Financial Modeling & Valuation

Chapter 11
Capital Budgeting and Project Finance Models

Post Graduate Program in Finance
Financial Modeling & Valuation   •   Post Graduate Diploma

Capital Budgeting and Project Finance Models

Introduction and Context

Capital budgeting is the process of evaluating and selecting long-term investments. Examples include constructing a manufacturing plant, developing a mine, installing renewable-energy capacity, acquiring software infrastructure, or entering a new market. Such decisions are strategically important because they commit capital for several years, involve uncertain cash flows, and are often difficult or costly to reverse.

Project finance is a specialized form of capital budgeting in which lenders rely primarily on the project’s future cash flows and assets for repayment. Unlike conventional corporate finance, project finance commonly uses a legally separate special-purpose vehicle (SPV), non-recourse or limited-recourse debt, contractual revenue arrangements, and extensive financial covenants.

A sound model must therefore answer two related questions:

  1. Does the project create value for its investors?
  2. Can the project generate sufficient and timely cash to meet operating, debt-service, and distribution obligations?

The first question is principally an investment appraisal issue. The second is a financing, liquidity, and risk-allocation issue. Confusing project value with debt capacity is a frequent modeling error.

Learning Objectives

After studying this chapter, the reader should be able to:

  • identify relevant incremental cash flows;
  • distinguish accounting profit from investment cash flow;
  • calculate and interpret NPV, IRR, payback, discounted payback, and profitability index;
  • incorporate tax, depreciation, working capital, salvage value, inflation, and financing effects appropriately;
  • analyze mutually exclusive projects and investment constraints;
  • recognize and value selected real options;
  • construct a project-finance model linking operations, funding, debt service, covenants, and distributions;
  • calculate debt-service coverage and related credit metrics;
  • assess model risks, governance requirements, and ethical issues.

1. The Investment Decision and Incremental Cash Flow

The correct basis for capital budgeting is the change in the firm’s future cash flows caused by accepting the project. These are incremental cash flows, not reported earnings.

Relevant cash flows generally include:

  • initial capital expenditure;
  • installation, commissioning, and development expenditure;
  • incremental revenues and operating costs;
  • tax payments or tax savings;
  • changes in working capital;
  • terminal or salvage proceeds;
  • opportunity costs of assets already owned;
  • externally imposed environmental, closure, or remediation costs.

Sunk costs are excluded because they have already occurred and cannot be changed by the decision. Allocated overhead is included only when it represents an incremental cash outflow. Cannibalization of existing products is included because it is an economic consequence of the project.

A useful operating cash-flow identity is:

OCF = EBIT × (1 − T) + D

where OCF is operating cash flow, EBIT is earnings before interest and tax, T is the marginal tax rate, and D is depreciation. The expression assumes depreciation is non-cash and that tax is payable on operating earnings. An equivalent form is:

OCF = (Revenue − Cash operating costs) × (1 − T) + D × T

The second expression makes the depreciation tax shield explicit. Both forms exclude interest because project operating cash flows should normally be evaluated before financing flows when using a weighted-average cost of capital.

The free cash flow to the firm (FCFF) for period t can be represented as:

FCFFt = EBITt × (1 − Tt) + Dt − Capext − ∆NWCt + SVt

Here, Capext is capital expenditure, ∆NWCt is the increase in net working capital, and SVt is after-tax salvage value or other terminal operating cash flow. If the project is valued using FCFF, interest and principal repayments are not deducted from FCFF; they are reflected in the discount rate or analyzed separately in the financing model.

Timing conventions

A model should specify whether cash flows occur at the beginning or end of each period. Most annual capital-budgeting models assume end-of-year flows. Construction expenditure may occur at time zero or over several construction periods. A one-year timing error can materially affect NPV, especially for leveraged projects.

Tax and depreciation

Depreciation is not itself a cash flow, but it reduces taxable income. If depreciation in period t is Dt, the tax shield is:

Tax shieldt = Dt × Tt

This assumes the entity has sufficient taxable income to use the deduction. If losses are carried forward, the benefit may be delayed. Tax rules concerning capital allowances, loss carryforwards, minimum taxes, withholding taxes, and depreciation methods must be modeled according to the relevant jurisdiction.

