Scheduling, Resources and Site LogisticsIntroductionInterior projects are often judged by visible outcomes—spatial quality, material finish, functionality and client satisfaction—but these outcomes depend heavily on invisible systems of planning. A well-designed interior can still fail commercially if materials arrive late, trades interfere with one another, labour is poorly coordinated, or work disrupts an occupied building. Scheduling, resource planning and site logistics convert a design proposal into a controlled sequence of physical production. In interior project management, a schedule is not merely a calendar. It is a time-based model of scope, dependencies, resources, procurement, access and risk. Effective scheduling answers five linked questions: - What work must be completed?
- In what logical order must it occur?
- How long will each activity take?
- What labour, materials, equipment and information are required?
- How can the work be delivered safely and efficiently within the site constraints?
This chapter develops practical methods for activity networks, Gantt schedules, milestones, critical-path analysis, resource planning, procurement lead-time management and logistics in both vacant and occupied environments. Learning ObjectivesBy the end of this chapter, students should be able to: - decompose an interior project into manageable activities and work packages;
- construct precedence networks and Gantt schedules;
- calculate early and late dates, float and the critical path;
- estimate activity durations using realistic assumptions;
- plan labour, materials, plant, information and specialist resources;
- integrate procurement lead times into the master programme;
- design site-access, storage, delivery, phasing and waste-management arrangements;
- adapt construction methods to occupied buildings; and
- evaluate schedule risks, ethical responsibilities and digital planning tools.
1. The Structure of an Interior Project ScheduleA project schedule should begin with a work breakdown structure (WBS). The WBS divides the project into deliverables and work packages rather than beginning with isolated dates. A typical small commercial fit-out may include: | Level | Example |
|---|
| Project | Retail fit-out | | Deliverable | Back-of-house installation | | Work package | Joinery, plumbing, electrical and finishes | | Activity | Install sink, connect waste and test supply |
An activity should have a clear start condition, finish condition, responsible party, estimated duration and required resources. “Complete reception area” is too broad for reliable control. “Install reception counter carcass,” “fit solid-surface top,” and “connect data outlets” are more measurable activities. 1.1 Activity attributesEach activity normally includes: - an identification code;
- a description and measurable output;
- predecessor and successor relationships;
- duration and calendar assumptions;
- labour and equipment requirements;
- material and information requirements;
- location or work zone;
- quality and safety constraints; and
- acceptance or handover criteria.
The level of detail must be appropriate. Excessively large activities conceal risk; excessively small activities create administrative burden. A useful activity may represent between one day and two weeks of work, although specialist or procurement activities may be longer. 1.2 Types of logical relationshipsThe most common relationship is finish-to-start (FS): activity B cannot begin until activity A finishes. For example, final painting may follow plaster repairs. Other relationships are useful when accurately justified: - Start-to-start (SS): one activity may begin when another begins, possibly with a lag.
- Finish-to-finish (FF): two activities must finish together or within a defined relationship.
- Start-to-finish (SF): a successor cannot finish until its predecessor starts; this is uncommon in ordinary fit-out work.
Relationships should express genuine technical or operational logic, not arbitrary preferences. Excessive use of finish-to-start links can make a programme appear longer than necessary, while unjustified overlap can create unsafe or impractical sequencing. 2. Estimating Activity DurationsDuration is the elapsed working time required to complete an activity under stated conditions. It is not identical to labour effort. Installing 100 m² of carpet may require 40 labour-hours, but if two installers work together for 20 hours, the elapsed duration may be approximately three working days after allowing for preparation, movement and breaks. A basic productivity model is: D = \frac{Q}{r × n} where: - D = activity duration in working time;
- Q = quantity of work, such as m², m or units;
- r = productivity per worker per unit time; and
- n = number of equivalent workers.
