Global Supply Chain Strategy and Network Design

Introduction

Global supply chain strategy concerns the long-term design and coordination of sourcing, production, inventory, transportation, information, and customer-service decisions across national borders. Network design translates strategy into a physical and organizational structure: which suppliers serve which plants, where facilities are located, how much capacity is installed, which markets are served, and how products move through the system.

A sound design must balance cost, service, risk, speed, flexibility, sustainability, and legal requirements. A network optimized only for average cost may fail during port closures, geopolitical conflict, pandemics, cyberattacks, exchange-rate shocks, or sudden demand changes. Conversely, excessive redundancy can make the network financially uncompetitive. The central managerial task is therefore not to minimize one cost, but to choose an appropriate trade-off for the firm's competitive strategy.

Learning Objectives

By the end of this chapter, students should be able to:

  1. Align supply chain strategy with business strategy and customer requirements.
  2. Distinguish lean, agile, responsive, resilient, and hybrid supply chain models.
  3. Explain the strategic effects of facility location, capacity, configuration, postponement, offshoring, and nearshoring.
  4. Calculate and interpret total landed cost and basic facility-location and capacity-allocation models.
  5. Evaluate network alternatives under cost, service, risk, sustainability, and governance criteria.

1. From Business Strategy to Supply Chain Strategy

Business strategy defines how a firm intends to compete—for example through low price, premium quality, rapid innovation, customization, or dependable availability. Supply chain strategy specifies the capabilities required to deliver that value proposition.

A useful alignment logic is:

Customer requirements → competitive priorities → supply chain capabilities → network choices → performance measures.

For example, a fashion company competing through rapid trend response needs short design-to-market cycles, postponement, flexible suppliers, and strategically located distribution facilities. A cement producer competing primarily through low delivered cost may favor efficient plants, high utilization, bulk transport, and inventory positioned close to predictable demand.

The principal competitive priorities are:

  • Cost: purchase, conversion, inventory, transport, facility, and administrative cost.
  • Quality: conformance, reliability, traceability, and regulatory compliance.
  • Speed: order-cycle time and time to market.
  • Dependability: consistent delivery against promise.
  • Flexibility: ability to change volume, product mix, source, or destination.
  • Innovation: ability to introduce new products and processes.
  • Sustainability: environmental and social performance over the life cycle.

The supply chain must also manage the efficient frontier: beyond a certain point, additional speed, resilience, or customization usually requires additional cost or capacity. Strategic alignment does not mean maximizing every objective; it means prioritizing the objectives that create customer and shareholder value.

Strategic fit and the demand–supply matrix

Demand uncertainty reflects variation in volume, product mix, and timing. Supply uncertainty reflects process instability, supplier reliability, lead-time variation, geopolitical exposure, and capacity constraints. Low uncertainty permits efficiency-oriented designs. High uncertainty requires flexibility, buffers, multiple sources, or postponement.

Demand and supply conditionsAppropriate emphasis
Low demand, low supply uncertaintyLean efficiency and high utilization
High demand, low supply uncertaintyAgile demand sensing and flexible fulfillment
Low demand, high supply uncertaintySupplier risk controls, buffers, and alternatives
High demand, high supply uncertaintyResponsive and resilient hybrid design

These are not rigid categories. A single firm may use a lean design for mature basic products and an agile design for seasonal products.

2. Major Supply Chain Strategy Models

Lean supply chains

Lean supply chains seek to remove activities that do not add customer value and to reduce variability, inventory, defects, waiting, unnecessary movement, and excess capacity. Typical practices include stable schedules, supplier development, standardization, continuous improvement, pull replenishment, and high asset utilization.

Lean is most suitable when demand is relatively predictable, products are standardized, and replenishment lead times are reliable. Its weakness is exposure to disruption and demand surges when little spare capacity or inventory exists.

Agile and responsive supply chains

An agile supply chain emphasizes rapid sensing and response. It uses flexible production, short planning cycles, modular products, postponement, strategic inventory, and information visibility. Responsiveness is especially valuable when products have short life cycles, high margins, or uncertain demand.

Agility should not be confused with speed alone. It includes the ability to change volume, mix, source, and destination without disproportionate cost. Flexible labor, versatile equipment, digital planning, and postponement are common enablers.

