Inventory Management & Control

Chapter 12
Specialized Inventory and Resilience

Post Graduate Programme in Materials Management
Inventory Management & Control   •   Post Graduate

Specialized Inventory and Resilience

Introduction

Inventory policy is most difficult when demand is uncertain, failure is costly, replenishment is slow, storage conditions are restrictive, or supply continuity is threatened. Conventional cycle-stock methods work reasonably well for stable, repeatable demand. They are less reliable for aircraft components, emergency medical supplies, maintenance spares, pharmaceuticals, chemicals, seasonal merchandise, returned products and items whose demand occurs irregularly.

Specialized inventory management therefore requires more than calculating an economic order quantity. It requires classification of consequences, failure modes, service obligations, regulatory constraints, lead-time exposure and recovery options. The central managerial question changes from “How cheaply can stock be held?” to “What inventory position provides an economically and operationally defensible level of continuity?”

Resilience extends this logic. A resilient inventory system can anticipate disruption, absorb shocks, maintain essential operations, recover within an acceptable time and adapt after learning from the event. Resilience does not mean holding unlimited stock. It means combining inventory with suppliers, information, substitution, capacity, contracts, transport alternatives and disciplined governance.

Learning Objectives

After studying this chapter, the learner should be able to:

  1. Distinguish spare-parts, critical, intermittent-demand, perishable, seasonal, hazardous and reverse-flow inventories.
  2. Select appropriate forecasting, stocking and replenishment policies for specialized items.
  3. Relate service level, downtime cost, obsolescence, shelf life and risk to inventory decisions.
  4. Apply relevant quantitative models, including safety stock, reorder points and intermittent-demand measures.
  5. Design a disruption-risk and continuity-planning framework.
  6. Evaluate technology, governance, ethical and regulatory implications.
  7. Critically assess trade-offs between efficiency, resilience and sustainability.

1. A Contingency View of Specialized Inventory

The correct policy depends on the interaction of six attributes:

AttributeTypical management question
Demand patternIs demand smooth, intermittent, lumpy or seasonal?
Consequence of shortageDoes shortage cause inconvenience, lost sales, production stoppage or danger to life?
Replenishment exposureHow long and how variable is supply lead time?
Product constraintIs the item perishable, hazardous, regulated or temperature-sensitive?
SubstitutabilityCan another item, supplier, process or repair method be used?
Recovery requirementHow quickly must service be restored after disruption?

A useful policy does not classify an item only by annual consumption value. ABC analysis measures expenditure concentration, but a low-value fuse may be operationally more important than a high-value office machine. A complementary criticality classification considers safety, environmental, legal, operational and reputational consequences.

A practical segmentation matrix combines value and criticality:

SegmentTypical policy
High value, high criticalityTight authorization, risk-adjusted safety stock, qualified dual supply and continuous review
High value, low criticalitySmall lots, postponement, supplier flexibility and strict working-capital control
Low value, high criticalityStandardization, guaranteed availability, local storage or emergency sourcing
Low value, low criticalitySimplified controls, periodic review and rationalized catalogue

This matrix should be supplemented by lifecycle status. New, mature, declining and obsolete items have different forecasting and sourcing requirements. A discontinued spare may require a final procurement decision even when current demand is negligible.

2. Spare Parts and Critical Inventory

2.1 Nature of spare-parts demand

Spare-parts demand is derived from equipment failures, preventive-maintenance schedules, refurbishment and operating conditions. It is therefore not necessarily correlated with production volume. A component may be consumed only once every several years, yet its absence may stop a plant immediately.

Spare parts commonly exhibit:

  • intermittent and lumpy demand;
  • long or uncertain supplier lead times;
  • technological obsolescence;
  • high variety and low individual throughput;
  • repairable or recoverable units;
  • strong dependence on installed equipment and failure modes.

The first control is a sound asset and bill-of-materials record. Part-number duplication, obsolete specifications and inaccurate equipment hierarchies create artificial shortages and excess stock.

