Interior Project & Cost Management

Chapter 7
Procurement, Tendering and Supplier Management

Advance Diploma in Interior Design Management
Interior Project & Cost Management   •   Advance Diploma

Procurement, Tendering and Supplier Management

Introduction

Procurement is the organised process through which an interior project obtains design services, construction work, furniture, finishes, equipment and specialist products. It is not merely purchasing. It connects project objectives, design information, commercial strategy, risk allocation, legal obligations and supply-chain performance.

For an interior design manager, procurement decisions influence cost certainty, design control, programme reliability, quality, sustainability and client satisfaction. A visually successful design can still fail if a bespoke item arrives after handover, an imported finish is unavailable, or a contractor prices incomplete information and later submits extensive variations.

This chapter examines four principal procurement routes—traditional, design-build, management and negotiated procurement—and develops a practical framework for tender preparation, bid evaluation, supplier selection and the management of long-lead, bespoke and imported items.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Compare traditional, design-build, management and negotiated procurement routes.
  2. Select a procurement route appropriate to project priorities and risk conditions.
  3. Prepare coordinated tender documentation and an auditable tender process.
  4. Evaluate bids transparently using price, quality, programme, risk and capability.
  5. Apply value-based supplier selection rather than selecting solely on lowest price.
  6. Plan and control long-lead, bespoke and imported products.
  7. Recognise ethical, legal, sustainability and governance responsibilities in procurement.

1. Procurement as a Strategic Management Function

Procurement has three related dimensions:

  • Commercial dimension: obtaining required scope at an acceptable total cost and allocating financial risk.
  • Technical dimension: ensuring that products and workmanship meet performance, design and regulatory requirements.
  • Relational dimension: coordinating clients, designers, contractors, manufacturers, logistics providers and installers.

A useful procurement decision considers the relationship between time, cost, quality, risk and control. These objectives can conflict. For example, early contractor involvement may improve buildability and programme certainty but reduce the client’s ability to obtain fully competitive prices after design development. A low initial price may be offset by variations, delays, maintenance costs or replacement of defective products.

The relevant commercial concept is whole-life value, not simply tender price. A simplified whole-life cost model is:

WLC = C₀ + Cₚ + Cₘ + Cᵣ + Cₑ − Rᵥ

where C0 is initial acquisition and installation cost; Cp is planned maintenance cost; Cm is operating cost; Cr is replacement or renewal cost; Ce is end-of-life or disposal cost; and Rv is residual or salvage value. All amounts must be expressed on a consistent basis, normally in the same currency and price level. If costs occur at different times, a discounted cash-flow model is more appropriate. The simplified expression is most useful for early comparison when reliable timing and discount-rate assumptions are not available.

2. Principal Procurement Routes

2.1 Traditional procurement

Under traditional procurement, the client appoints a designer or design team to develop the design and prepare tender information. A contractor is then appointed to construct or install the defined works. Design responsibility and construction responsibility are substantially separated.

Strengths include:

  • strong client control over design and specification;
  • competitive tendering based on a relatively complete design;
  • clear professional roles;
  • comparatively straightforward design-quality monitoring.

Limitations include:

  • the contractor’s buildability input may arrive late;
  • the project may take longer because design precedes construction procurement;
  • incomplete documentation can generate variations and claims;
  • coordination risk remains with the client’s design team.

Traditional procurement is suitable where design quality and client control are priorities, the scope can be developed before construction starts, and the client can tolerate a longer pre-construction period.

2.2 Design-build procurement

In design-build, one principal contractor accepts responsibility for both design and construction, either directly or through consultants and specialist subcontractors. The client defines requirements through employer’s requirements, performance specifications, concept information or a combination of these.

Strengths include a single point of responsibility, potential programme reduction through overlapping design and construction, and early contractor influence on cost and buildability. It can also reduce disputes concerning whether a defect is a design or construction responsibility.

Limitations include reduced direct control over detailed design, the possibility of design quality being subordinated to cost, and difficulty comparing tenders if bidders interpret performance requirements differently. The client must write requirements clearly and establish design review and approval procedures.

Design-build is appropriate where speed, integrated responsibility and performance outcomes are important, and where the client can manage design through briefs, samples, mock-ups, review gateways and quality standards.

2.3 Management contracting and construction management

Management approaches appoint a management organisation to coordinate work packages rather than relying only on a single main contractor performing all construction work.

