Infrastructure Project Management

Chapter 8
Risk, Uncertainty and Infrastructure Resilience

Bachelors Program in Construction Technology
Infrastructure Project Management   •   Bachelor

Risk, Uncertainty and Infrastructure Resilience

Introduction and context

Infrastructure projects are exposed to conditions that may prevent the planned scope, cost, time, quality or service performance from being achieved. A contractor may encounter unstable ground, a client may change requirements, a flood may damage temporary works, or an expected source of finance may become unavailable. These conditions are not merely project inconveniences: they can affect public safety, economic productivity, environmental quality and social equity for decades.

Risk management is the systematic process of identifying uncertain events, analysing their effects, selecting responses and monitoring changes. It is not an attempt to predict the future perfectly. Rather, it improves decisions by making assumptions visible, comparing alternatives and preparing proportionate actions. Resilience extends this perspective. A resilient infrastructure system can resist, absorb, recover from and adapt to disruptive events while continuing to provide essential services.

Risk management should begin during strategic planning and continue through design, procurement, construction, commissioning, operation, maintenance, decommissioning and renewal. Responsibility is shared among the owner, designers, contractors, operators, regulators, communities, insurers and suppliers.

Learning objectives

By the end of this chapter, students should be able to:

  1. distinguish risk, uncertainty, hazard, vulnerability, consequence and resilience;
  2. establish a practical infrastructure risk-management process and risk register;
  3. perform qualitative risk analysis using probability, impact and risk matrices;
  4. calculate expected monetary value and evaluate decision trees;
  5. apply sensitivity analysis and explain the use of Monte Carlo simulation;
  6. plan responses to project, climate, disaster and residual risks;
  7. evaluate governance, ethical and professional issues in resilient infrastructure decisions.

1. Fundamental concepts

Risk, uncertainty and hazard

Risk is commonly expressed as the effect of uncertainty on objectives. The effect may be negative (a threat) or positive (an opportunity). In simple models, risk is represented by a probability distribution of possible outcomes rather than by a single forecast.

Uncertainty is incomplete knowledge about future conditions, model parameters or outcomes. Aleatory uncertainty arises from natural variability, such as daily rainfall. Epistemic uncertainty arises from limited knowledge, such as insufficient information about subsurface strata. Aleatory uncertainty may be represented statistically; epistemic uncertainty often requires investigation, expert judgement, conservative assumptions or scenario analysis.

A hazard is a potentially damaging event or process, such as an earthquake, flood, fire, landslide or cyberattack. Vulnerability describes how susceptible an asset or community is to harm. Exposure identifies the people, assets or services located where a hazard may occur. Consequence is the resulting loss or effect, including fatalities, injury, cost, delay, environmental damage, service interruption and reputational harm.

A useful conceptual relationship is:

Risk ≈ Probability of event × Consequence

This is a screening relationship, not a universal law. It is most appropriate when probability and consequence can be meaningfully estimated and when their interaction is adequately represented by a product. Complex hazards may require conditional probabilities, distributions and system models.

Project risk and system risk

Project risk concerns delivery objectives such as cost, schedule, scope, quality and safety. System risk concerns the performance of the infrastructure and the wider network. For example, a bridge project may be delivered on time but still create system risk if its foundations are vulnerable to scour or if the surrounding road network has no alternate route.

Infrastructure risk is therefore multi-dimensional:

DimensionTypical question
SafetyCould people be killed or injured?
CostCould expenditure exceed the approved budget?
TimeCould completion or recovery be delayed?
PerformanceCould capacity, reliability or quality fall below requirements?
EnvironmentCould ecosystems, water or air quality be harmed?
SocialCould access, livelihoods or vulnerable groups be adversely affected?
SecurityCould deliberate or digital attacks interrupt service?
Reputation and complianceCould trust, licence or legal compliance be lost?

Resilience

Resilience is the capacity of an infrastructure system to maintain or rapidly restore acceptable function when subjected to disturbance. Four related capabilities are often considered:

  • resistance: limiting immediate damage;
  • absorption: sustaining essential functions during disruption;
  • recovery: restoring service efficiently;
  • adaptation: learning and changing in response to new conditions.

Resilience is not identical to robustness. A robust facility may withstand a specified event, whereas a resilient system may also degrade safely, use alternatives and recover after events beyond the original design basis. Resilience is also not absolute: it depends on the hazard, time horizon, service threshold and stakeholders considered.

