Global Sourcing & Procurement

Chapter 2
Global Supply Markets and Sourcing Context

Post Graduate Program in International Business
Global Sourcing & Procurement   •   Post Graduate

Global Supply Markets and Sourcing Context

Introduction

Global sourcing is not simply the purchase of goods from the lowest-cost country. It is the strategic design of an international supply base that can provide the required combination of cost, quality, capacity, innovation, resilience, compliance and speed. A sourcing decision is therefore an analysis of markets and institutions as much as an evaluation of suppliers.

The sourcing professional must understand three connected levels of the environment:

  1. Country level: macroeconomic, political, legal, social, technological and infrastructural conditions.
  2. Industry level: demand, supply capacity, competitive structure, entry barriers and bargaining power.
  3. Supplier level: capability, economics, governance, risk exposure and strategic fit.

These levels interact. A technically excellent supplier may be unsuitable if the country has unstable trade rules. Conversely, a low-risk country may not offer sufficient industry capacity or supplier expertise. Effective global procurement therefore combines market intelligence, economic analysis, institutional analysis and commercial judgment.

Learning Objectives

By the end of this chapter, the reader should be able to:

  • explain the structure of global supply markets;
  • apply supply–demand analysis to sourcing decisions;
  • use Porter’s Five Forces to assess supplier-market attractiveness;
  • evaluate country conditions through PESTLE and institutional analysis;
  • interpret the effects of trade blocs, tariffs and non-tariff barriers;
  • analyze exchange-rate exposure and geopolitical risk;
  • compare sourcing alternatives using total cost and risk-adjusted reasoning;
  • identify ethical, regulatory and governance implications of global sourcing.

1. The Global Sourcing Context

A supply market is the set of current and potential sellers capable of providing a product or service under specified commercial, technical and regulatory conditions. Its structure includes the number and size of suppliers, geographic concentration, technology, capacity, input dependence, logistics routes and institutional rules.

Global sourcing differs from domestic sourcing in several important ways:

DimensionDomestic sourcingGlobal sourcing
CurrencyUsually one currencyExchange-rate exposure
RegulationOne principal legal systemMultiple legal and regulatory systems
LogisticsShorter and more predictableLonger, multimodal and disruption-prone
CompetitionMore familiar marketGreater supplier choice but less information
RiskPrimarily domesticPolitical, trade, sanctions and country risk
CoordinationCommon language and norms more likelyCultural and institutional distance

The relevant decision is not “Which country has the lowest quoted price?” but “Which supply-market configuration creates the best risk-adjusted value over the intended planning horizon?”

Total landed cost

A basic sourcing comparison begins with total landed cost. A simplified unit-cost model is:

TLC = P + F + I + D + C + Q + H + R

where:

  • TLC = total landed cost per unit;
  • P = supplier purchase price;
  • F = international freight and transport;
  • I = insurance;
  • D = customs duty and tariffs;
  • C = customs clearance and brokerage;
  • Q = quality, inspection and compliance costs;
  • H = handling, warehousing and inventory-related costs;
  • R = expected cost of disruption, defects, delay or recovery.

This is a decision model rather than a universal accounting rule. Components must be defined consistently, and the buyer must avoid double counting costs already included in the supplier price or freight quotation. Taxes that are recoverable may be excluded from economic cost, while non-recoverable taxes should generally be included.

The final term, R, is especially important. A low-price source may become expensive when expected disruption, expedited freight, quality failures or regulatory remediation are considered.

2. Supply–Demand Analysis in Procurement

Demand conditions

Demand analysis concerns the buyer’s own requirements and the wider market. Important variables include forecast volume, seasonality, product life cycle, specification complexity, demand volatility and growth expectations. A buyer with stable, high volume has more leverage and may justify dedicated capacity. A buyer with intermittent demand may need flexible suppliers or a distributor network.

Demand is often represented as a function of price and other factors:

Qd = f(P, Y, Ps, T, E)

where Qd is quantity demanded, P is the product price, Y is buyer income or purchasing capacity, Ps represents prices of substitutes or complementary goods, T represents preferences or technology, and E represents expectations. In a conventional demand relationship, quantity demanded tends to fall as price rises, holding other factors constant. Procurement demand, however, may be derived from production schedules rather than final-consumer demand.

