Materials Planning and Supply CoordinationIntroductionMaterials planning is the disciplined process of determining what materials are required, in what quantities, and at what times so that production, distribution, and customer service objectives can be achieved. It connects market demand with purchasing, manufacturing, inventory, warehousing, transportation, and supplier management. Poor planning creates two opposing problems. Excess materials increase working capital, storage, insurance, obsolescence, and handling costs. Shortages interrupt production, delay customers, create emergency freight, and damage reputation. Effective planning therefore seeks not simply to minimise inventory, but to coordinate material availability with demand, capacity, lead times, and risk. This chapter examines bills of materials (BOMs), the master production schedule (MPS), material requirements planning (MRP), distribution requirements planning (DRP), lead-time and capacity planning, and alternative supply-coordination approaches including push, pull, just-in-time (JIT), Kanban, vendor-managed inventory (VMI), and consignment inventory. Learning ObjectivesBy the end of this chapter, the learner should be able to: - Explain the relationships among demand, the MPS, BOMs, inventory records, MRP, and purchasing.
- Construct and interpret a basic MRP record.
- Explain how DRP coordinates replenishment across a distribution network.
- Calculate lead-time offsets, projected inventory, and net requirements under stated assumptions.
- Explain the role of capacity information in validating material plans.
- Compare push, pull, JIT, Kanban, VMI, and consignment approaches.
- Evaluate planning choices in terms of cost, responsiveness, risk, technology, and governance.
1. The Planning ArchitectureA planning system normally operates at several time horizons: - Strategic planning determines facilities, technologies, supplier structures, and long-term capacity.
- Sales and operations planning (S&OP) balances aggregate demand and supply, usually over months or quarters.
- The master production schedule translates the aggregate plan into specific end items and time periods.
- MRP translates end-item requirements into component and raw-material requirements.
- Purchasing and shop-floor control execute planned orders, monitor exceptions, and revise plans.
The basic logic is: Demand forecast and customer orders → MPS → BOM explosion and inventory netting → planned purchase and production orders → capacity and supplier validation → execution and feedback. Planning is not a one-way calculation. Actual receipts, scrap, quality failures, demand changes, supplier delays, and capacity disruptions must be fed back into the system. A technically correct plan becomes operationally useless if its data are inaccurate or if planners ignore exception signals. Important planning terminology| Term | Meaning |
|---|
| Independent demand | Demand for finished goods or service items, usually driven by customers or forecasts. | | Dependent demand | Demand for components derived from the planned production of a parent item. | | Gross requirement | Total quantity needed before considering available inventory or scheduled receipts. | | Scheduled receipt | An order already released and expected to arrive in a specified period. | | Projected available balance | Inventory expected to remain after requirements and receipts. | | Net requirement | Additional quantity that must be supplied after inventory and scheduled receipts are considered. | | Planned order receipt | Quantity and timing proposed by the planning system. | | Planned order release | Date on which an order must be started or issued, after allowing for lead time. | | Lot-sizing rule | Rule used to convert net requirements into order quantities. | | Safety stock | Inventory held to protect against uncertainty in demand, supply, or processing. |
2. Bills of MaterialsA bill of materials is a structured description of the components, subassemblies, materials, quantities, and sometimes instructions required to make a product. It is the principal link between product design and material planning. A single-level BOM lists only the immediate components of an item. A multilevel BOM represents the complete product structure. A phantom item is a logical grouping used for planning or engineering convenience but not normally stocked as a separate physical item. An engineering BOM reflects product design, whereas a manufacturing BOM reflects how the product is actually assembled and may include packaging, process materials, and sequencing information. A BOM must identify: - item or part number and description;
- quantity per parent;
- unit of measure;
- effective dates and revision level;
- scrap or yield assumptions;
- alternate components, where authorised;
- lead time and make-or-buy status;
- engineering and quality documentation.