2.2 Criticality assessment

Criticality should be assessed using evidence rather than intuition. Relevant dimensions include:

  • maximum tolerable downtime;
  • safety and environmental effect of failure;
  • availability of substitutes;
  • repair time and technical complexity;
  • supplier lead time and geographic concentration;
  • installed base and failure frequency;
  • regulatory or contractual service obligations.

A weighted scoring model may be used, provided that managers document the weights and review them. For criterion scores cᵢ and weights wᵢ, where weights sum to 1:

C = ∑(i=1 to n) wᵢcᵢ

Here C is the composite criticality score, cᵢ is the normalized score for criterion i, and wᵢ is its importance weight. The model is a prioritization aid, not a substitute for engineering judgment. A single catastrophic safety consequence may justify escalation even if the total score is moderate.

2.3 Stocking policies for spares

Common policies include:

  1. Base-stock policy: maintain a target position and replenish each withdrawal. Suitable for critical items with frequent or consequential demand.
  2. Min–max policy: reorder at the minimum level and replenish toward the maximum. Suitable for moderate-value maintenance items.
  3. Periodic review: inspect stock at fixed intervals and order to a target level. Suitable when transaction costs are high and demand is relatively predictable.
  4. Emergency procurement: hold little or no stock but rely on rapid supplier response. Appropriate only when response time and supplier reliability are demonstrably adequate.
  5. Repair-and-return: use repairable pools, exchange units and turnaround-time control. This can reduce total ownership cost but requires reliable reverse logistics.

For a continuously reviewed item with approximately stable demand, independent replenishment lead time and normally distributed demand during lead time, the reorder point is:

ROP = μₗ + zσₗ

μₗ is expected demand during lead time, σₗ is the standard deviation of lead-time demand, and z is the standard-normal service factor. The units of ROP are units of inventory. The formula assumes that demand and lead-time uncertainty can be represented adequately by the estimated distribution and that replenishment is triggered when inventory position reaches ROP.

If daily demand has mean d and standard deviation σ_d, lead time is constant L days, and daily observations are independent, then:

μₗ = dL
σₗ = σd√L

Thus safety stock is zσ_d√L. If lead time is also variable, with independent demand and lead-time variation, a commonly used approximation is:

σₗ = √(Lσd² + d²σL²)

where σ_L is the standard deviation of lead time in days. If demand and lead time are correlated, the covariance term must be considered; blindly applying the independent formula can understate risk.

For highly critical spares, a cost-based model may be more appropriate than a target service level. The relevant comparison includes the marginal cost of holding another unit, the probability of shortage, downtime cost, emergency freight and safety consequences. A high stock value does not automatically justify a low service level.

3. Intermittent-Demand Inventory

Intermittent demand contains periods of zero demand separated by non-zero transactions. Lumpy demand also has high variation in the size of non-zero demands. Standard moving averages often perform poorly because zeros dilute the forecast and large events are difficult to anticipate.

Two descriptive measures are useful:

  • Inter-demand interval: the average number of periods between non-zero demands.
  • Demand-size variation: variation in the magnitude of non-zero demands.

Croston-type methods separately estimate the size of demand and the interval between demands. In a basic form, when demand occurs, the estimates are updated using smoothing parameter α, where 0 < α ≤ 1:

qₜ = qₜ₋₁ + α(xₜ − qₜ₋₁)

pₜ = pₜ₋₁ + α(τₜ − pₜ₋₁)

fₜ₊₁ = qₜ ÷ pₜ

qₜ is estimated non-zero demand size, pₜ is estimated inter-demand interval, xₜ is observed non-zero demand and τₜ is the interval since the preceding demand. The forecast fₜ₊₁ is average demand per period. The method is intended for intermittent demand and requires careful treatment of the initial values and forecast bias. It does not by itself determine safety stock or account for obsolescence.

For service measurement, fill rate and cycle-service level must be distinguished. Cycle-service level is the probability of no stockout during a replenishment cycle. Fill rate is the proportion of demand quantity supplied immediately. A system can have a high cycle-service level but a poor fill rate when occasional demand is very large.