If an asset with tax book value BV is sold for proceeds P, the after-tax sale proceeds are:

ATSV = P − T × (P − BV)

where ATSV is after-tax salvage value. If P exceeds BV, a taxable gain results; if it is lower, the formula captures the tax benefit of the loss, subject to applicable tax restrictions.

Working capital

An increase in working capital is normally an investment of cash. If receivables and inventory rise more than operating payables, cash is absorbed. At project termination, some or all of this working capital may be released. The model must avoid treating the initial investment and terminal recovery as the same cash flow.

2. Discounted Cash-Flow Appraisal

Net present value

Net present value is the present value of expected incremental cash flows less the initial investment:

NPV = ∑t=0n CFt ÷ (1 + r)t

where CFt is the incremental cash flow in period t, r is the appropriate discount rate per period, and n is the project life. Usually CF0 is negative. If the discount rate reflects the risk of the project and cash flows are measured consistently, a positive NPV indicates value creation.

The NPV rule is to accept an independent project when NPV > 0, reject it when NPV < 0, and remain economically indifferent when NPV is zero. NPV is generally the primary criterion because it measures value in currency and is additive across projects.

Discount rate and consistency

The discount rate must match the cash-flow definition:

  • FCFF is discounted at the project’s after-tax weighted-average cost of capital (WACC).
  • Free cash flow to equity is discounted at the cost of equity.
  • Nominal cash flows are discounted at a nominal rate.
  • Real cash flows are discounted at a real rate.

The Fisher relationship links nominal and real rates:

1 + rnominal = (1 + rreal) × (1 + inflation)

Thus, mixing real cash flows with a nominal discount rate overstates or understates value. The same consistency requirement applies to currency, tax assumptions, and inflation.

For a project with target debt weight wD, equity weight wE, pre-tax cost of debt kD, cost of equity kE, and tax rate T, a conventional WACC is:

WACC = wE × kE + wD × kD × (1 − T)

This formula assumes stable target weights, debt interest is tax deductible, and project risk is appropriately reflected in the component costs. A project-finance model may require a changing capital structure or a direct equity cash-flow approach instead.

Internal rate of return

The internal rate of return is the discount rate that makes NPV equal to zero:

0 = ∑t=0n CFt ÷ (1 + IRR)t

IRR is useful as a percentage return, but it has limitations. Multiple sign changes in cash flows can produce multiple IRRs. A nonconventional cash-flow pattern may produce no meaningful IRR. For mutually exclusive projects, the higher IRR may be inferior if the project has a lower NPV. Reinvestment assumptions embedded in IRR can also be unrealistic.

Modified internal rate of return (MIRR) separates the finance rate for negative cash flows from the reinvestment rate for positive cash flows. It is useful as a supplementary measure, but NPV remains the stronger value criterion.

Payback and discounted payback

Simple payback is the time required for cumulative undiscounted cash flows to recover the initial investment. If recovery occurs during a period, an approximation is:

Payback = Years before recovery + Unrecovered amount ÷ Cash flow in recovery year

Discounted payback applies the same procedure to discounted cash flows. Payback is intuitive and emphasizes liquidity, but it ignores cash flows after the cutoff and does not directly measure value creation. It should therefore be treated as a risk or liquidity indicator, not as a substitute for NPV.

Profitability index

For an investment with positive initial outlay I0, the profitability index is:

PI = PV of future cash inflows ÷ I0

A PI above 1 indicates positive NPV. PI is especially useful under capital rationing, although ranking by PI can fail when projects are indivisible, mutually exclusive, or have different scale and timing.

3. Worked Capital-Budgeting Example

Consider an illustrative project requiring an initial machine cost of 1,000,000 and initial working capital of 100,000. The machine is depreciated straight-line over four years to zero tax book value. Annual revenue is 900,000, cash operating cost is 500,000, and the tax rate is 25%. The machine is sold at the end of year four for 120,000. Working capital is fully recovered. The required return is 10%.

