Fundamentals of Electrical Engineering

Chapter 13
Electric Power Systems and Sustainable Energy

Bachelors Program in Electrical Engineering
Fundamentals of Electrical Engineering   •   Bachelor

Electric Power Systems and Sustainable Energy

Introduction

An electric power system converts primary energy into electricity, transports it over interconnected networks, and delivers it to consumers at acceptable voltage, frequency, reliability, safety, and cost. Historically, power flowed from large synchronous generators through transmission and distribution networks to passive loads. Modern systems also contain distributed generation, inverter-based resources, electric vehicles, responsive loads, energy storage, and digital controls. Consequently, both electrical power and operational information may flow in multiple directions.

Power-system engineering requires several interacting perspectives. Circuit models determine voltage, current, power flow, losses, and fault levels. Economic models compare capital, fuel, operating, and lifecycle costs. Reliability analysis measures interruption frequency and duration. Environmental assessment evaluates emissions, land, water, materials, and end-of-life impacts. No single technology is optimal under every criterion.

Learning Objectives

After studying this chapter, students should be able to:

  • explain the functions of generation, transmission, distribution, and system operation;
  • apply balanced three-phase power and per-unit calculations;
  • distinguish PQ, PV, and slack buses and interpret basic load-flow results;
  • calculate symmetrical three-phase fault current from a Thevenin equivalent;
  • explain protection coordination, grounding, and electrical safety;
  • calculate standard distribution reliability indices;
  • compare conventional generation, renewable generation, and storage quantitatively;
  • evaluate sustainable power-system choices using technical, economic, lifecycle, and environmental criteria.

1. Structure and Operation of an Electric Power System

1.1 Generation, transmission, and distribution

Generating stations convert chemical, nuclear, gravitational, kinetic, solar, or geothermal energy into electricity. Most conventional plants and many wind turbines ultimately use rotating generators, whereas photovoltaic modules and battery systems connect through power-electronic converters.

A generator step-up transformer raises voltage before bulk transmission. For a given three-phase power and power factor, increasing voltage reduces current. Lower current reduces conductor loss, which for a balanced three-phase line is

Ploss = 3I2R

where I is the rms line current in amperes and R is the resistance of one phase conductor in ohms. The expression assumes equal phase currents and neglects dielectric, corona, and auxiliary losses.

Transmission networks typically operate from tens to hundreds of kilovolts. Meshed configurations provide alternative routes for power transfer. High-voltage direct-current transmission is attractive for long submarine cables, asynchronous interconnections, and controllable long-distance transfer, although converter stations are costly.

Distribution substations reduce transmission voltage to medium-voltage feeder levels. Distribution transformers then supply low-voltage customers. Traditional radial feeders are simple and economical but have fewer alternative supply paths than meshed networks.

Bidirectional power and information flows in a modern electric power system Central generation thermal, hydro, wind Transmission Distribution Loads and EVs flexible demand DER and storage import or export System operator and controls measurement, dispatch, protection Solid: possible bidirectional electrical power flow Dashed: bidirectional measurement and control information
Bidirectional power and information flows in a modern electric power system
Figure: Bidirectional power and information flows in a modern electric power system

Figure: Modern grids can have bidirectional electrical power and information flows, particularly when distributed resources export energy.

1.2 Active power, reactive power, voltage, and frequency

For a balanced sinusoidal three-phase system,

P = \sqrt{3}VLLIL\cos\phi
Q = \sqrt{3}VLLIL\sin\phi
|S| = \sqrt{P2+Q2} = \sqrt{3}VLLIL

Here P is active power in watts, Q is reactive power in vars, S is apparent power in volt-amperes, VLL is rms line-to-line voltage, IL is rms line current, and \phi is the displacement angle between phase voltage and current. These equations assume balanced phases and sinusoidal fundamental-frequency quantities.

Active power balance strongly influences frequency. If generation is temporarily less than demand and losses, stored rotational or converter-controlled energy supplies the deficit, tending to reduce frequency. Reactive power and network voltage are closely coupled, although the relationship depends on network resistance, reactance, and operating condition. Excitation systems, capacitor banks, reactors, static var compensators, and inverter controls support voltage.