Supply conditions

Supplier supply depends on production capacity, input prices, technology, labor availability, capital investment, energy, infrastructure and expected profitability:

Qs = g(P, W, K, A, N, Es)

where Qs is quantity supplied, P is selling price, W is input cost, K is available capital and capacity, A is technology or productivity, N is the number of suppliers, and Es represents supplier expectations. The usual supply relationship is positive with price, but capacity constraints can make supply highly inelastic in the short run.

Market equilibrium occurs where quantity supplied equals quantity demanded:

Qs = Qd

Equilibrium is an analytical reference point, not necessarily an observable procurement price. Long-term contracts, administered prices, quotas and differentiated products may prevent a simple market-clearing outcome.

Elasticity and procurement leverage

Price elasticity of demand measures the responsiveness of quantity demanded to a change in price:

Ed = (∆Qd / Qd) ÷ (∆P / P)

Supply elasticity is defined similarly:

Es = (∆Qs / Qs) ÷ (∆P / P)

The formula uses percentage changes, so the result is dimensionless. Elasticity is most useful for assessing short-run responsiveness around a particular operating point. If supply is inelastic, a small increase in market demand can produce a substantial price increase. This is common where qualification takes years, production assets are specialized or critical minerals are geographically concentrated.

Worked example: capacity-constrained supply

Suppose a buyer requires 10,000 units per month, while qualified industry capacity is 11,000 units. A forecast increase of 20% raises demand to:

10,000 × (1 + 0.20) = 12,000 units

The market therefore has a potential shortfall of:

12,000 − 11,000 = 1,000 units

The procurement implication is not merely a likely price increase. The buyer must consider allocation risk, qualification of additional suppliers, redesign, inventory buffering or demand management. A supplier-market that appears competitive at current volumes may be structurally constrained at forecast volumes.

3. Industry Structure: Porter’s Five Forces

Porter’s Five Forces framework evaluates the competitive forces shaping profitability and bargaining conditions in an industry. In sourcing, it helps the buyer understand whether suppliers are likely to compete aggressively or retain substantial power.

Rivalry among existing suppliers

Rivalry is stronger when many similarly capable suppliers compete, switching costs are low, capacity is underutilized and products are weakly differentiated. It is weaker when a few suppliers dominate, capacity is scarce or technology is protected. Strong rivalry can support competitive bidding, but excessive rivalry may also encourage underpricing and later quality or delivery problems.

Threat of new entrants

Entry is limited by capital requirements, economies of scale, intellectual property, customer qualification, regulation, access to raw materials and reputation. A market with high entry barriers may require relationship-based sourcing and long-term capacity agreements rather than periodic tenders.

Bargaining power of suppliers

Supplier power rises when:

  • the supplier base is concentrated;
  • the buyer represents a small share of supplier sales;
  • inputs are unique or protected;
  • switching costs are high;
  • the supplier can credibly integrate downstream;
  • the buyer faces significant qualification or tooling costs.

Supplier power is not identical to supplier size. A small specialist firm may possess considerable power if it controls a critical technology.

Bargaining power of buyers

Buyer power rises when purchase volumes are large, specifications are standardized, alternative suppliers are credible and switching costs are low. Global companies often possess purchasing power at corporate level but lose it when business units buy independently or when demand is fragmented across plants.

Threat of substitutes

Substitutes may be alternative materials, technologies, processes or business models. For example, a manufacturer may substitute recycled material, additive manufacturing or a different component architecture. Substitution analysis should include lifecycle performance, regulatory approval and total cost, not merely purchase price.

Using the framework critically

Five Forces is an industry-level model. It does not replace supplier due diligence, country-risk analysis or operational feasibility testing. It can also understate cooperation, innovation ecosystems and the role of complementors. In modern technology markets, platform owners, standards bodies and governments may influence outcomes as much as conventional competitors.

4. Country Analysis: PESTLE and Institutional Factors

PESTLE analysis

PESTLE organizes macro-environmental analysis into six categories:

FactorSourcing questions
PoliticalIs policy stable? Are elections, sanctions or state intervention material?
EconomicWhat are inflation, interest rates, growth and labor-cost trends?
SocialAre labor practices, demographics and cultural expectations compatible?
TechnologicalIs infrastructure, cybersecurity and production technology adequate?
LegalWhat rules govern contracts, labor, competition, data and remedies?
EnvironmentalWhat climate, emissions, water and waste obligations apply?

