independent demand, a simple reorder-point relationship is often useful:

ROP = dL + SS

where ROP is reorder point in units, d is average demand per time unit, L is replenishment lead time in the same time unit, and SS is safety stock in units. This formula assumes relatively stable average demand and lead time; it is not a substitute for a complete MRP explosion when demand is dependent and scheduled by period.

MTS MRP should not be allowed to generate excessive nervousness from small forecast changes. Time fences, planning horizons, order modifiers, and exception thresholds can stabilize the plan.

3.2 Make-to-Order

In MTO, production begins after a customer order or a sufficiently firm commitment. MRP must protect delivery promises by linking component requirements to the specific order. Order pegging identifies which demand created a planned order and helps planners assess the consequences of cancellation, postponement, or priority changes.

MTO environments require:

  • reliable order promising and available-to-promise logic;
  • accurate manufacturing and purchasing lead times;
  • capacity checks for critical work centres;
  • reservation or allocation policies for scarce materials;
  • visibility of customer-specific specifications.

A common mistake is to treat MTO as simply “MTS with lower inventory.” MTO shifts risk from finished-goods inventory toward capacity, material availability, engineering responsiveness, and delivery-date reliability. If common raw materials are not stocked, procurement lead time may make the quoted delivery date unrealistic.

3.3 Assemble-to-Order

ATO postpones final configuration until the customer order is known. Standard modules are produced or purchased in advance, while final assembly is triggered by the order. MRP must distinguish forecast-driven module demand from order-driven configuration demand.

The BOM should represent valid configurations through modular structures, planning bills, or configurable BOMs. Planning bills group alternative options without incorrectly requiring every alternative simultaneously. ATO performance depends on postponement design: modules should be common enough to forecast reliably and differentiated late enough to preserve variety.

ATO planning commonly combines:

  • MRP for modules and purchased components;
  • final assembly scheduling for customer orders;
  • available-to-promise checks for option combinations;
  • configuration rules preventing incompatible selections.

3.4 Engineer-to-Order

ETO products are designed, engineered, procured, and manufactured for a particular customer or project. The engineering BOM may not exist when the order is accepted, and design changes can alter material requirements after procurement has begun.

MRP in ETO must be integrated with product lifecycle management, project management, document control, and change management. A project work breakdown structure (WBS) is often more appropriate than a conventional finished-product hierarchy alone. Procurement may need to begin for long-lead items before the design is fully complete, creating controlled provisional requirements.

Key controls include:

  • design-release milestones linked to procurement and production;
  • revision-controlled BOMs and routings;
  • effectivity dates and serial or lot traceability;
  • formal engineering-change authorization;
  • risk-based purchasing of long-lead items;
  • earned-value or milestone monitoring for project progress.

ETO cannot be managed effectively by assuming that all requirements are known at the start. The system must represent uncertainty and revision status explicitly.

3.5 Process Production

Process industries transform materials continuously or in batches. Examples include chemicals, food, pharmaceuticals, cement, and metals. Their planning structures differ from discrete manufacturing because formulas, yields, potency, density, co-products, by-products, shelf life, and campaign constraints are important.

MRP adaptations include:

  • formula or recipe management rather than only discrete BOMs;
  • variable-yield and loss-factor planning;
  • batch-size and vessel-capacity constraints;
  • campaign sequencing to reduce cleaning or changeover;
  • lot genealogy and expiry control;
  • co-product and by-product accounting.

If a process has an expected yield of 95%, the input requirement for a desired output quantity Qo is, under a simple constant-yield assumption:

Qi = Qo ÷ 0.95

Here Qi and Qo use the same mass or volume unit. The calculation is valid only when the yield factor is known, stable, and applicable to the batch conditions. In reality, yield may depend on equipment, temperature, formulation, operator, and lot characteristics.

3.6 Repetitive Production

Repetitive production makes a limited range of products at relatively stable rates, often on dedicated or mixed-model lines. Traditional MRP remains useful for medium- and long-range component planning, but detailed execution is frequently governed by rate-based schedules, line balancing, takt time, and pull replenishment.

Takt time is calculated as:

takt time = available production time ÷ required customer quantity

Available production time excludes planned breaks and other deliberately unavailable periods. The calculation assumes that demand and available time are expressed over the same interval. Takt time is a demand-rate measure, not automatically the actual cycle time or a guarantee of capacity.

A repetitive system may use MRP to plan weekly component needs while Kanban controls hourly or daily replenishment at the line. This separation reduces the temptation to use MRP transaction messages for every small movement.