System operators schedule generation and reserves while respecting thermal limits, voltage limits, stability limits, ramp rates, minimum generation, and contingencies. Because electricity must be balanced continuously, energy adequacy alone does not guarantee operability.

2. Per-Unit Modeling

Power networks contain multiple voltage levels and equipment ratings. The per-unit system expresses quantities as fractions of selected base values:

xpu = \frac{xactual}{xbase}

For a balanced three-phase system, select a three-phase apparent-power base SB and a line-to-line voltage base VB. The corresponding bases are

IB = \frac{SB}{\sqrt{3}VB}
ZB = \frac{VB2}{SB}

When SB is in MVA and VB is in kV, IB is in kA and ZB is in ohms. Voltage bases on opposite sides of a transformer should follow its rated voltage ratio. Under consistent bases, the ideal transformer ratio disappears from the per-unit impedance model.

If a stated impedance must be converted between bases at the same network location,

Zpu,new=Zpu,old\left(\frac{SB,new}{SB,old}\right)\left(\frac{VB,old}{VB,new}\right)2

The formula applies to impedance, not directly to admittance, and the voltages must refer to the same side of any transformer.

Worked Example: Transmission-Line Per-Unit Reactance

A 230 kV, three-phase network uses a 100 MVA base. A line has reactance 52.9 Ω per phase.

ZB = \frac{(230\ kV)2}{100\ MVA}=529\ \Omega
Xpu=\frac{52.9}{529}=0.100\ pu

The base current is

IB=\frac{100\ MVA}{\sqrt{3}(230\ kV)}=0.251\ kA=251\ A

Thus the line reactance is 0.100 pu on the selected base.

3. Load-Flow Analysis

Load flow, or power flow, determines bus-voltage magnitudes and angles, branch power transfers, and losses under steady-state conditions. It is central to planning, dispatch, voltage assessment, and contingency analysis.

3.1 Bus classifications

Bus typeSpecified quantitiesUsually calculated
PQ busActive power P and reactive power QVoltage magnitude V and angle \delta
PV busActive power P and voltage magnitude VReactive power Q and angle \delta
Slack busVoltage magnitude V and angle \deltaActive and reactive power needed to balance the model

A PV bus can remain a PV bus only while the generator stays within its reactive-power limits. If a limit is reached, practical algorithms usually fix reactive power at that limit and treat the bus as PQ.

3.2 AC power-flow equations

For an n-bus network with bus-admittance element Yij=Gij+jBij, the net injected powers at bus i are

Pi=\sumj=1nViVj[Gij\cos(\deltai-\deltaj)+Bij\sin(\deltai-\deltaj)]
Qi=\sumj=1nViVj[Gij\sin(\deltai-\deltaj)-Bij\cos(\deltai-\deltaj)]

Positive injection denotes generation minus load. Because these equations are nonlinear, Newton–Raphson, fast-decoupled, or Gauss–Seidel methods are used. Newton–Raphson generally provides strong convergence near a feasible operating point, while its Jacobian also reveals sensitivity information.

The DC load-flow approximation assumes voltage magnitudes near 1 pu, small angular differences, negligible resistance relative to reactance, and negligible reactive-power effects. For a lossless line between buses 1 and 2,

P12\approx\frac{\delta1-\delta2}{X12}

where power and reactance are in per unit and angles are in radians. It is useful for active-power screening but cannot assess voltage magnitude, reactive power, or resistive loss accurately.

Worked Example: Approximate Line Transfer

A lossless line has X=0.20\ pu on a 100 MVA base and transmits 50 MW from bus 1 to bus 2. Under the DC approximation,

Ppu=\frac{50}{100}=0.50\ pu
\delta1-\delta2=PpuX=(0.50)(0.20)=0.10\ rad=5.73^\circ

The result is an approximation; an AC load flow is required if voltage or reactive-power constraints are important.

4. Faults, Protection, and Grounding

4.1 Power-system faults

Faults arise from insulation breakdown, lightning, contamination, vegetation, equipment failure, excavation, animals, or human error. Common fault types include three-phase, line-to-line, single-line-to-ground, and double-line-to-ground faults. The three-phase fault is balanced and often convenient for rating studies, but a single-line-to-ground fault is more common in many grounded systems.