The model assumes that productivity is reasonably stable, workers are available for the stated period, and the work is not constrained by access, curing, inspection or other resources. In practice, an allowance should be made for handling, setup, supervision, congestion and interruptions. Doubling the workforce does not necessarily halve duration because of limited work fronts, supervision, access or tool availability. For uncertain activities, a three-point estimate can be used. The Program Evaluation and Review Technique (PERT) expected duration is: te = \frac{to + 4tm + tp}{6} where to is the optimistic duration, tm is the most likely duration and tp is the pessimistic duration. The estimate is most useful where the three values are based on informed judgment and the activity has a single dominant uncertainty. It should not be presented as a guarantee or as a substitute for site investigation. For example, a bespoke reception counter has an optimistic duration of 8 working days, a most likely duration of 12 days and a pessimistic duration of 22 days: te = \frac{8 + 4(12) + 22}{6} = \frac{78}{6} = 13\text{ working days} The result is 13 working days. The estimate should also identify the causes of uncertainty, such as shop-drawing approval, material availability or factory rework. 3. Activity Networks and Critical-Path AnalysisAn activity network represents activities and their logical dependencies. It reveals the sequence that controls project completion. The critical path is the longest path through the network, expressed in total duration. Activities on this path have zero total float under the stated assumptions. Consider the following simplified fit-out network: | Activity | Description | Duration | Predecessor |
|---|
| A | Site survey and setting out | 2 days | — | | B | Finalise design information | 4 days | A | | C | Order long-lead lighting | 1 day | B | | D | First-fix electrical work | 5 days | B | | E | Ceiling closure | 3 days | D | | F | Lighting delivery and installation | 4 days | C, E | | G | Testing and handover | 2 days | F |
3.1 Forward passThe forward pass calculates earliest start (ES) and earliest finish (EF). For a single predecessor: EF = ES + D For an activity with several predecessors: ES = max(EF1, EF2, …, EFk) The maximum is necessary because the activity cannot begin until all required predecessors have finished. Taking the values above and using day 0 as the project start: - A: ES 0, EF 2
- B: ES 2, EF 6
- C: ES 6, EF 7
- D: ES 6, EF 11
- E: ES 11, EF 14
- F: ES max(7, 14) = 14, EF 18
- G: ES 18, EF 20
The minimum project duration is therefore 20 working days, excluding calendars, holidays and risk allowances. 3.2 Backward pass and floatThe backward pass calculates latest allowable dates without delaying the project completion date. For the final activity, latest finish (LF) equals the planned project finish. Latest start (LS) is: LS = LF − D For an activity with several successors: LF = min(LS1, LS2, …, LSk) Total float is: TF = LS − ES = LF − EF Total float is the amount of time an activity can move without delaying the calculated project completion. Applying the backward pass gives the following simplified result: | Activity | ES | EF | LS | LF | Total float |
|---|
| A | 0 | 2 | 0 | 2 | 0 | | B | 2 | 6 | 2 | 6 | 0 | | C | 6 | 7 | 13 | 14 | 7 | | D | 6 | 11 | 6 | 11 | 0 | | E | 11 | 14 | 11 | 14 | 0 | | F | 14 | 18 | 14 | 18 | 0 | | G | 18 | 20 | 18 | 20 | 0 |
The critical path is A–B–D–E–F–G, with a duration of 20 working days. Activity C has seven working days of float, but this does not mean it can be ignored. Its delivery must still occur before F begins, and procurement delay can consume its float. Critical-path analysis is a planning model, not a prediction of reality. It depends on accurate durations, logical relationships and a defined working calendar. A non-critical activity can become critical when its float is consumed by late approvals, access restrictions, rework or delivery failure. 4. Gantt Schedules and MilestonesA Gantt schedule displays activities against time. It is particularly effective for communication because it shows duration, overlap, sequence and planned completion. A professional Gantt schedule should distinguish: - baseline dates approved at the planning stage;
- current forecast dates;
- actual start and finish dates;
- critical activities;
- procurement and approval activities;
- milestones; and
- access or shutdown constraints.
A milestone is a zero-duration control point representing a significant event, such as “building permit approved,” “ceiling closed,” “client practical completion inspection,” or “occupation permitted.” Milestones should be objectively verifiable. “Progress is good” is not a milestone. Schedules should be updated using a status date, often weekly. Each update records actual progress, remaining duration, forecast completion and reasons for variance. A bar that is simply coloured as complete can conceal incomplete testing, defects or unresolved documentation. 4.1 Schedule quality principlesA reliable schedule should be: - complete: all major scope, approvals, procurement and handover activities are included;
- logic-linked: activities have credible relationships;
- resource-aware: labour, plant, access and work zones are considered;
- measurable: progress can be assessed objectively;
- current: actual conditions replace outdated assumptions; and
- communicable: the format is understandable to the client and site team.
