Fundamentals of Accounting & Finance

Chapter 9
Budgeting, Planning and Performance Management

Bachelors Program in Accounting and Finance
Fundamentals of Accounting & Finance   •   Bachelor

Budgeting, Planning and Performance Management

Introduction

Budgeting translates strategy into coordinated operational and financial plans. It specifies expected revenues, resource requirements, cash flows and investments for a defined period. Performance management then compares outcomes with those plans, explains deviations and supports corrective action.

A budget is not merely a spending restriction. Properly designed, it performs four related functions: planning, coordination, resource allocation and control. It also establishes accountability. However, unrealistic targets, poorly selected performance indicators or excessive pressure may encourage dysfunctional behaviour. Effective systems therefore combine financial discipline with operational, customer, employee and strategic measures.

Learning Objectives

After studying this chapter, students should be able to:

  1. Explain the purposes, behavioural implications and limitations of budgeting.
  2. Prepare sales, production, materials, labour, overhead and cash budgets.
  3. Explain the integration of operating, capital and financial budgets.
  4. Apply flexible-budget and standard-cost variance analysis.
  5. Evaluate capital proposals using net present value.
  6. distinguish cost, revenue, profit and investment responsibility centres.
  7. Design relevant key performance indicators.
  8. Integrate financial and non-financial measures through a balanced scorecard.

1. Budgeting within the Planning and Control Cycle

Strategic planning identifies long-term objectives and competitive priorities. Tactical planning converts strategy into medium-term initiatives, while operational planning specifies short-term activities and resource requirements. Budgets usually cover one year, subdivided into months or quarters, although rolling budgets continually extend the planning horizon.

The management control cycle has four broad stages:

  1. Establish objectives and assumptions.
  2. Prepare coordinated plans and budgets.
  3. Execute operations and measure results.
  4. Compare results with relevant benchmarks, investigate deviations and respond.

Budgetary control includes both feedforward and feedback control. Feedforward control anticipates problems before execution—for example, forecasting a cash deficit and arranging finance. Feedback control compares actual outcomes with plans after activities have occurred.

1.1 Budgeting approaches

ApproachMain characteristicAppropriate use or limitation
Incremental budgetingAdjusts the previous budgetEfficient but may preserve waste
Zero-based budgetingRequires activities to be justified from zeroUseful for discretionary costs but resource-intensive
Activity-based budgetingBudgets activities and their cost driversConnects resource consumption to operational demand
Participative budgetingInvolves managers responsible for implementationImproves information and commitment but may create budgetary slack
Rolling budgetingRegularly adds a new future periodMaintains a current planning horizon
Beyond-budgeting practicesEmphasise adaptive targets and decentralised controlIncrease responsiveness but require strong governance and data systems

A budget may be imposed, negotiated or participative. Participation can improve local information and commitment. Nevertheless, managers may deliberately understate revenues or overstate costs to create budgetary slack. Senior management should challenge assumptions without turning the process into coercive target setting.

2. The Master Budget

The master budget is an integrated set of operating, capital and financial budgets. For a manufacturing organisation, the sales budget normally initiates the operating sequence. Forecast sales determine required production after allowing for finished-goods inventory. Production then drives direct-material, direct-labour and manufacturing-overhead budgets.

Sales also affect cash collections and budgeted revenue directly. Resource budgets determine production costs, inventory values, cash payments and cost of goods sold. Capital expenditure is driven by strategy, replacement needs, regulation and capacity requirements rather than by sales alone.

Correct information flows within a manufacturing master budget Strategy and assumptions Sales budget Selling and admin. Capital expenditurebudget Production budget Direct materials Direct labour Manufacturing overhead Inventory and costof goods sold Cash budget Budgeted incomestatement Budgeted statementof financial position units required capacity gap revenue collections payments investment cash flows depreciation
Correct information flows within a manufacturing master budget
Figure: Correct information flows within a manufacturing master budget

Figure: Integrated information flows in a manufacturing master budget. Production, not sales directly, drives materials, labour and manufacturing overhead; sales directly drives revenue and customer collections.