Resilient supply chains

Resilience is the capability to prepare for, absorb, recover from, and adapt to disruption. Resilience mechanisms include multi-sourcing, geographic diversification, alternate transport routes, emergency capacity, supplier financial monitoring, inventory buffers, and documented recovery plans.

A backup facility should be represented as a parallel alternative, not as a downstream stage in the normal process. The following schematic illustrates independent inbound and outbound connections.

Parallel primary and backup manufacturing plants with independent inbound and outbound flows Suppliersmaterials Primary plantnormal capacity Backup plantstandby/alternate Marketscustomers Parallel alternatives: either plant can receive inputs and serve markets
Parallel primary and backup manufacturing plants with independent inbound and outbound flows
Figure: Parallel primary and backup manufacturing plants with independent inbound and outbound flows

Figure: A resilience-oriented parallel plant configuration with independent inbound and outbound flows.

Resilience has an economic trade-off. The relevant question is not whether redundancy is desirable in principle, but whether its expected loss avoidance exceeds its additional cost. A simple expected disruption loss is:

Expected disruption cost = P(disruption) × Loss if disruption occurs

where probability and loss must be defined for the same time period. This expression is a screening tool, not a complete risk model; correlated disruptions and recovery time may require scenario analysis.

Hybrid strategies

Most international firms use a hybrid. A stable base product may be produced through a lean global system, while uncertain final configuration is postponed near the market. A firm may use long-term low-cost suppliers for predictable demand and qualified regional suppliers for surge or disruption coverage.

3. Network Design Decisions

Facility role and configuration

Facilities may be factories, suppliers, cross-docks, distribution centers, fulfillment centers, postponement centers, or returns facilities. Configuration choices include:

  • Centralized network: fewer large facilities, pooling demand and inventory, but longer average delivery distances.
  • Decentralized network: more regional facilities, shorter delivery distance, but duplicated inventory and higher fixed cost.
  • Direct-ship network: products move from supplier or plant to customer, reducing handling but requiring suitable transport economics.
  • Hub-and-spoke network: flows consolidate through hubs, often reducing transport cost while adding handling and dependence on hubs.
  • Multi-echelon network: inventory is positioned at more than one level, such as plant, regional distribution center, and local fulfillment site.

A facility should have a clearly defined role. Ambiguous roles create duplicated inventories, conflicting priorities, and poor accountability.

Location factors

Location analysis should include market access, supplier proximity, labor cost and skills, utilities, land, taxes, trade agreements, customs, infrastructure, political stability, climate exposure, cybersecurity, regulatory conditions, and social legitimacy. Low wages alone do not establish a low-cost location.

Capacity decisions

Capacity includes installed production, storage, handling, transport, and labor capability. A plant running near full utilization may have low unit cost but little ability to absorb peaks or disruptions. Capacity can be:

  • Dedicated: optimized for a product or market but less flexible.
  • Flexible: able to produce multiple products or serve multiple markets.
  • Expandable: designed for staged investment as demand becomes clearer.
  • Contracted: obtained from external manufacturers or logistics providers.

The decision horizon matters. Long-lived buildings justify more detailed scenario analysis than short-term contracted capacity.

Postponement

Postponement delays final form, configuration, labeling, packaging, or geographic allocation until demand is better known. It reduces finished-goods variety and obsolescence while retaining responsiveness. It is effective when product modules are common, final differentiation is inexpensive, and customers accept a later configuration step.

Postponement can occur in manufacturing, logistics, or information processes. Its costs include additional handling, delayed customer availability, specialized equipment, and possible loss of scale economies.

Offshoring and nearshoring

Offshoring places activities in a distant foreign location, often to obtain labor, scale, specialized capability, or supplier ecosystems. Nearshoring places activities in a geographically closer country or region to reduce lead time, transport exposure, cultural distance, and coordination difficulty.

Neither is automatically superior. Offshoring may have lower conversion cost but longer pipelines, higher inventory, greater political exposure, and less responsiveness. Nearshoring may improve speed and resilience but involve higher wages or smaller supplier bases. A robust comparison uses total landed cost and strategic risk rather than wage rate alone.