3.7 Project Production

Project production creates a unique output at a defined location or through a temporary organization. Shipbuilding, construction, aerospace development, and major capital equipment are examples. MRP must be linked with project scheduling, resource loading, procurement milestones, and cost control.

The project structure should identify work packages, deliverables, responsible parties, planned dates, and dependencies. Material requirements should be time-phased against engineering release, site readiness, installation sequence, and commissioning—not merely against a generic finished-product due date.

Project environments face several special risks: design maturity may be low, long-lead equipment may dominate the schedule, resources may be shared among projects, and late changes can have disproportionate effects. MRP is therefore one component of an integrated project-control system rather than the sole scheduling method.

4. Integrating MRP with Lean and JIT

Lean seeks to create customer value with less waste, while JIT emphasizes producing and replenishing what is needed, when it is needed, in the required quantity. MRP and lean are not inherently opposites. MRP is generally strong at planning across long horizons and coordinating dependent requirements; lean methods are strong at stabilizing flow and controlling short-interval replenishment.

A practical hierarchy is:

  1. Sales and operations planning establishes volume and capacity direction.
  2. The MPS translates the plan into feasible end-item requirements.
  3. MRP plans purchased and manufactured components over the planning horizon.
  4. Lean flow methods, standard work, visual controls, and Kanban manage execution near the point of use.

Conflict arises when MRP creates frequent rescheduling, large batch releases, or excessive inventory while the shop attempts to maintain flow. The solution is not necessarily to eliminate MRP; it may be to improve schedule stability, reduce lead times, apply time fences, use level loading, and limit the planning system to the decisions it is suited to make.

JIT requires dependable suppliers, short setup times, high equipment reliability, quality at source, and rapid problem resolution. Without these conditions, reducing inventory may expose problems without providing the capability to solve them.

5. Kanban and Pull Replenishment

Kanban is a signaling method that authorizes replenishment or production based on downstream consumption. A basic container-based relationship is:

N = D × L × (1 + S) ÷ C

where N is the required number of Kanban containers, D is average demand per time unit, L is replenishment lead time in the same time unit, S is a safety factor expressed as a decimal, and C is container capacity. The result is normally rounded up to a whole container. The formula assumes relatively stable demand, a defined replenishment lead time, and standardized container quantities.

For example, if a component is consumed at 240 units per day, replenishment takes 0.5 day, the safety factor is 10%, and each container holds 30 units:

N = 240 × 0.5 × 1.10 ÷ 30 = 4.4

The system requires five containers after rounding up. Kanban is most effective for repetitive, stable-flow items. It is less suitable for highly erratic demand, one-time project items, long-lead ETO components, or items with frequent engineering changes.

MRP can supply the broader replenishment and purchasing plan, while Kanban controls the physical movement of stable items. Electronic Kanban can transmit consumption signals to suppliers or internal cells, but digitization does not remove the need for accurate container sizes, locations, lead times, and authorizations.

6. Theory of Constraints and MRP

Theory of Constraints (TOC) argues that system performance is limited by one or a few constraints. Its five focusing steps are commonly expressed as:

  1. Identify the constraint.
  2. Exploit the constraint without major additional investment.
  3. Subordinate other activities to the constraint.
  4. Elevate the constraint when justified.
  5. Repeat when the constraint moves.

MRP often plans material availability for all work centres, whereas TOC emphasizes the flow through the constraint. If a bottleneck is starved, material shortages reduce throughput; if it is overloaded, releasing more work only increases work-in-process and lead time.

DBR (drum-buffer-rope) provides a useful integration mechanism. The drum is the constraint schedule, the buffer protects the constraint from disruption, and the rope controls release of work so that upstream activity does not overwhelm the system. MRP can generate time-phased requirements, while DBR modifies release priorities and buffer rules around the constraint.

Managers should distinguish local efficiency from system throughput. A non-bottleneck machine running continuously may produce inventory that does not increase completed sales. MRP exception messages should therefore be interpreted with bottleneck status and customer-flow priorities in mind.

7. Demand-Driven MRP

DDMRP extends conventional material planning with strategically positioned decoupling points, buffer profiles, and demand-driven replenishment. It seeks to reduce the amplification of demand variation by protecting selected points in the supply network rather than planning every item solely from forecast-derived requirements.