For a bolted, balanced three-phase fault represented by a Thevenin voltage and impedance at the fault location,

If=\frac{Vth}{Zth+Zf}

where If is the symmetrical rms fault current, Vth is the prefault phase-to-neutral Thevenin voltage, Zth is the positive-sequence Thevenin impedance, and Zf is the per-phase fault impedance. For a bolted fault, Zf=0. Unsymmetrical faults require positive-, negative-, and zero-sequence networks. Breaker duties must also consider dc offset, system X/R ratio, making current, and the fault-clearing time specified by the applicable standard.

Worked Example: Three-Phase Fault Current

An 11 kV bus uses a 50 MVA base and has a Thevenin reactance of 0.10 pu. Assume a prefault voltage of 1.0 pu, negligible resistance, and a bolted three-phase fault.

IB=\frac{50\ MVA}{\sqrt{3}(11\ kV)}=2.624\ kA
If,pu=\frac{1.0}{0.10}=10.0\ pu
If=(10.0)(2.624)=26.24\ kA

The corresponding symmetrical fault level is \sqrt{3}(11\ kV)(26.24\ kA)\approx500\ MVA, consistent with 50/0.10=500\ MVA.

4.2 Protection principles

A protection system uses instrument transformers, sensors, relays, communication channels, trip circuits, and circuit breakers to detect and isolate abnormal conditions. Its principal requirements are:

  • selectivity: isolate only the affected zone where possible;
  • speed: reduce equipment damage and instability;
  • sensitivity: detect the lowest fault current within the protected zone;
  • reliability: operate when required and avoid unnecessary operation;
  • coordination: provide primary and backup protection with appropriate margins.

Overcurrent, differential, distance, underfrequency, undervoltage, and earth-fault elements serve different applications. In a radial feeder, the downstream protective device should normally clear a local fault before upstream backup protection. Distributed generation can alter fault magnitude and direction, requiring directional elements, revised settings, communication-assisted schemes, or adaptive protection.

4.3 Grounding and earthing

System grounding intentionally connects the source or transformer neutral to earth directly or through impedance. Solid grounding produces relatively high ground-fault current and supports rapid detection. Resistance grounding limits current and can reduce damage and arc-flash energy, but requires suitable ground-fault protection. Resonant grounding uses an inductive arc-suppression coil to compensate network capacitive ground-fault current.

Equipment grounding bonds exposed conductive parts to a low-impedance fault-current path. It is distinct from neutral grounding. Substation grounding grids must control touch and step voltages, not merely achieve a low measured ground resistance. Design depends on soil resistivity, fault current division, clearing time, conductor geometry, surface layers, and applicable safety standards.

5. Reliability and Resilience

Reliability concerns the continuity and quality of supply under expected conditions. Resilience emphasizes preparation for, survival during, and recovery from high-impact disturbances such as severe weather, wildfire, cyberattack, or widespread equipment failure.

For a system with NT customers, interruption event i affecting Ni customers for duration ri hours gives:

SAIFI=\frac{\sumi Ni}{NT}
SAIDI=\frac{\sumi Ni ri}{NT}
CAIDI=\frac{\sumi Ni ri}{\sumi Ni}=\frac{SAIDI}{SAIFI}

SAIFI has units interruptions per customer, SAIDI has hours per customer, and CAIDI has hours per customer interruption. Momentary interruptions may be excluded or reported separately according to the regulator's definitions.

Worked Example: Reliability Indices

A utility serves 500 customers. During the reporting period, one sustained outage interrupts 100 customers for 2 hours, and another interrupts 200 customers for 1.5 hours. Assume each affected customer experiences only the stated event.

Total customer interruptions are

100+200=300

Total customer-interruption duration is

(100)(2)+(200)(1.5)=200+300=500\ customer\cdot h

Therefore,

SAIFI=\frac{300}{500}=0.60\ interruptions/customer
SAIDI=\frac{500\ customer\cdot h}{500\ customers}=1.00\ h/customer
CAIDI=\frac{500\ customer\cdot h}{300\ customer\ interruptions}=1.667\ h/interruption

The first event alone contributes (100\times2)/500=0.40\ h/customer to SAIDI. Reliability can be improved through vegetation management, condition monitoring, feeder automation, sectionalizing, redundancy, preventive maintenance, spare equipment, microgrids, and faster restoration. Each measure should be evaluated against cost and customer value of lost load.

