Highway Engineering

Chapter 12
Pavement Evaluation, Maintenance and Asset Management

Bachelors Program in Construction Technology
Highway Engineering   •   Bachelor

Pavement Evaluation, Maintenance and Asset Management

Introduction

A highway pavement is a long-lived public asset exposed to traffic, weather, drainage conditions, construction variability, and changing standards. Its performance gradually changes from a newly constructed, serviceable condition to a state requiring preservation, rehabilitation, or reconstruction. Pavement evaluation provides the evidence needed to understand that change. Maintenance converts evidence into action, while asset management connects engineering decisions with economics, risk, service objectives, and public accountability.

The central professional challenge is not simply to identify defects. It is to determine their causes, assess their severity and extent, predict their consequences, and select the intervention that provides the required level of service at the lowest justified life-cycle cost. A technically excellent treatment applied at the wrong time may be wasteful; a delayed treatment may cause rapid deterioration and substantially higher costs.

Learning Objectives

By the end of this chapter, students should be able to:

  1. Distinguish structural, functional, safety, and environmental pavement condition.
  2. Plan and interpret pavement condition surveys and testing programs.
  3. Diagnose common flexible and rigid pavement distresses by cause.
  4. Select appropriate routine maintenance, preservation, rehabilitation, and reconstruction treatments.
  5. Apply condition indicators, deterioration models, risk concepts, and life-cycle cost analysis.
  6. Explain how pavement asset-management systems prioritize projects under limited budgets.
  7. Recognize data-quality, ethical, environmental, and governance issues in pavement decisions.

1. Pavement Condition as a Multidimensional Concept

Pavement condition has several dimensions. A pavement can be structurally adequate but slippery, or smooth but structurally close to failure. Therefore, a single visual rating should not replace engineering diagnosis.

1.1 Structural condition

Structural condition concerns the pavement’s ability to carry present and anticipated traffic without excessive permanent deformation, fatigue cracking, or loss of support. Evidence may include deflection under a known load, layer thickness and material properties, subgrade strength, drainage performance, and observed structural distress.

A common field indicator is the surface deflection measured by a falling weight deflectometer (FWD). The FWD applies an impulse load intended to simulate a moving wheel load and records a deflection basin using sensors at several offsets. A large central deflection may indicate low overall stiffness; the shape of the basin helps distinguish weak surface layers from deeper foundation problems. Deflection is not, by itself, a direct measurement of remaining life; interpretation requires temperature, load, layer, and seasonal context.

1.2 Functional condition

Functional condition describes how well the pavement serves users. Important properties include:

  • longitudinal and transverse roughness;
  • skid resistance and texture;
  • rut depth and water-ponding potential;
  • ride quality and user comfort;
  • noise and splash effects; and
  • accessibility for bicycles, pedestrians, and people with disabilities where relevant.

The International Roughness Index (IRI) is widely used to express longitudinal profile roughness, commonly in m/km. It is calculated from a standardized quarter-car simulation of a measured road profile, not simply from the average size of visible defects. Lower IRI generally indicates a smoother ride, but acceptable limits depend on road class, speed, climate, and agency policy.

1.3 Safety and environmental condition

Safety evaluation considers friction, hydroplaning risk, visibility of markings, edge drop-offs, pavement geometry, and the interaction of defects with vehicle and pedestrian behavior. Environmental condition includes water infiltration, freeze–thaw damage, heat effects, oxidation, emissions associated with user delay, and material impacts over the asset life.

1.4 Condition indices

Agencies often combine distress observations into a Pavement Condition Index (PCI) or another condition score. A PCI-type index is useful for communication and network screening, but it is not a universal physical law. Its distress weights, deduct values, sampling rules, and thresholds must be calibrated to local materials, climate, traffic, and decision objectives. A score should never conceal a critical defect such as a dangerous skid deficiency or a localized structural failure.

2. Pavement Evaluation: From Question to Evidence

Evaluation begins with a management question. Examples are: “Which roads require immediate structural investigation?” “Will a thin overlay restore service for ten years?” or “Where should next year’s preservation funds be spent?” The question determines the data required.