5. Resource Planning and LevellingResources include labour, materials, equipment, information, space and specialist subcontractors. A schedule that ignores resource availability is only a theoretical sequence. 5.1 Labour planningLabour planning considers trade skills, crew size, working hours, supervision, fatigue, productivity and interface management. A resource histogram can show the number of workers required each day or week. Peaks may indicate an unsafe or inefficient concentration of labour, while troughs may indicate underuse or an opportunity to resequence work. Resource loading assigns estimated quantities to scheduled activities. If an activity requires 48 labour-hours and a crew supplies 16 productive labour-hours per day, the theoretical duration is: D = \frac{48}{16} = 3\text{ working days} This calculation assumes the crew can work continuously on an adequate work front. Productive hours are less than paid hours because of breaks, movement, setup, coordination and waiting. 5.2 Resource levelling and smoothingResource levelling changes activity dates, and sometimes the project completion date, to resolve over-allocation. Resource smoothing adjusts activities within available float so that resource demand becomes more even without changing the completion date. Typical responses include: - moving non-critical activities within float;
- dividing work into zones;
- changing crew size;
- using alternative qualified subcontractors;
- resequencing installations;
- extending working hours where legally and practically acceptable; and
- prefabricating components away from the congested site.
Acceleration has consequences. Additional labour may increase supervision and congestion; overtime may reduce quality and raise fatigue risk; and parallel work may create rework. The manager should compare time saved with additional cost and risk rather than assuming that more labour always improves performance. 5.3 Materials, equipment and informationMaterials must be planned by need date, not simply by order date. Equipment planning includes delivery, setup, operation, inspection, removal and storage. Information resources include approved drawings, samples, schedules, specifications, permits and method statements. A trade cannot be treated as “ready” if the physical material has arrived but the required approved information has not. A resource responsibility matrix, such as a RACI matrix, can clarify who is responsible, accountable, consulted and informed for key decisions. This is particularly useful for design approvals, samples, substitutions, shutdowns and client-provided items. 6. Procurement and Lead-Time IntegrationProcurement is a time-dependent process comprising specification, quotation, approval, purchase, manufacture, quality inspection, transport, delivery, receipt and installation. Long-lead items may include bespoke joinery, stone, imported lighting, specialist sanitaryware, acoustic products, furniture and access-control equipment. A procurement schedule should include at least: | Stage | Control question |
|---|
| Define | Is the specification complete and coordinated? | | Approve | Who approves samples, shop drawings and substitutions? | | Order | Has the purchase order been formally released? | | Manufacture | Are production dates and inspection points confirmed? | | Transport | Are customs, insurance and delivery constraints understood? | | Receive | Is there a protected location and inspection process? | | Install | Is the preceding work complete and the item protected? |
The required order date can be estimated as: To = Tn − (Ta + Tm + Tt + Tr + Ti) where: - To = latest required order date;
- Tn = date the item is needed on site;
- Ta = approval and information time;
- Tm = manufacturing time;
- Tt = transport time;
- Tr = receiving and inspection time; and
- Ti = installation preparation time.
All terms must use the same unit, such as calendar days or working days. The formula assumes the stages occur sequentially. If some stages overlap, the schedule should model the actual relationships rather than adding all durations blindly. Procurement risk can be reduced through early design freeze, approved alternatives, supplier capacity checks, sample approval, factory inspection, staged delivery and contingency planning. Substituting a product without checking fire performance, dimensions, warranty, acoustic properties, maintenance requirements or sustainability claims is professionally unacceptable. 7. Site Logistics PlanningSite logistics is the planned movement and temporary positioning of people, materials, tools, waste and information. It should be designed before mobilisation and reviewed as the project changes. 7.1 Access and deliveryThe logistics plan should identify: - vehicle approach and loading restrictions;
- booking procedures and delivery windows;
- loading-bay or lift capacity;
- pedestrian segregation;
- security and access control;
- unloading personnel and equipment;
- routes from delivery point to workface;
- protection of finished or occupied areas; and
- emergency access and escape routes.