A service-based view is useful. Let service performance at time t be S(t), and let the minimum acceptable service level be S_min. The duration of disruption is the period during which S(t) is below S_min. A simple recovery-performance measure is the area of lost service:

Loss of service = ∫[Smin − S(t)] dt, for S(t) < Smin

Here, the integral has units of service-units × time. The expression is conceptual and must be defined carefully for each service. It should not replace safety criteria or regulatory requirements.

2. The infrastructure risk-management process

A sound process is iterative rather than linear. It links organisational objectives, technical studies, procurement decisions, construction controls and operational learning.

Establish the context

The project team first defines objectives, stakeholders, decision authority, risk appetite, evaluation criteria, time horizon and boundaries. The context should include the physical site, interfaces, supply chain, legal environment, climate projections, community conditions and dependencies on electricity, communications, transport and water systems.

Risk appetite is the level and type of risk an organisation is willing to accept in pursuit of objectives. It must not be interpreted as permission to tolerate preventable harm. Legal duties, safety limits and human-rights obligations establish constraints beyond which risk cannot be traded simply against cost.

Identify risks

Identification methods include document review, site reconnaissance, workshops, interviews, checklists, cause-and-effect diagrams, assumptions analysis, interface reviews, historical data, hazard studies and scenario planning. Effective identification states the risk in a cause–event–effect format:

Because groundwater conditions are poorly characterised, a high water table may be encountered during excavation, causing dewatering costs, instability and delay.

This structure separates the cause from the uncertain event and its consequences. It improves ownership and response design.

Record risks in a risk register

A risk register is a controlled management document, not a one-time list. Typical fields include identification number, description, cause, event, consequence, category, owner, inherent probability, inherent impact, planned response, residual probability, residual impact, early-warning indicator, due date and status.

Risk owners should have authority and resources to manage their assigned risks. An action owner may be different: the risk owner remains accountable while a specialist performs a particular action.

Analyse risks

Analysis is normally conducted at two levels. Qualitative analysis prioritises risks using categories and professional judgement. Quantitative analysis assigns numerical values to selected risks where the decision warrants the effort. Quantitative analysis is especially useful for contingency, major alternatives, high-consequence hazards and portfolios with correlated risks.

Plan and implement responses

For threats, responses include:

  • avoid: change scope, location, method or design so the threat no longer applies;
  • reduce or mitigate: lower probability or consequence;
  • transfer or share: allocate financial or operational responsibility through contract, insurance or partnership, while recognising that accountability and physical consequences cannot always be transferred;
  • accept: take no proactive action beyond monitoring, often with a contingency plan.

For opportunities, corresponding responses include exploit, enhance, share and accept. A response should identify its trigger, cost, owner, timing and expected effect. “Monitor risk” alone is not a sufficient response unless monitoring is deliberate and linked to a decision threshold.

Monitor, review and communicate

Risk reviews should follow design changes, procurement events, incidents, new survey information, extreme weather, regulatory changes and changes in market conditions. Key risk indicators may include groundwater levels, productivity rates, supplier financial health, forecast rainfall, near misses and design-change frequency.

Communication should be timely, accessible and proportionate. Communities may hold essential knowledge about flooding or access routes that is absent from formal records. Consultation is therefore both an ethical obligation and a source of risk information.

3. Qualitative analysis

Probability and impact scales

A five-level scale may define probability as rare, unlikely, possible, likely and almost certain. Impact scales should be dimension-specific: for example, a safety impact scale may use fatalities and serious injuries, while a schedule scale may use weeks of delay. Avoid combining incomparable effects into a single unexplained score.

A risk score is often calculated as:

R = P × I

where P is the selected probability score and I is the selected impact score. This is an ordinal prioritisation tool, not a measured monetary risk. A score of 12 is not necessarily twice as risky as a score of 6, because the categories may not have equal intervals.

Risk matrices can be useful for screening but have limitations. Different combinations can receive the same score; rare catastrophic events may be hidden; and users may treat subjective categories as precise probabilities. High-consequence safety and environmental risks should receive specialist analysis even when their numerical score appears moderate.

Bow-tie thinking and controls

A bow-tie model links causes to a top event, then links the top event to consequences. Preventive barriers act before the event; mitigative barriers act after it. For a fuel-storage facility, weak inspection may contribute to loss of containment; bunding, detection, emergency isolation and firefighting reduce consequences. Barrier management asks whether controls are present, effective, independent and maintained.