In management contracting, the management contractor typically appoints trade contractors and manages their packages. In construction management, the client commonly contracts directly with trade contractors while the construction manager provides professional coordination and management advice.

Advantages include early start on site, flexibility for design development, access to specialist trade knowledge and improved suitability for complex or fast-track interiors.

Disadvantages include reduced early cost certainty, greater client exposure to package and interface risk, and a need for strong client-side management. The design must be coordinated continuously, and late decisions can cause procurement disruption.

These routes suit complex refurbishments, phased fit-outs and projects where early occupation or specialist coordination is more important than a fixed price at the outset.

2.4 Negotiated procurement

Negotiated procurement appoints a contractor or supplier through direct negotiation rather than a fully competitive tender. The negotiation may concern price, overheads, programme, risk allocation, design development, preliminaries and target-cost mechanisms.

It may be appropriate where:

  • the work is highly specialised;
  • confidentiality is important;
  • an existing supplier has unique knowledge;
  • the project is urgent;
  • market capacity is limited;
  • early involvement is needed to develop a realistic solution.

Negotiation is not a licence for poor governance. The client should document the reason for selection, obtain market evidence, benchmark rates, test assumptions, record conflicts of interest and establish approval thresholds. A negotiated route can be highly effective, but it is vulnerable to perceived favouritism and weak price challenge.

2.5 Comparative decision framework

CriterionTraditionalDesign-buildManagementNegotiated
Design controlHighMediumHigh to mediumVariable
Early price certaintyMedium to high if design is completeMedium to highLow to mediumVariable
Programme speedMediumHighHighHigh if promptly agreed
Client management demandMediumMediumHighMedium to high
Suitability for evolving designLimitedMediumHighHigh
Main riskDesign–construction interfaceReduced design controlCost and package riskWeak competition or transparency

No route is universally superior. Selection should follow a documented assessment of design maturity, programme urgency, project complexity, client capability, market conditions and desired risk allocation.

3. Procurement Strategy and Route Selection

A procurement strategy should begin with a project brief containing scope, performance requirements, budget, programme, quality aspirations, sustainability objectives and stakeholder constraints. The project manager should then identify the matters that are fixed and those that may develop.

Important route-selection questions include:

  1. Is the design sufficiently developed to describe the work accurately?
  2. Is a fixed price essential, or is early commencement more important?
  3. Does the work include specialist fabrication or unusual interfaces?
  4. Can the client evaluate technical proposals and manage design approvals?
  5. Who should carry risks such as inflation, design development, damage in transit, customs delay and product substitution?
  6. Is there a capable and competitive market?
  7. What level of cost and programme uncertainty can the client accept?

A risk register should assign each material risk to the party best able to control it. Transferring a risk to a contractor does not eliminate it; it may increase the tender price or produce defensive behaviour. Good procurement allocates risks realistically and prices them transparently.

4. Tender Documentation

Tender documentation converts design intent into an offer that can be priced and compared. Its completeness and consistency directly affect tender quality.

A typical interior tender package includes:

  • invitation to tender and instructions to tenderers;
  • form of tender and proposed contract conditions;
  • project brief and employer’s requirements;
  • drawings, schedules, specifications and room data sheets;
  • finishes, furniture, fixtures and equipment schedules;
  • bills of quantities or pricing schedules where appropriate;
  • programme requirements and sectional completion dates;
  • site information, access constraints and working-hour rules;
  • health, safety, environmental and quality requirements;
  • information-management and document-control requirements;
  • schedules for exclusions, assumptions, qualifications and proposed alternatives;
  • returnable schedules for labour, preliminaries, logistics and lead times.

The package should identify document status, revision, date and authorisation. A tender query register should record each clarification, its response and whether the response changes the tender information. All tenderers should receive material clarifications simultaneously.

Performance and prescriptive specifications

A prescriptive specification identifies a particular material, product, method or standard. It supports design control but may reduce competition. A performance specification states the required outcome—for example, acoustic performance, durability, fire classification, colour tolerance or load capacity—while allowing compliant solutions. Performance specifications can encourage innovation but require objective testing and competent evaluation.

A balanced package identifies mandatory characteristics, acceptable equivalents, testing requirements, sample approval procedures and responsibilities for verifying compliance.

