Industrial Engineering

Chapter 13
Engineering Economy, Costing and Project Management

Bachelors Program in Machine Technology
Industrial Engineering   •   Bachelor

Engineering Economy, Costing and Project Management

Introduction

Industrial engineers make decisions under technical, financial, and time constraints. Selecting a machine, replacing equipment, outsourcing a component, expanding capacity, or implementing automation requires more than determining technical feasibility. The alternative must also create sufficient economic value and be delivered within a controlled schedule, budget, and risk profile.

Engineering economy provides methods for comparing alternatives whose cash flows occur at different times. Costing converts resources into reliable estimates for planning and control. Project management organizes scope, time, cost, quality, resources, communication, and risk so that a proposed improvement becomes an operational result. Together, these disciplines support evidence-based decisions in manufacturing and machine technology.

Learning Objectives

By the end of this chapter, the learner should be able to:

  1. Explain the time value of money and construct cash-flow diagrams.
  2. Compare alternatives using present worth, annual worth, rate of return, and payback.
  3. Apply depreciation, life-cycle costing, and cost–benefit analysis.
  4. Prepare cost estimates, budgets, and value-engineering studies.
  5. Construct project networks and determine the critical path.
  6. Use PERT, resource planning, and risk-control methods.
  7. Evaluate economic and project-management decisions ethically and professionally.

1. Foundations of Engineering Economy

1.1 The economic decision process

A defensible engineering-economic decision normally follows these steps:

  1. Define the problem, need, constraints, and decision horizon.
  2. Identify feasible alternatives, including the do-nothing or baseline option.
  3. Estimate initial investment, operating cost, maintenance cost, revenues, salvage value, taxes, and other cash flows.
  4. Select an appropriate interest rate and evaluation method.
  5. Compare alternatives on a common basis.
  6. Test sensitivity to uncertain assumptions.
  7. Consider nonfinancial effects such as safety, environmental impact, quality, flexibility, and workforce capability.
  8. Document assumptions, calculations, approval authority, and implementation responsibilities.

Cash flows should be classified by when money is paid or received, not merely by when an accounting entry is recorded. A cash-flow diagram places time on a horizontal axis, with upward arrows representing receipts and downward arrows representing payments.

1.2 Time value of money

A monetary amount available today can be invested and therefore generally has greater economic value than the same nominal amount received later. Let P be present value, F future value, i the effective interest rate per period, and n the number of periods. Under a constant rate and discrete compounding:

F = P(1 + i)n

Thus,

P = F ÷ (1 + i)n

The rate and period must be consistent. For example, a monthly cash flow requires a monthly effective rate. If an annual nominal rate is compounded monthly, the periodic rate is normally the nominal annual rate divided by 12, unless the problem specifies an effective annual rate.

For a uniform end-of-period annual amount A, the present worth is:

P = A[(1 + i)n − 1] ÷ [i(1 + i)n]

and the equivalent annual worth is:

A = P[i(1 + i)n] ÷ [(1 + i)n − 1]

These annuity formulas assume equal payments, equal periods, a constant rate, and payments at the end of each period. A payment at the beginning of each period is an annuity due and is multiplied by (1 + i).

For a geometric gradient in which the first payment is A1 and payments grow at rate g, the present worth for i ≠ g is:

P = A1[1 − ((1 + g) ÷ (1 + i))n] ÷ (i − g)

This formula applies to payments at the end of periods and requires consistent rate definitions. A zero-growth series reduces to the uniform-annuity formula.

1.3 Effective interest and inflation

An effective annual rate measures actual growth over one year. If the nominal annual rate is r compounded m times per year, the effective annual rate is:

ieff = (1 + r ÷ m)m − 1

When inflation is relevant, the relationship between nominal rate in, real rate ir, and inflation rate f is:

1 + in = (1 + ir)(1 + f)

Nominal cash flows, which include inflation, must be discounted at a nominal rate. Constant-price or real cash flows must be discounted at a real rate. Mixing the two produces a biased result.

2. Economic Evaluation Methods

2.1 Present worth

Present-worth analysis converts all relevant cash flows to time zero. For cash flows Ct occurring at the end of period t, including an initial investment C0,

PW = C0 + ∑[t = 1 to n] Ct ÷ (1 + i)t

Here, costs are negative and receipts are positive. For mutually exclusive alternatives with equal study lives, the alternative with the greatest present worth is preferred, subject to nonfinancial constraints. If alternatives provide different benefits, incremental or equivalent-service analysis is required.