2.1 Evaluation levels

A practical hierarchy is:

LevelPurposeTypical evidence
Network screeningCompare many road sectionsInventory, visual surveys, roughness, traffic, safety records
Project-level investigationDiagnose a candidate treatmentDetailed distress mapping, cores, FWD, drainage and materials data
Design verificationSelect dimensions and construction requirementsLayer properties, climate, traffic spectra, mechanistic analysis, constructability review
Post-treatment evaluationConfirm performanceAcceptance tests, early distress, ride, friction, drainage, user feedback

2.2 Road inventory and segmentation

The network should be divided into homogeneous sections with similar pavement type, age, traffic, climate, drainage, maintenance history, and subgrade. Segments that are too long hide local failures; segments that are too short create excessive administrative and statistical noise. Changes in pavement structure, traffic category, or distress mechanism generally justify a new section.

A linear referencing system links observations to route and position. It should support repeatable surveys, photographs, test results, work orders, costs, and treatment history. Without stable referencing, apparent deterioration may reflect inconsistent locations rather than true pavement change.

2.3 Distress surveys

A distress survey records type, severity, extent, and location. Typical flexible-pavement distresses include fatigue or alligator cracking, longitudinal and transverse cracking, block cracking, reflection cracking, rutting, potholes, raveling, bleeding, and patch deterioration. Rigid-pavement distresses include transverse and longitudinal cracking, faulting, pumping, spalling, corner breaks, joint seal failure, and slab rocking.

Severity should be defined operationally. For example, low, medium, and high severity may be associated with crack width, edge deterioration, load-related movement, or the effect on ride. Extent may be reported as length, area, number per kilometre, or percentage of lane area. Surveyors must use consistent definitions and quality checks.

2.4 Automated and instrumental measurement

Modern survey vehicles may use laser profilers, inertial measurement units, cameras, three-dimensional scanners, GPS, and friction-measurement systems. These tools improve repeatability and coverage, but require calibration, validation, data filtering, and competent interpretation. Automated crack detection may confuse shadows, tar seals, lane markings, and construction joints with distress. Machine learning should assist—not replace—engineering review, especially for unusual conditions and high-consequence decisions.

2.5 Sampling and data quality

Network surveys may use systematic sampling, full coverage, or a statistically designed sample. Project investigations usually require targeted testing at representative and worst-case locations. Measurements should include metadata such as date, temperature, lane, equipment, calibration status, and surface condition.

A useful quality principle is “fitness for decision.” Highly precise roughness data do not compensate for absent drainage information when the suspected problem is water-related. Data uncertainty should be reported, particularly when two projects have nearly equal priority scores.

3. Diagnosing Pavement Distress

Diagnosis links the observed symptom to its mechanism. The same visible crack can result from fatigue, thermal contraction, reflection from an underlying layer, construction joints, or utility trench settlement. Treatment selection based only on appearance is therefore risky.

3.1 Flexible pavement distress mechanisms

Fatigue cracking is commonly associated with repeated tensile strain near the bottom of an asphalt layer, often accelerated by inadequate thickness, weak support, heavy loading, poor drainage, or aging. It usually develops into interconnected patterns in wheel paths.

Rutting is permanent deformation in wheel paths. It may arise from densification, shear flow in asphalt layers, granular base deformation, or subgrade failure. A rut profile and test pits help identify the active layer. Surface-only treatment is unlikely to succeed if the subgrade is deforming.

Block cracking forms large interconnected blocks and is often related to asphalt aging and thermal or volumetric movements rather than traffic fatigue. It may indicate oxidation, low-temperature susceptibility, or inadequate binder performance.

Raveling is the loss of aggregate from the surface, caused by poor adhesion, inadequate compaction, aging, moisture damage, or construction defects. It can reduce texture quality and expose the pavement to accelerated water entry.

Potholes are localized failures often produced by cracking, water entry, freeze–thaw action, and traffic. They require immediate hazard control, but repeated patching without correcting drainage or structural causes is inefficient.

3.2 Rigid pavement distress mechanisms

Concrete pavement performance depends on slab thickness, concrete properties, joints, load transfer, support uniformity, drainage, and environmental action. Faulting results from differential slab elevation, often associated with pumping and loss of support. Joint spalling may arise from incompressible materials, poor joint construction, freeze–thaw action, or inadequate load transfer. Corner breaks and transverse cracking may reflect combined load and temperature stresses.

3.3 A diagnostic workflow

A defensible diagnosis generally follows these steps:

  1. Define the distress and map its severity and extent.
  2. Examine its spatial pattern: wheel path, lane edge, joint, isolated spot, or full section.
  3. Review construction, maintenance, traffic, climate, and drainage history.
  4. Perform targeted tests such as cores, pits, moisture observations, FWD, profile, friction, or laboratory testing.
  5. Form competing hypotheses and test them against all evidence.
  6. Identify the failure mechanism, not merely the symptom.
  7. Select treatments that address the mechanism and verify constructability.