Tender readiness review

Before issue, the design manager should conduct a coordinated review covering:

  • drawing and schedule consistency;
  • dimensional coordination;
  • reflected ceiling, lighting, mechanical and furniture interfaces;
  • access, delivery and installation constraints;
  • fire, accessibility and other applicable regulatory requirements;
  • availability and lead time of critical products;
  • provisional sums and client-supplied items;
  • omissions, duplicated scope and ambiguous wording.

Tendering incomplete information without identifying the uncertainty encourages inconsistent assumptions and later disputes.

5. Tender Administration and Clarification

A controlled tender process normally follows these stages:

  1. establish the approved procurement strategy;
  2. prequalify or shortlist capable tenderers;
  3. issue identical tender information;
  4. hold a documented site visit or briefing where useful;
  5. receive questions through a controlled channel;
  6. issue numbered addenda to all tenderers;
  7. receive tenders by a defined deadline;
  8. secure, log and preserve submissions;
  9. evaluate against published criteria;
  10. clarify without allowing unequal competitive advantage;
  11. prepare an award recommendation and obtain approval;
  12. notify tenderers and conclude the contract or purchase order.

Clarification must be distinguished from negotiation. Clarification explains an ambiguity or confirms an evident error. Negotiation changes scope, price or commercial terms. If material negotiation is permitted, the process and authority to conduct it should be stated in advance.

6. Transparent Bid Evaluation

The evaluation model should be agreed before bids are opened. Criteria should be relevant, measurable and communicated to tenderers when appropriate. A common weighted model may include price, technical compliance, programme, quality capability, sustainability, relevant experience and commercial risk.

A weighted score can be calculated as:

S = ∑(wᵢ × rᵢ)

where S is the total score; wᵢ is the weight assigned to criterion i; and rᵢ is the bidder’s normalised rating for that criterion. Weights must use the same scale, and the sum of weights should equal 1 or 100%. Ratings should be defined before evaluation—for example, 0 to 5 with written descriptors. A score is not objective merely because it has a number; the evidence supporting each rating must be recorded.

For a low-price criterion, one possible normalisation is:

rp = (Pmin ÷ Pi) × 100

where Pmin is the lowest compliant evaluated price and Pi is bidder i’s evaluated price. This method rewards low price but can overemphasise small price differences. It should not be used to conceal non-compliance, nor should an abnormally low bid be accepted without investigating assumptions, omissions and delivery capability.

The evaluated price may differ from the submitted price because of arithmetic corrections, accepted alternatives, identified exclusions, provisional sums, taxes, delivery, installation, warranties and whole-life costs. Adjustments must be applied consistently and documented.

Example of weighted evaluation

Assume two compliant bids are evaluated using 60% price and 40% technical quality. Bid A is £100,000 and scores 80/100 for quality. Bid B is £110,000 and scores 95/100. The lowest-price rating is 100 for A and (100,000 ÷ 110,000) × 100 = 90.91 for B.

A’s total is (0.60 × 100) + (0.40 × 80) = 92. B’s total is approximately (0.60 × 90.91) + (0.40 × 95) = 92.55. Under these stated assumptions, B achieves the higher value score despite its higher tender price. The result does not automatically justify award: references, capacity, exclusions, financial standing and contract terms must still be checked.

7. Value-Based Supplier Selection

Supplier selection should examine the supplier’s ability to deliver the required outcome, not simply its catalogue price. A value-based assessment commonly considers:

  • technical compliance and product durability;
  • manufacturing capacity and quality-control systems;
  • design coordination and shop-drawing competence;
  • realistic lead time and production evidence;
  • installation capability and aftercare;
  • financial resilience and insurance;
  • ethical labour and responsible sourcing;
  • environmental impact and product documentation;
  • communication, responsiveness and problem-solving;
  • total cost of ownership.

Prequalification can use a proportionate questionnaire, references, sample review, factory visit, financial checks and evidence of previous comparable work. Overly burdensome prequalification can exclude smaller innovative suppliers, while inadequate checking can expose the project to failure.

Supplier performance should be measured after appointment. Useful indicators include on-time delivery, defect rate, response time, documentation completeness, installation rework and unresolved safety or quality issues. Measures should lead to corrective action rather than becoming merely administrative statistics.