2.2 Annual worth

Annual-worth analysis converts initial investment, operating cash flows, and salvage value into an equivalent uniform annual amount. For an investment P, salvage value S, and annual operating cash flow Ao:

AW = Ao − P(A ÷ P, i, n) + S(A ÷ F, i, n)

where

(A ÷ P, i, n) = i(1 + i)n ÷ [(1 + i)n − 1]

and

(A ÷ F, i, n) = i ÷ [(1 + i)n − 1]

The notation is a factor notation, not division of the letters. Annual worth is especially useful for comparing machines with unequal lives when each machine is assumed to be replaced by an identical successor at the end of its life, or when a common repeatability assumption is reasonable.

2.3 Rate of return

The internal rate of return is the discount rate that makes net present worth zero:

0 = ∑[t = 0 to n] Ct ÷ (1 + r)t

For a single conventional investment—an initial negative cash flow followed by positive cash flows—acceptance is commonly based on r ≥ MARR, where MARR is the minimum attractive rate of return. For mutually exclusive alternatives, incremental rate-of-return analysis is safer than independently ranking projects by IRR. Cash-flow patterns with multiple sign changes may produce multiple IRRs or no meaningful IRR; present-worth analysis should then be emphasized.

2.4 Payback period

The simple payback period is the time required for cumulative undiscounted cash inflows to recover the initial investment. If annual cash flow is constant, Payback = Initial investment ÷ Annual cash inflow. If cash flows vary, cumulative amounts are added year by year and the fractional year is interpolated when appropriate.

Discounted payback uses discounted rather than nominal cash flows. Payback is easy to communicate but ignores cash flows after recovery; simple payback also ignores the time value of money. It should therefore be used as a liquidity or screening measure, not as the sole investment criterion.

Worked Example 1: Present worth and payback

A machining centre costs $120,000, has an expected life of five years, a salvage value of $20,000, and annual operating savings of $35,000. Use an effective annual interest rate of 10% and assume savings occur at each year-end.

The present worth is:

PW = −120,000 + 35,000[(1.10)5 − 1] ÷ [0.10(1.10)5] + 20,000 ÷ (1.10)5

Since the five-year annuity factor at 10% is approximately 3.7908 and (1.10)5 ≈ 1.6105,

PW ≈ −120,000 + 35,000(3.7908) + 20,000 ÷ 1.6105 ≈ $18,527

The project is economically attractive at 10% because its present worth is positive. Simple payback is 120,000 ÷ 35,000 = 3.43 years. This payback figure does not credit the salvage value or the time value of money, so it cannot replace the present-worth result.

3. Depreciation, Taxes, and Life-Cycle Costing

Depreciation allocates the depreciable cost of an asset over its accounting life. It is not itself a cash outflow, but it can reduce taxable income. Tax treatment depends on jurisdiction and current law; engineering analysis should use approved accounting and tax advice.

For straight-line depreciation with first cost P, salvage value S, and recovery period N, the annual depreciation is:

D = (P − S) ÷ N

The book value after k years is:

BVk = P − kD

Under declining-balance depreciation, depreciation in a period is a fixed percentage of beginning book value. It accelerates tax deductions but must be applied according to the legally permitted method and any terminal-value rules.

Life-cycle cost includes all significant costs from acquisition through disposal. A general present-value model is:

LCC = C0 + ∑[t = 1 to n] (Coperation,t + Cmaintenance,t + Ctraining,t + Cenvironment,t − Rt) ÷ (1 + i)t + Cdisposal ÷ (1 + i)n

Here, Rt represents benefits or residual receipts. The model should include energy, tooling, spare parts, downtime, software, inspection, safety compliance, and disposal where material. The lowest purchase price is rarely identical to the lowest life-cycle cost.

4. Cost Estimation, Budgeting, and Cost–Benefit Analysis

4.1 Cost classification

Manufacturing costs may be classified as direct materials, direct labour, and manufacturing overhead. For decision analysis, variable costs change approximately with output, while fixed costs remain approximately constant over a relevant range. Avoidable costs matter to a decision; sunk costs do not. Opportunity cost is the value of the best resource use forgone.

