Entrepreneurial Finance and Investment DecisionsIntroductionConstruction entrepreneurship is often described in terms of opportunity recognition, technical competence and project delivery. Yet many construction ventures fail not because demand is absent or construction knowledge is inadequate, but because cash is unavailable at the moment it is needed. A profitable project can become insolvent when a client pays late, a subcontractor requires an advance, material prices rise, or retention money is withheld. Entrepreneurial finance therefore concerns both profitability and liquidity, while investment decision-making determines whether scarce capital should be committed to equipment, personnel, technology, property development or a new contracting operation. Construction finance is distinctive because revenues and costs are frequently uneven over time. Projects involve tendering costs, mobilization expenses, progress payments, retention, variations, bonds, insurance, claims and substantial working-capital requirements. The entrepreneur must translate a business idea into forecasts, cash-flow statements and funding requirements, then evaluate funding sources and investment returns under uncertainty. This chapter develops an integrated approach: forecast operating performance, model cash movements, identify financing gaps, compare bootstrapping, debt, equity, grants and venture capital, and assess investments using net present value (NPV), internal rate of return (IRR), valuation and financial-risk measures. Learning ObjectivesBy the end of this chapter, the learner should be able to: - Prepare basic revenue, cost, profit and cash-flow forecasts for a construction venture.
- Distinguish profit, cash flow, working capital and solvency.
- Estimate funding requirements and construct a sources-and-uses statement.
- Compare bootstrapping, debt, equity, grants and venture capital.
- Apply NPV, IRR, payback and profitability-index methods appropriately.
- Estimate enterprise value using discounted cash flow and market multiples.
- Analyse leverage, liquidity, sensitivity and scenario risk.
- Make financially responsible and ethically defensible investment recommendations.
1. The Financial Logic of a Construction VentureA construction business creates value when the present value of expected future cash inflows exceeds the capital invested and the risks undertaken. Three related but different questions must be answered: - Is the venture profitable? This concerns revenues and expenses under accrual accounting.
- Can it pay its obligations when due? This concerns cash receipts, cash payments and liquidity.
- Does it create value for investors? This compares risk-adjusted future cash flows with the opportunity cost of capital.
Profit is not the same as cash. If a contractor records a completed stage worth £100,000 but the client pays in 60 days, revenue and profit may be recognised before cash is received. Conversely, an advance payment may increase cash before the related work and profit are recognised. Depreciation reduces accounting profit but is not a current cash payment; purchasing equipment reduces cash immediately but is not normally an expense in full in the purchase period. A useful operating relationship is: Profit = Revenue − Operating expenses − Depreciation − Finance costs − Tax The exact treatment depends on the applicable accounting framework and tax rules. For management forecasting, cash flow should be modelled separately. Construction-specific cash pressuresImportant sources of pressure include: - tendering and design costs incurred before contract award;
- mobilization, site establishment and deposits;
- payment delays and disputed valuations;
- retention held by clients;
- advance payments to suppliers and subcontractors;
- performance, advance-payment and retention bonds;
- uncertain quantities, variations and claims;
- equipment purchases and maintenance;
- seasonal demand and weather disruption; and
- exposure to inflation, foreign exchange and interest-rate changes.
