Global sourcing decisions are often presented as price comparisons: one supplier quotes 9.80 currency units per component while another quotes 10.35. Such comparisons are frequently misleading. The lower quoted price may be offset by higher freight, duties, inspection, inventory, financing, quality, disruption, or end-of-life costs. Conversely, a higher unit price may create value through better quality, shorter lead time, lower inventory, or reduced regulatory exposure.

Cost, price and financial analytics provide the quantitative foundation for sourcing decisions. Price is the amount paid or payable to a supplier. Cost is the economic consumption of resources required to acquire, use and dispose of a product or service. Financial analytics converts operational assumptions into comparable monetary measures and tests how decisions change under uncertainty.

The central managerial principle is to evaluate economic value across the relevant time horizon and supply-chain boundary rather than selecting the lowest quoted price.

Learning Objectives

By the end of this chapter, the reader should be able to:

  1. Distinguish supplier price from total cost of ownership and landed cost.
  2. Construct a landed-cost and total-cost model with transparent assumptions.
  3. Apply should-cost analysis, cost breakdowns, learning curves and life-cycle costing.
  4. Use indexation and currency analysis in international contracts.
  5. Evaluate working-capital effects and the time value of money.
  6. Conduct sensitivity, scenario and break-even analysis.
  7. Assess the governance, ethical and practical limitations of cost models.

1. Price, Cost and Value

A supplier’s quoted price normally covers the supplier’s manufacturing or service cost, overhead allocation, profit, and selected commercial terms. It may exclude transport, insurance, customs duties, taxes, testing, financing, inventory, quality failure and disposal.

A useful distinction is:

  • Quoted price: the supplier’s contractual unit price.
  • Purchase price: quoted price adjusted for discounts, rebates, surcharges and payment terms.
  • Landed cost: purchase price plus costs required to bring the item to the buyer’s specified location and condition.
  • Total cost of ownership (TCO): all relevant costs incurred over acquisition, use, support and disposal.
  • Value: benefits received relative to total economic cost and risk.

The correct boundary depends on the decision. For a one-time spot purchase, landed cost may be sufficient. For equipment, software, logistics services or critical components, TCO and life-cycle costing are more appropriate.

2. Landed-Cost Modelling

A generic per-unit landed-cost model can be written as:

LC = P + F + I + D + C + H + Q + O − R

where:

  • LC = landed cost per unit;
  • P = supplier purchase price per unit;
  • F = freight and transport cost per unit;
  • I = cargo insurance per unit;
  • D = customs duty and non-recoverable import charges per unit;
  • C = customs brokerage and documentation cost per unit;
  • H = handling, terminal and inland delivery cost per unit;
  • Q = inspection, testing and compliance cost per unit;
  • O = other attributable acquisition costs; and
  • R = rebates or credits allocated per unit.

All terms must be measured in the same currency, quantity basis and time period. Recoverable value-added tax should generally be excluded from economic cost, whereas non-recoverable taxes should be included.

If duty is ad valorem, the duty may be calculated as:

D = τ × B

where τ is the duty rate and B is the customs valuation base. The base is defined by applicable customs rules and may include the transaction value plus specified assists, royalties, packing or transport costs. It must not be assumed automatically to equal the supplier’s invoice price.

Worked Example 1: Landed Cost

An importer buys 10,000 units at 12.00 euros each. Ocean freight is 4,800 euros, insurance is 0.4% of invoice value, duty is 6% of the customs value, brokerage is 950 euros, inland delivery is 1,600 euros, and inspection is 0.18 euros per unit. Assume the customs value is the invoice value and taxes are recoverable.

Invoice value:

10,000 × €12.00 = €120,000

Insurance:

0.004 × €120,000 = €480

Duty:

0.06 × €120,000 = €7,200

Inspection:

10,000 × €0.18 = €1,800

Total landed cost:

€120,000 + €4,800 + €480 + €7,200 + €950 + €1,600 + €1,800 = €137,830

Landed cost per unit:

€137,830 ÷ 10,000 = €13.783

The apparent purchase price of 12.00 euros is therefore 13.783 euros on the stated landed-cost basis.

3. Total Cost of Ownership

TCO extends landed cost beyond delivery. A practical model is:

TCO = A + L + QF + S + W + Rsk + E − V

where:

  • A = acquisition and landed cost;
  • L = logistics and inventory-related cost after receipt;
  • QF = expected quality-failure cost;
  • S = operating, service and maintenance cost;
  • W = working-capital financing cost;
  • Rsk = expected risk-related cost;
  • E = environmental, compliance and end-of-life cost; and
  • V = residual value, recovery value or avoided cost.