A useful total-cost model is:

Ctotal = F + vQ

where F is fixed cost, v variable cost per unit, and Q output quantity. If revenue per unit is p, break-even quantity is:

QBE = F ÷ (p − v)

This formula assumes constant unit price and variable cost, fixed cost over the relevant range, and one product or a known product mix. It is not valid when capacity, price, or unit cost changes substantially with volume.

Cost estimates should progress from conceptual estimates to preliminary estimates and finally to detailed, resource-based estimates. Common methods include analogy, parameter-based estimating, labour-hour estimates, vendor quotations, and bottom-up work-package estimating. Estimate quality depends on scope definition, historical data, escalation assumptions, and uncertainty analysis.

A project budget should contain a cost baseline organized by work package and time period. A contingency reserve addresses identified uncertainty; management reserve may address unforeseen work according to organizational policy. Reserves should not hide poor estimating or unauthorized scope changes.

4.2 Cost–benefit analysis

Cost–benefit analysis compares discounted benefits and costs. The benefit–cost ratio is:

BCR = Present worth of benefits ÷ Present worth of costs

A ratio greater than one indicates that discounted benefits exceed discounted costs, provided benefits and costs are defined consistently. Net present value, distributional effects, safety benefits, environmental effects, and uncertainty should also be reported. A high ratio does not automatically justify a project if it violates safety, legal, or ethical requirements.

Worked Example 2: Break-even and decision relevance

A factory is considering an automated inspection cell. Annual fixed cost is $90,000, variable inspection cost is $4 per unit, and the avoided external inspection cost is $10 per unit. The break-even volume is:

QBE = 90,000 ÷ (10 − 4) = 15,000 units per year

At 20,000 units, the annual contribution after fixed cost is (10 − 4)(20,000) − 90,000 = $30,000. A sunk feasibility-study cost must not be added to this decision, whereas the opportunity cost of using an existing technician elsewhere must be included if the technician is constrained.

5. Value Engineering and Design-to-Cost

Value engineering is a systematic method for achieving required functions at the lowest total cost without unacceptable loss of performance, quality, reliability, safety, or maintainability. Value is often represented conceptually as:

Value = Function performance ÷ Cost

This is a comparative concept rather than a universal physical law. Function analysis uses a verb–noun description, such as “support load,” “seal fluid,” or “transfer torque.” The team identifies basic functions, secondary functions, cost drivers, and unnecessary features.

A typical value-engineering study includes information gathering, function analysis, creative generation of alternatives, evaluation, development, and presentation. Cross-functional participation is essential: design, production, purchasing, quality, maintenance, safety, and users may see different sources of value. Cost reduction that transfers risk to operators, customers, suppliers, or the environment is not genuine value improvement.

6. Project Management Framework

A project is a temporary effort undertaken to create a defined product, process, or result. Operations are repetitive and ongoing; projects have a beginning, an authorized scope, and a planned completion. Industrial engineering projects may involve plant layout, CNC-cell installation, maintenance modernization, quality-system implementation, or production-line balancing.

The project management plan should integrate:

  • scope and requirements;
  • work breakdown structure and deliverables;
  • schedule and milestones;
  • cost baseline and funding;
  • quality criteria;
  • staffing and equipment;
  • procurement and supplier responsibilities;
  • communication and reporting;
  • risk responses; and
  • change-control procedures.

A work breakdown structure decomposes the total scope into deliverables and work packages. A work package should be sufficiently defined to estimate, schedule, assign, and control, but not so detailed that administration overwhelms engineering work.

7. Network Scheduling and the Critical Path

A precedence network represents logical relationships among activities. In an activity-on-node representation, each node is an activity and arrows show precedence. Common relationships include finish-to-start, start-to-start, finish-to-finish, and start-to-finish, although finish-to-start is most common.

For a deterministic activity duration, the forward pass calculates earliest start and finish:

EF = ES + duration

For an activity with predecessors,

ES = maximum(EF of all immediate predecessors)

The backward pass calculates latest times. For an activity with no successor, latest finish equals project duration. Otherwise,

LF = minimum(LS of all immediate successors)

and

LS = LF − duration

Total float is:

TF = LS − ES = LF − EF

Activities with zero total float form at least one critical path. Delaying a critical activity delays the project unless corrective action or approved schedule change occurs. A network may have several critical paths, and the critical path can change as actual performance develops.