For intermittent items, planners should also examine:

  • demand occurrence probability;
  • maximum credible demand rather than only the mean;
  • emergency procurement time;
  • equipment population and failure exposure;
  • commonality across multiple assets;
  • obsolescence and repair alternatives.

4. Perishable and Seasonal Inventory

4.1 Perishable inventory

Perishable inventory loses value through physical deterioration, expiry or legal restriction. Examples include food, vaccines, reagents and some adhesives. The effective inventory decision includes quantity, age and remaining shelf life.

A single-period or newsvendor model can help with a one-season decision. If demand is uncertain and unsold stock has a salvage value, the critical fractile is:

P(D ≤ Q*) = (Cᵤ) ÷ (Cᵤ + Cₒ)

Q* is the target order quantity, D is demand, Cᵤ is underage cost per unit and Cₒ is overage cost per unit. Underage cost may include lost margin, emergency replenishment and service consequences; overage cost includes purchase cost less salvage value, disposal and handling. The model assumes a single replenishment decision, known cost parameters and a specified demand distribution. It is not automatically suitable for multi-period products with replenishment opportunities.

Operational controls include FEFO—first-expiry, first-out—rather than merely FIFO; lot traceability; expiry alerts; temperature monitoring; quarantine procedures; validated storage; and disposal authorization. A product that remains physically present but cannot legally or clinically be used is not available inventory.

4.2 Seasonal inventory

Seasonality produces predictable variation across months, holidays, weather conditions or agricultural cycles. The objective is to position inventory before the demand peak without creating excessive post-season stock.

Seasonal planning combines:

  • baseline demand and seasonal indices;
  • promotion and price effects;
  • supplier capacity and pre-season constraints;
  • postponement or late customization;
  • markdown, transfer, return or salvage options;
  • forecast error and event uncertainty.

Seasonality should not be confused with trend. A seasonal index represents recurring relative variation, whereas trend represents longer-term growth or decline. Forecast systems should prevent calendar effects from being interpreted as permanent demand changes.

5. Hazardous and Regulated Inventory

Hazardous inventory includes flammable, explosive, toxic, corrosive, infectious, radioactive or environmentally harmful materials. The inventory decision is inseparable from legal compliance and risk control.

A sound policy covers:

  • approved classification and labelling;
  • segregation of incompatible substances;
  • quantity limits and authorized storage locations;
  • safety data sheets and employee training;
  • personal protective equipment and emergency equipment;
  • inspection, leak detection and incident reporting;
  • secure access and chain of custody;
  • licensed transportation and disposal;
  • emergency response and community protection.

The economic order quantity cannot justify unsafe storage. A larger batch may reduce ordering cost but increase exposure, insurance requirements and consequence severity. Conversely, excessive decentralization may increase transport risk. Decisions should be reviewed by competent safety, environmental and regulatory specialists.

Governance is especially important where inventory data can enable misuse, theft or unsafe handling. Access controls, segregation of duties and audit trails should be applied to high-consequence materials.

6. Reverse-Flow Inventory and Circular Operations

Reverse-flow inventory moves from the customer or user back toward inspection, repair, remanufacture, recycling, resale or disposal. Examples include returned products, reusable packaging, warranty units, recoverable spares and end-of-life electronics.

The reverse process usually includes:

  1. authorization and collection;
  2. transportation and receipt;
  3. identification and inspection;
  4. grading or testing;
  5. disposition decision;
  6. repair, refurbishment, harvesting or recycling;
  7. reintegration into available stock or certified disposal.

Reverse supply is uncertain in both timing and quality. A returned unit is not equivalent to a new unit until inspection establishes its condition. Inventory records should therefore distinguish expected returns, quarantined returns, repairable stock, certified serviceable stock and scrap.

A closed-loop policy may lower material cost and emissions, but it can introduce testing cost, warranty risk, contamination risk and longer cycle time. Product design for disassembly, common components, serial-level traceability and clear ownership of returned goods materially improve reverse-flow performance.