The model is not a universal accounting identity. It is a decision model whose categories must be adapted to avoid double counting. For example, if inventory carrying cost is already embedded in a logistics contract, it should not be added again.

Expected risk cost can be estimated as:

Rsk = ∑ pi × Ii

where pi is the probability of risk event i and Ii is its financial impact. This expected-value approach is useful for comparing alternatives, but it does not fully represent low-probability catastrophic events or risk aversion.

TCO should also distinguish one-time and recurring costs. Tooling, qualification and supplier development may be amortized over expected volume, but managers should retain visibility of the total cash commitment.

4. Should-Cost Analysis and Cost Breakdowns

A should-cost model estimates what a product or service ought to cost under specified technical, operational and market assumptions. It is not a claim about what the supplier actually spends. Its purpose is to improve negotiation quality, identify cost drivers and test supplier quotations.

A manufacturing should-cost model commonly includes:

Cs = M + DL + OH + Dep + Log + Q + Profit

where M is material cost, DL is direct labour, OH is manufacturing overhead, Dep is depreciation or capital recovery, Log is internal logistics, Q is quality cost, and Profit is an analytically selected profit allowance.

Material cost may be estimated from the bill of materials:

M = ∑ (qj × pj × (1 + sj))

where qj is the required quantity of material j, pj is its price, and sj is the scrap or yield-loss rate. If scrap is 5%, a simple model uses sj = 0.05. More precise models distinguish gross input, recoverable scrap and process yield.

Labour cost can be represented as:

DL = t × w × (1 + b)

where t is labour time per unit, w is the wage rate per hour, and b represents applicable benefits and payroll burden.

A cost breakdown should be evidence-based. Useful evidence includes engineering drawings, material indices, observed cycle times, wage benchmarks, machine rates, capacity utilization and supplier quotations. Cost breakdowns should not be confused with a demand that suppliers disclose confidential margins or proprietary information.

Illustrative Should-Cost Example

A component uses 2.4 kg of material at 3.20 euros per kilogram, with 6% scrap. Direct labour is 0.18 hours at 18 euros per hour including burden. Manufacturing overhead is 2.10 euros per unit, logistics and quality are 0.75 euros, and the target profit allowance is 8% of pre-profit cost.

Material cost:

2.4 × €3.20 × 1.06 = €8.1408

Labour cost:

0.18 × €18 = €3.24

Pre-profit cost:

€8.1408 + €3.24 + €2.10 + €0.75 = €14.2308

Profit allowance:

0.08 × €14.2308 = €1.1385

Should-cost estimate:

€14.2308 + €1.1385 = €15.3693

The result is a negotiation reference, not proof that a supplier is overcharging. Differences may arise from scale, yield, financing, technology, geographic conditions or legitimate risk.

5. Learning Curves and Volume Effects

Learning curves model reductions in average labour hours as cumulative output increases. The classical learning-curve relationship is:

Y = aXb

where Y is average labour time per unit at cumulative output X, a is the time for the first unit under the chosen convention, and b is the learning exponent. For a learning rate r observed whenever cumulative production doubles:

b = log₂(r)

If the learning rate is 80%, then b ≈ −0.3219. The model assumes comparable products, stable process conditions and a meaningful relationship between cumulative experience and productivity. It is less reliable when automation, product redesign, labour turnover or capacity constraints dominate.

The classical curve often describes cumulative average time, not necessarily the time for the next unit. This distinction is important in should-cost analysis and quotation evaluation. Managers should validate whether the supplier uses average, marginal or batch-level data.

Learning effects can lower unit cost, but the buyer may not automatically receive the benefit. Contracts can use open-book reviews, productivity-sharing mechanisms, target-costing or periodic price resets.

6. Life-Cycle Costing

Life-cycle costing evaluates costs from acquisition through disposal. It is especially relevant for capital equipment, vehicles, industrial systems, information systems and energy-consuming assets.

The present value of life-cycle cost is:

PV(LCC) = C₀ + ∑[t=1 to n] Ct ÷ (1 + k)t − Sn ÷ (1 + k)n

where C₀ is initial cost at time zero, Ct is cost in period t, k is the discount rate, n is the life in periods, and Sn is terminal residual value. Costs and residual value must be stated in the same currency and expressed consistently as nominal or real values.