4. Quantitative risk analysis

Expected value

For discrete mutually exclusive outcomes, the expected value is:

E[X] = ∑(pᵢxᵢ), i = 1 to n

where X is the outcome, pᵢ is the probability of outcome i, xᵢ is its numerical value, and ∑pᵢ = 1. The result is a probability-weighted average over repeated comparable situations; it is not a prediction that the average outcome will occur in one project.

For a threat represented as an additional cost, expected monetary value (EMV) is:

EMV = ∑(pᵢcᵢ)

where cᵢ is the cost under outcome i. If a risk has a 0.25 probability of causing a $400,000 loss, its EMV is:

EMV = 0.25 × $400,000 = $100,000

If outcomes include gains and losses, retain their signs. Expected value supports comparison but does not capture variance, catastrophic tails, risk attitude or distributional fairness.

Worked example: contingency comparison

Two construction methods have the following additional-cost outcomes:

MethodOutcomeProbabilityAdditional cost
ANo disruption0.70$0
AUtility relocation delay0.30$300,000
BNo disruption0.90$0
BSpecialist equipment failure0.10$500,000

For A, EMV = 0.70 × 0 + 0.30 × $300,000 = $90,000. For B, EMV = 0.90 × 0 + 0.10 × $500,000 = $50,000. On expected additional cost alone, B is preferable. However, the decision should also examine capital cost, safety, repair time, environmental effects and the credibility of the probabilities.

For a normally distributed cost X with mean μ and standard deviation σ, approximately 68% of observations lie within μ ± σ when the normal model is appropriate. This approximation should not be used for bounded, skewed or heavy-tailed construction costs without checking the distribution.

Decision trees

A decision tree represents choices as decision nodes and uncertain events as chance nodes. Each complete path has a probability and payoff. The expected monetary value of an alternative is the sum of path probabilities multiplied by path payoffs. Probabilities leaving a chance node must sum to one, and branches should be mutually exclusive and collectively exhaustive.

Consider a decision to conduct a $40,000 ground investigation. Without investigation, there is a 0.30 probability of an unexpected ground condition costing $300,000; otherwise the cost is $0. With investigation, the investigation cost is certain and the residual probability is reduced to 0.10, with the same $300,000 consequence.

Without investigation:

EMV = 0.30 × $300,000 = $90,000

With investigation:

EMV = $40,000 + 0.10 × $300,000 = $70,000

The investigation has an expected monetary advantage of $20,000. This conclusion assumes the investigation cost is fixed, the probabilities are credible and the investigation does not create other effects. Its value may be greater if it enables redesign or prevents a safety-critical failure.

Sensitivity analysis

Sensitivity analysis changes one input at a time, or a defined group of inputs, to determine which assumptions most influence the result. For a linear cost model:

C = C₀ + pL

C is expected cost, C₀ is base cost, p is probability of loss and L is loss magnitude. In the investigation example, the break-even probability p* for an investigation costing K is:

p* = K ÷ L

Thus p* = $40,000 ÷ $300,000 = 0.1333, or about 13.3%, if the investigation reduces the risk to zero. If the residual probability is 0.10, the correct break-even comparison includes the residual risk and gives the more general condition K < (p_before − p_after)L.

Sensitivity analysis can be displayed by tornado charts, scenario tables or spider plots. It does not assign probabilities to changed assumptions and therefore differs from Monte Carlo simulation.

Monte Carlo simulation

Monte Carlo simulation propagates uncertain inputs through a model by repeated random sampling. A typical procedure is:

  1. define the output, such as total cost or completion date;
  2. identify uncertain inputs and suitable distributions;
  3. specify correlations and constraints;
  4. sample one value for each input;
  5. calculate the output;
  6. repeat many times;
  7. inspect the output distribution and test the model.

If total cost is the sum of uncertain activities, one simulation trial may be represented by:

C^(k) = Cfixed + ∑Xᵢ^(k)

where k is the trial number, C_fixed is deterministic cost and Xᵢ^(k) is the sampled value of uncertain item i. The simulated mean is:

C̄ = (1/N)∑C^(k)

where N is the number of trials. The result is an estimate whose stability should be checked by increasing N and examining convergence.