7. Resilience, Disruption Risk and Continuity

7.1 Resilience versus robustness

Robustness is the ability to continue operating despite disturbances. Resilience additionally includes recovery, adaptation and learning. A robust inventory policy may use buffers; a resilient system combines buffers with visibility, alternatives and rapid decision-making.

Disruptions may arise from supplier failure, natural hazards, cyberattack, transport interruption, labour action, geopolitical conflict, quality incidents, epidemics, utility failure or sudden regulatory change. Risk should be assessed through both probability and consequence. Rare events cannot be dismissed solely because historical frequency is low.

A basic expected-loss representation is:

EL = ∑(j=1 to m) PⱼIⱼ

Pⱼ is the probability of disruption scenario j and Iⱼ is its impact, measured in an appropriate monetary or operational unit. Expected loss is useful for comparison but can understate catastrophic or highly uncertain outcomes. Scenario analysis, stress testing and risk appetite are therefore necessary complements.

7.2 The resilience portfolio

Resilience should be designed as a portfolio of measures:

  • strategic safety stock for essential items;
  • multiple qualified suppliers;
  • geographic diversification;
  • alternative materials and approved substitutes;
  • flexible manufacturing or postponement;
  • supplier capacity reservations;
  • emergency logistics contracts;
  • repair, remanufacturing and recovery capability;
  • accurate multi-echelon inventory visibility;
  • documented business-continuity procedures.

Each measure has cost and failure modes. Dual sourcing can reduce supplier concentration but may reduce volume leverage and complicate quality assurance. Local stock can shorten response time but increase inventory duplication. Visibility technology may improve detection while creating cybersecurity exposure.

7.3 Multi-echelon resilience

Inventory exists at suppliers, central warehouses, regional facilities, service vehicles and points of use. Optimizing each location independently can produce excessive total stock or hidden shortages. A multi-echelon approach considers where a unit should be held to serve several downstream locations and how transportation time affects service.

For critical items, positioning a small number of units centrally may be efficient if emergency transport is reliable. For geographically dispersed assets with severe downtime cost, local positioning may be justified. The answer depends on total response time, not warehouse stock alone.

7.4 Business continuity and recovery time

Continuity planning defines essential processes, minimum operating levels, maximum tolerable outage and recovery time objectives. Inventory policy should be linked to these requirements. If a process must recover within 24 hours, a supplier with a 30-day lead time cannot be the sole continuity solution.

A continuity plan should specify:

  • critical products, equipment and processes;
  • trigger thresholds and decision authority;
  • substitute materials and approved deviations;
  • alternate suppliers and transport routes;
  • emergency stock locations;
  • communication protocols;
  • regulatory and customer notifications;
  • recovery testing and post-event review.

8. Worked Example: Critical Maintenance Component

An engineering firm uses a critical sensor. Average demand is 0.20 units per day, daily demand standard deviation is 0.30 units, and supplier lead time is constant at 20 days. Management selects a 99% cycle-service level, for which z is approximately 2.33. Assume independent daily demand and a normal approximation.

Expected lead-time demand is:

μₗ = dL = 0.20 × 20 = 4.0 units

Lead-time standard deviation is:

σₗ = σd√L = 0.30√20 ≈ 1.34 units

Safety stock is:

SS = zσₗ = 2.33 × 1.34 ≈ 3.12 units

The reorder point is therefore:

ROP = 4.0 + 3.12 = 7.12 units

Since physical stock is normally counted in whole units, the policy would use an ROP of 8 units, subject to review of the discrete demand distribution and the fact that a normal model can produce unrealistic probabilities for low-volume items. The analysis also reveals an important managerial issue: if one sensor prevents a costly shutdown, the target service level may be justified; if an approved substitute exists, the policy could be less costly. The calculation is a starting point, not the final decision.