BOM accuracy is essential. If a product requires four fasteners but the BOM records three, MRP will systematically under-plan supply. If an obsolete revision remains active, the system may purchase unusable material. Governance therefore requires engineering-change control, version management, approval authority, and reconciliation between design, manufacturing, and enterprise systems. Dependent-demand calculationIf one parent requires q units of a component and P parent units are planned, gross component demand is: G = P × q Here, G is gross component requirement in units, P is the planned parent quantity, and q is component quantity per parent. This assumes no scrap, yield loss, substitutes, or inventory offset. If an expected usable yield is y, where 0 < y ≤ 1, the required input quantity is: Ginput = (P × q) ÷ y For example, 500 assemblies requiring 3 castings each need 1,500 usable castings. At a 95% yield, input demand is 1,500 ÷ 0.95 = 1,578.95, so at least 1,579 castings are required if fractional units are impossible. 3. The Master Production ScheduleThe MPS specifies which finished products or major assemblies will be produced, in which periods, and in what quantities. It is more detailed than an aggregate production plan but should not be treated as an unchangeable promise. The MPS must balance customer requirements, forecast demand, inventory policy, production rates, and available capacity. A good MPS has the following characteristics: - it is expressed in meaningful end-item units;
- its time buckets match the planning purpose;
- it includes a defined planning horizon;
- it respects cumulative and near-term capacity constraints;
- it distinguishes firm orders from forecasts;
- changes are controlled through time fences.
A frozen zone is a near-term period in which changes are restricted because materials and labour have already been committed. A slushy zone permits limited changes, while a liquid zone allows broader replanning. Time fences reduce nervousness: frequent changes to planned orders that create instability for suppliers and production teams. The MPS is influenced by available-to-promise (ATP). ATP represents uncommitted finished-product supply that can be promised to customers. A simple first-period calculation is: ATP = Beginning inventory + MPS receipt − Confirmed customer orders For later periods, ATP normally includes the next MPS receipt and subtracts customer orders up to the next MPS receipt. The exact calculation depends on the organisation’s order-allocation policy. 4. Material Requirements PlanningMRP is a time-phased planning method for dependent-demand items. It uses the MPS, BOM, inventory records, scheduled receipts, lead times, and lot-sizing rules to determine planned orders. The central MRP activities are: - BOM explosion: multiply parent requirements through each level of the product structure.
- Netting: subtract usable on-hand inventory and scheduled receipts.
- Offsetting: move required receipt dates backward by lead time.
- Lot sizing: convert net requirements into feasible order quantities.
- Capacity review: test whether the resulting plan can be executed.
- Release and control: authorise orders and monitor exceptions.
Core MRP relationshipsFor a period t, projected available balance can be represented as: PABt = PABt−1 + SRt + PORt − GRt where PABt is projected available balance at the end of period t, SRt is the scheduled receipt, PORt is the planned order receipt, and GRt is gross requirement. The formula assumes all quantities are in the same unit and that receipts are available during the stated period. If the desired minimum balance is safety stock SS, the net requirement may be calculated as: NRt = max(0, GRt + SS − PABt−1 − SRt) This expression assumes that beginning projected inventory is available for the requirement and that safety stock is protected rather than freely consumed. Some systems use different safety-stock and allocation conventions. A planned order receipt may be larger than the net requirement because of minimum order quantities, fixed order quantities, economic lot sizes, pack sizes, or supplier constraints. Planned order release is offset from receipt by lead time: Release period = Receipt period − Lead time Lead time must be expressed in the same time units as the planning periods. It may include queue time, setup, processing, inspection, transportation, receiving, and administrative time. Worked MRP exampleA finished product requires two units of component A. The MPS requires 100 finished products in week 3 and 80 in week 4. Component A has 30 units on hand, no scheduled receipts, a safety stock of 10 units, and a one-week lead time. Use lot-for-lot ordering. Gross requirements for A are: - Week 3: 100 × 2 = 200 units.
- Week 4: 80 × 2 = 160 units.
Assuming no earlier requirements, week 3 net requirement is: NR₃ = max(0, 200 + 10 − 30) = 180 units. The planned receipt is 180 units in week 3, and because lead time is one week, the planned release is in week 2. Projected balance after week 3 is 10 units. Therefore, week 4 net requirement is: NR₄ = max(0, 160 + 10 − 10) = 160 units. The planned receipt is 160 units in week 4, released in week 3. The resulting plan protects the 10-unit safety stock, subject to the assumptions that receipts arrive on time, all inventory is usable, and demand is accurately represented. Lot-sizing methodsCommon methods include: - Lot-for-lot: order exactly the net requirement. It minimises cycle inventory but may create many orders.
- Fixed order quantity: order a predetermined quantity, often due to supplier or process constraints.
- Periodic order quantity: cover requirements for a specified number of periods.
- Minimum order quantity: order no less than the supplier’s or process’s minimum.