Common distributions include triangular distributions for minimum, most likely and maximum estimates; normal distributions for approximately symmetric unbounded variation; lognormal distributions for positive, right-skewed quantities; and empirical distributions based on observed data. A triangular distribution should not be used merely because it is convenient: its bounds and mode require defensible evidence.

Correlation is essential. For example, multiple activities may be delayed by the same rainy season or inflation may affect several cost items. Treating correlated risks as independent can understate the probability of extreme outcomes. Simulation is also vulnerable to poor input assumptions, double counting, false precision and model error. A probability curve is not evidence of accuracy unless the model and data are credible.

5. Climate, disaster and cascading risk

Climate risk assessment should consider changing hazard frequency and intensity, exposure over the asset life, vulnerability, adaptation options and residual risk. Relevant hazards may include extreme rainfall, river and coastal flooding, heat, drought, wildfire, landslides, sea-level rise, permafrost degradation and compound events. Design should use appropriate historical evidence, climate projections, local topography and uncertainty ranges rather than a single unsupported scenario.

Disaster risk is often systemic. A flood may damage a substation, interrupt pumping, disable communications and prevent emergency access. Network analysis should identify critical nodes, single points of failure, dependencies and alternate routes. Recovery planning should include spare parts, mutual aid, emergency contracts, backup power, public communication and safe access for responders.

Adaptation pathways are preferable to one irreversible forecast. A project may initially use passive drainage capacity, reserve land for future expansion and define indicators that trigger additional works. This approach can reduce regret when future conditions are uncertain.

6. Resilient design and response planning

Resilience measures can be structural, operational, institutional or financial. Examples include elevated equipment, flood barriers, seismic detailing, slope stabilisation, redundant power, sectional isolation, modular replacement, emergency exercises, mutual-aid agreements, insurance and dedicated recovery funds.

The hierarchy of controls remains important: eliminate the hazard where practicable, substitute safer methods, use engineering controls, establish administrative controls and provide personal protective equipment. PPE is important but should not be the primary control for a systemic infrastructure hazard.

Response plans should define:

  • trigger conditions and responsible decision-makers;
  • immediate life-safety actions;
  • protection of critical equipment and records;
  • alternate service arrangements;
  • communication with authorities, workers and the public;
  • access, logistics and supply-chain priorities;
  • recovery sequence and acceptance criteria;
  • after-action review and improvement actions.

Residual risk must be documented after controls. Acceptance should be explicit, authorised at the proper level and supported by monitoring. Contract clauses should allocate responsibilities clearly for design assumptions, latent conditions, weather, force majeure, notification, records, insurance and change management. Transfer of financial risk does not remove the owner’s duty to ensure safe and functional infrastructure.

7. Applied case: illustrative urban flood-resilience project

Background

A fictional municipality plans a $60 million transport interchange beside a river. The interchange will connect buses, a rail station and an emergency access road. The design flood level is uncertain because rainfall patterns are changing and the catchment contains rapid development.

Problem

The preliminary design places electrical switchgear in a below-grade room. A flood could disable the interchange for several weeks, interrupt emergency access and damage neighbouring businesses. The project team must compare three options: retain the design, elevate equipment and use flood-resistant barriers, or relocate critical controls and provide a temporary operating mode.

Analysis

The team establishes service objectives: life safety, emergency access within 24 hours, limited passenger service within 72 hours and full restoration within 14 days. It combines hydraulic modelling, historical flood records, climate scenarios, stakeholder knowledge and a network-dependency review. It identifies correlated risks: river flooding, power loss and road inaccessibility may occur together.

The risk register assigns owners for hydraulic assumptions, electrical design, emergency operations, stakeholder communication and construction interfaces. A qualitative matrix flags the below-grade equipment risk as high consequence even though its annual probability is uncertain.

A quantitative model uses scenario ranges rather than a single probability. It tests construction cost, service interruption, equipment replacement, passenger disruption and avoided losses. Sensitivity analysis shows that flood depth, restoration duration and power redundancy dominate the result. Monte Carlo simulation is used only after the team agrees on distributions and correlations; the output is reported as ranges and percentiles, not as a falsely exact prediction.

Approach and solution

The selected concept elevates switchgear above the design flood level with additional allowance, separates critical circuits, installs watertight penetrations, reserves space for future barriers and provides a manual operating mode. The emergency plan establishes evacuation routes, portable power connections, pre-arranged pumps and public-information protocols. A trigger-based adaptation pathway requires review when observed flood levels, asset use or updated projections exceed defined thresholds.