4. Maintenance and Rehabilitation Treatments

Treatment terminology varies among agencies, but the following distinction is useful.

  • Routine maintenance preserves safety and operability through activities such as pothole repair, crack sealing, drainage cleaning, shoulder repair, vegetation control, and markings.
  • Preventive maintenance or preservation is applied while the pavement is still fundamentally sound, using crack sealing, surface treatments, microsurfacing, thin overlays, or joint maintenance.
  • Rehabilitation restores structural or functional capacity through overlays, partial-depth or full-depth repairs, recycling, slab replacement, or localized reconstruction.
  • Reconstruction replaces most or all of the pavement structure and is appropriate when existing materials or support cannot be economically restored.

4.1 Treatment selection principles

Treatment selection should consider:

  • distress mechanism and remaining structural capacity;
  • traffic loading and future demand;
  • climate, moisture, and freeze–thaw exposure;
  • available materials and construction season;
  • expected service life and failure mode;
  • work-zone safety and traffic management;
  • compatibility with drainage and utilities;
  • environmental impacts and recycled content;
  • agency capability and contractor availability; and
  • uncertainty and consequences of treatment failure.

Crack sealing can delay water entry when cracks are active and appropriate for sealing, but it will not restore a severely weakened base. A thin asphalt overlay can improve ride and seal a surface, but may reflect underlying cracks and cannot reliably correct deep rutting. Full-depth reclamation may address broad structural and moisture-related problems, but requires adequate construction control and may affect traffic for longer.

4.2 Selecting by decision matrix

A weighted decision matrix can make assumptions transparent. If criterion scores are normalized from 0 to 100, a composite score may be written as:

Sj = ∑(wi rij), with ∑wi = 1

Here, Sj is the score of treatment j, wi is the weight of criterion i, and rij is the normalized rating of treatment j on criterion i. The method is appropriate for comparing alternatives when criteria are explicitly defined and sensitivity-tested. It does not replace engineering judgment or life-cycle cost analysis, and scores must not be treated as objectively precise when inputs are uncertain.

5. Life-Cycle Cost and Performance

Initial construction cost alone can lead to poor asset decisions. Life-cycle cost analysis (LCCA) compares costs and, where appropriate, benefits over a defined analysis period. Costs may include agency construction and maintenance, user delay, vehicle operating effects, safety consequences, residual value, and environmental costs.

For a cost occurring in year t, its present value at discount rate i is:

PVt = Ct ÷ (1 + i)t

where Ct is the cost in currency units at year t, i is the real discount rate expressed as a decimal per year, and PVt is its present value. The rate and costs must be expressed consistently: real costs require a real discount rate, while nominal costs require a nominal rate including expected inflation.

The net present value of an alternative can be expressed as:

NPV = C0 + ∑[Ct ÷ (1 + i)t] − RV ÷ (1 + i)n

Here, C0 is the initial cost, Ct are future costs, RV is residual value at the end of year n, and n is the analysis period. If alternatives provide equivalent service, the lower NPV is generally preferred. If service levels differ, costs should be compared with performance and risk rather than cost alone.

Worked example: present value comparison

Two equivalent resurfacing alternatives are considered for 20 years. Alternative A costs 1.20 million currency units now and requires 0.20 million in year 8. Alternative B costs 1.45 million now and requires 0.08 million in year 12. Use a real discount rate of 4% and ignore residual value.

For A:

NPVA = 1.20 + 0.20 ÷ (1.04)8 million

Since (1.04)8 ≈ 1.369, NPVA ≈ 1.20 + 0.146 = 1.346 million.

For B:

NPVB = 1.45 + 0.08 ÷ (1.04)12 million

Since (1.04)12 ≈ 1.601, NPVB ≈ 1.45 + 0.050 = 1.500 million.

On agency cost alone, A has the lower present cost. This conclusion would require reconsideration if B provides materially better safety, lower user delay, greater reliability, or a longer service life beyond the analysis period.

6. Pavement Asset Management

Pavement asset management is a systematic, risk-based process for managing infrastructure throughout its life in order to achieve defined service objectives. It connects policy, data, engineering, economics, finance, operations, and public expectations.