- Economic order quantity: balance ordering and holding costs under relatively stable assumptions.
For the classical deterministic EOQ model: Q* = √(2DS ÷ H) where Q* is optimal order quantity in units per order, D is annual demand in units, S is ordering or setup cost per order, and H is annual holding cost per unit. The model assumes relatively constant demand, known replenishment time, instantaneous or predictable replenishment, no shortages, and constant costs. It is less suitable where demand is highly dependent, capacity is constrained, or minimum quantities dominate. 5. Distribution Requirements PlanningDRP applies time-phased planning to distribution networks. Whereas MRP plans components for production, DRP plans replenishment of finished goods or inventory items across plants, regional warehouses, distribution centres, and retail locations. A DRP record typically includes forecast demand, customer orders, on-hand inventory, safety stock, scheduled receipts, planned receipts, and planned releases. Demand at a regional warehouse becomes a requirement for the supplying distribution centre. Requirements are then aggregated upstream, allowing the central facility or plant to plan production and procurement. DRP is especially useful when: - facilities have defined replenishment relationships;
- transportation lead times are known;
- stock policies differ by location;
- customer demand is geographically dispersed;
- network inventory must be coordinated rather than managed independently.
DRP does not remove uncertainty. Forecast error, transport disruption, allocation rules, and warehouse capacity can still cause shortages or excess stock. It should therefore be integrated with transport planning, order promising, and inventory segmentation. 6. Lead-Time Planning and Capacity InformationLead time is not merely transit time. A realistic replenishment lead time can include order approval, supplier queueing, production, inspection, dispatch, transport, receiving, put-away, and system posting. Underestimating any element creates systematically late plans. Planners should distinguish: - standard lead time: an expected time under normal conditions;
- cumulative lead time: the time required through several linked stages;
- manufacturing lead time: time from release to finished output;
- purchasing lead time: time from order placement to accepted receipt;
- safety lead time: intentional early scheduling to protect against uncertainty.
Capacity planning validates whether planned orders can be produced. Relevant resources include labour hours, machine hours, tooling, supplier capacity, dock space, warehouse locations, transport lanes, and inspection capability. A basic load calculation is: Loadr,t = ∑i=1n Qi,t × timei,r where Loadr,t is required capacity on resource r in period t, Qi,t is quantity of item i processed in that period, and timei,r is resource time per unit. Units may be machine-hours or labour-hours. If available capacity is ACr,t, utilisation is: Utilisationr,t = Loadr,t ÷ ACr,t A utilisation above 1, or above the organisation’s practical limit, indicates overload. Practical capacity is often below theoretical capacity because of breaks, maintenance, changeovers, absenteeism, quality losses, and variability. Capacity requirements planning (CRP) therefore supplements MRP by identifying bottlenecks and proposing rescheduling, overtime, subcontracting, alternate routing, or lot-size changes. 7. Push, Pull, JIT, and KanbanPush systemsA push system releases work or replenishment based primarily on forecasts, planned schedules, and calculated requirements. MRP is commonly associated with push planning. Push methods are valuable where lead times are long, BOMs are complex, demand must be coordinated across many levels, or suppliers need advance visibility. Their weakness is that forecast errors can propagate upstream, creating excess inventory or inappropriate production. Pull systemsA pull system authorises replenishment in response to actual consumption or a downstream signal. It limits work-in-process and helps align supply with real usage. Pull systems are particularly effective for repetitive, stable flows, although they require reliable processes and clearly defined replenishment rules. Just-in-timeJIT is a management philosophy and operating system seeking to provide the required item, in the required quantity, at the required time, while eliminating waste. It includes reduced setup times, quality at source, standardised work, supplier development, reliable equipment, small lots, workplace organisation, and continuous improvement. JIT is not simply “zero inventory.” Inventory may be necessary where supply risk, geographic distance, demand volatility, or regulatory requirements make complete synchronisation unsafe. KanbanKanban is a visual or electronic signalling method that controls replenishment. A card, container, barcode scan, or system message authorises movement or production only when a downstream process consumes material. Kanban works best when demand and process times are