Outcome

The option has a higher initial cost but materially lowers expected service loss and improves recovery time. The municipality records residual risk, funds inspection and exercises, and requires the operator to report barrier condition and emergency-power test results. The design is reviewed at detailed design, before commissioning and after each significant flood.

Learning points

The case demonstrates that resilience is a service and governance issue, not only a structural-design issue. It also shows why life safety, network dependencies, uncertainty ranges, maintainability and future adaptation should be considered together. A financially attractive option can be unacceptable if it creates severe, concentrated consequences for vulnerable users.

8. Governance, ethics and professional practice

Risk decisions involve values as well as calculations. Discounting future losses can make long-lived climate protection appear less attractive, even though future generations inherit the consequences. Distributional analysis asks who receives protection, who bears construction disruption and who remains exposed. Vulnerable communities should not be treated merely as statistical exposure.

Professionals must disclose material assumptions, conflicts of interest, uncertainty and limitations. Data should be traceable, models independently reviewed where consequences are high, and decisions documented. Deliberately understating risk to secure approval is unethical and may breach law or professional codes.

Regulatory requirements vary by jurisdiction, but common obligations include building and environmental approvals, occupational health and safety, emergency management, accessibility, floodplain controls, critical-infrastructure security, procurement integrity and records management. Standards and guidance should be used as applicable references, not as substitutes for project-specific engineering judgement.

Digital twins, geographic information systems, remote sensing, sensor networks and artificial intelligence can improve risk monitoring. AI may identify patterns in inspection images or forecast demand, but it can also reproduce biased data, obscure reasoning or generate unsupported outputs. Human accountability, cybersecurity, privacy protection, validation, version control and fallback procedures are essential. A model should support—not replace—competent professional judgement.

9. Challenges and limitations

Risk analysis is limited by sparse data, changing conditions, optimism bias, anchoring, inconsistent definitions, hidden dependencies and correlated events. Cost and schedule estimates may be politically pressured. Risk registers can become administrative records disconnected from decisions. Risk matrices can encourage score manipulation. Monte Carlo outputs can give an illusion of objectivity. Resilience investments may have benefits that are difficult to monetise, such as social cohesion or avoided fatalities.

Good practice is therefore to use multiple evidence sources, challenge assumptions, distinguish facts from judgements, test extreme but plausible scenarios, analyse dependencies, review independent estimates, maintain change logs and revisit decisions as knowledge changes. Quantitative sophistication should be proportionate to decision importance and data quality.

Chapter Summary

Risk management addresses the effects of uncertainty on infrastructure objectives and must continue throughout the asset life cycle. Risk identification should express causes, uncertain events and consequences clearly, while a risk register assigns ownership, responses and monitoring duties. Qualitative analysis prioritises risks but should not be mistaken for precise measurement. Expected monetary value and decision trees support comparison of alternatives, whereas sensitivity analysis identifies influential assumptions and Monte Carlo simulation represents distributions, correlations and output ranges.

Resilience concerns resistance, absorption, recovery and adaptation. Climate and disaster risks require attention to changing hazards, exposure, vulnerability, dependencies and cascading failures. Effective responses combine design, operational, institutional and financial measures. Ethical governance requires transparent assumptions, attention to vulnerable groups, regulatory compliance, independent review and accountability for residual risk. Technology can improve evidence and monitoring only when its limitations and security implications are controlled.

Key Terms

Risk: The effect of uncertainty on objectives.

Uncertainty: Incomplete knowledge or variability concerning future conditions or outcomes.

Hazard: A potentially damaging event, condition or process.

Exposure: People, assets or services located where a hazard may occur.

Vulnerability: Susceptibility of an exposed element to harm.

Consequence: The effect produced by an event or condition.

Risk appetite: The level and type of risk an organisation is willing to accept.

Risk register: A controlled record of identified risks, analysis, owners, responses and status.

Risk owner: The person accountable for managing a particular risk.

Residual risk: Risk remaining after controls or responses are implemented.

Expected monetary value: Probability-weighted average monetary consequence.

Decision tree: A representation of choices, chance events, probabilities and outcomes.

Sensitivity analysis: Examination of how changes in assumptions affect results.

Monte Carlo simulation: Repeated random sampling used to propagate input uncertainty through a model.