The discount rate should reflect the organization’s approved financial methodology and the risk characteristics of the cash flows. A nominal rate should be applied to nominal cash flows that include expected inflation; a real rate should be applied to real cash flows.

Worked Example 2: Equipment Choice

Machine A costs 100,000 euros initially and requires 22,000 euros annually for three years. Machine B costs 125,000 euros initially and requires 12,000 euros annually. Assume a 10% discount rate, no residual value and end-of-year operating costs.

The three-year annuity factor is:

1/1.10 + 1/1.10² + 1/1.10³ ≈ 2.4869

Present value for A:

100,000 + 22,000 × 2.4869 = €154,712

Present value for B:

125,000 + 12,000 × 2.4869 = €154,843

On these assumptions, A has a slightly lower present cost, despite its higher annual operating cost. A conclusion should not be drawn without checking reliability, capacity, quality, tax, residual value and expected life.

7. Indexation and Inflation Management

International supply contracts often include price-adjustment mechanisms because labour, energy, metals, freight and foreign exchange costs change over time. A transparent indexation formula identifies the cost elements exposed to recognized indices.

A common structure is:

Pt = P₀ [wM(Mt/M₀) + wL(Lt/L₀) + wE(Et/E₀) + wF(Ft/F₀) + wFix]

where P₀ is the base price, Pt is the adjusted price, M, L, E and F are material, labour, energy and freight indices, subscripts 0 and t refer to the base and adjustment periods, and the weights sum to one:

wM + wL + wE + wF + wFix = 1

The fixed weight represents costs not indexed. The indices and publication dates must be specified contractually. Good clauses define the base period, adjustment frequency, caps and floors, data source, treatment of negative movements, and whether changes are symmetric.

Indexation is not the same as passing through every supplier cost. It is a negotiated risk-allocation mechanism. Poorly designed clauses can reward inefficiency or expose the buyer to costs unrelated to the supplied product.

8. Currency Analysis

Currency analysis requires clarity about the transaction currency, functional currency, payment date, exposure period and hedge policy. A buyer’s domestic-currency cost can be represented as:

CD = CF × SD/F

where CD is domestic-currency cost, CF is foreign-currency cost, and SD/F is domestic currency per unit of foreign currency.

If the exchange rate rises from 1.08 to 1.16 domestic currency units per euro, a euro-denominated invoice becomes more expensive in domestic-currency terms. Analysts must state quotation conventions explicitly because “exchange rate increases” can have opposite interpretations under different conventions.

A basic sensitivity to the exchange rate is:

∆CD = CF × ∆SD/F

For a 500,000-euro invoice and a rate movement of 0.08 domestic currency units per euro, the domestic-currency impact is 40,000 units.

Hedging instruments may include forward contracts, options and natural hedges. A hedge can reduce uncertainty but may create opportunity cost, collateral requirements, accounting complexity and counterparty exposure. Procurement, treasury, tax and accounting functions should agree on the policy rather than allowing buyers to make informal speculative decisions.

9. Working Capital and Payment Terms

Procurement choices affect cash conversion. Important measures include:

CCC = DIO + DSO − DPO

where CCC is the cash conversion cycle, DIO is days inventory outstanding, DSO is days sales outstanding, and DPO is days payable outstanding.

For procurement decisions, a longer payment period may reduce financing pressure, while excessive inventory caused by large minimum-order quantities may increase it. The annual carrying cost of inventory can be approximated as:

ICC = Iavg × h

where ICC is annual inventory carrying cost, Iavg is average inventory value and h is the annual carrying-rate percentage. The carrying rate may include financing, storage, insurance, obsolescence and shrinkage, but its components should be documented.

If annual demand is D units, order quantity is Q, unit cost is c, and cycle stock is approximated as Q/2, then average cycle-stock value is:

Iavg = (Q/2) × c

This is a simplified model that excludes safety stock, pipeline inventory and seasonal stock. Payment-term analysis should also consider early-payment discounts. A discount such as 2/10, net 30 may be attractive, but its effective annualized return depends on the exact convention and whether the buyer has available liquidity.

10. Sensitivity, Scenario and Break-Even Analysis

A financial model is not a fact; it is a structured representation of assumptions. Sensitivity analysis changes one variable at a time to identify influential drivers. Scenario analysis changes several logically connected assumptions together, such as a port disruption accompanied by higher freight, longer lead time and increased safety stock.

