Entrepreneurship and Innovation in Construction

Chapter 7
Technical, Market and Economic Feasibility

Bachelors Program in Construction Technology
Entrepreneurship and Innovation in Construction   •   Bachelor

Technical, Market and Economic Feasibility

Introduction

A construction opportunity may be technically impressive and commercially attractive yet still be a poor entrepreneurial investment. Feasibility analysis provides a disciplined basis for deciding whether an idea should proceed, be redesigned, deferred, or rejected. In construction entrepreneurship, feasibility is not a single calculation. It is an integrated assessment of whether a proposed project can be built, whether customers or users need it, whether the organisation has sufficient capacity, and whether the expected benefits justify the resources, risks, and opportunity costs involved.

This chapter examines four connected dimensions: technical feasibility, market feasibility, capacity feasibility, and economic feasibility. It then applies cost–benefit analysis, break-even analysis, lifecycle value assessment, sensitivity analysis, scenario analysis, and multicriteria decision-making. These tools do not eliminate uncertainty. Instead, they make assumptions visible, allow alternatives to be compared, and improve the quality of entrepreneurial judgement.

Learning objectives

By the end of this chapter, students should be able to:

  1. Evaluate the constructability and technical requirements of a construction opportunity.
  2. Assess demand, competition, market structure, and customer value.
  3. Analyse organisational, labour, equipment, supply-chain, and financial capacity.
  4. Distinguish capital cost, operating cost, lifecycle cost, revenue, benefit, and risk.
  5. Apply cost–benefit, break-even, discounted cash-flow, sensitivity, and scenario methods.
  6. Use a multicriteria decision matrix to compare construction alternatives.
  7. Communicate assumptions, limitations, ethical issues, and recommendations professionally.

1. The integrated feasibility framework

Feasibility should be treated as a staged decision process rather than a pass–fail inspection conducted at the end of project development. A typical sequence is:

Opportunity definition → preliminary screening → technical and market studies → capacity assessment → economic analysis → risk and uncertainty analysis → decision and implementation plan.

The dimensions are interdependent. A market may show strong demand for modular housing, but the opportunity is not feasible if the business lacks manufacturing capacity or if local planning rules prohibit the proposed density. Conversely, an available construction method is not attractive if clients will not pay for its benefits.

A feasibility report should distinguish:

  • Facts: verified site, cost, regulatory, or market information.
  • Assumptions: conditions adopted because complete information is unavailable.
  • Estimates: calculated values based on facts and assumptions.
  • Judgements: professional interpretations of attractiveness or risk.
  • Decision criteria: thresholds used to approve, revise, or reject the proposal.

This distinction is essential because false precision can make an uncertain estimate appear authoritative.

2. Technical feasibility and constructability

Technical feasibility asks whether the proposed facility, product, or service can be delivered to the required performance standard with available technology, resources, time, and regulatory approvals. It includes the following questions:

  • Is the site suitable in terms of ground conditions, access, utilities, climate, and hazards?
  • Are the design, materials, systems, and construction methods proven or adequately tested?
  • Can the work be sequenced safely and within the required programme?
  • Are skilled workers, specialist subcontractors, plant, and materials available?
  • Can tolerances, quality requirements, durability, maintainability, and sustainability targets be achieved?
  • Are planning, building-control, environmental, fire, occupational-safety, and accessibility requirements satisfied?

Constructability

Constructability is the extent to which design and project planning support efficient, safe, and reliable construction. It is influenced by design simplicity, standardisation, dimensional coordination, access, temporary works, logistics, procurement strategy, and the timing of information release.

A constructability review should occur before final design. Typical review questions include:

  1. Can workers safely access every work area?
  2. Can components be transported, lifted, stored, and installed using available equipment?
  3. Are interfaces between structural, architectural, mechanical, electrical, and digital systems clearly resolved?
  4. Are repetitive elements standardised without compromising performance?
  5. Can construction be maintained while a facility remains occupied?
  6. Are inspection, testing, commissioning, repair, and future replacement considered?

A technically feasible design can still be commercially weak if it requires rare skills, long-lead components, excessive temporary works, or high rework rates.

Technical assessment tools

Useful tools include site investigation, concept design, method statements, buildability workshops, digital coordination, energy modelling, prototype testing, supplier consultations, and risk registers. Building information modelling can reveal spatial clashes and improve quantity extraction, but it does not automatically validate design assumptions or guarantee constructability. Professional review remains necessary.