6.1 Core elements

A mature system includes:

  1. Objectives and level of service: acceptable ride, safety, availability, resilience, and environmental performance.
  2. Asset inventory: location, pavement type, layers, age, ownership, drainage, structures, and related assets.
  3. Condition and performance data: distress, roughness, friction, deflection, traffic, weather, and work history.
  4. Deterioration models: relationships predicting condition over time under specified actions and uncertainties.
  5. Treatment rules: feasible interventions, costs, expected lives, and constraints.
  6. Risk management: likelihood and consequence of failure, including network criticality.
  7. Investment optimization: selection of projects and timing under budget, workforce, and access constraints.
  8. Delivery and feedback: implementation, quality assurance, and performance monitoring.

6.2 Deterioration and intervention timing

A conceptual condition trajectory declines gradually and may accelerate after a threshold. Preservation is most effective before severe structural deterioration. However, the exact curve is not universal. Climate, traffic, materials, construction quality, maintenance, and measurement error must be represented or acknowledged.

A simple annual deterioration representation is:

Qt+1 = Qt − dt + It

where Qt is a condition measure at year t, dt is deterioration during the year, and It is the improvement credited to an intervention. This is a bookkeeping model, not a universal prediction equation. Values must be calibrated, bounded to the index definition, and adjusted for treatment effects and uncertainty.

6.3 Prioritization under constrained budgets

A priority score may combine condition, traffic, safety, strategic importance, risk, and treatment urgency. One transparent formulation is:

Pj = aCj + bTj + cRj + dUj, with a + b + c + d = 1

The variables are normalized scores for condition Cj, traffic or users Tj, risk Rj, and urgency Uj. The coefficients express policy weights. A score is a screening tool; it should not automatically override legal safety obligations, emergency works, equity commitments, or interdependent project opportunities.

More advanced systems use optimization to maximize network condition or total benefit subject to budget, minimum service, crew capacity, and project dependencies. They should report trade-offs, not produce an unexplained “optimal” list. Multi-year programming is preferable where it avoids repeated mobilization or coordinates with utilities and bridge works.

7. Illustrative Case: Regional Road Network Preservation

Background

A regional agency manages 1,200 lane-km of asphalt pavement. Its surveys show generally acceptable roughness, but increasing wheel-path rutting and fatigue cracking on freight corridors. The annual preservation budget is fixed, while reconstruction needs are growing.

Problem

Historically, projects were selected mainly by worst visual condition. This approach produced several late interventions, high user disruption, and insufficient attention to drainage and freight importance.

Analysis

The agency divided roads into homogeneous sections and combined condition surveys with traffic, FWD measurements, drainage inspections, treatment history, and unit costs. Investigation showed that some severely cracked sections had shallow structural deficiencies and required rehabilitation, while moderately distressed sections could be preserved economically by timely surface treatment. Several apparent pavement failures were traced to blocked side drains.

For each section, engineers estimated feasible treatments, expected performance, agency cost, work-zone effects, and uncertainty. A risk register identified high-consequence routes serving hospitals, ports, and evacuation corridors. The agency also tested the effect of alternative policy weights and discount rates.

Approach and solution

The program reserved funds for immediate safety and drainage works, then applied preservation to sections with adequate structural capacity, rehabilitation to sections with verified structural distress, and reconstruction only where alternatives were not cost-effective. Projects were bundled by corridor to reduce traffic disruption. Performance targets were established for roughness, rutting, cracking, and friction, with post-treatment surveys scheduled at defined intervals.

Outcome

The agency did not eliminate all poor-condition pavement within one budget cycle. Instead, it reduced the rate of deterioration, increased the proportion of roads receiving treatment before structural failure, and made the reasons for project selection auditable. The program also exposed a data gap: reliable friction measurements were unavailable on several high-speed routes, so funding was allocated for improved safety data.

Learning points

The case illustrates that asset management is not merely a database or a condition score. It is a continuous decision process linking diagnosis, treatment timing, risk, costs, service levels, and feedback. It also shows why drainage, safety, and network function must be considered alongside pavement appearance.

8. Governance, Sustainability, and Emerging Practice

Pavement decisions involve public money and unequal effects across communities. Agencies should document criteria, disclose uncertainty, avoid manipulating ratings to favor predetermined projects, and provide auditable records of inspection and procurement. Prioritization should consider equitable access and the needs of users who depend on reliable public transport or accessible walking routes.