PESTLE should be time-specific. A country can be attractive today but vulnerable to policy change, currency depreciation or infrastructure deterioration. Analysts should distinguish observable facts from assumptions and assign owners and review dates to major risks.

Institutions and transaction costs

Institutions are the formal and informal rules that shape economic behavior. Formal institutions include courts, customs agencies, standards authorities, property-rights systems and regulatory bodies. Informal institutions include business norms, trust, networks, social expectations and negotiation practices.

Institutional quality affects transaction costs: the costs of finding information, negotiating, monitoring and enforcing an exchange. Weak contract enforcement may increase the need for inspections, milestone payments, local representation, insurance and supplier diversification. However, institutional weakness should not be treated as a simplistic national stereotype. Conditions can vary significantly by region, industry, firm and special economic zone.

A useful due-diligence approach tests:

  • legal ownership and beneficial ownership;
  • licensing and export authorization;
  • history of regulatory violations;
  • labor and human-rights practices;
  • financial transparency;
  • anti-bribery controls;
  • data protection and cybersecurity;
  • ability to enforce warranty and intellectual-property rights.

5. Trade Blocs, Tariffs and Non-Tariff Measures

Trade blocs reduce or regulate barriers among participating economies. Their effects depend on rules of origin, product classification, customs procedures, standards and political commitments. Membership in a bloc does not automatically mean duty-free access for every product.

Tariffs

A tariff is a government charge on imported goods. For an ad valorem tariff, duty is calculated as a percentage of customs value:

D = t × Vc

where D is duty, t is the tariff rate expressed as a decimal, and Vc is customs value in the relevant valuation basis. For a specific tariff, duty is instead a fixed amount per physical unit:

D = d × Q

where d is duty per unit and Q is imported quantity. Actual customs treatment depends on tariff classification, valuation, origin and applicable exemptions. Professional analysis must use the current tariff schedule and authoritative customs guidance.

Rules of origin and non-tariff barriers

Rules of origin determine whether a product qualifies for preferential treatment. They may use a change in tariff classification, regional value content or a specified manufacturing process. Non-tariff measures include technical standards, labeling, quotas, licensing, sanitary requirements, local-content rules and conformity assessment.

These measures may serve legitimate public objectives, but they can also increase cost and delay. Procurement teams should involve customs, legal and technical specialists before committing to a sourcing route.

6. Exchange Rates and International Commercial Risk

Exchange rates affect supplier prices, buyer costs, margins and competitiveness. If a buyer’s reporting currency is the home currency and a supplier invoices in foreign currency, the home-currency cost is:

Ch = Cf × X

where Ch is home-currency cost, Cf is foreign-currency price, and X is home currency per unit of foreign currency. The units are essential. If X rises, the foreign currency has appreciated relative to the home currency and the buyer’s cost increases.

Worked example: currency movement

A contract price is €100 per unit. The exchange rate changes from 1.10 to 1.20 home-currency units per euro. The home-currency cost changes from:

100 × 1.10 = 110

to:

100 × 1.20 = 120

The increase is 10 home-currency units, or approximately 9.09% relative to the original cost:

(120 − 110) ÷ 110 × 100 ≈ 9.09%

This calculation assumes the euro price is fixed and ignores hedging costs, taxes and changes in freight or supplier pricing.

Currency risk can be managed through currency clauses, natural hedging, forward contracts, options, matching revenues and costs in the same currency, or shorter repricing intervals. Hedging does not eliminate commercial risk; it changes its timing, cost and distribution. Treasury and procurement must coordinate because a hedge that protects price may create volume or forecast risk.

7. Geopolitical and Supply-Network Risk

Geopolitical risk includes war, sanctions, diplomatic conflict, export controls, civil unrest, maritime disruption, cyberattacks and policy-driven resource restrictions. Its effect may be direct, such as a banned shipment, or indirect, such as a shortage of a critical input used by a tier-two supplier.

A supply network should therefore be mapped beyond the immediate supplier. Relevant tiers include raw-material producers, processors, component manufacturers, logistics providers, ports, data providers and financial institutions. Risk analysis should examine both probability and consequence, while recognizing that low-probability events can have catastrophic impact.