A financially competent entrepreneur establishes payment terms, credit controls, contingency allowances and financing arrangements before accepting work. 2. Forecasting Revenue, Costs and Working Capital2.1 Revenue forecastingRevenue forecasts should be built from operational drivers rather than unsupported percentages. For a quantity-based activity: Revenuet = ∑(Quantityi,t × Pricei,t) Here, i identifies a work item and t identifies the period. Quantity may be measured in m³, tonnes, labour-hours or completed units; price must use the same currency basis and period. The forecast should specify whether prices include tax, escalation, subcontractor margins and approved variations. For a contracting business, a schedule of expected work can include bid probability. If a prospective contract has estimated value £500,000 and a 40% probability of award, its probability-weighted pipeline contribution is £200,000. This is useful for planning but must not be treated as committed revenue. A prudent forecast separates secured backlog, likely awards and speculative opportunities. 2.2 Cost forecastingCosts should be classified by behaviour and traceability: | Cost classification | Construction example | Forecast question |
|---|
| Direct variable | Concrete, steel, direct labour | How does cost change with output? | | Direct fixed for a project | Site manager salary, site office | What is committed for the project duration? | | Indirect overhead | Head-office rent, accounting | What supports several projects? | | Capital expenditure | Crane, vehicle, software system | What asset is acquired and when? | | Contingency | Uncertain ground conditions | What risk is being allowed for? |
A contribution estimate is: Contribution = Revenue − Variable costs and the contribution margin ratio is: Contribution margin ratio = Contribution ÷ Revenue These measures are useful for short-term decisions, provided fixed costs, capacity constraints and project-specific risks are not ignored. 2.3 Break-even analysisIf fixed costs are constant over the relevant range and unit price and variable cost are stable, break-even quantity is: QBE = Fixed costs ÷ (Unit selling price − Unit variable cost) The denominator is the unit contribution. The formula is a short-run model; it is unreliable when construction prices, productivity, capacity or fixed costs change materially with output. For multiple projects, a weighted contribution margin or project-specific cash model is preferable. 2.4 Working capitalWorking capital is the investment required to support day-to-day operations. A simplified operating working-capital measure is: Operating working capital = Trade receivables + Inventories − Trade payables A cash-conversion-cycle approximation is: CCC = DSO + DIO − DPO where DSO is days sales outstanding, DIO is days inventory outstanding and DPO is days payable outstanding. In construction, DSO may be extended by certification and retention, while DPO is constrained by contractual and ethical obligations to suppliers. Deliberately delaying payment beyond agreed terms is not a sound financing strategy. 3. Preparing Forecast Statements3.1 Forecast income statementA forecast income statement estimates accounting performance: | Item | Period 1 (£) | Period 2 (£) |
|---|
| Revenue | 600,000 | 780,000 | | Direct and operating costs | (480,000) | (624,000) | | EBITDA | 120,000 | 156,000 | | Depreciation | (20,000) | (25,000) | | EBIT | 100,000 | 131,000 | | Finance cost | (12,000) | (14,000) | | Profit before tax | 88,000 | 117,000 |
EBITDA means earnings before interest, tax, depreciation and amortisation. It is a performance indicator, not cash flow, because it excludes capital expenditure, tax, working-capital movements and debt repayment. 3.2 Forecast cash-flow statementA cash-flow statement is commonly divided into operating, investing and financing activities. A direct operating forecast may be prepared as: Net cash flowt = Cash receiptst − Cash operating paymentst − Taxt − Interestt − Capital expendituret − Principal repaymentst + New financingt The opening and closing cash balances are: Closing casht = Opening casht + Net cash flowt The signs must be consistent: receipts and financing inflows are positive; payments, investments and repayments are negative. Tax and interest treatment should reflect the jurisdiction and the purpose of the forecast. Worked Example 1: Monthly cash requirementAn illustrative contractor begins a small fit-out project. The following cash movements are forecast: | Month | Receipts (£) | Operating payments (£) | Equipment (£) | Financing inflow (£) |
|---|
| 1 | 40,000 | 85,000 | 30,000 | 80,000 | | 2 | 95,000 | 90,000 | 0 | 0 | | 3 | 120,000 | 100,000 | 0 | 0 |