Annual depreciation is 250,000. Therefore:

EBIT = 900,000 − 500,000 − 250,000 = 150,000

Annual operating cash flow is:

OCF = 150,000 × (1 − 0.25) + 250,000 = 362,500

Because the tax book value is zero, after-tax salvage value is:

ATSV = 120,000 − 0.25 × (120,000 − 0) = 90,000

The cash-flow schedule is:

YearOperating cash flowOther cash flowNet cash flow
00−1,100,000−1,100,000
1362,5000362,500
2362,5000362,500
3362,5000362,500
4362,50090,000 + 100,000552,500

The present value of inflows is approximately:

PV = 362,500 ÷ 1.10 + 362,500 ÷ 1.102 + 362,500 ÷ 1.103 + 552,500 ÷ 1.104
PV ≈ 1,285,700

Thus:

NPV ≈ 1,285,700 − 1,100,000 = 185,700

The project is financially attractive at a 10% required return. Its simple payback is between years 3 and 4: cumulative cash flow after year 3 is 87,500,000? No. Correctly, cumulative cash flow after year 3 is −12,500, so payback is approximately:

Payback = 3 + 12,500 ÷ 552,500 ≈ 3.02 years

This example illustrates why cash-flow schedules should be checked mechanically. The terminal cash flow includes both after-tax disposal proceeds and working-capital recovery; omitting either would understate NPV.

4. Risk, Scenario Analysis, and Real Options

A single-point forecast conceals uncertainty. A professional model should identify value drivers, such as volume, price, operating margin, capital cost, construction delay, tax rate, exchange rate, and terminal value.

Sensitivity analysis

Sensitivity analysis changes one assumption at a time while holding others constant. It identifies variables to which NPV is most responsive, but it does not represent a probability distribution and may ignore correlations.

Scenario analysis

Scenario analysis changes several related assumptions simultaneously. Typical scenarios are downside, base, and upside. Scenarios should have internally coherent assumptions: a recession may reduce volume and price while increasing credit losses, rather than changing only one variable.

Simulation

Monte Carlo simulation assigns probability distributions to uncertain variables and generates a distribution of NPV or debt-service coverage. It is useful when uncertainty is multidimensional, but its conclusions depend on distributional assumptions and correlations. Simulation is not a replacement for economic judgment.

Real options

Traditional NPV often assumes a passive project. In practice, management may delay, expand, contract, abandon, switch inputs, or stage investment. These flexibilities are real options.

A deferral option has value when waiting can reveal information while preserving the opportunity to invest. An abandonment option can limit downside if assets have resale value. An expansion option benefits from unexpectedly strong demand. Staged investment can reduce exposure before technical or commercial uncertainty is resolved.

Real-option analysis is most credible when there is:

  • identifiable uncertainty;
  • an explicit managerial action;
  • a meaningful decision date;
  • limited loss if the option is not exercised;
  • a model linking states of nature to project cash flows.

A decision tree is often more transparent than a highly abstract option formula. Risk-neutral option methods may be appropriate for replicable financial risks, but commodity, regulatory, technical, and strategic risks often require scenario-based or hybrid analysis. A common mistake is to add a vaguely estimated “option value” to NPV without identifying the underlying decision rule.

5. Project-Finance Architecture

Project finance separates the project from its sponsors through an SPV. The SPV owns project assets, signs key contracts, borrows funds, receives revenue, pays costs and taxes, services debt, and distributes residual cash to sponsors.

Typical contractual arrangements include:

  • engineering, procurement, and construction (EPC) contracts;
  • operation and maintenance agreements;
  • offtake or power-purchase agreements;
  • supply agreements;
  • concession or lease agreements;
  • insurance and hedging arrangements;
  • direct agreements with lenders.

The model should follow the cash waterfall rather than merely calculate accounting profit. A typical waterfall is:

Project finance cash flow waterfall Revenueand receipts Operatingcosts and tax Debt serviceand reserves Residual cashto sponsors Cash is distributed only after priority obligations are met Reserve accounts, lock-up tests, and covenant breaches can interrupt distributions.
Project finance cash flow waterfall
Figure: Project finance cash flow waterfall

Figure: Simplified project-finance cash-flow waterfall.