6. Quantitative Comparison of Generation Technologies

Technology choice depends on resource availability, system needs, financing, fuel exposure, construction time, environmental constraints, and public acceptance. The following ranges are representative screening values rather than project quotations. Costs are approximate recent US-dollar ranges before project-specific financing, taxes, subsidies, and grid-integration costs. Lifecycle emissions include supply-chain and construction effects but vary by methodology.

TechnologyConversion efficiencyCapacity factorCapital cost ($/kW)Approx. LCOE ($/MWh)Lifecycle emissions (g CO₂-e/kWh)
Coal steam plant33–45%40–80%2,000–6,50070–170800–1,000
Natural-gas combined cycle50–64%30–85%900–2,00045–110350–550
Nuclear fission32–37% thermal80–95%6,000–12,000140–2205–20
Reservoir hydropower85–95% turbine-generator30–70%2,000–7,00040–1201–100+
Onshore windNot a thermal metric30–55%1,200–2,50030–807–20
Utility solar PV18–24% module efficiency12–30%700–1,50025–7020–60
Geothermal power10–20% thermal70–95%2,500–6,50055–11010–50

Capacity factor is

CF=\frac{Eactual}{PratedT}

where Eactual is generated energy, Prated is rated power, and T is the period duration. A low capacity factor does not necessarily imply poor equipment efficiency; solar and wind output is limited mainly by resource availability.

The levelized cost of electricity is commonly estimated as

LCOE=\frac{\sumt=0n\frac{Ct}{(1+r)t}}{\sumt=0n\frac{Et}{(1+r)t}}

where Ct is cost in year t, Et is net electricity supplied, r is the real discount rate when real costs are used, and n is project life. Costs should include construction, operation, fuel, major replacements, decommissioning, and other items appropriate to the study boundary. LCOE does not by itself measure dispatchability, reliability contribution, network cost, or time-varying market value.

6.1 Conventional and low-carbon firm generation

Coal and gas plants can be dispatchable, but their economics depend strongly on fuel and carbon prices. Gas combined-cycle plants are efficient and flexible, while methane leakage affects their lifecycle climate performance. Carbon capture can reduce stack emissions but consumes energy, raises cost, and requires transport and secure storage.

Nuclear power provides high-capacity-factor, low-operational-carbon generation. Challenges include high initial capital, long construction periods, radioactive-waste governance, cooling requirements, and low-probability but high-consequence risk management.

Hydropower can provide rapid response, inertia, storage, and black-start capability. Reservoir projects may alter river ecology, sediment transport, land use, and communities. Reservoir methane emissions vary widely, especially with climate and biomass conditions.

6.2 Variable renewable generation

Wind and solar have no fuel cost and low operational emissions. Their output is weather-dependent, so high penetrations may require transmission expansion, geographic diversity, forecasting, flexible demand, storage, reserve, and improved inverter controls. Curtailment can be economically rational when additional energy has low value or network limits bind.

Renewable equipment also has lifecycle impacts. Mining, manufacturing, land use, recycling, and disposal must be included. Responsible sourcing and producer-recovery programs can reduce material and social risks.

7. Energy Storage and Flexibility

Storage absorbs energy at one time and supplies it later. It can provide energy shifting, frequency response, reserve, voltage support, congestion relief, black start, and backup power. However, one device cannot necessarily provide all services simultaneously because power, energy, state-of-charge, thermal, and cycle-life constraints interact.

Round-trip efficiency is

\etaRT=\frac{Eout}{Ein}

where both energies are measured at consistent electrical boundaries over a complete charge–discharge cycle. Auxiliary consumption and self-discharge should be included when material.