The final outputs commonly include the budgeted income statement, cash budget and budgeted statement of financial position. Because the schedules are interdependent, a change in sales volume, inventory policy or payment timing may affect multiple statements.

3. Preparing Operating Budgets

3.1 Sales budget

For a single product, budgeted sales revenue is:

Budgeted sales revenuet = Qt × Pt

where Qt is forecast sales volume in period t and Pt is the expected selling price per unit. Quantities must be expressed in units and prices in currency per unit.

Forecasts should consider market conditions, capacity, seasonality, confirmed orders, competitors and price elasticity. A forecast is an estimate; a budget is an authorised plan based partly on that estimate.

3.2 Production budget

For a manufacturer:

Production unitst = Sales unitst + Desired ending finished goodst − Beginning finished goodst

This inventory-flow identity assumes quantities are measured in the same physical unit. It does not apply directly to service organisations that have no storable output.

Suppose Orion Manufacturing expects first-quarter sales of 10,000 units and second-quarter sales of 12,000 units. Desired ending finished goods equal 20% of the following quarter’s sales, and beginning inventory is 2,000 units.

Q1 production = 10,000 + (20% × 12,000) − 2,000 = 10,400 units

3.3 Direct-materials purchases budget

Material purchases = Material required for production + Desired ending material inventory − Beginning material inventory

If each unit requires 3 kg, first-quarter production requires 31,200 kg. Assume second-quarter production is 12,400 units, desired material inventory is 10% of the following quarter’s production needs, and beginning materials inventory is 3,120 kg. Desired ending inventory is therefore 10% × 12,400 × 3 = 3,720 kg.

Purchases = 31,200 + 3,720 − 3,120 = 31,800 kg

At $4 per kg, budgeted purchases cost 31,800 × $4 = $127,200. Purchase cost is not necessarily the same as the period’s cash payment because suppliers may offer credit.

3.4 Direct-labour and overhead budgets

Direct-labour cost = Production units × Standard hours per unit × Wage rate per hour

If each unit requires 0.5 direct-labour hours at $20 per hour:

10,400 × 0.5 × $20 = $104,000

Manufacturing overhead should be separated into variable and fixed components:

Total overhead = Variable rate × Activity level + Fixed overhead

If variable overhead is $6 per direct-labour hour and quarterly fixed overhead is $40,000:

Overhead = $6 × 5,200 hours + $40,000 = $71,200

If fixed overhead contains $8,000 of depreciation, cash overhead is $63,200. Depreciation affects profit but is not a current-period cash payment.

4. Cash Budgeting and Financing Needs

A profitable organisation may still fail if it cannot meet obligations when due. The cash budget focuses on timing rather than accrual recognition.

Ending cash before financing = Beginning cash + Cash receipts − Cash disbursements

If the result falls below the minimum required balance, borrowing or another financing source is included:

Financing required = max(0, Minimum cash − Cash before financing)

This simplified formula assumes financing can be obtained immediately and excludes interest unless it is separately budgeted.

Worked cash budget

Orion expects first-quarter sales revenue of $500,000. It collects 60% of current-quarter sales during the quarter and expects to collect $180,000 from opening receivables. Cash collections are therefore:

$180,000 + (60% × $500,000) = $480,000
Cash budget itemAmount ($)
Beginning cash60,000
Cash collections480,000
Cash available540,000
Materials payments118,600
Direct labour104,000
Cash manufacturing overhead63,200
Cash selling and administration65,000
Capital expenditure90,000
Tax payment20,000
Total disbursements460,800
Ending cash before financing79,200

The minimum cash requirement is $75,000, so no borrowing is required. The $118,600 materials payment comprises $55,000 of opening payables plus 50% of current purchases of $127,200.

Cash budgets should include realistic collection delays, supplier terms, payroll dates, taxes, dividends, interest and capital expenditure. Scenario and sensitivity analysis are especially important where demand or collection patterns are uncertain.