Resilience: Capacity to resist, absorb, recover from and adapt to disruption.

Redundancy: Provision of additional or alternative capacity so one failure does not stop service.

Cascading failure: A sequence in which one disruption causes failures in dependent systems.

Adaptation pathway: A staged strategy with future actions triggered by changing conditions.

Key risk indicator: A measurable signal used to monitor changing risk exposure.

Review Questions

Short Answer Questions

  1. Distinguish aleatory uncertainty from epistemic uncertainty.
  2. What information should be recorded in a risk register?
  3. Why is a qualitative risk score not necessarily a measured probability?
  4. State the four capabilities commonly associated with infrastructure resilience.
  5. What is the purpose of a risk owner?

Long Answer Questions

  1. Explain the complete infrastructure risk-management process from establishing context through monitoring and review.
  2. Compare risk avoidance, mitigation, transfer and acceptance, including suitable infrastructure examples.
  3. Explain expected monetary value, decision trees and the limitations of using expected value alone.
  4. Describe how climate change and system dependencies should influence infrastructure resilience planning.
  5. Discuss the governance and ethical responsibilities associated with communicating uncertainty in major projects.

Analytical / Application Questions

  1. A project faces a 0.20 probability of a $750,000 flood loss. A mitigation measure costs $90,000 and reduces the probability to 0.05. Calculate the expected loss before and after mitigation and state whether the measure is favourable on expected monetary value alone.
  2. Develop a risk register entry for unexpected contaminated soil on a highway project. Include cause, event, consequences, owner, indicators and at least two response actions.
  3. A hospital access road depends on electricity, communications and one river crossing. Analyse two possible cascading-disruption scenarios and propose structural, operational and governance measures to improve resilience.

Multiple Choice Questions with Answers

Question 1

Which statement best distinguishes a hazard from vulnerability?

A. A hazard is potential harm; vulnerability is susceptibility to that harm.

B. A hazard is a project objective; vulnerability is its budget.

C. A hazard is always a financial loss; vulnerability is always a probability.

D. A hazard is a control measure; vulnerability is a risk owner.

Correct Answer: A. A hazard is potential harm; vulnerability is susceptibility to that harm.

Question 2

A risk has probability 0.25 and consequence $400,000. What is its expected monetary value?

A. $100,000

B. $160,000

C. $300,000

D. $400,000

Correct Answer: A. $100,000

Question 3

Which response changes the project so that a threat no longer applies?

A. Acceptance

B. Transfer

C. Avoidance

D. Monitoring

Correct Answer: C. Avoidance

Question 4

What is a principal limitation of a qualitative risk matrix?

A. It cannot list risk owners.

B. Its scores may imply precision that the categories do not possess.

C. It always requires Monte Carlo simulation.

D. It can only be used after construction.

Correct Answer: B. Its scores may imply precision that the categories do not possess.

Question 5

In a decision tree, probabilities leaving a single chance node should generally:

A. sum to zero

B. sum to one

C. be identical

D. be greater than one

Correct Answer: B. sum to one

Question 6

What is the main purpose of sensitivity analysis?

A. To identify which assumptions most influence an outcome

B. To guarantee that a forecast will occur

C. To eliminate all uncertainty from a model

D. To assign legal responsibility to a contractor

Correct Answer: A. To identify which assumptions most influence an outcome

Question 7

Which issue can cause Monte Carlo simulation to understate extreme outcomes?

A. Including correlations between related risks

B. Using too many trials

C. Treating correlated risks as independent

D. Checking convergence

Correct Answer: C. Treating correlated risks as independent

Question 8

Which resilience capability concerns restoring service after disruption?

A. Recovery

B. Exposure

C. Transfer

D. Procurement

Correct Answer: A. Recovery

Question 9

A risk owner is primarily responsible for:

A. Managing the assigned risk and ensuring appropriate action

B. Approving every project invoice

C. Replacing the regulator

D. Guaranteeing that the risk cannot occur

Correct Answer: A. Managing the assigned risk and ensuring appropriate action

Question 10

A mitigation costs $90,000, reducing a 0.20 probability of a $750,000 loss to 0.05. What is the expected net monetary effect compared with no mitigation?

A. $22,500 improvement

B. $90,000 loss

C. $112,500 improvement

D. $150,000 improvement

Correct Answer: A. $22,500 improvement

Infrastructure Project Management
Chapter 8 of 15