A preliminary technical feasibility register can be structured as follows:

AreaEvidence requiredTypical riskPossible response
SiteSurveys, geotechnical report, utilities informationUnknown ground conditionsAdditional investigation; contingency
DesignDrawings, specifications, performance calculationsUnresolved interfacesDesign coordination; prototype
ResourcesLabour, plant, suppliersCapacity shortageFramework agreements; substitution
ProgrammeLogic network, lead timesDelayed completionEarly procurement; float
ComplianceCodes, permits, approvalsRejection or redesignEarly authority consultation
QualityInspection and testing planDefects and reworkHold points; independent inspection

3. Market feasibility and demand

Market feasibility evaluates whether a sufficient number of customers, clients, users, or public authorities recognise a need and are willing and able to support the proposed value proposition. Demand is not identical to need. A community may need affordable homes, but effective demand depends on income, financing, eligibility, public subsidy, and competing alternatives.

Market definition

The market should be defined by customer group, geography, project type, time period, and purchasing mechanism. For example, “construction” is too broad; “energy-efficient, two-bedroom rental units for moderate-income households within a 30-kilometre radius over the next three years” is more useful.

Important market questions include:

  • Who makes the purchasing decision?
  • Who pays, who uses, and who bears risk?
  • What problem does the proposed product solve?
  • What alternatives are available?
  • How price-sensitive are customers?
  • What procurement rules and qualification requirements apply?
  • Is demand cyclical, seasonal, policy-dependent, or tied to interest rates?

Demand estimation

Demand estimation may combine historical data, planning pipelines, surveys, interviews, tender databases, competitor analysis, demographic information, and expert judgement. A simple market-sizing structure is:

Effective demand = Potential customers × Adoption rate × Purchase frequency

The result must be interpreted carefully. “Potential customers” may represent households, developers, public agencies, or projects. The adoption rate should reflect awareness, affordability, regulation, switching costs, and competitive response.

Market research should avoid leading questions. A respondent claiming to prefer a sustainable material does not necessarily represent a paid order. Stronger evidence includes signed letters of intent, repeat purchasing behaviour, tender participation, pilot contracts, or revealed willingness to pay.

Competition and value proposition

Competitive analysis should compare total customer value rather than price alone. Relevant dimensions include initial price, programme, reliability, quality, warranty, energy performance, maintenance, carbon impact, financing, and risk transfer. A new construction venture may succeed by reducing defects or delivery time even if its direct price is not the lowest.

Market feasibility also requires analysis of substitute technologies. For example, a modular system competes not only with another modular supplier but also with conventional in-situ construction, renovation, leasing, or postponement of the project.

4. Capacity feasibility

Capacity feasibility examines whether the organisation can deliver the opportunity at the required scale and quality. Capacity is multidimensional:

  • Human capacity: managers, supervisors, trades, engineers, estimators, and digital specialists.
  • Physical capacity: factories, offices, yards, plant, tools, vehicles, and storage.
  • Financial capacity: working capital, borrowing ability, bonding, guarantees, and cash-flow resilience.
  • Organisational capacity: systems, governance, procurement, quality control, and project experience.
  • Supply-chain capacity: availability and reliability of subcontractors and suppliers.

A firm may have enough annual labour hours but still lack capacity at a particular time. A basic utilisation measure is:

Utilisation = Actual output ÷ Practical capacity × 100%

Practical capacity is lower than theoretical capacity because it allows for maintenance, setup, interruptions, training, weather, and normal inefficiency. High utilisation is not always desirable: if utilisation approaches 100%, even a small delay can create severe congestion and overtime.

Capacity analysis should identify bottlenecks. If a project requires 12,000 specialist installation hours and the firm has 8 installers available for 20 weeks at 30 productive hours per week, available productive capacity is:

8 × 20 × 30 = 4,800 productive hours

The opportunity cannot be accepted without additional labour, revised duration, subcontracting, or a different method. This calculation assumes all eight installers are available for the full period and that 30 hours per week represents productive, rather than paid, time.

5. Economic feasibility and lifecycle value

Economic feasibility considers whether the project creates sufficient financial or social value relative to its costs and risks. The analysis must use a consistent perspective. A private developer may evaluate profit and cash return; a public agency may evaluate social benefits; a contractor may evaluate contribution margin, working-capital exposure, and failure risk.