8. Long-Lead, Bespoke and Imported Items

Long-lead items

Long-lead items include specialist lighting, lifts, control equipment, natural stone, custom furniture, sanitaryware, acoustic products and imported finishes. A procurement schedule should identify required-on-site date, approval date, manufacturing duration, shipping duration, customs clearance, inspection, contingency and installation duration.

A simplified required-order date is:

Do = Dr − (Ta + Tm + Ts + Tc + Ti + Tb)

where Do is the latest target order date; Dr is the required-on-site date; Ta is approval time; Tm is manufacturing time; Ts is shipping time; Tc is customs and clearance time; Ti is inspection and delivery time; and Tb is planned time contingency. All durations must use the same unit and represent realistic calendar or working-day conventions. The expression assumes sequential activities; where activities overlap, a properly networked programme is required instead of simple addition.

The schedule should include decision gates: technical approval, sample approval, shop-drawing approval, order placement, production inspection, dispatch, customs clearance, delivery and installation sign-off.

Bespoke items

Bespoke procurement requires a design freeze, approved samples or prototypes, agreed tolerances, shop drawings, material confirmation, finish control and a clear responsibility matrix. The contract should state who owns design responsibility, intellectual property, moulds, jigs, prototypes and unused materials. Inspection should occur at appropriate stages rather than only after delivery, when correction may be impossible.

Imported items

Imported goods introduce currency, customs, sanctions, duties, tax, logistics, packaging, damage, certification and political risks. The purchase documentation should define the delivery term, point at which risk transfers, insurance responsibility, required shipping documents, country of origin, inspection arrangements and responsibility for import compliance. International delivery terms should be interpreted using the applicable current Incoterms® rules and stated precisely; a term alone does not resolve every tax or regulatory obligation.

A contingency is not a substitute for planning. The team should investigate alternative sources, confirm regulatory acceptance, obtain realistic freight quotations and identify a locally available substitute that meets the design and performance requirements.

9. Contract and Supplier Controls

A purchase order or subcontract should define scope, price, payment milestones, taxes, programme, inspection, packaging, delivery, installation, defects, warranties, insurance, intellectual property, confidentiality, changes, termination and dispute procedures. For design-related supply, it should also identify the hierarchy of documents and the process for approving substitutions.

Change control is essential. A supplier request should state the reason for change, technical effect, cost effect, programme effect, warranty effect and approval required. No substitution should be accepted solely because it is available sooner or cheaper; equivalence must be demonstrated against the specified performance and design intent.

Payment should be linked to verifiable milestones, such as approved shop drawings, completed production, inspection, delivery and accepted installation. Retention, warranties or other security mechanisms may be appropriate depending on contract terms and applicable law.

10. Ethics, Governance and Sustainability

Procurement decisions must be impartial, defensible and consistent with organisational policy and applicable law. Core controls include declaration of interests, segregation of duties, approval limits, secure tender records, equal information to bidders and documented reasons for decisions.

Common ethical risks include gifts, undisclosed relationships, bid information leakage, favouritism, collusion and manipulation of specifications to advantage a particular supplier. A conflict does not necessarily prove wrongdoing, but it must be disclosed and managed.

Sustainable procurement should consider embodied carbon, durability, repairability, recycled content, responsible forestry or mineral sourcing, packaging, transport distance, local employment and end-of-life recovery. Claims such as “green”, “natural” or “recyclable” should be supported by credible evidence. Sustainability criteria must be relevant to the project and applied consistently, not used as vague preferences.

11. Digital Tools and Artificial Intelligence

Building information modelling, cloud-based document control, procurement dashboards and barcode or RFID tracking can improve coordination and traceability. A digital procurement register can connect an item’s specification, supplier, approval status, purchase order, production status, shipping documents and installation record.

Artificial intelligence may assist with classifying specifications, identifying missing schedule data, comparing supplier responses and flagging inconsistent quantities. However, AI outputs require human verification. Confidential tender prices and personal data should not be uploaded to unauthorised systems. AI cannot replace professional judgement concerning compliance, buildability, ethical sourcing or contractual responsibility.

Illustrative Case: Bespoke Reception Desk for a Hotel Fit-Out

Background

A hotel refurbishment includes a curved reception desk with stone-effect surfaces, integrated lighting and concealed service access. The desk is manufactured overseas, with a quoted production period of eight weeks and shipping period of three weeks.