4. Total Landed Cost

Total landed cost (TLC) is the cost of making a product available at the relevant destination. A general product-level expression is:

TLC = P + C + D + H + I + T + Q + R + E

where:

  • P = purchase or manufacturing cost;
  • C = customs duties and brokerage;
  • D = international and domestic transportation;
  • H = handling, port, and terminal charges;
  • I = pipeline and cycle inventory carrying cost;
  • T = taxes and applicable fees;
  • Q = quality, inspection, and compliance cost;
  • R = expected risk-related cost, if explicitly estimated; and
  • E = environmental and other externality cost included by the decision maker.

All terms must use the same currency, volume basis, and time period. Duties may be calculated on customs value under the applicable tariff rules, and taxes may be recoverable or nonrecoverable; therefore they must not be added mechanically.

For inventory in transit, a basic carrying-cost estimate is:

Pipeline carrying cost = V × r × (L ÷ 365)

where V is the inventory value in currency, r is the annual carrying-rate decimal, and L is transit time in days. This assumes a simple proportional annual rate and constant value during transit. It excludes financing complexities and risk of obsolescence unless those are included in r.

Worked example: offshoring versus nearshoring

A firm compares two sources for 10,000 units. Values below are per unit unless stated otherwise.

ComponentOffshoreNearshore
Purchase cost$40.00$45.00
Freight and handling$5.00$2.00
Duty$3.00$0.00
Quality/compliance$1.00$0.50
Inventory carrying cost$1.50$0.60
Risk allowance$0.50$0.30
Total landed cost$51.00$48.40

For offshore supply, 40 + 5 + 3 + 1 + 1.50 + 0.50 = 51.00. For nearshore supply, 45 + 2 + 0 + 0.50 + 0.60 + 0.30 = 48.40. Although the nearshore purchase price is higher, its total landed cost is lower by $2.60 per unit, or $26,000 for 10,000 units. The result depends on the stated assumptions and should be tested under exchange-rate, tariff, volume, and disruption scenarios.

5. Quantitative Network-Design Methods

Facility-location cost model

For candidate facilities j = 1, …, m and customer markets i = 1, …, n, a basic capacitated allocation model is:

Minimize Z = ∑ⱼ Fⱼyⱼ + ∑ᵢ∑ⱼ cᵢⱼxᵢⱼ

subject to:

∑ⱼ xᵢⱼ = dᵢ for every market i
∑ᵢ xᵢⱼ ≤ Kⱼyⱼ for every facility j
yⱼ ∈ {0,1}; xᵢⱼ ≥ 0

Here Fj is the fixed cost of opening facility j, yj is 1 if opened and 0 otherwise, cij is variable cost per unit from facility j to market i, xij is allocated quantity, di is market demand, and Kj is facility capacity. The model assumes known demand, linear variable costs, divisible flows, and no service constraint beyond full demand coverage. It is a simplified mixed-integer linear program; real models may add multiple products, emissions, sourcing rules, lead times, and disruption scenarios.

Worked facility comparison

A company must serve two markets, East and West, each requiring 100 units. It may open facilities A and B. Fixed costs and capacities are:

FacilityFixed costCapacity
A$1,000200 units
B$700120 units

Variable shipping costs per unit are:

OriginEastWest
A$2$8
B$6$3

A only: A has capacity 200, so it serves both markets. Total cost = 1,000 + (100×2) + (100×8) = 2,000.

B only: B has capacity 120 and cannot meet total demand of 200, so it is infeasible without an external source or unmet-demand penalty.

A and B: Fixed cost is 1,000 + 700 = 1,700. Assign A to East and B to West: shipping cost is (100×2) + (100×3) = 500. Total = $2,200. Therefore A-only is cheaper by $200 under the assumptions, despite B's lower West transport cost. If a service rule requires each market to receive supply within a specified maximum distance, or if disruption resilience is valued, opening both may still be justified.

This example demonstrates why location analysis must combine fixed cost, capacity, and allocation rather than selecting the lowest transport rate for each lane.

Capacity-allocation comparison

Suppose annual demand is 1,000 units. A plant has regular capacity of 800 units at $10 per unit and an available flexible supplier can provide up to 400 units at $14 per unit. If the plant is the preferred source, the least-cost allocation is:

  • Plant: 800 units × $10 = $8,000.
  • Flexible supplier: 200 units × $14 = $2,800.
  • Total variable cost = $10,800, or $10.80 per unit.

Using the flexible supplier for all demand would cost $14,000, while attempting to assign all demand to the plant would violate its capacity constraint. The calculation illustrates the value of qualified surge capacity even when it is not used for base volume.