Opening cash is £20,000. In month 1: Net cash flow1 = 40,000 − 85,000 − 30,000 + 80,000 = 5,000 Closing cash is therefore £25,000. In month 2, net cash flow is £5,000 and closing cash is £30,000. In month 3, net cash flow is £20,000 and closing cash is £50,000. If the £80,000 financing inflow were unavailable, month-1 closing cash would be negative £55,000. The financing requirement is at least £55,000 to avoid a cash deficit, before allowing for a management buffer, fees and forecast error. A robust model also includes a minimum cash balance. If management requires £20,000 at all times, the required funding in the no-financing scenario would be £75,000 rather than £55,000. 3.3 Sources and uses of fundsA sources-and-uses statement checks whether planned funding matches planned expenditure. | Uses | £ | Sources | £ |
|---|
| Equipment | 30,000 | Owner savings | 25,000 | | Initial materials and labour | 55,000 | Bank loan | 50,000 | | Working-capital reserve | 20,000 | Grant | 10,000 | | Fees and contingency | 10,000 | Total sources | 85,000 | | Total uses | 115,000 | Funding gap | 30,000 |
The gap can be addressed by additional equity, a working-capital facility, revised procurement, staged equipment acquisition or stronger client payment terms. Funding should be matched to purpose: long-lived assets should generally be funded by stable long-term capital, while temporary receivable gaps may be funded by a suitable short-term facility. 4. Funding Choices and Capital StructureBootstrappingBootstrapping uses personal savings, retained profits, customer deposits, pre-sales, supplier credit agreed on normal terms, shared equipment and careful staged investment. Advantages include control, speed and no mandatory interest. Limitations include constrained growth, concentration of personal risk and the possibility that undercapitalisation damages delivery quality. Customer advances may be valuable, but they create an obligation to perform. They should not be treated as free money. Contractual safeguards, segregation of funds where required and accurate cash forecasting are essential. Debt financeDebt may include term loans, overdrafts, asset finance, invoice finance and revolving credit. It preserves ownership but requires repayment regardless of project profitability. Relevant terms include principal, interest rate, arrangement fees, maturity, security, covenants and repayment schedule. The periodic payment on a fully amortising loan can be calculated as: A = P × [r(1 + r)n] ÷ [(1 + r)n − 1] where A is the payment per period, P is the initial principal, r is the interest rate per period and n is the number of payments. This assumes equal periodic payments, a constant rate and no additional fees or early repayment. The periodic rate and payment frequency must match. Debt is appropriate only when forecast cash flows can support repayment under realistic downside scenarios. Security requirements may expose personal or business assets. A lender’s approval is not evidence that a project is economically attractive; it indicates that the lender accepts the credit risk under specified conditions. Equity financeEquity investors contribute capital in exchange for ownership and a claim on residual value. Equity has no contractual repayment like debt, but it dilutes founders and may introduce governance rights, reporting requirements and different strategic objectives. A pre-money valuation is the value before new investment; post-money valuation is: Post-money valuation = Pre-money valuation + New investment If an investor contributes £200,000 at a post-money valuation of £1,000,000, the investor’s nominal ownership is 20%, subject to the capitalization structure and investment agreement. Grants and public supportGrants can reduce dilution and repayment obligations, but they may require matching funds, eligible expenditure, procurement compliance, milestone reporting, intellectual-property conditions and repayment if terms are breached. Grant income should not be assumed until eligibility and award conditions are confirmed. Venture capitalVenture capital is generally suited to scalable businesses with large growth potential, such as construction software, industrialized construction, robotics, marketplaces or low-carbon building technologies. A conventional local contractor with linear revenue growth may be better suited to retained earnings, debt or private investment. Venture capital can provide expertise and networks, but it normally requires substantial equity, rapid growth and investor influence. Entrepreneurs should evaluate strategic fit, liquidation preferences, board rights, future dilution and exit expectations rather than focusing only on the cash amount. 