9. Illustrative Case: Resilience at NorthRiver Water Utility

Background

NorthRiver Water Utility operates treatment plants across three regions. Chlorine dosing equipment depends on a specialized valve supplied by one overseas manufacturer. Annual consumption is low, demand is intermittent and each valve is inexpensive relative to the cost of a plant outage. The valve is also subject to regulatory approval.

Problem

A port closure delayed shipments for eight weeks. Two plants had no spare valve, and emergency procurement required technical revalidation. The utility had adequate total inventory on paper, but the stock was concentrated at one central depot and transport access was disrupted.

Analysis

The utility mapped installed assets, failure modes, lead times and substitute possibilities. It discovered duplicate part numbers, inconsistent minimum levels and no formal criticality score. Historical average demand understated exposure because failure events were clustered during severe operating conditions. The central depot’s stock did not satisfy the plants’ recovery-time objectives.

Approach

NorthRiver adopted a resilience portfolio:

  • classified dosing valves as high-criticality items;
  • established local emergency quantities at each plant;
  • retained a central reserve for network balancing;
  • qualified a second supplier and an approved alternative design;
  • introduced serial-level records and failure reporting;
  • contracted emergency transport routes;
  • tested a quarterly continuity drill;
  • created expiry and inspection controls for stored seals and related consumables.

The utility did not simply double inventory. It reduced duplicate part numbers, improved repair capability and used a risk-based allocation model. Supplier contracts included notification of capacity changes and quality documentation.

Outcome

In a subsequent regional transport disruption, the plants maintained treatment operations while the central reserve was repositioned. Total inventory value increased modestly, but expected downtime exposure fell substantially. The exercise also identified a cyber vulnerability in the warehouse system, leading to offline emergency records and stronger access controls.

Learning points

  1. Total network stock is not the same as usable stock.
  2. Criticality depends on consequences, substitutes and recovery time.
  3. Resilience is achieved through complementary measures rather than inventory alone.
  4. Continuity exercises reveal dependencies that routine reporting misses.
  5. Regulatory approval must be integrated into substitute and recovery planning.

10. Performance Measurement and Governance

Specialized inventory requires a balanced scorecard. Useful measures include:

DimensionExample measures
Servicecritical-item availability, downtime hours, emergency fill rate
Forecastingbias, interval error, demand-occurrence accuracy
Working capitalinventory value, obsolescence, repairable-pool utilization
Resiliencerecovery time, supplier concentration, tested alternatives
Quality and safetyexpiry losses, incidents, quarantine duration, audit findings
Sustainabilitydisposal volume, return recovery rate, emissions from emergency freight

Metrics require precise definitions. “Availability” may mean system availability, stock availability or technical serviceability. A high fill rate achieved by excessive emergency freight is not necessarily good performance. Conversely, a low consumption rate for a critical spare may reflect successful prevention rather than overstocking.

Policies should include ownership, approval limits, review frequency, exception handling and audit evidence. Master-data governance is particularly important: wrong units of measure, duplicate specifications, inaccurate lead times and missing shelf-life data can invalidate sophisticated analytics.

11. Technology and Artificial Intelligence

Technologies supporting specialized inventory include enterprise asset-management systems, warehouse management systems, RFID, barcode and serial tracking, IoT condition monitoring, digital twins and supplier-risk platforms. Predictive maintenance can use vibration, temperature, pressure or operating-hour data to estimate failure risk and improve spare positioning.

Artificial intelligence can support anomaly detection, demand classification, supplier-risk scanning and recommendation of reorder policies. However, its use requires:

  • reliable and sufficiently long historical data;
  • explainable recommendations for safety-critical decisions;
  • human approval for substitutions and regulatory actions;
  • monitoring for data drift and model bias;
  • cybersecurity and access control;
  • clear accountability when recommendations are wrong.

AI should not be used to create false precision. Sparse intermittent demand and unprecedented disruptions provide weak evidence for purely statistical prediction. Scenario analysis, engineering knowledge and expert challenge remain essential.

12. Challenges, Limitations and Ethical Issues

The principal challenge is that resilience is partly an insurance decision. The benefit of preparedness is often invisible when disruption does not occur, while its cost appears in current budgets. Managers may therefore underinvest until a failure exposes the weakness.