reasonably stable, container quantities are standard, defects are controlled, and replenishment routes are dependable. A simplified kanban quantity relationship is: N = (D × L × (1 + S)) ÷ C where N is the required number of containers, rounded up to a whole number, D is demand per time unit, L is replenishment lead time in the same time unit, S is the safety factor expressed as a decimal, and C is container capacity. This is a planning approximation, not a universal law. It assumes relatively stable demand, consistent container size, and a lead time that includes the full replenishment loop. For example, demand is 40 units per hour, replenishment lead time is 1.5 hours, safety factor is 10%, and each container holds 20 units: N = (40 × 1.5 × 1.10) ÷ 20 = 3.3. The system requires 4 containers after rounding up. The number should be reviewed when demand, lead time, quality, or container availability changes. 8. VMI and Consignment InventoryIn vendor-managed inventory, the supplier monitors agreed customer inventory data and makes replenishment decisions within defined limits. The customer may retain ownership, or ownership may transfer at receipt depending on the contract. VMI can reduce administrative workload, improve visibility, and coordinate replenishment across multiple customer locations. It also requires accurate data, clear service levels, trust, exception management, and agreement on responsibility for obsolete or excess inventory. In consignment inventory, stock is physically held at or near the customer but remains owned by the supplier until the customer consumes it or another contractual transfer event occurs. Consignment can improve material availability while reducing the customer’s working-capital investment. The supplier, however, carries greater financial and obsolescence risk and must control stock accuracy, insurance, loss, damage, and returns. | Approach | Replenishment trigger | Typical ownership | Main strength | Main risk |
|---|
| Push/MRP | Forecast and planned requirements | Customer or supplier | Coordinates complex structures | Forecast-driven excess or shortage | | Pull | Actual downstream consumption | Usually customer | Limits unnecessary replenishment | Sensitive to disruption and variability | | JIT | S synchronised demand and waste reduction | Varies | Low waste and short flow | Low buffers increase vulnerability | | Kanban | Container or electronic signal | Varies | Simple visual control | Needs stable processes | | VMI | Supplier monitors customer stock | Contract-specific | Shared replenishment responsibility | Dependence on data and governance | | Consignment | Consumption or agreed transfer event | Supplier until transfer | Customer cash-flow benefit | Supplier exposure and control complexity |
No approach is universally superior. Many organisations use a hybrid: MRP for long-lead and low-volume components, Kanban for repetitive internal consumption, VMI for strategic suppliers, and safety stock for critical or uncertain items. 9. Applied Case: Meridian AppliancesThe following is an illustrative case. BackgroundMeridian Appliances assembles commercial refrigeration units. Demand is seasonal, the product has a multilevel BOM, and compressors are sourced from an overseas supplier with an eight-week purchasing lead time. Local fasteners and packaging materials are consumed steadily on the assembly line. ProblemThe company used monthly forecasts and manual spreadsheets. It frequently expedited compressors, while fasteners accumulated in several warehouses. Engineering changes were communicated by email, causing obsolete components to remain in stock. Production supervisors also released work orders without checking whether test capacity was available. AnalysisAn audit found three principal causes: - The MPS was changed inside the frozen zone, so purchasing and production received unstable signals.
- The BOM contained outdated compressor and control-board revisions.
- All materials were managed using the same policy, despite major differences in value, demand variability, lead time, and criticality.
The company calculated that compressor demand should be driven by the approved MPS and exploded through the current BOM. Fasteners were suitable for a two-bin Kanban system because usage was stable and replenishment was local. The supplier of compressors had sufficient visibility to support a VMI arrangement, but ownership remained with Meridian until receipt because of contractual and quality requirements. ApproachMeridian implemented the following measures: - a monthly S&OP review to reconcile demand, supply, and capacity;
- a frozen two-week MPS zone and controlled changes thereafter;
- engineering-change approval linked to BOM revision dates;
- MRP for compressors, control boards, and major subassemblies;
- Kanban for standard fasteners and packaging;
- supplier visibility of the compressor MPS and on-hand balance;
- weekly capacity checks for compressor testing and final assembly;
- exception reports for late orders, projected shortages, and obsolete stock.