A practical risk register records:

RiskTriggerExposureEarly indicatorResponse
Export restrictionNew control listCritical componentRegulatory noticeAlternative design/source
Port disruptionStrike or conflictDelayed shipmentsCongestion dataRerouting and buffer stock
Currency shockMonetary or political eventCost escalationVolatility increaseHedge or reprice
Supplier failureLiquidity deteriorationCapacity lossLate paymentsFinancial review and dual source

Resilience options include dual or multiple sourcing, regionalization, supplier development, inventory buffers, modular product design, approved substitutes, capacity reservations and stronger visibility beyond tier one. Each option has a cost. Resilience is not synonymous with maximum redundancy; it is the economically justified ability to absorb and recover from disruption.

8. Integrating Market Analysis into a Sourcing Decision

A disciplined sourcing process converts environmental analysis into a decision rather than a descriptive report.

Step 1: Define the requirement

Specify demand volume, quality, service levels, technical standards, delivery location, contract duration, sustainability expectations and acceptable risk.

Step 2: Segment the category

Classify the purchase by business impact and supply risk. A strategically important, supply-constrained category deserves deeper market intelligence and executive governance than a routine, competitive item.

Step 3: Scan countries and industries

Use PESTLE, Five Forces, trade analysis, logistics assessment and institutional research. Compare not only current cost but likely conditions over the contract horizon.

Step 4: Build and qualify the supplier set

Assess capability, capacity, financial health, technology, quality systems, labor practices, ownership, compliance, cybersecurity and continuity planning.

Step 5: Model total cost and scenarios

Test exchange-rate movements, tariff changes, demand growth, lead-time variation, disruption and supplier failure. Scenario analysis is more informative than a single point forecast.

Step 6: Choose the commercial architecture

Possible structures include spot buying, framework agreements, indexed pricing, take-or-pay capacity contracts, dual sourcing, local assembly or strategic partnership. Contract design should reflect market power and uncertainty.

Step 7: Establish governance

Define performance measures, audit rights, escalation procedures, change-control rules, sanctions screening, business-continuity obligations and exit provisions.

Decision matrix

A weighted decision matrix can structure judgment:

S = ∑(wi × ri)

where S is the total score, wi is the weight assigned to criterion i, and ri is the supplier’s normalized rating. The weights should sum to 1, or 100%, and all ratings must use the same scale. The method is transparent but not objectively precise: weights and ratings reflect managerial assumptions. Sensitivity analysis should test whether a small change in assumptions changes the ranking.

9. Applied Case: Strategic Sourcing of Battery Components

This is an illustrative case, constructed for learning purposes.

Background

A global equipment manufacturer seeks a five-year supply of battery modules. Supplier A is located in a low-cost country with an established battery cluster. Supplier B is located closer to the final assembly plants but has higher labor costs and less proven scale. Supplier C is technologically advanced but depends on a single upstream processor in a politically sensitive region.

Problem

The procurement team initially recommends Supplier A because its quoted unit price is 8% below Supplier B’s. However, the category is strategically important, demand is forecast to grow by 25%, and new rules may impose origin and recycling requirements.

Analysis

Supply–demand analysis indicates that the regional industry has limited qualified capacity. A 25% demand increase could create allocation pressure. Five Forces shows high entry barriers because qualification, safety testing and intellectual property create substantial switching costs. Supplier power is therefore significant.

PESTLE analysis identifies three country issues: possible tariff changes, differing recycling obligations and energy-price volatility. Institutional analysis raises questions about enforcement of labor standards in the upstream supply chain. Exchange-rate analysis shows that Supplier A invoices in a currency expected to be volatile relative to the buyer’s reporting currency.

The team calculates total landed cost rather than comparing quoted prices. It also models a disruption scenario involving a six-week port closure and a base case involving a 12% currency movement. Supplier A remains cheapest in the base case, but Supplier B becomes economically preferable in the disruption scenario because of shorter transit time and a qualified secondary plant.

Approach and solution

The company adopts a portfolio strategy:

  • Supplier A receives 60% of forecast volume under a capacity and compliance agreement;
  • Supplier B receives 40% and is developed as a regional backup;
  • Supplier C is not selected for initial volume but is retained for technology collaboration;
  • pricing includes an agreed currency-adjustment mechanism;
  • contracts require disclosure of critical upstream processors;
  • battery recycling and responsible-minerals obligations are audited;
  • a quarterly capacity and geopolitical review is established;
  • product engineering approves a technically compatible substitute module.

Outcome

The company accepts a slightly higher expected purchase cost than the single-source option, but reduces exposure to transport interruption, currency volatility and supplier concentration. The decision also preserves innovation access and improves regulatory readiness.