5. Capital Budgets

Capital budgeting evaluates long-term investments such as equipment, software, buildings and sustainability projects. Relevant cash flows are incremental after-tax cash flows. Sunk costs are excluded, while opportunity costs, working capital and disposal proceeds are included.

For a project with an initial outflow and future cash flows, net present value is:

NPV = −I0 + ∑t=1n CFt ÷ (1 + r)t

where I0 is the initial cash investment, CFt is incremental after-tax cash flow in period t, r is the risk-appropriate periodic discount rate, and n is the project life. Cash-flow periods and the discount-rate period must be consistent. A project creates financial value if NPV is positive, assuming forecasts and the discount rate are valid.

Worked capital-investment decision

A machine costs $200,000 and requires $10,000 of working capital immediately. It produces annual after-tax cash inflows of $65,000 for four years. At the end of year 4, it has a $20,000 after-tax disposal value and the working capital is recovered. The discount rate is 10%.

NPV = −$210,000 + $65,000 × [1 − (1.10)−4] ÷ 0.10 + $30,000 ÷ (1.10)4

The four-year annuity factor is approximately 3.1699. Thus:

NPV ≈ −$210,000 + $206,041 + $20,490 = $16,531

The project is financially acceptable because its NPV is positive. Management should still assess strategic fit, implementation risk, environmental effects and forecast uncertainty.

6. Flexible Budgets and Performance Analysis

A static or planning budget is prepared for one planned activity level. Comparing actual costs at 11,000 units with a budget based on 10,000 units confuses volume effects with cost control. A flexible budget recalculates expected revenue and variable costs at actual activity while retaining budgeted prices, input standards and fixed costs.

For a cost with variable rate v, actual activity x and budgeted fixed cost F:

Flexible-budget cost = v × x + F

This linear cost function is valid only within the relevant range in which the variable rate and fixed-cost total remain approximately constant.

6.1 Profit reconciliation

Orion planned sales of 10,000 units. The budgeted selling price is $50, variable cost is $27.50 per unit and fixed costs are $85,000.

Planning-budget profit = 10,000 × ($50 − $27.50) − $85,000 = $140,000

Actual volume was 11,000 units, so flexible-budget profit is:

11,000 × ($50 − $27.50) − $85,000 = $162,500

Actual revenue was $539,000 and actual costs were as follows:

ItemFlexible budget ($)Actual ($)Effect on profit
Revenue550,000539,00011,000 U
Direct materials132,000136,4004,400 U
Direct labour110,000115,5005,500 U
Variable manufacturing overhead33,00034,1001,100 U
Variable selling cost27,50028,6001,100 U
Fixed costs85,00087,0002,000 U
Operating profit162,500137,40025,100 U

The favourable activity variance is $162,500 − $140,000 = $22,500 F. The flexible-budget performance variance is $25,100 U. Consequently, actual profit is $2,600 below the original plan:

$22,500 F − $25,100 U = $2,600 U

This decomposition shows that higher volume helped profit, but lower selling prices and higher costs more than offset that benefit.

7. Standard-Cost Variances

Standards specify expected input quantity and price for a defined output. Under the following convention, a positive cost variance is unfavourable and a negative cost variance is favourable.

7.1 Direct-material variances

Material price variance = AQ × (AP − SP)
Material usage variance = SP × (AQ − SQ)

Here AQ is actual input quantity used, AP is actual price per input unit, SP is standard price per input unit, and SQ is the standard quantity allowed for actual output. If the price variance is calculated at purchase rather than usage, AQ must represent quantity purchased.

For 11,000 units, standard material usage is 11,000 × 3 = 33,000 kg. Actual usage was 34,100 kg at the standard price of $4 per kg.

Usage variance = $4 × (34,100 − 33,000) = $4,400 U

7.2 Direct-labour variances

Labour rate variance = AH × (AR − SR)
Labour efficiency variance = SR × (AH − SH)

Here AH and SH are actual and standard hours, while AR and SR are actual and standard hourly wage rates. Orion used 5,500 hours at $21 per hour. The standard is 0.5 hour per unit at $20 per hour, so standard hours for 11,000 units are 5,500.