Storage technologyRound-trip efficiencyTypical discharge durationIndicative lifePrincipal characteristics
Lithium-ion battery85–95%0.5–8 h2,500–8,000 cyclesFast response; thermal management and mineral sourcing required
Flow battery65–85%4–12+ h10,000+ cycles possiblePower and energy can be sized relatively independently
Pumped hydro70–85%4–24+ h30–80 yearsMature and large-scale; geographically constrained
Compressed-air storage40–70%4–24+ h20–40 yearsSite and thermal-process dependent
Hydrogen, electricity-to-electricity25–45%Days to seasonalSystem dependentLow round-trip efficiency but potentially long-duration storage

Installed lithium-ion system cost may be roughly $150–500/kWh, but duration, safety systems, interconnection, cycle specification, and market conditions strongly affect cost. Comparing storage solely by $/kWh is misleading: power-related cost in $/kW, energy-related cost in $/kWh, efficiency, degradation, lifetime throughput, and residual value all matter.

A battery with nominal energy EN, allowable depth of discharge DOD, and discharge efficiency \etad can deliver approximately

Edelivered=EN(DOD)\etad

provided temperature, aging, reserve requirements, and power limits are respected.

8. Illustrative Case: A Resilient University Microgrid

Background

A fictional university campus consumes 24 GWh annually and has a 5 MW peak demand. Critical laboratories, communications, and emergency services require 1.5 MW during an upstream outage. The existing 11 kV radial connection experiences weather-related interruptions.

Problem

The university seeks lower operational emissions and improved resilience without assuming that annual renewable energy automatically guarantees supply at every hour.

Analysis

Engineers consider 4 MW of solar PV with a 20% capacity factor and 3 MW of wind with a 35% capacity factor. Estimated annual gross generation is

EPV=(4\ MW)(8760\ h)(0.20)=7.008\ GWh
Ewind=(3\ MW)(8760\ h)(0.35)=9.198\ GWh

Combined gross renewable production is 16.206 GWh, equivalent to 67.5% of annual campus consumption before curtailment and losses. This percentage does not mean that renewables serve 67.5% of demand in every hour.

A 2 MW/8 MWh battery is proposed. If operating limits make 80% of nominal energy available at the AC delivery boundary, usable energy is 6.4 MWh. At a constant 1.5 MW critical load, the energy-limited support duration is

t=\frac{6.4\ MWh}{1.5\ MW}=4.27\ h

The 2 MW inverter rating exceeds the 1.5 MW critical load, so energy—not power—is limiting in this simplified calculation. Actual design must reserve margin for battery aging, temperature, motor starting, forecast error, and black-start sequencing.

A load-flow study checks 11 kV feeder voltage, reverse power, transformer loading, and reactive-power requirements. A fault study determines whether existing switchgear can interrupt the revised fault current. Because inverter-based resources may contribute limited and controlled fault current, conventional overcurrent protection alone may not detect every islanded fault reliably.

Approach and Solution

The selected design combines renewable generation, the battery, controllable building loads, and an islanding controller. Directional relays and transfer-trip communication are installed, and critical feeders are separated from noncritical loads. The grounding arrangement is explicitly reviewed for both grid-connected and islanded operation. Operating rules maintain a minimum battery state of charge when severe weather is forecast.

Outcome

The project materially reduces purchased annual energy and can support critical demand for approximately 4.27 hours under the stated assumptions. It does not provide indefinite autonomy. A longer outage requires load shedding, renewable availability, or dispatchable backup. The case demonstrates that energy, power, protection, grounding, and temporal coincidence must all be considered.

Learning Points

  • Annual energy balance is not the same as hourly adequacy.
  • Storage has separate power and energy limits.
  • Distributed generation can change voltage, reverse flow, and protection behavior.
  • Resilience requires operational procedures as well as installed equipment.

9. Governance, Regulation, and Contemporary Developments

Power systems are regulated because failures can endanger the public and disrupt essential services. Utilities and operators must comply with grid codes, interconnection rules, reliability standards, environmental permits, worker-safety requirements, and consumer-protection obligations. Transparent planning should consider affordability and energy justice: network modernization costs and reliability benefits may not be distributed equally.

Cybersecurity has become a core engineering responsibility. Digital relays, smart meters, distributed-resource aggregators, and remote controls expand the attack surface. Good practice includes network segmentation, authenticated access, secure updates, logging, backup control modes, incident response, and supply-chain assurance.