Its commonly described elements include:

  • strategic inventory positioning;
  • buffer profiles based on lead time, variability, and item characteristics;
  • visually managed buffer zones;
  • demand-driven net-flow calculations;
  • planned adjustment and execution priorities.

DDMRP is not simply a larger safety-stock calculation and should not be adopted without understanding item criticality, supply variability, lead-time compression, and network structure. It may be valuable where long and variable lead times create planning nervousness, but its performance depends on sound parameter governance and disciplined replenishment execution.

A useful comparison is that traditional MRP asks, “What is required, and when, based on the schedule?” DDMRP adds, “Where should inventory decouple the flow, and which replenishment signals should receive priority?” In practice, organizations may use conventional MRP for long-lead procurement and DDMRP or pull methods for selected decoupling points.

8. Hybrid Architecture for Contemporary Operations

No single method should control every item. A hybrid architecture can assign planning and execution methods according to product characteristics.

Decision or item characteristicSuitable approach
Long-lead, low-volume purchased itemMRP with supplier collaboration and risk review
Stable, high-volume line-side componentKanban or supermarket replenishment
Constraint-dependent operationTOC priorities and DBR
Forecast-sensitive finished productMPS, MRP, and safety-stock policy
Configurable final productATO planning and order-driven assembly
Project-specific engineered itemProject MRP, WBS, and milestone control
Variable, uncertain supply network itemDDMRP or strategically buffered planning

Governance must define which system is authoritative for each decision. For example, MRP may own planned purchase requirements, Kanban may own point-of-use movement, and the finite-capacity schedule may own the sequence at a bottleneck. Unclear ownership creates duplicate signals, conflicting priorities, and excess inventory.

9. Worked Application: Hybrid Industrial Pump Producer

Background

The following is an illustrative case. Meridian Pumps produces industrial pumps for water-treatment and chemical-processing customers. Standard pump bodies and motor modules are made for stock. Final configurations are assembled to order. Large corrosion-resistant systems are engineered to order. The company uses MRP, but delivery performance has declined.

Problem

The company experiences three symptoms:

  • finished-goods inventory is high for slow-moving standard models;
  • final assembly frequently waits for valves and control panels;
  • engineering changes disrupt procurement for ETO projects.

The same MRP parameters are being applied to all products. The plant also releases shop orders based on system dates without considering the capacity-constrained test cell.

Analysis

The decoupling points are different. Standard pump bodies belong to an MTS policy, common motor modules to an ATO policy, and customer-specific control panels to an MTO or ETO policy. The test cell is the principal constraint. A single forecast-driven MPS cannot represent all these conditions accurately.

Data analysis finds three additional causes:

  1. The BOM for one motor module includes an obsolete fastener quantity.
  2. Supplier lead times are copied from quotations rather than measured performance.
  3. Engineering revisions are communicated by email and are not consistently linked to purchase-order effectivity.

Approach

Management implements a segmented policy:

  • standard pump bodies are planned with differentiated safety stocks based on demand variability and service requirements;
  • common motor modules are replenished through a supermarket and Kanban at the assembly line;
  • customer-specific panels are pegged to sales orders and checked against supplier capacity before promising dates;
  • ETO projects use WBS-linked material requirements and formal engineering-release gates;
  • the test cell becomes the drum in a DBR system, and upstream releases are subordinated to its feasible schedule;
  • MRP remains the planning system for long-lead procurement and medium-term component requirements.

Master-data governance is strengthened through monthly BOM audits, lead-time measurement, engineering-change effectivity rules, and cycle-count accuracy targets.

Outcome

After implementation, the company reduces slow-moving finished-goods inventory while improving availability of common modules. Expedite orders decline because customer-specific panels are identified earlier. The test cell experiences less overload, although some upstream work centres show lower utilization. Management correctly interprets this as a system-level improvement rather than a problem, because completed and tested orders increase.

Learning Points

The case illustrates four principles:

  • production environments should be segmented rather than controlled by one universal policy;
  • MRP, Kanban, and TOC can be complementary when decision rights are explicit;
  • engineering and master-data governance are operational capabilities, not administrative details;
  • local utilization is less important than reliable end-to-end flow and customer delivery.

10. Performance Measurement and Governance

A contemporary MRP system should be evaluated through a balanced set of measures:

  • schedule adherence and master production schedule stability;
  • customer on-time delivery and order-fill performance;
  • inventory accuracy and record integrity;
  • inventory turns and days of supply;
  • shortage frequency and expedite activity;
  • supplier on-time delivery and lead-time variability;
  • capacity utilization at constraints;
  • plan nervousness, measured through reschedules and quantity changes;
  • engineering-change cycle time;
  • forecast bias and forecast error where forecasts are used.