Environmental assessment may include material extraction, fuel and energy use, recycling, greenhouse-gas emissions, water quality, construction waste, and user delay. Warm-mix asphalt, reclaimed asphalt pavement, in-place recycling, optimized haulage, durable materials, and climate-resilient drainage can reduce impacts, but environmental claims require system boundaries and verified assumptions.

Artificial intelligence can support image classification, anomaly detection, deterioration forecasting, and work-order optimization. Its limitations include biased training data, poor transfer between climates and pavement types, lack of explainability, cyber risk, and automation errors. Agencies should retain human accountability, validate models on local data, monitor drift, protect personal and location-sensitive information, and preserve raw evidence for audit.

Climate change increases the importance of resilience. Higher temperatures can accelerate rutting and binder aging; intense rainfall can overwhelm drainage; freeze–thaw patterns may change; and wildfire, flooding, or coastal hazards may interrupt corridors. Asset plans should test scenarios rather than relying only on historical averages.

9. Best-Practice Checklist

A professional pavement-management program should:

  • define service objectives before ranking projects;
  • maintain a complete, spatially referenced inventory;
  • use repeatable distress definitions and calibrated equipment;
  • combine functional, structural, safety, drainage, and traffic evidence;
  • diagnose causes before selecting treatments;
  • preserve sound pavements before deterioration accelerates;
  • distinguish routine maintenance from structural rehabilitation;
  • compare alternatives using consistent life-cycle assumptions;
  • include risk, uncertainty, resilience, equity, and environmental effects;
  • coordinate pavement works with utilities and other assets;
  • verify construction quality and document treatment performance; and
  • review predictions against actual outcomes and update models.

Challenges and Limitations

No evaluation system perfectly predicts pavement performance. Measurements vary with temperature, moisture, equipment, operators, and survey timing. Condition indices can obscure localized hazards. Deterioration models calibrated to one region may fail elsewhere. Life-cycle analysis depends on uncertain service lives, costs, discount rates, and user impacts. Budget optimization may produce mathematically efficient but politically or socially unacceptable outcomes if objectives are incomplete. Finally, preservation can be difficult to justify publicly because its benefit is the failure that does not occur. These limitations require transparent assumptions, sensitivity analysis, professional judgment, and continual learning.

Chapter Summary

Pavement evaluation measures more than visible defects: it addresses structural capacity, ride quality, friction, safety, drainage, environmental performance, and network function. Effective evaluation begins with a clear decision question, uses homogeneous sections and reliable data, and combines surveys with targeted structural and materials testing. Diagnosis must identify the mechanism causing distress before treatment is selected.

Routine maintenance, preventive preservation, rehabilitation, and reconstruction serve different conditions and objectives. Treatment timing is critical because preserving a sound pavement is often less costly and less disruptive than repairing advanced failure. Life-cycle cost analysis discounts future costs consistently and should be combined with performance, risk, user, and environmental considerations.

Pavement asset management integrates inventory, condition data, deterioration models, treatment rules, risk, budgets, and performance feedback. Prioritization tools support transparent decisions but do not replace engineering responsibility or public governance. Sustainable and resilient practice requires attention to materials, climate, drainage, equity, data quality, and responsible use of automated and AI-based technologies.

Key Terms

Pavement evaluation: Systematic measurement and interpretation of pavement condition and performance.

Structural condition: Ability of a pavement structure to carry traffic without unacceptable distress.

Functional condition: Serviceability characteristics such as roughness, rutting, and ride quality.

Distress: Observable or measurable deterioration of pavement materials or performance.

Pavement Condition Index (PCI): A condition-rating framework based on distress type, severity, and extent.

International Roughness Index (IRI): Standardized measure of longitudinal road-profile roughness.

Falling Weight Deflectometer (FWD): Device that measures pavement deflection under an impulse load.

Fatigue cracking: Load-associated interconnected cracking caused by repeated structural strain.

Rutting: Permanent longitudinal depressions in wheel paths.

Raveling: Loss of surface aggregate from a pavement.

Preservation: Timely action that maintains a pavement before major structural deterioration.

Rehabilitation: Work that restores functional or structural capacity without necessarily rebuilding the entire pavement.

Reconstruction: Replacement of most or all of the pavement structure.

Life-cycle cost analysis: Comparison of costs over an asset’s analysis period using present-value principles.

Discount rate: Rate used to convert future monetary values to present values.