Other limitations include:

  • unreliable probability estimates for rare events;
  • trade-offs between local autonomy and network efficiency;
  • obsolete or counterfeit spare parts;
  • supplier reluctance to disclose capacity and risk information;
  • conflicting objectives among finance, operations, engineering and safety;
  • excessive reliance on historical demand;
  • environmental harm from disposal and emergency transport.

Ethically, organizations must not reduce safety stock where doing so creates unacceptable risk to workers, patients, customers or communities. Hazardous materials require protection of both employees and the public. Perishable medical inventory raises equity issues when allocation is constrained. Reverse logistics must avoid exporting hazardous waste or exploiting informal recycling labour. Resilience planning should also consider vulnerable communities rather than protecting only the most profitable operations.

Best-Practice Framework

A mature specialized-inventory programme should:

  1. establish accurate item, asset and supplier master data;
  2. classify value, criticality, demand pattern, shelf life and hazard;
  3. quantify service and recovery requirements;
  4. model demand and lead-time uncertainty transparently;
  5. combine inventory with sourcing, repair, substitution and logistics alternatives;
  6. design FEFO, quarantine, segregation and traceability controls where required;
  7. evaluate network rather than isolated locations;
  8. conduct disruption scenarios and continuity exercises;
  9. monitor service, cost, risk, quality and sustainability together;
  10. review policies after failures, near misses, engineering changes and supplier events.

Chapter Summary

Specialized inventory cannot be managed effectively through a single universal model. Spare parts require asset knowledge, criticality analysis and attention to downtime and obsolescence. Intermittent demand requires separate treatment of demand occurrence and demand size. Perishable inventory requires shelf-life control, FEFO and disposal governance, while seasonal inventory requires pre-positioning and post-season strategies. Hazardous inventory is governed first by safety and regulation, and reverse-flow inventory depends on inspection, grading, repair and traceability.

Resilience combines anticipation, absorption, recovery and learning. Its instruments include safety stock, multi-echelon positioning, qualified suppliers, substitutes, repair capability, emergency logistics, visibility and tested continuity plans. Quantitative formulas such as reorder points, safety stock and critical fractiles are useful only when their assumptions, units and limitations are understood. Effective governance balances service, working capital, safety, sustainability and ethical responsibility.

Key Terms

Critical inventory: Stock whose shortage has serious operational, safety, legal or financial consequences.

Spare part: An item held to restore or maintain equipment.

Intermittent demand: Demand with repeated periods of zero consumption.

Lumpy demand: Intermittent demand with highly variable non-zero quantities.

Criticality: The consequence and urgency associated with item unavailability.

Reorder point: Inventory position at which replenishment is initiated.

Safety stock: Additional stock held to protect against uncertainty.

Cycle-service level: Probability of no stockout during a replenishment cycle.

Fill rate: Proportion of demand supplied immediately from available stock.

Perishable inventory: Stock that loses usability or value with time.

FEFO: First-expiry, first-out issuing policy.

Seasonal inventory: Stock positioned to meet recurring time-based demand variation.

Hazardous inventory: Materials presenting physical, health or environmental danger.

Reverse logistics: Movement of products or materials back from users for recovery or disposal.

Repairable pool: Collection of units that can be repaired and returned to service.

Resilience: Capacity to anticipate, absorb, recover from and adapt to disruption.

Robustness: Ability to continue functioning despite disturbance.

Recovery time objective: Maximum acceptable time to restore a process or service.

Critical fractile: Target cumulative demand probability in a single-period stocking model.

Multi-echelon inventory: Inventory managed across several connected supply-chain levels.

Review Questions

Short Answer Questions

  1. Why can ABC analysis alone misclassify critical spare parts?
  2. Distinguish cycle-service level from fill rate.
  3. What is the purpose of FEFO in perishable inventory?
  4. Identify four dimensions used in criticality assessment.
  5. How does reverse-flow inventory differ from conventional forward inventory?