Sources and uses

At financial close, sources must equal uses:

Total sources = Total uses

Sources may include sponsor equity, shareholder loans, senior debt, subordinated debt, grants, and vendor finance. Uses may include construction costs, development fees, financing fees, interest during construction, reserve funding, taxes, and initial working capital. A sources-and-uses imbalance indicates either an incomplete model or an implicit funding assumption.

Debt sizing and repayment

Debt may be sculpted to match expected cash available for debt service. A principal repayment schedule can be designed so that the debt-service coverage ratio remains near a target level, subject to minimum debt-service and legal constraints.

Debt service generally comprises interest and scheduled principal:

Debt servicet = Interestt + Principal repaymentt

For a level-payment amortizing loan with initial principal P, periodic interest rate i, and n payments, the payment is:

Payment = P × i × (1 + i)n ÷ [(1 + i)n − 1]

This formula assumes equal periodic payments, a fixed rate, and no fees or balloon balance. Project-finance loans frequently use sculpted or partially amortizing structures instead.

Debt-service coverage ratio

A common DSCR definition is:

DSCRt = CFADSt ÷ Debt servicet

CFADS means cash flow available for debt service. It is usually derived from operating cash flow after operating costs, taxes, and permitted working-capital movements, but before debt service and distributions. The exact definition is contractual.

A DSCR of 1.30× means that CFADS is 1.30 times scheduled debt service. A minimum DSCR covenant may prohibit distributions or trigger cure mechanisms when the ratio falls below the threshold. DSCR must not be calculated using EBITDA unless the financing documents explicitly define it that way; EBITDA is not necessarily cash available for debt service.

Other metrics include:

LLCR = NPV of CFADS over the debt life at the debt discount rate ÷ Debt outstanding
PLCR = NPV of CFADS over the project life at the debt discount rate ÷ Debt outstanding

LLCR is commonly more conservative because it uses only cash flows during the loan life. Definitions differ by transaction and must be read from the financing agreement.

Covenants and reserves

Typical covenants include minimum DSCR, minimum reserve balance, loan-life coverage ratio, restrictions on additional debt, change-of-control restrictions, insurance requirements, and limitations on distributions. Reserve accounts may include a debt-service reserve account (DSRA), maintenance reserve, major-repair reserve, and decommissioning reserve.

A covenant breach does not always mean immediate default. Documents may provide cure rights, cash sweeps, distribution lock-up, mandatory prepayment, or lender step-in rights. The model should represent these states explicitly rather than simply displaying a warning cell.

6. Integrated Project-Finance Modeling Process

A robust model is usually constructed in modules:

  1. Assumptions: dates, construction schedule, operating assumptions, tax, inflation, financing terms, and scenario controls.
  2. Construction: capital expenditure, contingency, drawdown, capitalized interest, and completion date.
  3. Operations: production, availability, price, escalation, operating costs, working capital, and taxes.
  4. Funding: equity, debt drawdowns, fees, interest, repayment, and reserves.
  5. Cash waterfall: revenues through costs, taxes, reserves, debt service, and distributions.
  6. Statements: income statement, cash-flow statement, balance sheet, and debt schedule.
  7. Returns: project IRR, equity IRR, NPV, payback, and distributions.
  8. Covenants and sensitivities: DSCR, LLCR, downside cases, and stress tests.

The model should maintain a clear distinction between cash available for debt service, cash available for distribution, and accounting profit. Each balance should roll forward:

Closing balancet = Opening balancet + Increasest − Decreasest

Examples include debt, cash reserves, fixed assets, working capital, and retained earnings. Balance checks and sources-equals-uses checks should be visible, not hidden in complex formulas.

7. Investment Prioritization Under Constraints

When capital is unlimited and projects are independent, accept every project with positive NPV. Under a capital budget, management must prioritize.