Break-even location analysis

If two alternatives have fixed costs F1 and F2 and unit variable costs v1 and v2, their break-even volume, when v1 ≠ v2, is:

Q* = (F₂ − F₁) ÷ (v₁ − v₂)

This formula applies only when both alternatives serve the same product and demand conditions and variable costs are linear over the relevant range. For example, Site A has fixed cost $100,000 and variable cost $12; Site B has fixed cost $180,000 and variable cost $10. Setting total costs equal gives Q* = (180,000 − 100,000) ÷ (12 − 10) = 40,000 units. Below 40,000 units A is cheaper; above 40,000 units B is cheaper, assuming no capacity limits or nonlinear charges.

6. A Structured Network-Design Process

  1. Clarify strategy and service promises. Define target markets, product families, order-cycle requirements, and competitive priorities.
  2. Segment products and customers. Separate predictable from volatile demand and standard from customized products.
  3. Map the current network. Record suppliers, facilities, flows, capacities, lead times, inventory, costs, risks, and emissions.
  4. Develop alternatives. Consider centralization, regionalization, postponement, outsourcing, nearshoring, dual sourcing, and capacity expansion.
  5. Build a total-cost and service model. Include fixed, variable, inventory, customs, quality, risk, and sustainability terms.
  6. Test scenarios. Examine demand growth, tariffs, exchange rates, disruption, carbon prices, supplier failure, and transport changes.
  7. Evaluate governance and implementation. Assess contracts, ownership, data, labor, regulatory approval, and transition risk.
  8. Select and monitor. Use a balanced scorecard and revise the network as assumptions change.

Useful performance indicators include total landed cost, perfect-order rate, order-cycle time, forecast error, capacity utilization, inventory turns, cash-to-cash cycle time, recovery time, supplier concentration, emissions per unit, injury rates, and audit findings. No single metric is sufficient. High utilization, for example, may improve cost while reducing resilience.

7. Illustrative Case: Meridian Appliances

Background

Meridian Appliances, a fictional mid-sized manufacturer, sells standardized countertop appliances in Europe and North America. It currently sources motors from East Asia, performs final assembly in one Asian plant, and ships finished goods by ocean. Demand for its basic model is predictable, but premium models have seasonal and promotional volatility.

Problem

Ocean lead time is 35–45 days, finished-goods inventory is high, and a port disruption caused repeated stockouts. Management is considering: (A) retaining the existing centralized model, (B) opening a European postponement center supplied with semi-finished modules, or (C) nearshoring final assembly in Eastern Europe while retaining Asian component suppliers.

Analysis

The basic model has stable demand and benefits from scale, so a lean Asian production base remains attractive. Premium models require late customization and are more exposed to forecast error. A postponement center could receive common motors, housings, and electronics, then perform final labeling, packaging, and configuration near customers. Nearshore assembly would improve response time but could duplicate equipment and require supplier qualification.

Meridian constructs a model including fixed facility cost, ocean and road freight, duty, pipeline inventory, quality costs, emissions, and disruption scenarios. It imposes capacity constraints and requires at least two qualified sources for critical electronic components. Under normal demand, centralization has the lowest direct cost. Under a high-demand scenario, postponement has the lowest combined cost because it reduces premium-product obsolescence and emergency air freight. Nearshore assembly has the strongest recovery performance but the highest base cost.

Approach and solution

Meridian adopts a segmented hybrid design:

  • Continue Asian production for the predictable basic model.
  • Establish a smaller European postponement operation for premium variants.
  • Qualify a second component supplier in a different country.
  • Maintain a limited strategic inventory of critical electronics.
  • Use dual transport options and a documented port-disruption playbook.
  • Review the model quarterly using demand, tariff, capacity, and disruption data.

Outcome

The design does not attempt to make every product locally. It places efficiency-oriented volume in the global plant and flexibility-oriented final differentiation near the market. Its success depends on module standardization, accurate inventory visibility, supplier qualification, and disciplined rules for when to activate alternate capacity.

Learning points

  1. Network design should be segmented by product and uncertainty, not selected once for the entire company.
  2. Total landed cost can reverse a purchase-price decision.
  3. Resilience requires usable alternatives, not merely a second name on a supplier list.
  4. Postponement is valuable when late differentiation is technically and economically feasible.
  5. Scenario analysis is essential because the cheapest normal-state design may not be the cheapest over the full risk horizon.