Worked Example 3: Critical path

Consider the following activities:

ActivityDuration (days)Immediate predecessor
A: define requirements3—
B: design fixture5A
C: order components7A
D: fabricate fixture4B
E: install components3C
F: test cell2D and E

The paths are A–B–D–F = 3 + 5 + 4 + 2 = 14 days and A–C–E–F = 3 + 7 + 3 + 2 = 15 days. Therefore, the expected deterministic project duration is 15 days and A–C–E–F is the critical path. Activity D has one day of float, assuming the stated relationships and no resource limitations.

8. PERT and Schedule Uncertainty

The Program Evaluation and Review Technique (PERT) uses three time estimates for an activity: optimistic a, most likely m, and pessimistic b. The beta-distribution approximation for expected duration is:

te = (a + 4m + b) ÷ 6

The activity variance is:

σ² = [(b − a) ÷ 6]2

These formulas assume that the three estimates reasonably represent uncertainty and that activity durations are described by the PERT approximation. For a critical path, expected project duration is approximated by the sum of expected durations. If activities are treated as independent, path variance is the sum of activity variances:

σ²project = ∑ σ²activity

The corresponding standard deviation is σproject = √σ²project. A normal approximation for completing by deadline T is:

Z = (T − μ) ÷ σproject

where μ is expected project duration. This approximation can be misleading when paths merge, activities are correlated, or the critical path changes. Simulation is preferable for complex schedules.

9. Resource Planning and Project Control

A schedule based only on precedence may be infeasible when the same technician, crane, machine, or specialist is assigned to overlapping activities. Resource planning identifies required labour, equipment, materials, and facilities by time period. Resource leveling changes activity timing to reduce peaks; resource smoothing adjusts within available float where possible. If resources are severely constrained, the resulting schedule may require a different critical-path analysis.

Project control compares actual performance with the approved baseline. Earned value management provides an integrated view of scope, schedule, and cost. Let:

  • PV = planned value, the budgeted value of scheduled work;
  • EV = earned value, the budgeted value of completed work; and
  • AC = actual cost of completed work.

Schedule variance and cost variance are:

SV = EV − PV
CV = EV − AC

Schedule and cost performance indexes are:

SPI = EV ÷ PV
CPI = EV ÷ AC

Values above one indicate favourable performance for the respective index; values below one indicate unfavourable performance. Earned value does not measure quality or safety, and a project can show favourable cost performance while producing defective or unsafe output.

10. Risk Management and Governance

Risk is an uncertain event or condition that may affect objectives. A practical process is to identify risks, analyze probability and impact, prioritize them, plan responses, assign owners, monitor triggers, and record lessons learned. Threat responses include avoid, mitigate, transfer, and accept. Opportunity responses include exploit, enhance, share, and accept.

A qualitative risk matrix ranks probability and consequence, but ordinal scores should not be treated as precise monetary forecasts. Quantitative analysis may use expected monetary value:

EMV = ∑ probabilityi × consequencei

EMV is useful for portfolios of uncertain outcomes but does not describe the full distribution or risk attitude. Schedule and cost contingency should be supported by identified risks, historical performance, and, where justified, Monte Carlo simulation.

Governance requires authorized scope, traceable assumptions, segregation of duties, procurement transparency, document control, and escalation of material deviations. Engineers must not conceal cost overruns, manipulate forecasts, accept conflicts of interest, or trade away safety for schedule. Relevant regulations may concern occupational safety, environmental emissions, labour, procurement, accounting, data protection, and product compliance; exact requirements depend on jurisdiction and industry.

11. Integrated Applied Case

Illustrative case: Automated deburring cell

Background. A medium-sized manufacturer produces aluminium housings. Manual deburring creates variable cycle time, repetitive-motion exposure, and overtime during peak demand. Management is considering an automated deburring cell.

Problem. The proposed cell costs $260,000 installed. Expected annual labour and scrap savings are $92,000, annual maintenance and energy cost is $24,000, life is six years, and salvage value is $30,000. The company uses a 9% MARR. Installation must be completed before the next model launch in 18 weeks.

Analysis. Net annual operating benefit is 92,000 − 24,000 = $68,000. The present worth is:

PW = −260,000 + 68,000[(1.09)6 − 1] ÷ [0.09(1.09)6] + 30,000 ÷ (1.09)6

Using an annuity factor of approximately 4.4859 and (1.09)6 ≈ 1.6895,

PW ≈ −260,000 + 68,000(4.4859) + 30,000 ÷ 1.6895 ≈ $64,868

The investment is attractive financially, but the team also evaluates guarding, interlocks, operator training, maintenance access, noise, spare-part availability, and integration with quality inspection.