For a two-supplier decision, the break-even quantity can be found when fixed and variable costs are equal:

Q* = (FB − FA) ÷ (vA − vB)

where FA and FB are fixed costs for alternatives A and B, vA and vB are variable costs per unit, and the denominator must be non-zero. The result is meaningful only within the feasible operating range.

Example: Break-Even Sourcing Volume

Supplier A requires 20,000 euros of tooling and has a variable landed cost of 8.40 euros per unit. Supplier B requires 5,000 euros of tooling and has a variable landed cost of 8.90 euros per unit.

Q* = (20,000 − 5,000) ÷ (8.90 − 8.40) = 30,000 units

Below 30,000 units, B is cheaper because its fixed cost is lower. Above 30,000 units, A is cheaper because its variable cost advantage exceeds its additional tooling cost.

Sensitivity tables should show both absolute and percentage effects. A tornado chart is often useful, but a simple spreadsheet table can be more auditable. Monte Carlo simulation may be appropriate when multiple uncertain variables have probability distributions; however, the quality of the output depends on the quality of the distributions and correlations.

11. Integrated Illustrative Case: Global Sourcing of a Control Module

Background

A European industrial-equipment company is sourcing 50,000 control modules annually. Supplier X is domestic; Supplier Y is located overseas. The procurement team initially recommends Y because its quoted price is 18.20 euros compared with X’s 20.00 euros.

Problem

The executive committee requires an analysis incorporating freight, duty, quality, inventory, currency and disruption risk. The decision horizon is one year, and all values are converted to euros.

Analysis

The relevant assumptions are:

Cost elementSupplier XSupplier Y
Quoted unit price€20.00€18.20
Freight and insurance€0.35€1.10
Duty and brokerage€0.00€1.25
Inspection and compliance€0.20€0.45
Expected quality cost€0.30€0.75
Incremental inventory cost€0.40€1.05
Expected disruption cost€0.10€0.60
Total estimated cost€21.35€23.40

The overseas supplier’s quoted price advantage is 1.80 euros, but its additional non-price costs total 4.20 euros. Therefore, the estimated TCO advantage lies with X by 2.05 euros per unit, or 102,500 euros annually at 50,000 units.

The result should be tested. Suppose Y improves quality, reducing expected quality cost by 0.40 euros, and freight falls by 0.30 euros. Y’s revised cost is:

€23.40 − €0.40 − €0.30 = €22.70

It remains above X’s 21.35 euros. A separate currency scenario could increase Y’s cost if the euro weakens against the sourcing currency. Conversely, a long-term contract, local buffer stock or supplier development could reduce Y’s inventory and disruption costs.

Approach and Solution

The company should not reject Y solely from the base case. It should request a transparent cost model, validate duty classification and lead-time assumptions, negotiate service-level commitments, assess dual sourcing, and evaluate whether a currency hedge or price-adjustment clause is appropriate. A staged award could preserve competition while generating operational evidence.

Outcome

The illustrative decision is to award the initial volume primarily to X while qualifying Y as a secondary supplier. This preserves resilience and future bargaining power. The recommendation is conditional on validating the estimated risk costs and monitoring actual performance.

Learning Points

  1. Quoted price is an incomplete decision variable.
  2. Risk costs should be explicit rather than hidden in vague contingency percentages.
  3. A TCO model supports negotiation but does not replace supplier due diligence.
  4. Dual sourcing may be rational even when a single supplier has the lowest modeled cost.
  5. The model should be updated using actual freight, defect, inventory and disruption data.

12. Governance, Ethics and Limitations

Cost analytics can create governance problems when models are deliberately structured to justify a predetermined award. Common weaknesses include double counting, optimistic assumptions, selective use of indices, hidden currency exposure, inappropriate allocation of overhead and treating uncertain risks as precise numbers.

Ethically, buyers should avoid using fabricated should-cost data to pressure suppliers, demanding disclosure of trade secrets without justification, or shifting unmanageable risks to financially vulnerable suppliers. Responsible sourcing requires attention to labour conditions, environmental impacts, human rights and the distributional consequences of aggressive cost reduction.

Important controls include:

  • documented assumptions and data sources;
  • version control and approval of model changes;
  • separation of facts, estimates and management judgments;
  • independent review of customs, tax and accounting treatments;
  • sensitivity analysis for material assumptions;
  • clear treatment of recoverable taxes and currency effects;
  • avoidance of double counting;
  • reconciliation to actual invoices and operational data; and
  • periodic post-award verification.