5. Investment AppraisalTime value of moneyA pound received today is normally worth more than a pound received later because today’s pound can be invested, future receipts are uncertain and inflation reduces purchasing power. The present value of a future cash flow is: PVt = CFt ÷ (1 + k)t where CF_t is the cash flow at time t, k is the discount rate per period and t is the number of periods. The rate and cash-flow periods must be consistent. Net present valueFor an investment requiring initial outflow I₀ and generating cash flows CF₁ through CFₙ: NPV = −I₀ + ∑[CFt ÷ (1 + k)t] NPV is positive when the investment is expected to create value at the selected discount rate. It is generally the preferred decision rule for mutually exclusive investments, provided cash flows, risk and the discount rate are estimated consistently. Worked Example 2: NPVA construction technology investment costs £100,000 now and is expected to generate £45,000, £50,000 and £40,000 at the ends of years 1, 2 and 3. The discount rate is 10%. NPV = −100,000 + 45,000/1.10 + 50,000/1.102 + 40,000/1.103 The present values are approximately £40,909, £41,322 and £30,053. Therefore: NPV ≈ −100,000 + 40,909 + 41,322 + 30,053 = 12,284 The investment has an estimated positive NPV of approximately £12,284, subject to the assumptions. The cash flows should be incremental, after-tax cash flows where appropriate, and should include working-capital investment, residual value and relevant capital expenditure. Internal rate of returnIRR is the discount rate that makes NPV equal to zero: 0 = −I₀ + ∑[CFt ÷ (1 + IRR)t] IRR is intuitive as a percentage return, but it can mislead when cash flows change sign more than once, when projects differ in scale or timing, or when reinvestment assumptions are unrealistic. NPV should normally resolve conflicts between NPV and IRR. A project is conventionally acceptable if IRR exceeds the required return, provided the cash-flow pattern supports a meaningful IRR. Payback and profitability indexPayback is the time needed to recover the initial investment from undiscounted cash flows. It is simple and useful for liquidity risk, but it ignores cash flows after payback and usually ignores the time value of money. Discounted payback improves the first limitation but remains incomplete. The profitability index is: PI = Present value of future inflows ÷ Initial investment A PI greater than 1 indicates positive NPV for a conventional investment, but ranking by PI can be inappropriate when projects are mutually exclusive or capital is not perfectly divisible. 6. Valuation of a Construction VentureDiscounted cash-flow valuationFor a business with forecast free cash flows and a terminal value: Enterprise value = ∑[FCFt ÷ (1 + WACC)t] + TV ÷ (1 + WACC)n A perpetual-growth terminal value is often represented as: TV = FCFn+1 ÷ (WACC − g) where FCF is free cash flow, WACC is the weighted average cost of capital and g is the perpetual growth rate. This terminal formula requires WACC > g and assumes a stable long-term growth rate. Since terminal value can dominate the estimate, sensitivity analysis is essential. Free cash flow to the firm may be approximated as: FCF = EBIT(1 − Tax rate) + Depreciation − Capital expenditure − Increase in operating working capital This formulation is appropriate for cash flow available to both debt and equity providers, subject to consistent treatment of financing and tax. Market multiplesComparable-company or transaction multiples, such as enterprise value to EBITDA, can provide a market cross-check. A multiple is meaningful only when the comparator has similar business model, growth, margin, risk, accounting policies and capital intensity. A high-growth construction-software company should not automatically be valued using the multiple of a mature general contractor. Cost of capitalWACC combines the required returns of debt and equity providers: WACC = [E ÷ (D + E)]Re + [D ÷ (D + E)]Rd(1 − T) where E is market value of equity, D is market value of interest-bearing debt, R_e is required return on equity, R_d is pre-tax cost of debt and T is the applicable tax rate. The tax adjustment applies only where interest is tax-deductible and the model assumes the relevant tax conditions. Book values may be used for practical estimates, but market-value weights are theoretically preferable. 7. Financial Risk and Decision QualityLeverage and coverageDebt magnifies returns to equity when operating returns exceed the cost of debt, but it magnifies losses in the opposite case. Common indicators include: Debt-to-equity ratio = Interest-bearing debt ÷ Equity Interest coverage = EBIT ÷ Interest expense Current ratio = Current assets ÷ Current liabilities These ratios require comparable accounting definitions and should be interpreted with cash-flow forecasts. A current ratio above 1 does not guarantee liquidity if receivables are disputed or inventory cannot be converted quickly into cash. Sensitivity and scenario analysisSensitivity analysis changes one assumption at a time, such as price, volume, cost or payment delay, to identify influential variables. Scenario analysis changes several related assumptions together. For example: - Base case: planned productivity and payment timing.