OutcomeAfter two planning cycles, emergency compressor orders declined, and the number of fastener stockouts fell. Inventory did not fall uniformly: safety stock for compressors was retained because of long supply risk, while low-risk consumables were reduced. The company also discovered that better data discipline, rather than a particular software feature, produced much of the improvement. Learning pointsThe case demonstrates that planning methods must be matched to demand and supply characteristics. MRP, Kanban, VMI, and safety stock can coexist. The essential requirements are accurate master data, disciplined governance, realistic lead times, capacity validation, and clear accountability. 10. Implementation, Technology, and GovernanceEnterprise resource planning (ERP) systems integrate MPS, MRP, purchasing, inventory, warehouse transactions, and supplier information. Advanced planning and scheduling systems may add finite-capacity scheduling, scenario analysis, constraint modelling, and optimisation. Warehouse-management systems improve location, scanning, lot, and serial control. Artificial intelligence and machine learning can support demand sensing, anomaly detection, lead-time prediction, supplier-risk monitoring, and parameter recommendations. Their value depends on data quality and human oversight. An algorithm trained on historical shortages may interpret expedites as normal demand and reproduce the same instability. Planners should therefore validate recommendations, document overrides, monitor bias, and preserve audit trails. Governance should define: - ownership of item, BOM, lead-time, and supplier master data;
- approval of engineering changes and substitutions;
- inventory ownership and valuation under VMI or consignment;
- service-level, liability, quality, and data-sharing obligations;
- cybersecurity and access controls;
- treatment of obsolete, damaged, expired, or recalled materials;
- escalation procedures for shortages and capacity failures.
Relevant performance measures include schedule adherence, supplier on-time delivery, inventory accuracy, forecast error, stockout frequency, inventory turns, order-cycle time, planned-order stability, capacity utilisation, and obsolete inventory. Metrics should be balanced. Reducing inventory while increasing stockouts is not an improvement in total supply-chain performance. Challenges and LimitationsMaterials planning faces several limitations: - forecasts are uncertain, especially for new products;
- BOMs may not reflect actual consumption or yield;
- lead times vary with congestion and supplier priorities;
- safety stock can conceal process problems;
- local optimisation can shift inventory or cost elsewhere;
- ERP outputs are only as reliable as transaction discipline;
- pull systems can fail when replenishment is disrupted;
- JIT can be vulnerable to disasters, geopolitical events, and transport interruptions;
- VMI may create dependence or disputes over data and ownership;
- consignment can obscure accountability for loss and obsolescence.
Resilience requires segmentation rather than indiscriminate buffering. Critical items may need dual sourcing, qualified substitutes, strategic stock, or contingency capacity. Less critical items may be managed with simpler replenishment rules. Best-Practice Checklist- Keep BOMs, inventory balances, lead times, units of measure, and revision dates accurate.
- Separate independent demand from dependent demand.
- Establish MPS time fences and a formal change-control process.
- Use realistic, periodically reviewed lead times.
- Validate MRP results against supplier, labour, machine, warehouse, and transport capacity.
- Match replenishment method to demand stability, value, criticality, and supply risk.
- Use exception management rather than manually reviewing every item equally.
- Integrate engineering, procurement, production, logistics, finance, and suppliers.
- Measure service, total cost, stability, and resilience together.
- Treat technology as an enabler of disciplined processes, not a substitute for them.
Chapter SummaryMaterials planning translates demand into coordinated decisions about production, procurement, inventory, and distribution. The MPS establishes end-item requirements; the BOM explodes those requirements into dependent component demand; MRP nets inventory and scheduled receipts, applies lot-sizing rules, and offsets orders by lead time. DRP extends similar time-phased logic across distribution networks. Capacity information is necessary because a material plan is feasible only when suppliers, machines, labour, testing, warehouse space, and transport can support it. Push systems provide advance coordination, whereas pull systems respond to consumption. JIT and Kanban reduce waste and work-in-process when processes are stable. VMI and consignment shift elements of replenishment responsibility, information access, ownership, and financial risk between supply-chain partners. Effective implementation depends on accurate master data, controlled changes, realistic lead times, capacity validation, appropriate segmentation, and balanced performance measures. The strongest organisations use hybrid systems rather than treating any single planning philosophy as universally applicable. Key TermsBill of materials: Structured list of components and quantities required to make an item. Capacity requirements planning: Analysis of whether available resources can execute planned orders. Consignment inventory: Stock owned by the supplier until consumption or another agreed transfer event. Dependent demand: Demand calculated from the requirements of a parent item. Distribution requirements planning: Time-phased replenishment planning for distribution locations. Engineering change control: Formal authorisation and communication of product or process revisions. Frozen zone: Planning period in which changes are highly restricted. Gross requirement: Total requirement before inventory and scheduled receipts are deducted. Independent demand: Demand originating from customers or forecasts rather than a parent item. Just-in-time: System for synchronising supply and production while eliminating waste. Kanban: Signal that authorises replenishment or movement based on consumption. Lot-for-lot: Lot-sizing rule that orders the exact net requirement. Master production schedule: Time-phased plan for producing specified finished items. Material requirements planning: System that calculates time-phased dependent-material requirements. Net requirement: Additional supply needed after available inventory and scheduled receipts are considered. Planned order release: Date an order should be issued or production started. Safety stock: Inventory held against uncertainty. Vendor-managed inventory: Arrangement in which a supplier monitors and replenishes customer inventory under agreed rules. Review Questions5 Short Answer Questions- Distinguish independent demand from dependent demand.