The rate variance is 5,500 × ($21 − $20) = $5,500 U, while the efficiency variance is zero.

Variances identify where investigation may be useful; they do not establish causation. A materials-usage variance may result from poor-quality purchases, machine problems, employee training or an unrealistic standard. Managers should investigate material, recurring and controllable variances rather than automatically penalising employees.

8. Responsibility Accounting

Responsibility accounting assigns performance measures to organisational units and managers with authority over relevant decisions.

Responsibility centreManager primarily accountable forTypical measures
Cost centreCosts and operational efficiencyCost per unit, quality, cycle time
Revenue centreRevenue generationSales, market share, customer acquisition
Profit centreRevenue and costsContribution margin, operating profit
Investment centreProfit and invested assetsReturn on investment, residual income

The controllability principle holds that managers should be evaluated mainly on items they can significantly influence. This does not mean uncontrollable information should be ignored; it should be reported separately or interpreted appropriately.

8.1 Return on investment and residual income

ROI = Operating profit ÷ Average operating assets

ROI is dimensionless and normally expressed as a percentage. It can be decomposed as:

ROI = (Operating profit ÷ Sales) × (Sales ÷ Average operating assets)

The first component is operating margin; the second is asset turnover. Managers evaluated solely on ROI may reject a positive-NPV project if it lowers their division’s current average ROI.

Residual income = Operating profit − (Required rate × Average operating assets)

Residual income is measured in currency and encourages acceptance of investments earning more than the required rate. Because it is an absolute amount, comparisons across differently sized divisions require care.

9. Key Performance Indicators and the Balanced Scorecard

A key performance indicator is a measure selected because it represents progress toward an important objective. A strong KPI has a clear owner, definition, data source, reporting frequency, target and intended managerial response.

Measures may be:

  • financial or non-financial;
  • leading or lagging;
  • internal or external;
  • quantitative or qualitative.

Financial measures are important but predominantly lagging. A balanced scorecard links strategy to measures across four perspectives.

PerspectiveCentral questionExample objectives and measures
FinancialHow do owners view performance?Profitability, cash conversion, ROI
CustomerHow do target customers view the organisation?Retention, satisfaction, delivery reliability
Internal processWhich processes must excel?Defect rate, throughput time, forecast accuracy
Learning and growthCan capabilities improve?Skills, engagement, system availability, innovation

The scorecard is based on hypothesised cause-and-effect relationships. For example, employee training may improve process quality, which may increase customer retention and eventually financial performance. These relationships should be tested rather than assumed.

Poor KPI design can cause gaming. A call centre measured only by call duration may terminate calls quickly without solving customer problems. Balanced measures could combine response time, first-contact resolution, customer satisfaction and cost per resolved enquiry.

10. Illustrative Integrated Case: Meridian Medical Devices

Background and problem

Meridian Medical Devices is a fictional manufacturer experiencing rapid demand growth. Its annual static budget showed strong profit, but recurring cash shortages, late deliveries and rising material waste caused concern. Production managers were evaluated only on cost variances, while sales personnel were rewarded solely for revenue.

Analysis

The company’s review identified four weaknesses:

  1. Sales forecasts were not translated into production and resource requirements.
  2. Customer credit terms were omitted from cash planning.
  3. Static-budget comparisons treated higher activity as poor cost control.
  4. Departmental measures encouraged sales discounts, excessive inventories and delayed maintenance.

Approach and solution

Meridian introduced an integrated master budget. The sales budget fed the production budget; production drove materials, labour and overhead. Collection and payment schedules were incorporated into a rolling 13-week cash forecast. Capital projects were evaluated using after-tax incremental cash flows and NPV.