- Downside case: 10% material inflation, 30-day payment delay and two-month programme extension.
- Upside case: higher productivity and earlier certification.
A break-even analysis can identify the maximum cost increase or minimum revenue required for NPV to remain zero. Probabilistic simulation may be justified for large or complex portfolios, but its output is only as credible as the input distributions and correlations. Risk-adjusted decision-makingRisks should be allocated to the party best able to control them and priced where appropriate. A contingency is not a substitute for risk identification. Entrepreneurs should distinguish: - Known costs: included in the base estimate;
- Identified but uncertain costs: assessed through allowances or scenarios; and
- Unknown risks: addressed through reserves, insurance, contract provisions and management flexibility.
8. Applied Case: GreenBuild Modular SystemsThis is an illustrative case, not a report of an actual company. BackgroundGreenBuild Modular Systems is a proposed start-up that will manufacture low-carbon bathroom pods for medium-sized housing contractors. The founders have construction experience but limited capital. They require £300,000 for tooling, certification, software, initial inventory and working capital. ProblemThe founders must choose between a bank loan, equity investment and a staged launch. The bank offers a £180,000 loan at a fixed annual rate with monthly repayments and requires personal guarantees. An angel investor offers £300,000 for 30% equity, a board seat and information rights. A public innovation grant could provide £75,000, but only after eligible expenditure and with milestone reporting. The initial forecast assumes sales of 120 pods in year 1, rising to 250 in year 3. AnalysisThe founders first construct a monthly cash forecast rather than relying on the attractive three-year profit forecast. The model includes tooling payments before production, customer deposits, inventory lead times, certification fees, warranty provisions, tax, loan repayments and delayed customer receipts. The downside case assumes a six-month certification delay and material costs 12% above budget. The bank loan appears cheaper than equity in the base case, but repayments begin before reliable sales are established. Under the downside case, interest coverage falls below the lender’s covenant and cash becomes negative. The angel investment reduces insolvency risk but gives away significant ownership and introduces governance constraints. The grant is non-dilutive but cannot fund all early cash needs and should not be treated as certain until awarded. Approach and solutionThe recommended structure is staged financing: - Founders contribute a defined amount sufficient to complete design and grant application.
- The company secures milestone-based customer deposits with contractually clear refund and delivery conditions.
- It applies for the grant and uses a smaller working-capital facility rather than the full loan.
- It purchases tooling in stages, subject to certification milestones.
- It obtains an independent review of the forecast and negotiates a debt covenant based on realistic cash measures.
- If scale-up is validated, it seeks equity at a higher valuation rather than accepting premature dilution.
The investment decision is based on NPV under base, downside and upside scenarios, not on IRR alone. The board also establishes a minimum cash reserve and weekly cash reporting during the launch. OutcomeUnder the illustrative assumptions, the staged plan has a lower maximum financing need and avoids negative cash in the downside case. Its expected NPV is lower than the most aggressive expansion plan, but its probability of survival is materially higher. This reflects an important entrepreneurial principle: a theoretically higher return is not necessarily preferable when it exposes the venture to unacceptable liquidity or governance risk. Learning points- Forecast cash by month when payment timing is uncertain.
- Treat grants and customer deposits according to their conditions.
- Match financing maturity to asset life and cash-flow timing.
- Evaluate dilution, control and strategic fit alongside funding cost.
- Use downside scenarios before committing to irreversible expenditure.