The largest item is not always the most difficult delivery. Fragile glass, long joinery components, heavy stone or items requiring controlled lifting may impose greater constraints than their dimensions suggest. 7.2 Storage and material handlingStorage should be located as close as practical to the point of use while preserving circulation, fire safety and emergency access. Materials should be stored according to manufacturer instructions. Moisture-sensitive boards, finishes and adhesives may require dry, ventilated storage; heavy items may require load-capacity verification; and high-value equipment may need secure storage. A just-in-time delivery system reduces storage demand but increases dependence on transport reliability and accurate installation readiness. A hybrid approach is often appropriate: standard materials are delivered in controlled batches, while vulnerable or high-value items remain with the supplier until the site is ready. 7.3 Temporary works and site protectionTemporary works may include hoardings, dust screens, temporary lighting, floor protection, signage, welfare facilities, fire points, temporary power and protection of existing services. Temporary works are not secondary concerns: they affect safety, productivity, client confidence and the preservation of existing assets. 7.4 Waste and reverse logisticsWaste should be planned from purchase through disposal. Segregation of timber, metal, plasterboard, packaging and general waste can improve recovery and reduce disposal cost. The plan should identify collection frequency, container location, lifting method and documentation. Reusable packaging and off-site prefabrication can reduce waste and site congestion. 8. Phasing and Work in Occupied EnvironmentsOccupied environments—offices, hotels, healthcare facilities, educational buildings and retail premises—require a different planning logic from vacant sites. The project must protect occupants while maintaining essential operations. A phasing strategy may divide the project into zones or time windows. Each phase should have defined: - scope and boundaries;
- possession and release dates;
- temporary services;
- access and egress arrangements;
- noise, dust and vibration controls;
- fire and life-safety provisions;
- communication arrangements;
- cleaning and inspection requirements; and
- criteria for returning the area to operation.
The sequence should consider the users’ critical activities. For example, a healthcare project may prohibit shutdowns during clinical periods, while an office project may permit noisy work after business hours but require secure daily reinstatement. Occupied-site controls include negative-air or dust-control arrangements where appropriate, sealed waste routes, low-odour products, acoustic barriers, controlled deliveries, daily housekeeping and advance notification of disruptive work. “Out of hours” work does not remove obligations concerning worker welfare, noise regulation, security or emergency response. A useful principle is to separate construction completion from operational readiness. An area may be physically complete but not ready for occupation until testing, cleaning, signage, commissioning, training and statutory inspections are complete. 9. Integrated Case: Illustrative Office Reception RefurbishmentBackgroundThis illustrative case concerns a 180 m² reception refurbishment in an occupied office building. The scope includes a bespoke reception desk, new lighting, acoustic wall panels, carpet tiles, paintwork and revised access-control devices. The reception must remain operational throughout the six-week programme. ProblemThe initial contractor proposal placed all deliveries during business hours and scheduled painting before ceiling works were complete. The proposal also treated the bespoke desk as an ordinary installation item, although the supplier required six weeks from approved shop drawings to delivery. The client’s facilities manager identified risks to visitor access, data security, dust control and emergency routes. AnalysisThe project team created a WBS and identified the following controlling activities: - survey and confirm existing services;
- coordinate and approve desk and lighting information;
- release bespoke desk fabrication;
- establish temporary reception and protected pedestrian route;
- complete enabling and first-fix works;
- install ceiling and lighting systems;
- complete finishes and acoustic panels;
- install desk and access-control equipment;
- test, clean, inspect and transfer operations.
The team used two work zones: a temporary reception zone and a construction zone. Deliveries were restricted to 07:00–08:00, before peak visitor movement. A temporary desk preserved basic reception functions, while a dust-controlled barrier separated the work area. Approach and solutionThe schedule was revised so that shop-drawing approval became an early milestone rather than an administrative footnote. The desk was released immediately after approval. Ceiling and first-fix work were sequenced before final painting. Acoustic panels were delivered only after the area was dry and secure. The installation of access-control devices was coordinated with the building’s security contractor and followed by functional testing. A daily interface meeting was held with facilities management, security and the contractor. The logistics plan identified a protected route, a waste collection point, a temporary fire-extinguisher location and a daily close-down inspection. No work was permitted to obstruct the designated escape path. OutcomeThe reception remained operational, and the project achieved practical completion within the revised six-week programme. The desk delivery had no float, so its approval and fabrication were monitored twice weekly. Minor paint defects were corrected before the final cleaning period because quality inspections were embedded in the schedule rather than left until handover. Learning points- Long-lead procurement must be linked to design approvals and milestones.
- Occupied projects require operational planning, not merely construction sequencing.
- Temporary arrangements must be designed, maintained and inspected.
- Handover includes testing, cleaning, training and documentation.
- Site logistics should be communicated to building users, not only to trades.