A model’s precision should not be confused with accuracy. A result reported as 23.417 euros may be less credible than a carefully supported range of 23.0–24.0 euros. Decision-makers should communicate uncertainty, not conceal it.

13. Technology and Contemporary Developments

Digital procurement platforms increasingly combine enterprise-resource-planning data, freight rates, commodity indices, supplier performance, foreign-exchange data and contract terms. Machine-learning systems can detect anomalous prices, classify spend and forecast cost drivers. Generative AI can assist with extracting assumptions from contracts and explaining model outputs.

However, AI-generated estimates require human validation. Risks include biased historical data, fabricated benchmarks, leakage of confidential supplier information, opaque recommendations and inappropriate confidence. Effective governance requires access controls, audit trails, data lineage, model testing and clear accountability for the sourcing decision.

Contemporary cost analytics also incorporates carbon pricing, product carbon footprints, circularity, supply-chain finance and geopolitical risk. These additions are valuable only when definitions, boundaries and measurement methods are transparent. A carbon cost, for example, should specify whether it represents an internal shadow price, a regulatory liability or an externally purchased offset.

Best-Practice Checklist

Before approving a global sourcing decision, managers should ask:

  1. Is the comparison made on a consistent quantity, location, currency and time basis?
  2. Are all material landed-cost and TCO elements included?
  3. Are taxes classified as recoverable or non-recoverable correctly?
  4. Are cost drivers supported by evidence?
  5. Are indexation, currency and payment-term assumptions explicit?
  6. Have quality, disruption and compliance costs been estimated without double counting?
  7. Has the result been tested through sensitivity and scenario analysis?
  8. Are risks, ethical impacts and supplier financial health considered?
  9. Can the model be audited and updated after award?
  10. Does the recommended award maximize resilient value rather than minimize quoted price?

Chapter Summary

Cost, price and financial analytics enable sourcing professionals to compare alternatives on an economically meaningful basis. Landed cost extends the supplier price to the buyer’s receiving point, while total cost of ownership includes quality, inventory, operating, risk, compliance and end-of-life effects. Should-cost analysis decomposes a product or service into materials, labour, overhead, capital, logistics, quality and profit assumptions. Learning curves help explain productivity changes, while life-cycle costing discounts future costs and residual value to a common present basis.

Indexation allocates inflation and input-cost risk through explicit weights and published indices. Currency analysis requires clear exchange-rate conventions and coordinated treasury policy. Working-capital measures connect sourcing decisions to inventory, payment terms and the cash conversion cycle. Sensitivity, scenario and break-even analysis reveal which assumptions drive the recommendation and where a decision changes.

At postgraduate level, the central lesson is not simply to construct a sophisticated spreadsheet. It is to establish a defensible decision boundary, use reliable evidence, communicate uncertainty, avoid double counting, and integrate financial, operational, strategic, ethical and resilience considerations.

Key Terms

Price: Monetary amount quoted or charged by a supplier.

Cost: Economic consumption of resources associated with an activity or decision.

Landed cost: Purchase price plus costs required to deliver goods to the specified destination.

Total cost of ownership: Acquisition, use, support, risk and disposal costs over the relevant ownership horizon.

Should-cost analysis: Analytical estimate of what a product or service ought to cost under stated assumptions.

Cost breakdown: Structured decomposition of total cost into identifiable drivers.

Learning curve: Relationship between cumulative output and declining average labour time or cost.

Life-cycle costing: Evaluation of costs from acquisition through operation and disposal.

Indexation: Contractual adjustment of price using specified cost or market indices.

Ad valorem duty: Customs duty calculated as a percentage of a valuation base.

Currency exposure: Potential change in domestic-currency value caused by exchange-rate movements.

Working capital: Short-term capital invested in operating assets net of operating liabilities.

Cash conversion cycle: Days inventory plus days receivable minus days payable.

Inventory carrying cost: Cost of financing, storing, insuring and risking inventory.

Sensitivity analysis: Assessment of the effect of changing one variable while holding others constant.

Scenario analysis: Evaluation of a coherent set of jointly changed assumptions.

Break-even quantity: Volume at which competing alternatives have equal total cost.

Expected risk cost: Probability-weighted financial impact of uncertain events.

Nominal cash flow: Cash flow stated in money-of-the-period terms, including inflation effects.