Artificial intelligence can improve load forecasting, renewable forecasting, equipment diagnostics, outage prediction, and restoration prioritization. AI outputs should not bypass physical constraints or accountable human decision-making. Training-data bias, model drift, explainability, cybersecurity, and fail-safe operation require governance.

Contemporary developments include grid-forming inverters, virtual power plants, dynamic line ratings, wide-area measurement, vehicle-to-grid operation, long-duration storage, advanced conductors, and flexible demand. Their value depends on validated models, interoperability, communications, market design, and protection practices.

10. Engineering Best Practices and Limitations

Sound power-system studies should:

  1. document base quantities, sign conventions, and data sources;
  2. validate equipment ratings and network topology;
  3. test normal operation and credible contingencies;
  4. include reactive-power and voltage constraints, not only active energy;
  5. coordinate protection after generation or topology changes;
  6. distinguish expected energy from firm capacity and resilience;
  7. state economic year, currency, discount rate, and study boundary;
  8. perform sensitivity analysis for fuel, resource, demand, cost, and policy uncertainty;
  9. assess lifecycle impacts and end-of-life obligations;
  10. verify model results against measurements where possible.

All models are abstractions. Per-unit and steady-state load-flow models do not by themselves represent electromagnetic transients, protection timing, harmonics, small-signal stability, or cascading failure. Likewise, LCOE and average emissions cannot fully describe temporal system value. Professional decisions require several complementary studies.

Chapter Summary

Electric power systems integrate generation, transmission, distribution, loads, storage, protection, control, and communications. Balanced three-phase equations relate active, reactive, and apparent power, while the per-unit system simplifies networks containing multiple ratings and voltage levels. Load-flow analysis determines steady-state voltage and power transfer; full AC analysis is required when voltage, reactive power, and losses matter.

Fault analysis establishes equipment and protection duties. Selective, sensitive, rapid, and reliable protection must be coordinated with grounding and operating configuration. Reliability indices such as SAIFI, SAIDI, and CAIDI quantify interruption performance, while resilience addresses severe disturbances and recovery.

Generation and storage technologies must be compared using efficiency, capacity factor, cost, flexibility, lifecycle emissions, environmental effects, and reliability contribution. Renewable energy can reduce emissions and fuel exposure, but annual production does not ensure continuous adequacy. Storage, flexible demand, transmission, dispatchable resources, and sound controls help integrate variable resources. Sustainable power-system design therefore combines physical analysis, economics, environmental assessment, safety, governance, and social responsibility.

Key Terms

Active power: The average rate at which electrical energy performs useful work, measured in watts.

Apparent power: The product of rms voltage and current, measured in volt-amperes.

CAIDI: Average duration of a sustained interruption experienced per customer interruption.

Capacity factor: Actual energy production divided by production at rated power over the same period.

Distributed energy resource: A smaller generator, storage system, or controllable load connected within a distribution system.

Fault level: The prospective short-circuit power or current at a network location.

Grounding: Intentional electrical connection of a system point or exposed conductive equipment to earth or a grounding network.

LCOE: Discounted lifetime cost per unit of discounted electricity production.

Load flow: Steady-state calculation of bus voltages, branch flows, and network losses.

Per unit: A normalized quantity expressed relative to a selected base value.

Protection coordination: Selection of protective-device characteristics so the device nearest a fault operates first where practicable.

Reactive power: Oscillatory power associated with electric and magnetic field energy, measured in vars.

Resilience: Ability to prepare for, withstand, recover from, and adapt to disruptive events.

Round-trip efficiency: Energy recovered from storage divided by energy supplied to it over a complete cycle.

SAIDI: Average sustained interruption duration per customer during a reporting period.

SAIFI: Average number of sustained interruptions per customer during a reporting period.

Slack bus: Reference load-flow bus that balances modeled active and reactive power mismatch.

Thevenin equivalent: A voltage source and series impedance representing a linear network at specified terminals.

Variable renewable energy: Renewable generation whose available output varies with weather or natural conditions.

Review Questions

Short Answer Questions

  1. Why does increasing transmission voltage reduce conductor losses for a fixed power transfer?
  2. Distinguish active, reactive, and apparent power.
  3. What quantities are specified at PQ, PV, and slack buses?
  4. State the principal requirements of a protection system.
  5. Distinguish system grounding from equipment grounding.