8. Challenges, Ethics, Regulation, and Technology

Global network decisions raise ethical questions about wages, safety, forced labor, environmental harm, community displacement, and corruption. Due diligence should extend beyond first-tier suppliers where feasible. Firms must comply with customs valuation, rules of origin, sanctions, export controls, product safety, labor, data-protection, and environmental regulations. A low-cost location that depends on abusive labor or misleading origin claims is not a defensible strategic choice.

Digital technologies improve visibility and analysis. Transportation-management systems, control towers, digital twins, IoT tracking, and machine-learning forecasts can support scenario evaluation and exception management. Artificial intelligence can identify demand patterns, estimate disruption signals, and recommend allocations, but it does not eliminate judgment. Data bias, false confidence, cyber risk, explainability, and accountability must be governed. Human approval is especially important for sanctions, supplier termination, safety, and high-impact workforce decisions.

Contemporary practice increasingly incorporates carbon accounting, circular logistics, repair and remanufacturing, regional resilience, and geopolitical scenario planning. Network models should distinguish operational emissions from broader life-cycle effects and state boundaries clearly. Sustainability claims must be auditable rather than based on unverified supplier assertions.

Best-Practice Checklist

  • Start with customer value and competitive priorities.
  • Segment products, markets, and uncertainty.
  • Use total landed cost, not purchase price alone.
  • Make capacities, fixed costs, and allocation constraints explicit.
  • Test normal, peak, disruption, tariff, and exchange-rate scenarios.
  • Treat resilience as a capability with measurable cost and recovery targets.
  • Use postponement where modularity and late differentiation are feasible.
  • Qualify alternatives before a crisis occurs.
  • Include ethical, environmental, regulatory, and cybersecurity criteria.
  • Revisit the network as demand, technology, policy, and risk conditions change.

Chapter Summary

Supply chain strategy must reinforce the firm's business strategy and customer promise. Lean systems emphasize waste reduction and efficiency under predictable conditions; agile and responsive systems emphasize speed and flexibility; resilient systems provide recovery capability through alternatives, buffers, and geographic or supplier diversification. Hybrid strategies segment these approaches by product, market, and uncertainty.

Network design determines facility roles, locations, capacities, configuration, sourcing, postponement, and market allocation. Centralization can pool inventory and reduce fixed cost, while decentralization can improve service and reduce delivery distance. Offshoring and nearshoring must be assessed through total landed cost, not wage rates alone. Facility-location models show how fixed cost, capacity, and transportation interact, and capacity-allocation models make resource constraints visible. Scenario analysis extends these models to disruption, demand, tariffs, and sustainability. Effective design combines quantitative analysis with governance, ethics, regulatory compliance, technology, and managerial judgment.

Key Terms

Supply chain strategy: Long-term choices governing supply capabilities and competitive priorities.

Strategic fit: Alignment between business strategy, customer requirements, and supply chain capabilities.

Lean supply chain: A system focused on waste elimination, stability, and efficient resource use.

Agile supply chain: A system designed to respond quickly to uncertain demand or supply.

Responsive supply chain: A system emphasizing speed, flexibility, and customer reaction.

Resilience: The ability to prepare for, absorb, recover from, and adapt to disruption.

Hybrid strategy: A design combining different strategic approaches for different segments.

Network design: Decisions about facilities, flows, capacities, sourcing, and market assignment.

Centralization: Concentrating activities in relatively few facilities.

Decentralization: Distributing activities among multiple regional facilities.

Postponement: Delaying final configuration or differentiation until demand is clearer.

Offshoring: Locating activities in a distant foreign country or region.

Nearshoring: Locating activities in a geographically proximate foreign region.

Total landed cost: All relevant costs required to make a product available at destination.

Capacity: The maximum feasible output, handling, storage, or service capability.

Fixed cost: Cost that does not vary with short-run volume within a relevant range.

Variable cost: Cost that changes with the quantity produced, transported, or handled.

Facility-location model: A quantitative model selecting facilities and assigning flows.

Pipeline inventory: Inventory currently moving through the supply chain.

Postponement center: A facility performing late-stage configuration near the market.