Cost classification

Important cost categories include:

  • Initial capital cost: land, design, permits, construction, equipment, commissioning, and financing during construction.
  • Operating cost: energy, labour, consumables, insurance, administration, and routine services.
  • Maintenance cost: preventive, corrective, and replacement expenditure.
  • Decommissioning cost: removal, disposal, remediation, and site reinstatement.
  • Opportunity cost: value of the next-best use of capital, land, labour, or management time.
  • External cost: impacts imposed on others, such as noise, congestion, emissions, or ecological damage.

Lifecycle costing evaluates costs and benefits over a defined analysis period rather than focusing only on construction price. A lower initial cost may produce higher energy, maintenance, replacement, or disruption costs.

Present value and net present value

Money received or spent at different times cannot be compared directly without recognising the time value of money. The present value of a future cash flow is:

PVt = CFt ÷ (1 + r)t

where PVt is present value at time zero of cash flow CFt occurring at time t, and r is the discount rate per period. The units of t must match the period used for r.

For a project with initial investment I0 and cash flows from year 1 to year n, net present value is:

NPV = −I0 + ∑t=1n CFt ÷ (1 + r)t

NPV assumes cash flows and the discount rate are estimated consistently, the timing of flows is known, and the discount rate reflects the relevant opportunity cost and risk. A positive NPV indicates value creation relative to that discount rate; it does not guarantee that the project is liquid or risk-free.

Worked example: lifecycle NPV

An energy retrofit costs £120,000 immediately. It is expected to save £32,000 per year for five years, and has a residual value of £10,000 at the end of year five. Using an annual discount rate of 8%:

NPV = −120,000 + 32,000 × [1 − (1.08)^−5] ÷ 0.08 + 10,000 ÷ (1.08)5

The five-year annuity factor at 8% is approximately 3.9927. Therefore:

NPV ≈ −120,000 + 32,000 × 3.9927 + 10,000 ÷ 1.4693
NPV ≈ −120,000 + 127,766 + 6,806
NPV ≈ £14,572

Under these assumptions, the retrofit has a positive NPV of approximately £14,572. The result is sensitive to actual energy prices, equipment performance, maintenance, discount rate, and the residual value. Taxes, inflation, grants, and financing effects would need separate treatment if relevant.

Cost–benefit analysis

Cost–benefit analysis compares monetised benefits with monetised costs. The benefit–cost ratio is:

BCR = Present value of benefits ÷ Present value of costs

A BCR above 1 indicates that monetised benefits exceed monetised costs. However, BCR can favour a small project over a larger project with greater absolute value, so NPV and distributional effects should also be considered. Benefits may include revenue, avoided energy cost, reduced travel time, improved productivity, reduced accidents, avoided maintenance, or environmental gains. When benefits cannot be reliably monetised, they should not be assigned arbitrary monetary values merely to create a precise-looking ratio.

6. Break-even analysis

Break-even analysis identifies the activity level at which revenue equals total cost. With constant unit price and unit variable cost:

QBE = F ÷ (P − V)

where QBE is break-even quantity, F is fixed cost, P is selling price per unit, and V is variable cost per unit. The contribution margin per unit is P − V. The formula assumes a single product or a constant sales mix, linear revenue and variable cost, unchanged prices, and fixed costs within the relevant activity range.

Worked example

A small prefabrication venture has annual fixed costs of £240,000. Each unit sells for £18,000 and has variable cost of £12,000:

QBE = 240,000 ÷ (18,000 − 12,000) = 40 units

The venture must sell 40 units annually to cover operating costs. If expected sales are 50 units, operating profit before financing and tax is:

Profit = 50 × 18,000 − [240,000 + 50 × 12,000] = £60,000

Break-even analysis is less reliable when construction projects are unique, prices are negotiated, overhead allocation is arbitrary, or capacity constraints cause overtime and subcontracting. It should therefore be used with project-specific cash-flow analysis.

7. Uncertainty: sensitivity and scenarios

A feasibility estimate is conditional on assumptions. Sensitivity analysis changes one variable at a time to identify which assumptions most influence the outcome. Common variables include construction cost, selling price, demand, programme duration, interest rate, energy savings, labour productivity, and residual value.

For a performance measure Y depending on input x, a simple local sensitivity can be expressed as:

Sensitivity ≈ ∆Y ÷ ∆x

If percentage changes are used, an elasticity-style measure is:

E = (% change in Y) ÷ (% change in x)

These measures are descriptive, not universal laws. They depend on the chosen base case and range. A tornado chart can rank variables by their effect on NPV or profit.