Problem

The required-on-site date is 20 August. Design approval is expected to take two weeks, customs clearance one week, local delivery and inspection one week, and installation one week. The project team initially planned to place the order on 1 July, but this leaves little allowance for production or shipping disruption. A supplier also proposes a cheaper laminate alternative without demonstrating fire, durability or colour equivalence.

Analysis

Using the sequential planning expression, the minimum duration from approval to accepted installation is:

2 + 8 + 3 + 1 + 1 = 15 weeks, before contingency. If approval is complete on 1 June, the item should be ordered no later than approximately 17 June for a 20 August requirement, subject to the project’s calendar convention. A contingency of two weeks would move the target order date to approximately 3 June. The dates must be confirmed through the project programme rather than treated as a substitute for detailed scheduling.

Approach

The design manager requires a full-size finish sample, coordinated shop drawings, a method for protecting the curved components, evidence of performance compliance and a factory inspection before dispatch. The supplier’s alternative is evaluated against the written criteria rather than accepted on price alone. A local fabricator is also investigated as a fallback, although its capacity and finish capability must be verified.

The purchase order identifies approved drawings, finish codes, tolerances, delivery responsibility, packaging, inspection rights, defects obligations and the point at which damage risk transfers. The procurement register records every approval and date.

Outcome

The overseas supplier is retained because it provides the required finish and has demonstrated production capacity. The order is placed earlier than originally planned, and the local fabricator remains a contingency option. The proposed laminate is rejected because evidence of equivalence is incomplete. The desk arrives before installation, with minor packaging damage identified during inspection and corrected under the supplier’s delivery obligation.

Learning points

The case demonstrates that procurement risk begins before the purchase order. Early identification, design freeze, evidence-based substitution review, realistic lead-time calculation, inspection and documented responsibility are essential. The lowest quoted price would not necessarily have delivered the highest project value.

Challenges and Limitations

Procurement decisions are made with incomplete information. Market prices change, suppliers may overstate capacity, design development may continue after tender, and imported goods may be affected by events outside the project team’s control. Weighted scoring can create false precision if criteria are poorly defined. Whole-life cost is sensitive to assumptions about maintenance, replacement and inflation. Risk registers can also become passive documents unless owners, actions and review dates are assigned.

Professional judgement therefore remains necessary. The appropriate response is not to seek certainty where none exists, but to expose assumptions, compare scenarios, allocate risks deliberately, maintain alternatives and update the procurement strategy as evidence changes.

Chapter Summary

Procurement is a strategic function linking design intent, cost, time, quality, risk and supply-chain performance. Traditional procurement offers strong design control; design-build integrates design and construction responsibility; management routes support flexibility and early work but require greater client management; and negotiated procurement can suit specialist or urgent work but demands strong governance.

Effective tendering depends on coordinated information, fair administration, controlled clarification and evaluation criteria established before bids are assessed. Transparent evaluation combines price with technical compliance, programme, capability, sustainability and risk. Value-based supplier selection considers total cost and delivery capability rather than initial price alone.

Long-lead, bespoke and imported items require early identification, design approval, realistic schedule calculation, inspection, responsibility allocation and contingency planning. Ethical procurement requires impartiality, auditability, responsible sourcing and protection of confidential information. Digital systems can improve traceability, while AI should support—not replace—professional judgement.

Key Terms

Procurement: The organised acquisition of works, services, products and materials.

Traditional procurement: A route separating substantial design responsibility from construction responsibility.

Design-build: A route in which one principal contractor is responsible for design and construction.

Management contracting: A route using a management contractor to coordinate trade contractors.

Construction management: A route in which the client commonly contracts directly with trade contractors under professional management.

Negotiated procurement: Direct appointment and commercial agreement with a selected contractor or supplier.

Tender: A formal offer to provide defined works or goods at stated terms.

Addendum: A controlled amendment or clarification issued to tender information.

Performance specification: A specification stating required outcomes rather than prescribing every product or method.

Prescriptive specification: A specification identifying particular products, materials or methods.

Evaluated price: A tender price adjusted consistently for relevant qualifications, corrections and cost effects.

Whole-life cost: The total relevant cost of acquisition, operation, maintenance, renewal and disposal.

Long-lead item: An item requiring substantial time for approval, manufacture, transport or installation.

Bespoke item: A product designed or manufactured specifically for a project.

Design freeze: An agreed point after which defined design information cannot change without controlled approval.