Learning points

  1. Quoted price is not total cost.
  2. Capacity and qualification barriers can create supplier power.
  3. Country risk often enters through lower-tier suppliers.
  4. Resilience can be designed through volume allocation, contracts and engineering choices.
  5. A sourcing decision should be robust across plausible scenarios, not optimal only under one forecast.

10. Governance, Ethics and Sustainability

Global sourcing creates responsibilities beyond commercial efficiency. Buyers can influence labor conditions, environmental performance, corruption risk and community outcomes through supplier selection and contract governance.

Important controls include risk-based human-rights due diligence, prohibition of forced and child labor, responsible recruitment, occupational safety, environmental compliance, anti-bribery controls, sanctions screening and grievance mechanisms. Audits alone are insufficient: announced audits may miss actual conditions, and suppliers may shift violations to subcontractors. Effective governance combines worker voice, traceability, corrective action, purchasing-practice reform and credible consequences.

Sustainability claims should be evidence-based. Procurement teams should distinguish actual emissions reductions from certificate purchases, and should define system boundaries, data quality and verification standards. Ethical sourcing also requires examining the buyer’s own behavior: unrealistic price targets, sudden forecast changes and late payments can transfer risk to vulnerable suppliers.

11. Technology, Data and Contemporary Developments

Digital procurement platforms can improve supplier discovery, spend visibility, contract management and risk monitoring. Artificial intelligence can assist with classification, document review, anomaly detection, news monitoring and scenario generation. Nevertheless, AI outputs may reproduce biased data, misclassify suppliers or create false confidence. Human review is required for sanctions, legal interpretation, supplier exclusion and high-consequence decisions.

Contemporary supply-market developments include regionalization of production, strategic industrial policy, critical-mineral competition, carbon-border measures, cybersecurity regulation and increased scrutiny of supply-chain transparency. These trends do not imply that globalization has ended. Rather, global sourcing is becoming more selective, networked and politically governed. Firms increasingly balance efficiency with resilience, sovereignty concerns and verifiable sustainability.

12. Limitations of Sourcing Frameworks

No framework provides certainty. PESTLE can become a checklist without causal analysis. Five Forces may oversimplify ecosystems characterized by collaboration and platforms. Supply–demand models often assume stable relationships that fail during crises. Weighted matrices can disguise subjective judgments behind numerical scores. Country rankings may hide regional and firm-level variation. Cost models may omit learning effects, switching costs, reputation damage and option value.

Good analysis therefore requires triangulation: combine quantitative data with supplier interviews, legal advice, operational validation, scenario analysis and continuous monitoring. Assumptions should be documented, challenged and updated.

Chapter Summary

Global sourcing decisions depend on the interaction of country, industry and supplier-market conditions. Supply–demand analysis reveals capacity, elasticity and allocation pressure. Porter’s Five Forces explains competitive structure and bargaining power, while PESTLE identifies macro-environmental influences. Institutional analysis shows how laws, enforcement, norms and transaction costs shape practical feasibility.

Trade blocs and tariffs must be examined through classification, origin and non-tariff requirements. Exchange rates affect home-currency cost and should be addressed through contractual, operational and financial tools. Geopolitical risk requires mapping beyond tier-one suppliers and preparing responses to disruption. Total landed cost, scenario analysis and governance are more reliable than quoted price alone. The strongest sourcing strategies combine cost competitiveness with resilience, ethical conduct, regulatory compliance and long-term strategic fit.

Key Terms

Supply market: The group of current and potential sellers able to meet a defined requirement.

Global sourcing: The strategic acquisition of goods or services across national borders.

Total landed cost: The complete economic cost of obtaining and using an imported item.

Demand elasticity: The responsiveness of quantity demanded to a change in price.

Supply elasticity: The responsiveness of quantity supplied to a change in price.

Capacity constraint: A limitation preventing suppliers from meeting additional demand promptly.

Porter’s Five Forces: A framework for analyzing industry competition and bargaining conditions.

Supplier power: The ability of suppliers to influence price, terms, availability or standards.

PESTLE: Analysis of political, economic, social, technological, legal and environmental factors.

Institutional environment: Formal and informal rules shaping economic transactions.

Transaction cost: The cost of searching, negotiating, monitoring and enforcing an exchange.

Trade bloc: A group of economies coordinating trade rules or reducing barriers among members.