Scenario analysis changes several related assumptions coherently. Typical scenarios are:

  • Base case: most defensible assumptions.
  • Upside case: strong demand, efficient delivery, and favourable prices.
  • Downside case: delay, cost escalation, weaker demand, and financing pressure.
  • Stress case: severe but plausible disruption, such as supplier failure or regulatory change.

Scenarios should be internally consistent. It is unreasonable to combine a major demand collapse with unusually high selling prices unless a clear mechanism explains the relationship. Probabilities may be assigned when evidence supports them. Expected monetary value is:

EMV = ∑ pi Vi

where pi is the probability of scenario i and Vi is its value. Expected value should not be mistaken for a forecast: it may conceal a low-probability, high-loss outcome that threatens survival.

8. Multicriteria decision analysis

Many construction decisions involve conflicting objectives. A method may have a favourable NPV but poor carbon performance, long procurement time, or unacceptable safety exposure. Multicriteria decision analysis (MCDA) makes these trade-offs explicit.

A simple weighted-sum model is:

Sj = ∑i=1m wi xij

where Sj is the score of alternative j, wi is the weight of criterion i, and xij is the normalised score of alternative j on criterion i. Weights should sum to 1. Scores must be normalised so that higher values consistently mean better performance. Cost and risk criteria therefore require reverse scaling or another justified transformation.

Illustrative comparison of two construction systems:

CriterionWeightSystem A scoreSystem B score
Lifecycle cost0.358070
Programme0.209065
Quality risk0.207585
Carbon performance0.158570
Supply availability0.106090
Weighted score1.0079.2574.25

System A is preferred under these weights, but the conclusion is not objective in isolation. The team should test whether a change in weights reverses the ranking. Stakeholders should also identify “must-pass” criteria, such as legal compliance or minimum safety performance. An alternative failing a mandatory criterion should not be rescued by a high score elsewhere.

9. Illustrative case: modular student accommodation

The following is a fictional illustrative case designed for educational use.

Background

BuildFast Ltd., a small construction venture, is considering a modular student-accommodation project consisting of 80 rooms near a university. The proposed system uses factory-produced bathroom pods and timber-framed room modules. The client values completion before the academic year and has indicated a target rental level.

Problem

The modular solution has a higher initial procurement price than conventional construction. Management must determine whether the shorter programme, reduced site labour, and lower expected defects justify the premium. The project also faces uncertain planning approval, factory capacity constraints, and possible increases in material prices.

Analysis

The technical review identified adequate road access, but a turning-radius problem required a temporary traffic-management plan. The factory could produce only 12 modules per week, while the programme required 16 per week. The proposal therefore required either overtime, a second supplier, or a 7-week extension. Fire-stopping interfaces and lifting plans were identified as critical quality and safety controls.

Market interviews indicated strong demand, but the client’s willingness to pay depended on opening before the academic year. A two-month delay would reduce the first-year revenue opportunity. This illustrates why demand analysis must include timing and service reliability, not only the number of potential tenants.

The economic model included capital cost, financing during construction, rental revenue, maintenance, defect rectification, and residual value. The team used NPV at the client’s specified discount rate and performed sensitivity tests on completion date, module cost, occupancy, and maintenance expense. Under the base case, modular construction produced a positive NPV of £0.42 million compared with £0.31 million for conventional construction. Under the downside case of a two-month delay and 8% module-cost escalation, modular NPV fell to £0.05 million, while conventional construction remained at £0.18 million.

An MCDA was then conducted using lifecycle cost, programme certainty, quality risk, carbon, supply resilience, and local employment. Modular construction ranked first in the base weighting, but its ranking reversed when supply resilience and local employment were given substantially greater weight.

Approach and solution

BuildFast did not accept the proposal unconditionally. It negotiated a second manufacturing source, required a binding production schedule, obtained early planning clarification, and established inspection hold points for fire-stopping and lifting connections. The contract included clear responsibility for design interfaces and delay consequences. The client also approved a contingency and a decision gate after the first prototype module.

Outcome

In the illustrative case, the project proceeded after prototype approval and additional supply assurance. The final decision was not based solely on the positive NPV. It depended on risk controls that made the technical and programme assumptions more credible.

Learning points

  1. Technical feasibility and economic feasibility are linked through programme, quality, and risk.
  2. Capacity constraints can invalidate an otherwise attractive business model.
  3. A positive base-case NPV is insufficient where downside outcomes threaten viability.
  4. MCDA exposes values and trade-offs that financial analysis alone cannot represent.
  5. Contractual allocation, prototyping, and staged approval can reduce uncertainty before full commitment.