A practical procedure is:

  • remove projects that fail strategic, legal, technical, or risk requirements;
  • calculate NPV using consistent assumptions;
  • identify mutually exclusive alternatives;
  • rank or optimize projects subject to budget and timing constraints;
  • assess portfolio concentration and correlation;
  • test the selected portfolio under downside scenarios.

Profitability index may help when projects are divisible and the constraint is a single-period capital limit. However, an optimization model is preferable when projects are indivisible or span multiple years. The objective can be stated as:

Maximize ∑ NPVj × xj

subject to:

∑ Investmentj,t × xj ≤ Budgett

where xj is 1 if project j is selected and 0 otherwise. Additional constraints can represent labor, risk, strategic minimums, or project dependencies. This is a simplified binary-integer formulation; real decisions may require staged decisions and uncertainty modeling.

8. Illustrative Case: Solar Project Finance

The following is a fictional illustrative case. SunCo develops a 100-megawatt solar project through an SPV. Construction lasts 18 months. A long-term power-purchase agreement provides predictable revenue, while a portion of output is exposed to merchant prices. The project is funded with 70% senior debt and 30% sponsor equity.

Background and problem

Lenders must determine whether projected cash flows support the requested debt and whether sponsors receive an acceptable return. Management must decide whether to build immediately or delay six months to obtain additional information about equipment prices and grid connection costs.

Analysis

The model includes:

  • monthly construction expenditure and debt drawdown;
  • capitalized interest during construction;
  • production based on capacity, irradiation, and technical availability;
  • degradation of output over time;
  • contracted and merchant revenue;
  • operating costs, land lease, insurance, and taxes;
  • working-capital timing;
  • debt sculpting to a minimum 1.25× DSCR;
  • DSRA funding equal to six months of scheduled debt service;
  • distribution lock-up if DSCR falls below 1.15×;
  • downside scenarios involving lower irradiation, delayed completion, and reduced merchant prices.

Approach and solution

The base case produces positive project NPV and an equity IRR above the sponsor’s hurdle rate. However, the downside case shows that a six-month construction delay reduces the first operating year’s CFADS and causes a temporary distribution lock-up. The model therefore supports less debt than the initial 70% request unless the EPC contractor provides delay liquidated damages or sponsors provide a completion-support commitment.

The deferral option has strategic value because equipment prices may fall, but waiting risks losing the grid-connection slot. Rather than inserting an arbitrary option premium, management models two decision dates and compares expected value under specified probabilities and decision rules. Immediate construction is selected if the probability-weighted value of preserving the connection exceeds the expected benefit of waiting.

Outcome

The recommended structure uses slightly lower senior debt, a larger DSRA, and a partial hedge of interest-rate exposure. Distribution tests are linked to actual covenant definitions. The project remains viable, but the financing is made more resilient to delay and output risk.

Learning points

  • Project value and debt capacity are different decisions.
  • Construction risk can dominate operating risk before commercial operation.
  • Contract design can be as important as spreadsheet forecasts.
  • A model should show the actions triggered by covenant failure.
  • Real-option analysis requires an identifiable managerial choice and uncertainty, not merely an optimistic adjustment.

9. Governance, Ethics, and Contemporary Practice

Capital-budgeting models influence employment, environmental outcomes, public infrastructure, and investor wealth. Analysts have an ethical duty to present assumptions transparently and avoid manipulating timing, tax benefits, terminal values, or discount rates to achieve a predetermined answer.

Important governance practices include:

  • version control and an assumptions log;
  • separation of inputs, calculations, and outputs;
  • independent review of formulas;
  • documented sources for market, technical, tax, and legal assumptions;
  • controlled use of macros and external links;
  • scenario and stress testing;
  • audit trails for overrides;
  • clear distinction between forecast, commitment, and judgment.

AI tools can assist with anomaly detection, sensitivity generation, documentation, and code review. They should not be treated as authorities on tax law, engineering performance, contractual definitions, or investment approval. Confidential project data must be protected, and every AI-generated output requires human validation. Explainability is particularly important when model outputs affect communities, tariffs, environmental commitments, or access to essential services.