Approach and solution. The project team creates a work breakdown structure, obtains supplier quotations, and develops a network with design, procurement, foundation work, installation, programming, validation, and training. A risk register identifies long lead times, software integration failure, inadequate extraction, and operator resistance. Procurement of the robot and safety hardware begins early, while installation is scheduled during a planned shutdown. A controlled pilot verifies cycle time and defect rate before full acceptance.

Outcome. In this illustrative scenario, the positive present worth supports approval, but release of final funds is tied to safety validation and production acceptance. The baseline includes contingency for integration risk rather than treating the estimate as certain.

Learning points. Economic attractiveness is necessary but not sufficient. Life-cycle costs, risk, safety, schedule feasibility, maintainability, and human factors determine whether the project creates durable value.

12. Technology, AI, and Contemporary Practice

Digital manufacturing systems increasingly connect costing, enterprise-resource-planning data, maintenance records, production rates, and project dashboards. Parametric estimating can improve consistency when historical data are well structured. AI may assist with demand forecasting, anomaly detection, schedule-risk prediction, and estimate classification. However, models can reproduce biased historical decisions, hide assumptions, or produce false precision. Human review, data lineage, access control, cybersecurity, validation, and documented accountability remain essential.

Digital twins and simulation can test capacity, material flow, energy use, and maintenance policies before physical implementation. Their results are only as reliable as model boundaries, input data, and validation procedures. A sophisticated dashboard does not compensate for an incomplete scope statement or an inaccurate cost baseline.

13. Best-Practice Checklist

  • Use consistent nominal or real cash flows and discount rates.
  • Include the baseline alternative and relevant opportunity costs.
  • Separate sunk, avoidable, fixed, variable, and life-cycle costs.
  • Test results for sensitivity to rate, volume, life, salvage, and delays.
  • Use incremental analysis for mutually exclusive alternatives.
  • Define scope before estimating and maintain a controlled baseline.
  • Link schedule activities to deliverables and responsible owners.
  • Recalculate the critical path after major changes.
  • Level scarce resources before promising a completion date.
  • Maintain a live risk register with triggers and response owners.
  • Treat safety, legal compliance, quality, and environmental protection as constraints, not optional benefits.
  • Record assumptions so that another engineer can reproduce the decision.

Chapter Summary

Engineering economy compares alternatives by recognizing the time value of money. Present worth, annual worth, rate of return, and payback answer different questions and must be applied under consistent rate, timing, life, and cash-flow assumptions. Depreciation affects accounting and taxation, while life-cycle costing captures acquisition, operation, maintenance, downtime, and disposal. Cost estimation and budgeting convert scope into a controllable financial baseline; cost–benefit analysis tests whether discounted benefits justify discounted costs. Value engineering improves required function without sacrificing safety or performance.

Project management turns an approved alternative into a controlled result. Work breakdown structures define scope, network schedules establish precedence, critical-path analysis identifies activities controlling completion, and PERT represents duration uncertainty. Resource planning recognizes that precedence-only schedules may be infeasible. Earned value integrates scope, cost, and schedule indicators, while risk management identifies uncertainty and assigns response actions. Ethical governance requires transparency, traceability, compliance, and protection of people and the environment. Sound industrial-engineering decisions therefore combine quantitative economics with technical judgment, project discipline, and responsible professional conduct.

Key Terms

Time value of money: The principle that money available at different times has different economic value.

Present worth: The equivalent value of future cash flows expressed at a chosen base date.

Annual worth: The uniform annual equivalent of an investment’s cash flows.

MARR: Minimum attractive rate of return used as an investment benchmark.

Internal rate of return: The rate that makes the net present worth of cash flows equal to zero.

Payback period: Time required to recover an initial investment from cash inflows.

Depreciation: Accounting allocation of an asset’s depreciable cost over its recovery period.

Life-cycle cost: Total relevant cost from acquisition through operation and disposal.

Opportunity cost: Value of the best alternative use of a scarce resource.

Sunk cost: A past cost that cannot be changed by a current decision.

Break-even point: Output or sales level at which relevant revenue equals relevant cost.

Value engineering: Systematic improvement of required function relative to total cost.