10. Professional, ethical, and governance considerations

Feasibility analysis has ethical consequences. Analysts should not omit inconvenient data, manipulate discount rates to obtain approval, double-count benefits, or present uncertain estimates as guaranteed outcomes. Conflicts of interest should be declared, especially where consultants are paid contingent on project approval.

Governance should establish independent review for high-value or high-risk projects. Assumptions need owners, sources, dates, and review triggers. Cost estimates should state whether they include taxes, inflation, design development, contingency, land, financing, and abnormal site conditions. A risk allowance is not a substitute for identifying and managing risk.

Regulatory feasibility includes planning, building regulations, environmental assessment, labour law, procurement rules, accessibility, fire safety, health and safety, data protection, and professional licensing. Digital tools and AI can assist with cost classification, document checking, demand analysis, clash detection, and scenario generation. However, AI outputs may contain bias, fabricated references, outdated codes, or hidden assumptions. Human experts must verify data, explain decisions, protect confidential information, and retain accountability.

11. Best-practice decision process

A robust feasibility study should:

  1. Define the decision, alternatives, perspective, analysis period, and success criteria.
  2. Gather evidence from site, design, market, supply-chain, financial, and regulatory sources.
  3. Separate facts, assumptions, estimates, and judgements.
  4. Identify technical bottlenecks and mandatory compliance conditions.
  5. Estimate demand using more than stated preference.
  6. Model capacity, cash flow, lifecycle cost, and working-capital exposure.
  7. Use NPV or an appropriate economic measure, with transparent discounting.
  8. Test break-even, sensitivity, downside, and stress scenarios.
  9. Compare non-financial criteria using a transparent MCDA process.
  10. Recommend a staged decision with conditions, responsibilities, and review gates.

Challenges and limitations

No feasibility method predicts the future with certainty. Market data may be incomplete, cost estimates may mature as design develops, and relationships between variables may be nonlinear. Discount rates can undervalue long-term environmental or social effects. BCR and NPV may favour benefits that are easy to monetise rather than benefits that matter most. Break-even analysis can be misleading for unique projects. MCDA can create a false impression of precision if weights and scores are arbitrary.

The appropriate response is not to abandon analysis but to improve transparency, use ranges rather than single-point estimates, conduct independent challenge, and establish decision gates. Feasibility is a continuing activity: assumptions should be updated as design, procurement, market conditions, and regulation change.

Chapter Summary

Technical, market, capacity, and economic feasibility are complementary dimensions of construction entrepreneurship. Technical feasibility tests whether a proposal can be designed, approved, resourced, and built safely and reliably. Market feasibility examines effective demand, customer value, competition, procurement, and timing. Capacity feasibility considers labour, plant, finance, organisation, and supply chains. Economic feasibility compares costs and benefits over time and should include lifecycle effects, opportunity costs, and risk.

NPV discounts future cash flows and indicates value relative to a chosen discount rate. Cost–benefit analysis compares monetised benefits and costs, while break-even analysis identifies the activity level needed to cover fixed and variable costs. Sensitivity analysis reveals influential assumptions; scenario analysis explores coherent alternative futures. MCDA supports decisions where cost, programme, quality, carbon, safety, and supply resilience conflict. Sound professional judgement requires transparent assumptions, ethical reporting, regulatory awareness, staged commitment, and human oversight of digital and AI tools.

Key Terms

Technical feasibility: The ability to deliver a proposal using available technology, resources, time, and compliant methods.

Constructability: The extent to which design and planning support safe, efficient, and reliable construction.

Market feasibility: The assessment of demand, customers, competition, procurement, and willingness to pay.

Effective demand: Demand supported by both need or preference and the ability and willingness to purchase.

Capacity feasibility: The assessment of whether organisational resources can deliver the opportunity.

Fixed cost: A cost that remains approximately constant within a relevant activity range.

Variable cost: A cost that changes with the quantity or volume of output.

Lifecycle cost: The total relevant cost from acquisition through operation, maintenance, replacement, and disposal.

Opportunity cost: The value of the next-best alternative use of a resource.

Discount rate: The rate used to convert future cash flows into present value.

Net present value: Present value of benefits or cash inflows less present value of costs or investment.

Benefit–cost ratio: Present value of benefits divided by present value of costs.

Break-even quantity: Output level at which total revenue equals total cost.

Contribution margin: Selling price less variable cost per unit.

Sensitivity analysis: Examination of the effect of changing one input on an outcome.

Scenario analysis: Evaluation of outcomes under coherent sets of alternative assumptions.