9. Governance, Ethics and Contemporary PracticeFinancial decisions must comply with company law, tax rules, accounting standards, lending agreements, grant conditions, securities regulation and applicable anti-money-laundering requirements. Entrepreneurs should not manipulate forecasts to obtain finance, conceal liabilities, misclassify customer advances as earned revenue or delay recognition of known losses. Transparent assumptions are especially important where founders, investors, lenders and clients have unequal information. Construction finance also has social and supply-chain consequences. Aggressive cash preservation that causes late payment to small subcontractors can transfer insolvency risk to vulnerable firms. Ethical financial management includes fair payment, accurate certification, responsible procurement and adequate provision for safety and quality. Digital systems can improve finance by linking estimating, scheduling, procurement, progress measurement and accounting. AI-assisted forecasting may identify patterns in payment delays, productivity and cost variance, but outputs require human review. Risks include biased historical data, unsupported confidence, cyberattack, confidentiality breaches and unclear accountability. A model should retain an audit trail of data sources, assumptions, version changes and approvals. Best practice is to maintain an integrated model with: - a clearly documented assumptions sheet;
- monthly or weekly cash forecasts;
- separate base, downside and upside cases;
- reconciliation between forecast income statement, cash flow and balance sheet;
- approval controls for commitments and variations;
- rolling reforecasting against actual results; and
- decision logs explaining why funding and investment choices were made.
Chapter SummaryEntrepreneurial finance in construction integrates profitability, liquidity, risk and value creation. Revenue and cost forecasts should be based on operational drivers, while cash forecasts must reflect certification, retention, payment delays, deposits, capital expenditure, taxation and financing. Profit does not guarantee cash availability, and a profitable business can fail through insolvency. Funding requirements are identified through cash-flow forecasts and sources-and-uses statements. Bootstrapping preserves control but may restrict growth; debt avoids ownership dilution but creates mandatory repayment; equity shares risk and control; grants are conditional; and venture capital is appropriate mainly for scalable, high-growth models. Investment appraisal uses present value, NPV, IRR, payback and profitability index, with NPV generally the strongest value-creation criterion. Valuation can use discounted cash flow and market multiples, but assumptions about growth, risk and terminal value require sensitivity analysis. Responsible decisions combine financial calculations with scenario analysis, covenant awareness, ethical treatment of suppliers, legal compliance and sound governance. The best financing plan is not necessarily the cheapest in the base case; it is the plan that supports value creation while preserving resilience under plausible adverse conditions. Key TermsEntrepreneurial finance: Financial planning and decision-making for creating and growing a venture. Liquidity: Ability to meet financial obligations when they fall due. Solvency: Ability to meet obligations over the longer term. Working capital: Current operating resources invested in receivables and inventory less operating payables. Cash-conversion cycle: Time between paying for inputs and collecting cash from customers. EBITDA: Earnings before interest, tax, depreciation and amortisation. Capital expenditure: Spending that acquires or improves a long-lived asset. Bootstrapping: Financing growth primarily from founder resources, operating cash and retained profits. Debt finance: Borrowed capital requiring repayment, usually with interest. Equity finance: Capital exchanged for ownership and residual claims. Grant: Conditional public or institutional funding that normally does not require repayment if terms are met. Venture capital: Equity investment aimed at scalable, high-growth ventures. Discount rate: Required return used to convert future cash flows to present value. Net present value: Present value of future cash flows less the initial investment. Internal rate of return: Discount rate that makes an investment’s NPV equal to zero. Enterprise value: Value of operating assets available to debt and equity providers. WACC: Weighted average cost of capital. Leverage: Use of debt or fixed financial commitments to finance operations. Sensitivity analysis: Testing the effect of changing one assumption. Scenario analysis: Testing a coordinated set of assumptions representing a possible future. Review QuestionsShort Answer Questions- Why can a construction project be profitable but cash-deficient?