Metrics must be interpreted together. Increasing inventory turns while customer service collapses is not success. Similarly, high machine utilization may indicate excessive work-in-process if the resource is not the constraint.

Governance issues include authorization of parameter changes, segregation of duties for item and BOM maintenance, audit trails for engineering revisions, traceability for regulated materials, and controlled access to customer and supplier data. In regulated sectors, electronic records may need to comply with applicable quality and record-retention requirements. AI-assisted forecasting or anomaly detection should be explainable enough for planners to challenge inappropriate recommendations; automated decisions should not bypass approval controls for safety-critical, regulated, or contractual commitments.

11. Challenges and Limitations

MRP and its associated methods have several limitations:

  1. Data dependence: inaccurate BOMs, inventory, or lead times produce precise but wrong recommendations.
  2. Forecast dependence: MTS plans are vulnerable to demand shifts and product substitution.
  3. Nervousness: frequent replanning can create unstable orders and supplier confusion.
  4. Finite-capacity weakness: basic MRP may assume capacity that does not exist.
  5. Organizational fragmentation: sales, engineering, purchasing, and manufacturing may optimize different objectives.
  6. Parameter burden: safety stocks, lot sizes, time fences, buffers, and Kanban quantities require continual review.
  7. Change complexity: hybrid environments can generate conflicting signals unless ownership is explicit.
  8. Technology overconfidence: integration and analytics do not replace process discipline or managerial judgment.

Contemporary systems increasingly provide finite-capacity planning, scenario analysis, supplier portals, Internet-of-Things data, machine-learning forecasts, and event-driven alerts. These capabilities improve visibility but also increase the need for data stewardship, cybersecurity, model validation, and human accountability.

12. Best-Practice Implementation Sequence

A practical implementation sequence is:

  1. Map products, processes, demand types, and decoupling points.
  2. Segment items by volume, variability, value, criticality, and supply risk.
  3. Establish one controlled source for item, BOM, routing, lead-time, and revision data.
  4. Stabilize the MPS and define planning time fences.
  5. Validate capacity, especially at bottlenecks and shared resources.
  6. Assign MRP, Kanban, TOC, DDMRP, or project-control methods by item and process.
  7. Define signal ownership and escalation rules.
  8. Pilot the design in a representative value stream.
  9. Measure service, flow, inventory, stability, and constraint performance.
  10. Improve parameters through structured review rather than uncontrolled overrides.

The objective is not maximum automation. It is a coherent system in which planning signals are credible, execution priorities are visible, and decisions support customer value and total system performance.

Chapter Summary

MRP remains a central planning logic for dependent demand, but its application must reflect the production environment. MTS relies on forecasts and inventory policies; MTO relies on order pegging and feasible promise dates; ATO relies on modular structures and postponement; ETO requires project, engineering, and change control; process production requires formulas, yields, batches, and traceability; repetitive production benefits from rate-based planning and pull replenishment; and project production requires integration with WBS and milestone control.

Lean, JIT, Kanban, TOC, and DDMRP should not be treated as automatic substitutes for MRP. They address different time horizons, signals, and control problems. MRP is generally effective for coordinated, time-phased planning, while Kanban and lean methods support stable execution, TOC protects system constraints, and DDMRP positions buffers against variability. A successful contemporary architecture assigns clear decision rights, maintains high-quality data, and evaluates total flow rather than isolated utilization or inventory measures.

Key Terms

MRP: A time-phased system for planning dependent material and component requirements.

Master Production Schedule: A statement of planned end-item production by period.

Bill of Material: A structured representation of component relationships and usage quantities.

Dependent Demand: Demand calculated from the requirements of another item.

Decoupling Point: The point separating forecast-driven activity from order-driven activity.

Make-to-Stock: Production completed before the customer order is received.

Make-to-Order: Production initiated in response to a customer order.

Assemble-to-Order: Standard modules are prepared in advance and final assembly follows the order.

Engineer-to-Order: Product design and production are developed for a specific order.

Planned Order Release: The planned authorization date for initiating supply or production.

Order Pegging: Linking a component requirement to the order or demand source that created it.

Kanban: A signal authorizing replenishment or production based on consumption.

JIT: A production and replenishment philosophy emphasizing timely flow and low waste.

Takt Time: Available production time divided by required customer quantity.