Multicriteria decision analysis: A structured method for comparing alternatives using several weighted criteria.

Constructability review: A systematic examination of design and planning from the perspective of construction delivery.

Decision gate: A formal point at which a project is approved, revised, paused, or rejected.

Review Questions

5 Short Answer Questions

  1. What is the difference between technical feasibility and market feasibility?
  2. Define practical capacity and explain why it is lower than theoretical capacity.
  3. What does a positive NPV indicate, and what does it not guarantee?
  4. State the assumptions behind the basic break-even quantity formula.
  5. Why should facts, assumptions, estimates, and judgements be separated in a feasibility report?

5 Long Answer Questions

  1. Explain how constructability review can influence lifecycle value, safety, programme, and profitability.
  2. Discuss the main methods for estimating demand for a new construction product or service.
  3. Compare NPV, benefit–cost ratio, and break-even analysis, including the strengths and limitations of each.
  4. Explain how sensitivity analysis and scenario analysis should be used together in an uncertain construction investment.
  5. Describe a transparent MCDA process for selecting between two construction methods.

3 Analytical / Application Questions

  1. A contractor has fixed costs of £300,000, a selling price of £25,000 per unit, and variable cost of £17,500 per unit. Calculate the break-even quantity and operating profit at 50 units. State the assumptions of your calculation.
  2. A proposed project has a positive base-case NPV but becomes negative if completion is delayed by three months. Design a decision-gate and risk-response plan that could justify proceeding or stopping the project.
  3. Develop a weighted decision matrix for two construction systems using at least five criteria, including one mandatory compliance criterion. Explain how your weights and scores were selected and test whether the ranking is sensitive to the weights.

Multiple Choice Questions with Answers

Question 1

Which statement best describes constructability?

A. The market price of a completed building

B. The extent to which design and planning support safe and efficient construction

C. The total present value of project benefits

D. The number of workers employed on a project

Correct Answer: B. The extent to which design and planning support safe and efficient construction

Question 2

A project has fixed costs of £240,000, a selling price of £18,000 per unit, and a variable cost of £12,000 per unit. What is its break-even quantity?

A. 20 units

B. 30 units

C. 40 units

D. 60 units

Correct Answer: C. 40 units

Question 3

In the formula PVt = CFt ÷ (1 + r)t, what does r represent?

A. Residual value

B. Discount rate per period

C. Variable cost per unit

D. Production quantity

Correct Answer: B. Discount rate per period

Question 4

Which result generally indicates that a project creates value relative to the selected discount rate?

A. Negative NPV

B. Zero revenue

C. Positive NPV

D. Break-even quantity above capacity

Correct Answer: C. Positive NPV

Question 5

Which is an example of effective demand rather than merely a stated need?

A. A community expresses concern about housing shortages

B. A respondent says sustainable buildings are desirable

C. A client signs a letter of intent at an affordable price

D. A planner identifies a theoretical population increase

Correct Answer: C. A client signs a letter of intent at an affordable price

Question 6

What is the main purpose of sensitivity analysis?

A. To change all assumptions simultaneously into one forecast

B. To identify how changes in inputs affect an outcome

C. To eliminate the need for professional judgement

D. To calculate only fixed costs

Correct Answer: B. To identify how changes in inputs affect an outcome

Question 7

In a weighted-sum MCDA model, the criterion weights should normally:

A. All equal zero

B. Sum to 1

C. Be greater than the scores

D. Apply only to financial criteria

Correct Answer: B. Sum to 1

Question 8

A firm has 8 installers, each providing 30 productive hours per week, for 20 weeks. What is the available productive capacity?

A. 240 hours

B. 600 hours

C. 4,800 hours

D. 9,600 hours

Correct Answer: C. 4,800 hours

Question 9

Which statement about scenario analysis is correct?

A. It changes only one variable while holding all others constant

B. It evaluates coherent sets of alternative assumptions

C. It proves which future will occur

D. It is applicable only to environmental projects

Correct Answer: B. It evaluates coherent sets of alternative assumptions

Question 10

Which practice is most appropriate when using AI in feasibility analysis?

A. Accepting all generated estimates without checking sources

B. Using AI to replace regulatory and professional accountability

C. Verifying outputs, protecting confidential data, and documenting assumptions

D. Removing uncertainty from the final report

Correct Answer: C. Verifying outputs, protecting confidential data, and documenting assumptions

Entrepreneurship and Innovation in Construction
Chapter 7 of 14