- What information does a BOM provide to MRP?
- Explain the difference between a planned order receipt and a planned order release.
- What is the purpose of a frozen zone in an MPS?
- State one major difference between VMI and consignment inventory.
5 Long Answer Questions- Explain the relationship among S&OP, the MPS, BOM explosion, MRP, purchasing, and capacity planning.
- Discuss the assumptions and limitations of the classical EOQ model in a dependent-demand environment.
- Compare push, pull, JIT, and Kanban systems, including conditions under which each is appropriate.
- Explain how inaccurate BOMs and lead times affect inventory, service, and production performance.
- Discuss the governance requirements for implementing VMI and consignment inventory.
3 Analytical / Application Questions- A product requires 4 units of component B. The MPS calls for 150 units in week 2 and 100 units in week 3. Component B has 80 units on hand, no scheduled receipts, safety stock of 20 units, and a one-week lead time. Using lot-for-lot logic, calculate the planned receipts and releases.
- A distribution centre consumes 60 units per day. Replenishment lead time is 3 days, the safety factor is 15%, and each Kanban container holds 30 units. Calculate the number of containers, rounding up, and state two assumptions behind the calculation.
- Recommend a planning approach for a critical imported component, a stable locally sourced fastener, and a high-value item with uncertain demand. Justify the role of MRP, Kanban, safety stock, VMI, or consignment in each recommendation.
Multiple Choice Questions with AnswersQuestion 1Which document provides the product structure used to calculate dependent component requirements? A. Bill of materials B. Goods-received note C. Sales invoice D. Warehouse picking list Correct Answer: A. Bill of materials Question 2A parent item requires 3 components per unit. If the MPS plans 400 parent units and no yield loss is assumed, what is the gross component requirement? A. 133 units B. 397 units C. 1,200 units D. 1,600 units Correct Answer: C. 1,200 units Question 3What is the main purpose of netting in MRP? A. To convert machine hours into labour hours B. To subtract usable inventory and scheduled receipts from gross requirements C. To determine customer selling prices D. To approve engineering revisions Correct Answer: B. To subtract usable inventory and scheduled receipts from gross requirements Question 4An order is required in week 5 and has a two-week lead time. In which week should it be released, assuming no other constraints? A. Week 2 B. Week 3 C. Week 4 D. Week 7 Correct Answer: B. Week 3 Question 5Which approach replenishes stock primarily in response to actual downstream consumption? A. Push planning B. Pull planning C. Aggregate forecasting D. Capacity smoothing Correct Answer: B. Pull planning Question 6A Kanban system has demand of 50 units per hour, lead time of 2 hours, a 20% safety factor, and containers holding 25 units. How many containers are required after rounding up? A. 4 B. 5 C. 6 D. 8 Correct Answer: C. 6 Question 7Which statement best describes consignment inventory? A. The customer always owns stock before it is shipped B. The supplier owns stock until a specified transfer event, often consumption C. Stock cannot be stored at the customer’s facility D. The inventory is never included in physical counts Correct Answer: B. The supplier owns stock until a specified transfer event, often consumption Question 8What does capacity requirements planning primarily test? A. Whether planned orders can be supported by available resources B. Whether product prices exceed material costs C. Whether customer addresses are correct D. Whether a BOM has marketing approval Correct Answer: A. Whether planned orders can be supported by available resources Question 9Which condition most supports the use of Kanban? A. Highly irregular demand and unreliable replenishment B. Stable consumption, standard containers, and dependable processes C. No visibility of downstream usage D. A product with no repeatable process Correct Answer: B. Stable consumption, standard containers, and dependable processes Question 10In vendor-managed inventory, who normally makes replenishment decisions within agreed rules? A. The end customer exclusively B. The transport carrier C. The supplier D. The external auditor Correct Answer: C. The supplier
|