Theory of Constraints: A management approach focused on improving the system’s limiting constraint.

Drum-Buffer-Rope: A constraint-based scheduling and release method.

Demand-Driven MRP: A planning approach using strategic buffers and demand-driven replenishment signals.

Plan Nervousness: Frequent changes in planned quantities, dates, or orders.

Master Data Governance: Controlled management of item, BOM, routing, lead-time, and revision information.

Review Questions

Short Answer Questions

  1. What are the three principal inputs to an MRP system?
  2. Define the customer-order decoupling point.
  3. Why is order pegging important in make-to-order production?
  4. State one limitation of Kanban in an engineer-to-order environment.
  5. What is the purpose of the “rope” in drum-buffer-rope control?

Long Answer Questions

  1. Compare MTS, MTO, ATO, and ETO environments with respect to demand signals, inventory policy, and MRP requirements.
  2. Explain how MRP and lean/JIT can be integrated without creating contradictory production signals.
  3. Discuss the adaptations required for applying MRP in process industries.
  4. Evaluate the role of master-data governance in contemporary MRP performance.
  5. Explain how TOC and MRP can be combined in a capacity-constrained production system.

Analytical / Application Questions

  1. A component is consumed at 360 units per day. Replenishment takes 0.75 day, the safety factor is 15%, and each Kanban container holds 45 units. Calculate the required number of containers and state the rounding assumption.
  2. A manufacturer produces standard modules for stock but performs final configuration only after customer orders. Design an MRP and replenishment architecture, identifying which activities should be forecast-driven and which should be order-driven.
  3. A plant has high machine utilization, rising work-in-process, and declining on-time delivery. Using TOC and MRP concepts, diagnose the likely problem and propose a control response.

Multiple Choice Questions with Answers

Question 1

Which production environment generally requires final assembly to be triggered by a customer order while common modules are prepared in advance?

A. Make-to-stock

B. Assemble-to-order

C. Engineer-to-order

D. Project production

Correct Answer: B. Assemble-to-order

Question 2

In the net-requirements relationship, which item is subtracted from gross requirements?

A. Projected available inventory and scheduled receipts

B. Customer lead time

C. Work-centre capacity

D. Forecast bias

Correct Answer: A. Projected available inventory and scheduled receipts

Question 3

A component is consumed at 240 units per day, replenishment takes 0.5 day, safety factor is 10%, and container capacity is 30 units. How many Kanban containers are required?

A. 3

B. 4

C. 5

D. 6

Correct Answer: C. 5

Question 4

Which method is most directly concerned with identifying and managing the system constraint?

A. Kanban

B. Theory of Constraints

C. Forecast disaggregation

D. Lot-for-lot planning

Correct Answer: B. Theory of Constraints

Question 5

In engineer-to-order production, which capability is especially important?

A. Ignoring design revisions until shipment

B. Revision-controlled BOMs and engineering-release milestones

C. Producing all finished goods before orders arrive

D. Eliminating project structures

Correct Answer: B. Revision-controlled BOMs and engineering-release milestones

Question 6

Takt time is calculated as:

A. Required quantity divided by inventory

B. Available production time divided by required customer quantity

C. Lead time divided by batch size

D. Safety stock divided by demand variability

Correct Answer: B. Available production time divided by required customer quantity

Question 7

Which statement best describes a suitable division between MRP and Kanban?

A. Kanban must replace all MRP calculations

B. MRP can plan broader requirements while Kanban controls stable point-of-use replenishment

C. MRP should control every hourly material movement

D. Kanban is only suitable for unique project items

Correct Answer: B. MRP can plan broader requirements while Kanban controls stable point-of-use replenishment

Question 8

What is a principal risk of applying one set of MRP parameters to all production environments?

A. It guarantees excessive capacity

B. It ignores differences in demand, uncertainty, and decoupling points

C. It eliminates the need for master data

D. It prevents all engineering changes

Correct Answer: B. It ignores differences in demand, uncertainty, and decoupling points

Question 9

In drum-buffer-rope, the drum represents:

A. The supplier invoice

B. The finished-goods warehouse

C. The schedule of the system constraint

D. The forecast error

Correct Answer: C. The schedule of the system constraint

Question 10

Which characteristic is particularly relevant to process-industry MRP?

A. Formula management and variable yields

B. Only discrete unit serial numbers

C. Absence of batch constraints

D. No need for traceability

Correct Answer: A. Formula management and variable yields