Substitution: A proposed alternative to a specified product, material or method.

Prequalification: Assessment of supplier capability before invitation to tender.

Procurement register: A controlled record of item status, responsibility, approvals, orders and delivery information.

Incoterms® rules: Standardised international trade terms defining selected delivery responsibilities and risk allocations.

Conflict of interest: A situation in which personal or organisational interests may improperly influence a procurement decision.

Review Questions

Short Answer Questions

  1. What is the principal distinction between traditional procurement and design-build procurement?
  2. State two advantages and two limitations of management procurement.
  3. Why should tender clarifications be issued to all tenderers?
  4. What is meant by whole-life value in supplier selection?
  5. Identify four controls needed when procuring an imported bespoke item.

Long Answer Questions

  1. Compare traditional, design-build, management and negotiated procurement routes for a complex hotel interior project.
  2. Explain how a coordinated tender package should be prepared and reviewed before issue.
  3. Discuss how price, quality, programme and risk can be combined in a transparent bid-evaluation model.
  4. Explain the responsibilities of an interior design manager in managing long-lead and bespoke items.
  5. Evaluate the ethical, sustainability and governance issues associated with supplier selection.

Analytical / Application Questions

  1. A project has an evolving design, a fixed opening date and several specialist trade packages. Recommend a procurement route and justify the allocation of major risks.
  2. Two suppliers offer different prices, lead times and technical proposals. Construct an evaluation framework and explain what evidence you would require before award.
  3. An imported lighting system is delayed at customs after the supplier claims that responsibility transferred at dispatch. Analyse the information and contractual controls that should have been established before ordering.

Multiple Choice Questions with Answers

Question 1

Which procurement route normally gives the client the greatest direct control over detailed design before construction tendering?

A. Traditional procurement

B. Design-build procurement

C. Construction management

D. Negotiated procurement

Correct Answer: A. Traditional procurement

Question 2

A principal advantage of design-build procurement is:

A. Guaranteed lowest market price

B. A single principal responsibility for design and construction

C. Complete client control of every design detail

D. Elimination of all project risks

Correct Answer: B. A single principal responsibility for design and construction

Question 3

In a weighted evaluation model, what should normally happen before bids are opened?

A. The preferred supplier should be informally selected

B. Evaluation criteria and weights should be established

C. All bidders should be allowed to revise their prices

D. The lowest price should automatically receive the contract

Correct Answer: B. Evaluation criteria and weights should be established

Question 4

Using the chapter’s simplified formula, an item requiring 2 weeks for approval, 8 weeks for manufacture, 3 weeks for shipping, 1 week for customs and 1 week for delivery requires at least:

A. 10 weeks

B. 12 weeks

C. 15 weeks

D. 17 weeks

Correct Answer: C. 15 weeks

Question 5

Which document most directly helps control the status of approvals, orders and deliveries for critical items?

A. A procurement register

B. A design mood board

C. A staff attendance sheet

D. A marketing brief

Correct Answer: A. A procurement register

Question 6

Why should a proposed product substitution be evaluated against written performance requirements?

A. To ensure that a cheaper product is always selected

B. To determine whether it is genuinely equivalent to the specified solution

C. To avoid recording the change

D. To transfer all responsibility to the supplier

Correct Answer: B. To determine whether it is genuinely equivalent to the specified solution

Question 7

Which is an appropriate governance control in tendering?

A. Giving one bidder confidential information

B. Changing evaluation weights after seeing prices

C. Declaring and managing conflicts of interest

D. Accepting undocumented verbal promises

Correct Answer: C. Declaring and managing conflicts of interest

Question 8

In the whole-life cost expression, which item represents planned maintenance?

A. C₀

B. Cₚ

C. Cᵣ

D. Rᵥ

Correct Answer: B. Cₚ

Question 9

A management procurement route is particularly suitable where:

A. The design must never develop after appointment

B. Early work and package flexibility are important

C. The client has no management capability at all

D. A single fixed price is the only objective

Correct Answer: B. Early work and package flexibility are important

Question 10

Which action is most appropriate when a tender is abnormally low?

A. Accept it automatically because it is cheapest

B. Reject it without examination

C. Investigate assumptions, omissions and delivery capability

D. Ask other bidders to match it secretly

Correct Answer: C. Investigate assumptions, omissions and delivery capability

Interior Project & Cost Management
Chapter 7 of 15