Asset management: Coordinated, life-cycle management of infrastructure to achieve service objectives.

Deterioration model: Relationship used to estimate condition change over time.

Risk: Combination of the likelihood and consequence of an adverse event.

Level of service: Defined performance standard experienced by users or required by an agency.

Homogeneous section: Road segment with sufficiently similar structure, environment, traffic, and performance.

Review Questions

Short Answer Questions

  1. Why should structural and functional pavement condition be evaluated separately?
  2. What information should a distress survey record besides distress type?
  3. State two limitations of using a single pavement condition index.
  4. Distinguish preservation from rehabilitation.
  5. Why is drainage information important in pavement diagnosis?

Long Answer Questions

  1. Explain a complete pavement-evaluation workflow from management question to treatment recommendation.
  2. Compare the mechanisms and appropriate investigations for fatigue cracking, rutting, and raveling.
  3. Explain how life-cycle cost analysis supports pavement treatment selection and identify its principal assumptions.
  4. Describe the main components of a pavement asset-management system.
  5. Discuss how safety, sustainability, resilience, and equity should influence pavement investment decisions.

Analytical / Application Questions

  1. A road has good ride quality but rapidly increasing wheel-path rutting. Propose a diagnostic program and explain which treatment decisions the results could support.
  2. Two treatments have similar present costs, but one has greater uncertainty in service life and lower traffic disruption. Design a decision framework that accounts for cost, risk, and user effects.
  3. A municipality can fund either preventive treatments on ten moderate-condition roads or reconstruction of two severely failed roads. Explain what data and policy objectives are needed to recommend a defensible program.

Multiple Choice Questions with Answers

Question 1

Which measurement is primarily associated with longitudinal ride quality?

A. International Roughness Index

B. Falling Weight Deflectometer basin

C. Binder penetration

D. Concrete air content

Correct Answer: A. International Roughness Index

Question 2

What is the most appropriate first principle when selecting a pavement treatment?

A. Choose the treatment with the lowest initial price

B. Match the treatment to the diagnosed distress mechanism

C. Apply reconstruction to every cracked section

D. Use the same treatment throughout the network

Correct Answer: B. Match the treatment to the diagnosed distress mechanism

Question 3

A pavement with interconnected cracking in wheel paths most commonly exhibits which distress?

A. Block cracking

B. Fatigue cracking

C. Bleeding

D. Joint spalling

Correct Answer: B. Fatigue cracking

Question 4

In present-value analysis, a future cost is generally converted to present value by:

A. Multiplying by (1 + i)^t

B. Dividing by (1 + i)^t

C. Adding the discount rate to the cost

D. Dividing by the analysis period only

Correct Answer: B. Dividing by (1 + i)^t

Question 5

If an agency’s real discount rate is 4%, a cost of 104 units occurring one year from now has a present value of approximately:

A. 96 units

B. 100 units

C. 104 units

D. 108 units

Correct Answer: B. 100 units

Question 6

Which investigation is especially useful for estimating pavement response under a simulated wheel load?

A. Falling Weight Deflectometer testing

B. Visual color matching

C. Paint thickness measurement

D. Traffic-sign inspection

Correct Answer: A. Falling Weight Deflectometer testing

Question 7

What is a principal limitation of an aggregate pavement condition index?

A. It can never be calculated from field data

B. It may conceal a critical localized safety defect

C. It measures only construction cost

D. It is independent of distress severity

Correct Answer: B. It may conceal a critical localized safety defect

Question 8

In a weighted decision matrix, the weights should normally:

A. Sum to zero

B. Sum to one when expressed as proportions

C. All be equal regardless of policy

D. Be selected after the preferred treatment is known

Correct Answer: B. Sum to one when expressed as proportions

Question 9

Which action best represents preventive pavement preservation?

A. Replacing the entire pavement after foundation failure

B. Sealing suitable cracks before major structural deterioration

C. Ignoring low-severity defects until potholes form

D. Removing all drainage facilities

Correct Answer: B. Sealing suitable cracks before major structural deterioration

Question 10

Why should AI-based pavement distress detection be locally validated?

A. Because models may misclassify conditions outside their training data

B. Because automated surveys cannot collect location data

C. Because pavement distress is unrelated to images

D. Because validation eliminates the need for engineering review

Correct Answer: A. Because models may misclassify conditions outside their training data

Highway Engineering
Chapter 12 of 14