Tariff: A government charge imposed on imported goods.

Rule of origin: A rule determining the economic nationality of a product.

Non-tariff measure: A regulatory or administrative measure affecting international trade other than a tariff.

Exchange-rate exposure: The risk that currency movements alter the value or cost of a transaction.

Geopolitical risk: The possibility that political conflict or state action disrupts commercial activity.

Resilience: The capability of a supply network to absorb, adapt to and recover from disruption.

Risk-adjusted cost: Cost evaluated together with the expected consequences of uncertainty and disruption.

Supplier governance: The systems used to control performance, compliance, risk and accountability.

Review Questions

Short Answer Questions

  1. What distinguishes total landed cost from supplier quoted price?
  2. Identify the six components of PESTLE analysis.
  3. Why does limited qualified capacity increase supplier power?
  4. What are rules of origin?
  5. State two methods for managing exchange-rate exposure.

Long Answer Questions

  1. Explain how supply–demand analysis can improve an international sourcing decision.
  2. Apply Porter’s Five Forces to a strategically important component industry.
  3. Discuss how institutional quality influences transaction costs and supplier governance.
  4. Explain the relationship between tariffs, rules of origin and non-tariff measures.
  5. Critically evaluate the use of weighted decision matrices in global sourcing.

Analytical / Application Questions

  1. A supplier offers a lower unit price but operates in a country with volatile currency and unreliable ports. Design a structured evaluation using total landed cost and scenario analysis.
  2. A buyer faces a 25% demand increase in an industry with limited qualified capacity. Recommend commercial and operational responses, explaining the trade-offs.
  3. Construct a risk register for a global sourcing category exposed to sanctions, cyberattacks and lower-tier supplier concentration. Specify indicators and mitigation actions.

Multiple Choice Questions with Answers

Question 1

Which factor most directly increases supplier bargaining power?

A. Many qualified suppliers with spare capacity

B. Low switching costs for the buyer

C. A unique input controlled by a small number of suppliers

D. Highly standardized products

Correct Answer: C. A unique input controlled by a small number of suppliers

Question 2

If a product costs €100 and the exchange rate is 1.20 home-currency units per euro, what is its home-currency cost?

A. €83.33

B. 100 home-currency units

C. 120 home-currency units

D. 121.20 home-currency units

Correct Answer: C. 120 home-currency units

Question 3

Which item is normally included in a total landed cost analysis?

A. Only the supplier’s quoted price

B. Freight, duty and relevant quality costs

C. The supplier’s annual revenue

D. The buyer’s share price

Correct Answer: B. Freight, duty and relevant quality costs

Question 4

Which PESTLE category includes customs law and contract enforcement?

A. Political

B. Social

C. Legal

D. Environmental

Correct Answer: C. Legal

Question 5

A 20% increase in demand from a baseline of 10,000 units equals:

A. 10,200 units

B. 11,000 units

C. 12,000 units

D. 20,000 units

Correct Answer: C. 12,000 units

Question 6

What is the primary purpose of rules of origin?

A. To determine a product’s economic nationality for trade treatment

B. To set the supplier’s profit margin

C. To calculate employee turnover

D. To measure product elasticity

Correct Answer: A. To determine a product’s economic nationality for trade treatment

Question 7

Which condition generally strengthens buyer bargaining power?

A. High supplier concentration and unique technology

B. Large purchase volume and credible alternatives

C. High switching costs and scarce capacity

D. A single approved supplier

Correct Answer: B. Large purchase volume and credible alternatives

Question 8

Which response best addresses geopolitical disruption risk?

A. Rely exclusively on the lowest-price supplier

B. Ignore lower-tier suppliers

C. Use diversification, visibility and tested continuity plans

D. Remove all contractual requirements

Correct Answer: C. Use diversification, visibility and tested continuity plans

Question 9

In the decision-matrix formula S = ∑(wi × ri), what does wi represent?

A. The supplier’s currency

B. The weight assigned to criterion i

C. The tariff rate

D. The quantity demanded

Correct Answer: B. The weight assigned to criterion i

Question 10

Why should AI-supported supplier screening retain human review?

A. AI cannot process any procurement data

B. AI outputs may contain bias, errors or false confidence

C. Human review eliminates all risk

D. AI is legally prohibited in procurement

Correct Answer: B. AI outputs may contain bias, errors or false confidence

Global Sourcing & Procurement
Chapter 2 of 15