Monthly reports separated activity variances from flexible-budget performance variances. Responsibility reports distinguished controllable costs from allocated corporate costs. Management also adopted a balanced scorecard:

  • Financial: operating cash flow and residual income.
  • Customer: on-time delivery and complaint resolution.
  • Internal process: material yield, defect rate and manufacturing cycle time.
  • Learning and growth: technical certification and preventive-maintenance completion.

Outcome

The revised forecast showed that profitable growth would create a temporary financing need because customers paid later than suppliers. Meridian arranged a short-term credit facility before the shortage occurred. A proposed automated testing system had a positive NPV and was expected to reduce defects. Performance reviews no longer treated every adverse variance as employee failure; managers investigated causes and interdependencies.

Learning points

Integrated budgeting exposes operational and cash consequences that an income statement alone cannot reveal. Flexible budgets improve fairness, while balanced measures reduce dependence on short-term financial outcomes. However, success still depends on reliable data, ethical conduct and managerial judgement.

11. Governance, Ethics and Contemporary Practice

Budget systems affect employee rewards, careers and resource access. Ethical risks include manipulating forecasts, delaying necessary expenditure, accelerating sales, concealing adverse information and pressuring staff to meet impossible targets. Governance should include documented assumptions, independent review, approval limits, audit trails and confidential reporting channels.

Technology enables continuous forecasting, real-time dashboards and automated consolidation. Predictive analytics and AI can improve demand, collection and cash-flow forecasts, but model outputs remain sensitive to biased data, structural changes and hidden assumptions. Human oversight is essential. Organisations should document models, restrict data access, test forecast accuracy and monitor whether automated recommendations disadvantage particular stakeholders.

Contemporary practice increasingly uses rolling forecasts, driver-based planning and scenario analysis. These techniques improve adaptability but do not eliminate accountability. Best practice combines an approved baseline, updated forecasts, transparent variance explanations and strategy-linked performance measures.

Chapter Summary

Budgeting converts organisational strategy into coordinated operating, cash and capital plans. In a manufacturing master budget, sales requirements determine production after inventory adjustments, and production drives materials, labour and overhead. Sales also directly determines budgeted revenue and customer collections. Cash budgets reveal timing-related financing needs, while capital budgets assess long-term investments using incremental cash flows and discounted-value techniques.

Flexible budgets distinguish the effects of activity changes from operating performance. Standard-cost variances provide more detailed information on prices, quantities, wage rates and efficiency, but require causal investigation. Responsibility accounting aligns measures with managerial authority through cost, revenue, profit and investment centres. KPIs and balanced scorecards supplement financial outcomes with customer, process and organisational-capability measures. Ethical governance, reliable data and professional judgement are essential throughout the planning and performance-management process.

Key Terms

Activity variance: The difference between a flexible budget at actual activity and the original planning budget.

Balanced scorecard: A framework integrating financial, customer, internal-process, and learning-and-growth measures.

Budgetary slack: Deliberate understatement of revenue or overstatement of resource requirements.

Capital budget: A plan and evaluation of long-term investment expenditure.

Cash budget: A schedule of expected cash receipts, payments and financing.

Controllability principle: The principle that managers should primarily be assessed on items they can significantly influence.

Cost centre: A responsibility centre whose manager is primarily accountable for costs.

Driver-based planning: Budgeting based on operational variables that cause revenues, costs or cash flows.

Flexible budget: A budget recalculated for the actual level of activity.

Investment centre: A responsibility centre accountable for profit and invested assets.

Key performance indicator: A strategically important measure used to monitor progress toward an objective.

Master budget: The integrated collection of operating, capital and financial budgets.

Net present value: Present value of future incremental cash flows less the initial investment.

Participative budgeting: A budgeting process involving managers responsible for implementing the budget.

Profit centre: A responsibility centre accountable for both revenue and costs.

Residual income: Operating profit less a required return on operating assets.

Responsibility accounting: A system linking performance information to areas of managerial authority.

Rolling budget: A budget continuously extended by adding a new future period.

Standard cost: A predetermined cost based on expected input prices and quantities.