Long Answer Questions

  1. Explain the functions and interactions of generation, transmission, distribution, storage, loads, and system operation.
  2. Derive the three-phase current and impedance base equations from selected power and voltage bases.
  3. Explain the AC load-flow equations, their nonlinear nature, and the limitations of the DC approximation.
  4. Compare coal, gas, nuclear, hydropower, wind, solar PV, and geothermal generation using technical, economic, and environmental criteria.
  5. Discuss how distributed energy resources affect voltage regulation, fault behavior, protection coordination, and cybersecurity.

Analytical / Application Questions

  1. A 132 kV network uses a 100 MVA base. Calculate base current, base impedance, and the per-unit value of a 34.85 Ω line reactance.
  2. A utility serves 2,000 customers. An outage interrupts 300 customers for 1 hour, and a second outage interrupts 500 customers for 2 hours. Calculate SAIFI, SAIDI, and CAIDI.
  3. Design a preliminary storage specification for a 3 MW critical load requiring four hours of support. State assumptions for depth of discharge, efficiency, reserve margin, and inverter power.

Multiple Choice Questions with Answers

Question 1

On a 100 MVA, 230 kV three-phase base, what is the base impedance?

A. 230 Ω

B. 398 Ω

C. 529 Ω

D. 690 Ω

Correct Answer: C. 529 Ω

Question 2

Under the DC load-flow approximation, a line with X=0.20\ pu transfers P=0.50\ pu. What is the approximate bus-angle difference?

A. 0.025 rad

B. 0.10 rad

C. 0.40 rad

D. 2.50 rad

Correct Answer: B. 0.10 rad

Question 3

A sustained outage interrupts 100 of 500 customers for 2 hours. What is this event's contribution to SAIDI?

A. 0.20 h/customer

B. 0.40 h/customer

C. 1.00 h/customer

D. 2.00 h/customer

Correct Answer: B. 0.40 h/customer

Question 4

A system has SAIDI of 1.00 h/customer and SAIFI of 0.60 interruptions/customer. What is CAIDI?

A. 0.60 h/interruption

B. 1.00 h/interruption

C. 1.67 h/interruption

D. 2.50 h/interruption

Correct Answer: C. 1.67 h/interruption

Question 5

An 11 kV system has a 50 MVA base, prefault voltage of 1.0 pu, and Thevenin reactance of 0.10 pu. Neglecting resistance and fault impedance, what is the symmetrical three-phase fault current?

A. 2.62 kA

B. 5.25 kA

C. 10.0 kA

D. 26.2 kA

Correct Answer: D. 26.2 kA

Question 6

A battery has 8 MWh nominal energy and 80% is available at its AC delivery boundary. For how long can it supply a constant 1.5 MW load, neglecting additional reserve requirements?

A. 2.67 h

B. 4.27 h

C. 5.33 h

D. 6.40 h

Correct Answer: B. 4.27 h

Question 7

Which load-flow bus has active power and voltage magnitude specified under normal operation?

A. PQ bus

B. PV bus

C. Slack bus

D. Isolated bus

Correct Answer: B. PV bus

Question 8

A storage system receives 100 MWh and later supplies 90 MWh at the same measurement boundary. What is its round-trip efficiency?

A. 10%

B. 81%

C. 90%

D. 111%

Correct Answer: C. 90%

Question 9

Which statement best describes levelized cost of electricity?

A. It directly measures a plant's contribution to system reliability.

B. It is discounted lifetime cost divided by discounted lifetime electricity production.

C. It equals capital cost divided by rated power.

D. It includes only fuel and maintenance expenses.

Correct Answer: B. It is discounted lifetime cost divided by discounted lifetime electricity production.

Question 10

In a coordinated radial feeder protection scheme, which device should normally clear a local downstream fault first?

A. The nearest downstream protective device

B. The generator circuit breaker in every case

C. The most remote upstream relay

D. All protective devices simultaneously

Correct Answer: A. The nearest downstream protective device

Fundamentals of Electrical Engineering
Chapter 13 of 15