Contemporary models increasingly incorporate climate-transition risk, carbon prices, supply-chain disruption, cyber risk, geopolitical uncertainty, and sustainability-linked financing conditions. These variables should be connected to cash flows and contractual mechanisms rather than added as unsupported narrative claims.

Challenges and Limitations

Capital-budgeting and project-finance models are simplified representations. Key limitations include:

  • forecast error in demand, prices, costs, and timing;
  • dependence on tax and accounting assumptions;
  • model risk from incorrect formulas or circular references;
  • uncertain correlations between downside variables;
  • difficulty valuing nonfinancial strategic benefits;
  • unstable discount rates over long project lives;
  • ambiguity in covenant definitions;
  • political, regulatory, and force-majeure risks;
  • false precision from excessive decimal places.

A model should therefore be used as a decision-support system, not as a substitute for due diligence, engineering review, legal analysis, or managerial judgment.

Best-Practice Checklist

Before approving a project model, confirm that:

  • all cash flows are incremental and correctly timed;
  • sunk costs are excluded and opportunity costs included;
  • nominal and real assumptions are consistent;
  • tax effects, loss utilization, and salvage values are documented;
  • working capital is invested and recovered appropriately;
  • NPV is the primary value criterion;
  • mutually exclusive projects are compared on incremental cash flows;
  • sources equal uses and balance sheets balance;
  • debt schedules roll forward without unexplained plugs;
  • CFADS and DSCR follow contractual definitions;
  • covenant breaches trigger modeled consequences;
  • downside cases include delay, cost overrun, volume, price, and interest-rate risks;
  • outputs have been independently reviewed and reconciled.

Chapter Summary

Capital budgeting evaluates long-term investments using incremental after-tax cash flows. NPV is generally the primary decision criterion because it measures value creation in currency and accommodates differences in scale and timing. IRR, payback, discounted payback, and profitability index provide useful supplementary information but have important limitations.

Correct analysis requires careful treatment of depreciation tax shields, working capital, opportunity costs, salvage proceeds, inflation, discount-rate consistency, and project timing. Sensitivity analysis, scenarios, simulation, and real-options reasoning improve decisions under uncertainty.

Project finance adds a contractual and cash-waterfall dimension. The SPV, sources-and-uses schedule, debt amortization, CFADS, DSCR, LLCR, reserves, covenants, and distribution restrictions must be integrated. A project may have positive economic value but insufficient debt capacity, or adequate debt service in the base case but unacceptable downside risk. Sound practice combines quantitative appraisal with technical, legal, environmental, ethical, and governance review.

Key Terms

Incremental cash flow: Cash flow caused by accepting a project.

Sunk cost: A past cost that cannot be changed by the current decision.

Opportunity cost: Value sacrificed by using a resource for one project rather than its next-best use.

Net present value (NPV): Present value of future incremental cash flows less initial investment.

Internal rate of return (IRR): Discount rate that makes project NPV equal to zero.

Payback period: Time required to recover the initial investment from undiscounted cash flows.

Profitability index: Present value of future inflows divided by initial investment.

FCFF: Free cash flow available to all capital providers before financing flows.

WACC: Weighted-average cost of debt and equity, adjusted for the debt tax shield.

Depreciation tax shield: Tax saving generated by deductible depreciation.

Working capital: Operating investment in receivables, inventory, and related current accounts net of operating liabilities.

Real option: Value of managerial flexibility to alter a project in response to future information.

Special-purpose vehicle (SPV): Legally separate entity established to own and finance a project.

Cash flow available for debt service (CFADS): Contractually defined cash available to pay debt service.

Debt-service coverage ratio (DSCR): CFADS divided by debt service.

Loan-life coverage ratio (LLCR): Present value of loan-life CFADS divided by outstanding debt.

Debt-service reserve account (DSRA): Reserve maintained to support scheduled debt service.

Cash waterfall: Priority sequence governing the use and distribution of project cash.

Covenant: Contractual requirement or restriction imposed by lenders.

Capital rationing: Selection of projects when available investment funds are constrained.