10. Risk, Governance and Professional ResponsibilitySchedule risks commonly arise from incomplete information, late decisions, unrealistic productivity assumptions, unavailable labour, access restrictions, defective work, supplier failure and changing client requirements. A risk register should record probability, impact, owner, response and review date. A simple qualitative matrix may classify risks as low, medium or high, but the classification should be supported by evidence. Where useful, expected monetary value can be estimated as: EMV = P × I where P is the probability of an event and I is its financial impact. Both values must use compatible units. EMV is a prioritisation aid, not a prediction of the exact eventual cost and not a justification for ignoring low-probability catastrophic hazards. Ethical scheduling requires honest reporting. Managers should not hide delay by changing the baseline without approval, claim progress for unverified work, or compress activities in ways that compromise safety and quality. Labour planning must respect working-time rules, competence requirements, welfare, fair treatment and non-discrimination. Regulatory requirements vary by jurisdiction, but commonly include building regulations, fire safety, accessibility, occupational health and safety, waste controls, noise restrictions, permits and building-management rules. The schedule should include time for inspections, approvals and commissioning. Compliance is part of the work, not an optional addition. 11. Digital Tools, BIM and AIScheduling software can calculate dates, display dependencies, generate resource histograms and compare baseline with current forecasts. Building information modelling (BIM) can connect programme activities to spatial elements, supporting four-dimensional planning. This is useful for testing phasing, access routes, temporary works and conflicts. Digital tools do not correct poor assumptions. A visually sophisticated programme can remain unreliable if quantities, calendars, dependencies or progress data are inaccurate. Data ownership, revision control and approval status must be explicit. AI may assist with extracting activities from specifications, identifying potential procurement risks, comparing schedule updates or suggesting alternative sequences. However, professional judgement remains necessary because AI may misread ambiguous drawings, overlook site-specific constraints, reproduce biased assumptions or treat estimated dates as facts. Human review, traceable sources, confidentiality protection and approval controls are essential. Challenges and LimitationsScheduling models simplify reality. Productivity varies with skill, congestion, weather, supervision, rework and learning effects. Critical paths can change as actual conditions develop. Float is not always freely usable because access, noise, procurement or client operations may constrain activities that appear independent in the network. Likewise, resource estimates may be distorted by counting workers rather than productive capacity. Procurement dates supplied by vendors may exclude inspection, customs, quality rejection or site-readiness delays. Finally, a schedule cannot replace communication. Daily coordination, site observation and timely decisions are required to maintain control. Best-Practice ChecklistBefore mobilisation, the project manager should confirm that: - the WBS includes design, approvals, procurement, construction, testing and handover;
- activity relationships reflect actual technical logic;
- critical and near-critical activities are identified;
- durations include realistic productivity and access assumptions;
- long-lead items have approval and delivery milestones;
- labour and equipment demand has been reviewed for peaks;
- delivery routes, storage and waste arrangements are documented;
- temporary works and emergency routes are protected;
- occupied-building controls are agreed with facilities management; and
- progress reporting records actual evidence, forecast dates and corrective action.
Chapter SummaryScheduling, resource planning and site logistics form an integrated control system for interior projects. A work breakdown structure defines the work; activity networks establish logical sequence; Gantt schedules communicate timing; milestones identify verifiable control points; and critical-path analysis reveals the activities that determine completion. Duration estimates must distinguish labour effort from elapsed time and must state their assumptions. Resource planning covers labour, materials, equipment, information and space. Procurement must incorporate approval, manufacture, transport, inspection and installation readiness. Logistics planning coordinates access, deliveries, storage, protection, waste and emergency routes. In occupied environments, phasing must protect users and preserve operations as well as deliver the construction scope. Reliable programmes are updated from evidence, openly report uncertainty and integrate safety, quality, regulatory compliance and ethical responsibility. Digital tools, BIM and AI can improve visibility and analysis, but they depend on accurate data and professional judgement. Key TermsWork breakdown structure: Hierarchical division of project scope into deliverables and work packages. Activity: A defined item of work with a start, finish, duration and required resources. Predecessor: An activity or condition that logically precedes another activity. Successor: An activity that follows another activity in a network. Finish-to-start: Relationship in which a successor starts after its predecessor finishes. Gantt schedule: Time-scaled chart showing activities, durations and progress. Milestone: Zero-duration event representing a significant achievement or decision. Critical path: Longest logical path determining the calculated project duration. Float: Time by which an activity may move without affecting a defined schedule date. Early start: Earliest date an activity can begin according to network logic. Latest finish: Latest date an activity can finish without delaying the planned completion. Productivity: Quantity of output achieved per unit of labour or resource input. Resource levelling: Adjustment of dates or sequence to resolve resource over-allocation. Lead time: Time from initiating procurement to availability for use. Long-lead item: Item requiring an extended period for approval, manufacture or delivery. Site logistics: Planning of movement, access, storage, protection and waste on site. Phasing: Division of work into zones or stages with controlled possession and release. Occupied environment: Building or area that remains in use during construction. Commissioning: Verification that systems and installations operate as intended. Baseline: Approved reference programme against which actual performance is compared. Review QuestionsShort Answer Questions- What is the purpose of a work breakdown structure in an interior project?