- Define working capital and identify two construction-specific working-capital pressures.
- What is the difference between a forecast income statement and a cash-flow statement?
- State two advantages and two limitations of debt finance.
- Why is NPV generally preferred to simple payback for value-creation decisions?
Long Answer Questions- Explain how a construction entrepreneur should prepare a revenue, cost and cash-flow forecast for a new contracting business.
- Compare bootstrapping, debt, equity, grants and venture capital in terms of cost, control, risk and suitability.
- Explain the assumptions and limitations of NPV, IRR and discounted cash-flow valuation.
- Discuss how payment terms, retention and subcontractor obligations affect construction liquidity.
- Describe an integrated governance system for managing financial forecasts, commitments and investment decisions.
Analytical / Application Questions- A contractor has opening cash of £25,000, receipts of £70,000 and payments of £110,000 in month 1. It must retain a £15,000 minimum cash balance. Calculate the additional funding required.
- An equipment investment costs £80,000 and generates £35,000, £35,000 and £30,000 at the ends of years 1–3. Using a 10% discount rate, calculate its NPV and recommend whether it should proceed, assuming no terminal value.
- A start-up must choose between a loan that creates fixed monthly repayments and equity that causes 25% dilution. Design a base case and downside case, identify the most important assumptions, and recommend a financing structure with justification.
Multiple Choice Questions with AnswersQuestion 1Which statement best distinguishes profit from cash flow? A. Profit always equals cash received during the period. B. Cash flow includes only non-current assets. C. Profit may be recognised before a customer pays, whereas cash flow records actual cash movements. D. Cash flow excludes financing transactions. Correct Answer: C. Profit may be recognised before a customer pays, whereas cash flow records actual cash movements. Question 2A project has fixed costs of £60,000, a selling price of £50 per unit and variable cost of £30 per unit. What is the break-even quantity? A. 1,200 units B. 2,000 units C. 3,000 units D. 6,000 units Correct Answer: C. 3,000 units Question 3Which funding source normally involves ownership dilution? A. Term loan B. Trade payable C. Grant D. Equity investment Correct Answer: D. Equity investment Question 4A project costs £100,000 and has future cash-flow present values totaling £112,284. What is its NPV? A. £12,284 B. £100,000 C. £112,284 D. £212,284 Correct Answer: A. £12,284 Question 5What does IRR represent? A. The discount rate at which NPV equals zero B. The project’s accounting profit margin C. The percentage of costs financed by debt D. The time required to collect receivables Correct Answer: A. The discount rate at which NPV equals zero Question 6Which item is normally a use of funds in a construction start-up? A. Owner equity contribution B. Bank loan proceeds C. Purchase of construction equipment D. Grant receipt Correct Answer: C. Purchase of construction equipment Question 7If debt is £120,000 and equity is £80,000, what is the debt-to-equity ratio? A. 0.67 B. 1.00 C. 1.50 D. 2.00 Correct Answer: C. 1.50 Question 8Which statement about venture capital is most accurate? A. It is normally free funding with no governance implications. B. It is most suitable for every small construction contractor. C. It commonly provides equity capital in exchange for ownership and investor rights. D. It requires fixed monthly repayment like a term loan. Correct Answer: C. It commonly provides equity capital in exchange for ownership and investor rights. Question 9In a discounted cash-flow valuation, terminal value is especially sensitive to which assumptions? A. Office layout and branding colour B. WACC and perpetual growth rate C. Number of directors only D. Historical invoice sequence only Correct Answer: B. WACC and perpetual growth rate Question 10Which action is most appropriate when a downside cash forecast shows a negative balance? A. Ignore it because accounting profit is positive. B. Increase the forecast revenue without evidence. C. Assess staged expenditure, payment terms and suitable contingency funding. D. Delay payment to subcontractors without regard to contract terms. Correct Answer: C. Assess staged expenditure, payment terms and suitable contingency funding.
|