Real cash flow: Cash flow stated in constant purchasing-power terms.

Review Questions

Short Answer Questions

  1. Why is quoted supplier price insufficient for most international sourcing decisions?
  2. Distinguish landed cost from total cost of ownership.
  3. What is the purpose of a should-cost model?
  4. Why must nominal cash flows be paired with a nominal discount rate?
  5. What is the difference between sensitivity analysis and scenario analysis?

Long Answer Questions

  1. Explain how a multinational buyer should construct and govern a total-cost-of-ownership model.
  2. Discuss the assumptions, uses and limitations of learning-curve analysis in procurement.
  3. Explain how indexation clauses can allocate inflation risk between buyer and supplier.
  4. Analyse the relationship between payment terms, inventory and the cash conversion cycle.
  5. Evaluate the ethical and governance risks associated with supplier cost breakdowns and should-cost analysis.

Analytical / Application Questions

  1. A supplier quotes 15.00 euros per unit, but freight, duty, inspection, inventory and expected quality costs are 1.20, 0.90, 0.25, 0.60 and 0.45 euros respectively. Calculate the estimated landed/TCO cost per unit and explain which additional assumptions should be validated.
  2. Supplier A has fixed cost of 30,000 euros and variable cost of 7.80 euros per unit. Supplier B has fixed cost of 8,000 euros and variable cost of 8.35 euros per unit. Calculate the break-even quantity and recommend how the result should be used in a sourcing decision.
  3. Design a three-scenario analysis for an overseas sourcing decision involving exchange-rate movement, port disruption and supplier quality deterioration. Identify the variables, assumptions and managerial actions associated with each scenario.

Multiple Choice Questions with Answers

Question 1

Which measure most directly includes acquisition, use, support and disposal costs?

A. Quoted price

B. Total cost of ownership

C. Invoice value

D. Ad valorem duty

Correct Answer: B. Total cost of ownership

Question 2

A product has an invoice value of €120,000 and a 6% duty rate based on that value. What is the duty?

A. €720

B. €6,000

C. €7,200

D. €12,000

Correct Answer: C. €7,200

Question 3

In a should-cost model, which item is normally a direct material cost driver?

A. Cumulative exchange-rate exposure

B. Bill-of-materials quantity multiplied by material price

C. Days sales outstanding

D. Residual asset value

Correct Answer: B. Bill-of-materials quantity multiplied by material price

Question 4

If a learning curve has a learning rate below 100%, what does it generally indicate?

A. Average labour time rises as cumulative output increases

B. Average labour time falls as cumulative output increases

C. Material prices are fixed permanently

D. Foreign exchange risk has been eliminated

Correct Answer: B. Average labour time falls as cumulative output increases

Question 5

Which expression represents the cash conversion cycle?

A. DIO + DSO − DPO

B. DPO + DSO − DIO

C. DIO − DSO + DPO

D. DIO × DSO × DPO

Correct Answer: A. DIO + DSO − DPO

Question 6

A foreign invoice is €500,000 and the exchange-rate movement is 0.08 domestic currency units per euro. What is the approximate domestic-currency impact?

A. 4,000 units

B. 40,000 units

C. 400,000 units

D. 6,250 units

Correct Answer: B. 40,000 units

Question 7

What is the primary purpose of an indexation clause?

A. To eliminate all supplier profit

B. To adjust price according to specified cost or market movements

C. To convert nominal cash flows into real cash flows automatically

D. To guarantee the lowest possible freight rate

Correct Answer: B. To adjust price according to specified cost or market movements

Question 8

Supplier A has fixed cost €20,000 and variable cost €8.40; Supplier B has fixed cost €5,000 and variable cost €8.90. At what volume are their costs equal?

A. 15,000 units

B. 20,000 units

C. 30,000 units

D. 50,000 units

Correct Answer: C. 30,000 units

Question 9

Which statement about expected risk cost is correct?

A. It equals the highest possible loss in every case

B. It is calculated by summing probability multiplied by impact for relevant events

C. It excludes all low-probability events automatically

D. It is identical to supplier profit

Correct Answer: B. It is calculated by summing probability multiplied by impact for relevant events

Question 10

Why should a nominal discount rate be used with nominal cash flows?

A. To ensure inflation treatment is consistent

B. To remove the need for a customs valuation

C. To guarantee a positive net present value

D. To eliminate residual value from the calculation

Correct Answer: A. To ensure inflation treatment is consistent