- Define the critical path and explain the meaning of zero total float.
- Identify four stages that should appear in a procurement schedule.
- Why is storage planning important for moisture-sensitive materials?
- State two additional considerations required when working in an occupied building.
Long Answer Questions- Explain how a Gantt schedule and an activity network complement one another in project control.
- Describe the forward-pass and backward-pass methods used in critical-path analysis.
- Discuss how resource levelling can affect project duration, cost and quality.
- Explain how procurement lead times should be integrated with design approvals and construction activities.
- Develop a site-logistics strategy for a small commercial interior fit-out in a constrained urban building.
Analytical / Application Questions- An activity requires 96 labour-hours. A crew provides 24 productive labour-hours per working day. Calculate the theoretical duration and identify two reasons why the actual duration may differ.
- A bespoke item is needed on day 30. Approval requires 5 working days, manufacture 12 working days, transport 4 working days, receiving inspection 1 working day and installation preparation 2 working days. Calculate the latest order date, assuming all stages are sequential and use working days.
- Using the case study, explain how temporary reception arrangements, delivery windows and phased work zones reduce operational risk in an occupied office.
Multiple Choice Questions with AnswersQuestion 1Which relationship means that Activity B can begin only after Activity A has finished? A. Start-to-start B. Finish-to-start C. Finish-to-finish D. Start-to-finish Correct Answer: B. Finish-to-start Question 2An activity has ES = 6 working days and duration = 5 working days. What is its earliest finish? A. 1 working day B. 5 working days C. 11 working days D. 30 working days Correct Answer: C. 11 working days Question 3Which activity is normally included in a procurement lead-time schedule? A. Only the supplier’s manufacturing period B. Approval, manufacture, transport and receiving inspection C. Only the installation period D. Only the client’s payment period Correct Answer: B. Approval, manufacture, transport and receiving inspection Question 4A task requires 48 labour-hours and a crew provides 16 productive labour-hours per day. What is the theoretical duration? A. 2 days B. 3 days C. 16 days D. 64 days Correct Answer: B. 3 days Question 5What does total float measure? A. The total number of workers on site B. The amount of material stored on site C. The time an activity can move without delaying a defined schedule date D. The difference between paid and productive hours Correct Answer: C. The time an activity can move without delaying a defined schedule date Question 6Which is the best example of a project milestone? A. Install wall panels for three days B. Complete practical-completion inspection C. Move materials through the loading bay D. Paint the reception wall Correct Answer: B. Complete practical-completion inspection Question 7Why may doubling the workforce fail to halve an activity’s duration? A. Because labour has no relationship to duration B. Because access, work fronts, supervision and congestion may constrain productivity C. Because schedules cannot include more than one worker D. Because materials become unnecessary Correct Answer: B. Because access, work fronts, supervision and congestion may constrain productivity Question 8Which measure is particularly important when planning work in an occupied building? A. Removing all temporary barriers B. Maintaining protected access and emergency routes C. Delivering all materials during peak visitor periods D. Deferring cleaning until after occupation Correct Answer: B. Maintaining protected access and emergency routes Question 9In the PERT equation, which estimate receives the greatest weighting? A. Optimistic estimate B. Most-likely estimate C. Pessimistic estimate D. The average of the three estimates without weighting Correct Answer: B. Most-likely estimate Question 10What is the primary purpose of resource smoothing? A. To increase every activity’s duration B. To use available float to make resource demand more even without changing completion C. To remove all procurement activities D. To eliminate the need for progress updates Correct Answer: B. To use available float to make resource demand more even without changing completion
|