Review Questions

Short Answer Questions

  1. Why are sunk costs excluded from incremental cash-flow analysis?
  2. Distinguish FCFF from free cash flow to equity.
  3. Why is depreciation included in operating cash flow even though it is non-cash?
  4. What does a DSCR of 1.25× mean?
  5. State one limitation of the IRR criterion.

Long Answer Questions

  1. Explain how NPV, IRR, payback, discounted payback, and profitability index differ as investment criteria.
  2. Discuss the importance of consistency between cash flows, inflation assumptions, tax treatment, currency, and discount rate.
  3. Explain the structure and economic rationale of project finance using an SPV.
  4. Describe how a project-finance model should represent debt service, reserves, covenants, and distributions.
  5. Evaluate the role of real options in capital budgeting and explain why option value should not be added arbitrarily.

Analytical / Application Questions

  1. A project requires 500,000 of initial investment and produces annual after-tax cash flows of 180,000 for four years. At a 12% discount rate, calculate its NPV and determine whether it should be accepted.
  2. A project has CFADS of 26 million and annual debt service of 20 million. Calculate DSCR and explain the implications if the minimum covenant is 1.20×.
  3. Two mutually exclusive projects have different investment scales and lives. Design an analysis that determines which project creates greater value, explaining why IRR alone may produce the wrong choice.

Multiple Choice Questions with Answers

Question 1

Which cash flow should normally be excluded from a project’s incremental cash-flow analysis?

A. An opportunity cost of using an existing asset

B. A sunk feasibility-study cost already paid

C. Additional working-capital investment

D. After-tax salvage proceeds

Correct Answer: B. A sunk feasibility-study cost already paid

Question 2

A project has EBIT of 400,000, depreciation of 100,000, and a tax rate of 25%. What is its operating cash flow, assuming no other adjustments?

A. 300,000

B. 325,000

C. 400,000

D. 425,000

Correct Answer: B. 325,000

Question 3

What is the principal decision rule for an independent project under the NPV method?

A. Accept when NPV is less than zero

B. Accept when IRR is below the discount rate

C. Accept when NPV is greater than zero

D. Accept only when payback is less than one year

Correct Answer: C. Accept when NPV is greater than zero

Question 4

If nominal cash flows are used in a valuation, which discount rate is generally consistent?

A. A real discount rate

B. A nominal discount rate

C. The tax rate only

D. The inflation rate only

Correct Answer: B. A nominal discount rate

Question 5

A project has CFADS of 15 million and debt service of 12 million. Its DSCR is:

A. 0.80×

B. 1.00×

C. 1.25×

D. 1.80×

Correct Answer: C. 1.25×

Question 6

Which item is normally included in project debt service?

A. Depreciation expense

B. Interest and scheduled principal repayment

C. Revenue growth

D. Sponsor’s target IRR

Correct Answer: B. Interest and scheduled principal repayment

Question 7

What is a major limitation of the simple payback period?

A. It always includes the time value of money

B. It ignores cash flows after the recovery point

C. It cannot be calculated for projects with initial investment

D. It measures NPV directly

Correct Answer: B. It ignores cash flows after the recovery point

Question 8

In a project-finance cash waterfall, distributions to sponsors generally occur:

A. Before operating costs

B. Before taxes and debt service

C. After priority costs, reserves, and debt service

D. Only during construction

Correct Answer: C. After priority costs, reserves, and debt service

Question 9

Which situation most clearly represents a real option?

A. A historical accounting allocation

B. The ability to delay construction while preserving the investment opportunity

C. A fixed depreciation charge

D. A mandatory interest payment

Correct Answer: B. The ability to delay construction while preserving the investment opportunity

Question 10

If a project’s profitability index is 1.15, what does this generally indicate, assuming conventional cash flows and the stated investment basis?

A. The project has negative NPV

B. The present value of inflows is 15% greater than the initial investment

C. The project’s IRR is exactly 15%

D. The project must be rejected

Correct Answer: B. The present value of inflows is 15% greater than the initial investment

Financial Modeling & Valuation
Chapter 11 of 15