Long Answer Questions

  1. Explain how a firm should design a policy for intermittent-demand spare parts.
  2. Discuss the relationship between inventory efficiency and supply-chain resilience.
  3. Compare the managerial requirements of perishable, seasonal and hazardous inventory.
  4. Explain how multi-echelon positioning can improve continuity while controlling total inventory.
  5. Evaluate the role and limitations of artificial intelligence in specialized inventory management.

Analytical / Application Questions

  1. A critical item has daily demand mean 0.5 units, daily standard deviation 0.4 units, constant lead time of 16 days and a target z-value of 2.05. Assuming independent daily demand and a normal approximation, calculate lead-time demand, safety stock and reorder point. State one limitation of the calculation.
  2. A hospital has a low-use implant with a long lead time and no approved substitute. Design a policy addressing criticality, stocking location, expiry, supplier risk, traceability and continuity testing.
  3. A manufacturer must choose between holding additional local stock and qualifying a second supplier. Develop a decision framework that considers cost, recovery time, supplier reliability, regulatory approval, environmental impact and catastrophic risk.

Multiple Choice Questions with Answers

Question 1

Which characteristic most strongly distinguishes a critical spare from an ordinary low-demand item?

A. Its annual purchase price is always high

B. Its shortage can cause serious operational, safety or legal consequences

C. It is always consumed every month

D. It can never be repaired

Correct Answer: B. Its shortage can cause serious operational, safety or legal consequences

Question 2

Under the stated assumptions, if average daily demand is d and constant lead time is L, expected lead-time demand is:

A. d ÷ L

B. d + L

C. dL

D. L ÷ d

Correct Answer: C. dL

Question 3

Which issuing rule is generally preferred for products controlled by expiry date?

A. LIFO

B. FEFO

C. Random issue

D. Highest-cost-first

Correct Answer: B. FEFO

Question 4

A key limitation of a basic Croston-type method is that it:

A. Cannot represent any zero demand

B. Separately estimates demand size and interval but does not by itself determine safety stock

C. Requires demand to be perfectly seasonal

D. Can only be used for hazardous materials

Correct Answer: B. Separately estimates demand size and interval but does not by itself determine safety stock

Question 5

Which statement best describes resilience?

A. It means maximizing inventory at every location

B. It means eliminating all uncertainty

C. It combines anticipation, absorption, recovery and adaptation

D. It is identical to minimizing procurement cost

Correct Answer: C. It combines anticipation, absorption, recovery and adaptation

Question 6

If daily demand standard deviation is σ_d and constant lead time is L, under independent daily demand the lead-time standard deviation is:

A. σ_dL

B. σ_d ÷ √L

C. σ_d√L

D. σ_d + L

Correct Answer: C. σ_d√L

Question 7

Which control is especially important for hazardous inventory?

A. Ignoring segregation requirements to reduce handling

B. Using safety stock as a substitute for legal compliance

C. Segregation of incompatible substances and controlled access

D. Removing all labels from containers

Correct Answer: C. Segregation of incompatible substances and controlled access

Question 8

In reverse logistics, a returned unit should normally be treated as serviceable stock:

A. Immediately upon customer return

B. Only after inspection, testing or certification establishes its condition

C. Only when its purchase price is known

D. Before transportation is arranged

Correct Answer: B. Only after inspection, testing or certification establishes its condition

Question 9

The critical fractile in a single-period stocking model is based primarily on:

A. Underage and overage costs

B. Warehouse floor area only

C. Supplier count only

D. Historical average price only

Correct Answer: A. Underage and overage costs

Question 10

Why may centrally held inventory fail to provide resilience to geographically dispersed facilities?

A. Central stock is never counted in inventory records

B. Transport disruption or excessive response time can make it unusable when needed

C. Central warehouses cannot hold spare parts

D. Local facilities always have lower demand

Correct Answer: B. Transport disruption or excessive response time can make it unusable when needed

Inventory Management & Control
Chapter 12 of 15