Review Questions

Short Answer Questions

  1. What is meant by strategic fit in supply chain management?
  2. State two conditions under which a lean supply chain is appropriate.
  3. How does postponement reduce forecast-related risk?
  4. Distinguish offshoring from nearshoring.
  5. Why is capacity utilization alone an incomplete performance measure?

Long Answer Questions

  1. Compare lean, agile, responsive, and resilient supply chain strategies, including their strengths and limitations.
  2. Explain how business strategy should influence facility location and network configuration.
  3. Discuss the components and assumptions of total landed cost.
  4. Explain how a centralized network differs from a decentralized network in cost, service, and risk terms.
  5. Describe a complete process for evaluating a global network redesign.

Analytical / Application Questions

  1. A company must choose between a low-cost offshore source and a higher-price nearshore source. Design a total-landed-cost analysis and identify at least four sensitivity variables that should be tested.
  2. Using the facility-location model in this chapter, explain how adding a capacity constraint or a maximum-service-distance constraint could change the preferred network.
  3. Design a hybrid network for a company selling one predictable standard product and one seasonal customized product. Justify sourcing, postponement, inventory, and resilience choices.

Multiple Choice Questions with Answers

Question 1

Which supply chain strategy is generally most appropriate when demand is predictable, products are standardized, and processes are stable?

A. Lean strategy

B. Purely speculative strategy

C. Emergency-only strategy

D. Maximum-customization strategy

Correct Answer: A. Lean strategy

Question 2

What is the principal purpose of postponement?

A. To eliminate all transportation costs

B. To delay final differentiation until demand information improves

C. To maximize finished-goods inventory

D. To replace every supplier with a local supplier

Correct Answer: B. To delay final differentiation until demand information improves

Question 3

A product has a purchase cost of $40, freight and handling of $5, duty of $3, and quality cost of $1 per unit. What is the subtotal of these four total-landed-cost components?

A. $47

B. $48

C. $49

D. $50

Correct Answer: C. $49

Question 4

In the basic capacitated facility-location model, what does the constraint ∑ᵢ xᵢⱼ ≤ Kⱼyⱼ primarily enforce?

A. Each market must be served by every facility

B. Facility shipments cannot exceed the capacity of an opened facility

C. All facilities must operate at full capacity

D. Transportation cost must equal fixed cost

Correct Answer: B. Facility shipments cannot exceed the capacity of an opened facility

Question 5

A facility has regular capacity of 800 units at $10 per unit. Demand is 1,000 units, and an approved flexible supplier can provide the remaining units at $14 per unit. What is the total variable cost of the least-cost feasible allocation?

A. $8,000

B. $10,000

C. $10,800

D. $14,000

Correct Answer: C. $10,800

Question 6

A site has fixed cost $100,000 and variable cost $12 per unit. A second site has fixed cost $180,000 and variable cost $10 per unit. At what volume are their total costs equal?

A. 20,000 units

B. 30,000 units

C. 40,000 units

D. 80,000 units

Correct Answer: C. 40,000 units

Question 7

Which statement best describes a resilient backup facility?

A. It must always receive output from the primary plant before serving customers

B. It is a parallel alternative with qualified inbound and outbound connections

C. It replaces all normal production immediately

D. It is useful only when demand is perfectly predictable

Correct Answer: B. It is a parallel alternative with qualified inbound and outbound connections

Question 8

Which item is normally included in total landed cost?

A. Only supplier purchase price

B. Only direct labor cost

C. Purchase, transport, duties, handling, inventory, and relevant compliance costs

D. Shareholder dividends only

Correct Answer: C. Purchase, transport, duties, handling, inventory, and relevant compliance costs

Question 9

A centralized network commonly provides which advantage?

A. Guaranteed zero disruption risk

B. Inventory pooling and potentially lower duplicated fixed costs

C. Shorter delivery distance to every customer

D. No need for capacity planning

Correct Answer: B. Inventory pooling and potentially lower duplicated fixed costs

Question 10

Why should a firm test both normal and disruption scenarios in network design?

A. Because variable costs are always identical across locations

B. Because the lowest normal-state cost may not minimize cost and service loss over the risk horizon

C. Because fixed costs never matter

D. Because disruption scenarios eliminate the need for quantitative models

Correct Answer: B. Because the lowest normal-state cost may not minimize cost and service loss over the risk horizon