Review Questions

Short Answer Questions

  1. Distinguish a sales forecast from a sales budget.
  2. Why does the production budget drive direct-material and direct-labour budgets?
  3. What is the difference between a static budget and a flexible budget?
  4. State the controllability principle.
  5. Why should financial KPIs be combined with non-financial measures?

Long Answer Questions

  1. Explain how operating, cash, capital and financial budgets are integrated within a master budget.
  2. Evaluate the advantages and behavioural risks of participative budgeting.
  3. Explain how flexible-budget analysis improves the interpretation of actual performance.
  4. Compare cost, revenue, profit and investment responsibility centres.
  5. Critically evaluate the four balanced-scorecard perspectives and their proposed causal relationships.

Analytical / Application Questions

  1. A company expects sales of 20,000 units in April and 24,000 in May. Ending finished goods must equal 25% of the following month’s sales. April begins with 5,000 units. Calculate April production and explain how a change in inventory policy would affect cash requirements.
  2. Actual production is 9,000 units. Each unit should use 2.5 kg of material at $6 per kg. Actual usage is 23,400 kg at $6.20 per kg. Calculate the material price and usage variances and suggest possible operational causes.
  3. Design a balanced scorecard for an online retailer, including one objective and one KPI for each perspective. Explain the strategic connections among the measures.

Multiple Choice Questions with Answers

Question 1

A manufacturer expects sales of 8,000 units this month and 10,000 next month. Desired ending finished goods equal 20% of next month's sales, and beginning finished goods are 1,600 units. What is budgeted production?

A. 8,000 units

B. 8,400 units

C. 9,600 units

D. 10,000 units

Correct Answer: B. 8,400 units

Question 2

Production requires 10,000 kg of material. Desired ending material inventory is 1,200 kg and beginning inventory is 1,000 kg. How much material should be purchased?

A. 9,800 kg

B. 10,000 kg

C. 10,200 kg

D. 12,200 kg

Correct Answer: C. 10,200 kg

Question 3

Which budget directly establishes the units that drive direct-material and direct-labour requirements in a manufacturing organisation?

A. Sales budget

B. Production budget

C. Cash budget

D. Capital expenditure budget

Correct Answer: B. Production budget

Question 4

A cost has a variable rate of $6 per unit and fixed costs of $30,000. What is its flexible-budget amount at an actual activity of 8,000 units, assuming operations remain within the relevant range?

A. $48,000

B. $72,000

C. $78,000

D. $180,000

Correct Answer: C. $78,000

Question 5

Standard material quantity for actual output is 4,000 kg at $5 per kg. Actual usage is 4,200 kg. What is the material usage variance?

A. $1,000 favourable

B. $1,000 unfavourable

C. $21,000 unfavourable

D. $20,000 favourable

Correct Answer: B. $1,000 unfavourable

Question 6

Which cash flow should normally be excluded from a net present value calculation?

A. Incremental working capital

B. After-tax disposal proceeds

C. A sunk feasibility-study cost already paid

D. Opportunity cost of using an owned building

Correct Answer: C. A sunk feasibility-study cost already paid

Question 7

Which responsibility centre is accountable for operating profit and the assets employed to generate it?

A. Cost centre

B. Revenue centre

C. Profit centre

D. Investment centre

Correct Answer: D. Investment centre

Question 8

A division earns operating profit of $120,000 on average operating assets of $800,000. If the required return is 12%, what is residual income?

A. $24,000

B. $96,000

C. $105,600

D. $216,000

Correct Answer: A. $24,000

Question 9

Which measure is most likely to be a leading indicator of future process quality?

A. Last year's operating profit

B. Current employee technical-training completion

C. Historical dividend payments

D. Prior-year return on investment

Correct Answer: B. Current employee technical-training completion

Question 10

In a balanced scorecard, manufacturing defect rate is normally classified under which perspective?

A. Financial

B. Customer

C. Internal process

D. Learning and growth

Correct Answer: C. Internal process

Fundamentals of Accounting & Finance
Chapter 9 of 15