Work breakdown structure: Hierarchical decomposition of project scope into deliverables and work packages.

Critical path: The longest logical path through a project network.

Float: Allowable schedule delay that does not violate a specified constraint.

PERT: A schedule technique using optimistic, most likely, and pessimistic duration estimates.

Baseline: Approved reference plan for scope, schedule, or cost control.

Earned value: Budgeted value of work actually completed.

Risk register: Controlled record of risks, analysis, owners, triggers, and responses.

Life-cycle decision: A decision evaluated over the complete economic and operational life of an asset or system.

Review Questions

Short Answer Questions

  1. Why must a discount rate and cash-flow timing use consistent periods?
  2. Distinguish a sunk cost from an opportunity cost.
  3. What does a positive present worth indicate when the discount rate is the MARR?
  4. Define total float in a project network.
  5. Why should payback not normally be the sole investment criterion?

Long Answer Questions

  1. Explain present-worth, annual-worth, internal-rate-of-return, and payback methods, including one strength and one limitation of each.
  2. Describe how life-cycle costing differs from purchase-price comparison in selecting manufacturing equipment.
  3. Explain the stages of a value-engineering study and the role of cross-functional participation.
  4. Describe how a work breakdown structure, network schedule, critical path, and resource plan are connected.
  5. Discuss ethical and governance requirements when an engineering project is over budget or behind schedule.

Analytical / Application Questions

  1. A machine costs $180,000, provides $52,000 annual savings for five years, and has $15,000 salvage value. At 8%, calculate its present worth and state whether it meets a zero-present-worth acceptance criterion.
  2. Construct a precedence network for a production-cell installation and determine the critical path when procurement and installation share one specialist. Explain how resource leveling may change the schedule.
  3. A project has three major risks with probabilities and financial consequences of 0.2 and −$40,000, 0.1 and −$100,000, and 0.3 and +$30,000. Calculate the combined EMV and explain why EMV alone is insufficient for approval.

Multiple Choice Questions with Answers

Question 1

Which method converts all project cash flows to a common base date?

A. Present-worth analysis

B. Simple payback

C. Resource leveling

D. Critical-path analysis

Correct Answer: A. Present-worth analysis

Question 2

A machine costs $50,000 and produces constant annual savings of $10,000. Ignoring salvage and interest, what is the simple payback period?

A. 0.2 years

B. 4 years

C. 5 years

D. 60 years

Correct Answer: C. 5 years

Question 3

Which cost should generally be excluded from a current alternative comparison?

A. Future maintenance cost

B. Opportunity cost of constrained labour

C. Sunk feasibility-study cost

D. Avoidable energy cost

Correct Answer: C. Sunk feasibility-study cost

Question 4

In a project network, an activity with zero total float is normally part of the:

A. Resource pool

B. Critical path

C. Cost baseline

D. Risk register only

Correct Answer: B. Critical path

Question 5

Using PERT, if optimistic time is 2 days, most likely time is 5 days, and pessimistic time is 8 days, the expected time is:

A. 3 days

B. 4 days

C. 5 days

D. 6 days

Correct Answer: C. 5 days

Question 6

If earned value is $80,000 and actual cost is $100,000, the cost performance index is:

A. 0.80

B. 1.25

C. $20,000

D. $180,000

Correct Answer: A. 0.80

Question 7

Which statement about life-cycle costing is correct?

A. It considers only the purchase price.

B. It excludes disposal costs by definition.

C. It includes relevant costs over the asset’s useful life.

D. It is identical to straight-line depreciation.

Correct Answer: C. It includes relevant costs over the asset’s useful life.

Question 8

For an investment with conventional cash flows, an internal rate of return greater than the MARR generally indicates that the investment:

A. Fails the economic test

B. Meets the rate-of-return screen

C. Has zero present worth at the MARR

D. Has no operating cost

Correct Answer: B. Meets the rate-of-return screen

Question 9

What is the principal purpose of a work breakdown structure?

A. To calculate inflation

B. To decompose project scope into manageable deliverables

C. To replace safety validation

D. To determine tax depreciation automatically

Correct Answer: B. To decompose project scope into manageable deliverables

Question 10

A benefit–cost ratio greater than one generally means that:

A. Discounted benefits exceed discounted costs

B. The project has no risk

C. The payback is exactly one year

D. The project is legally approved

Correct Answer: A. Discounted benefits exceed discounted costs