ERP Selection, Configuration and ImplementationIntroductionEnterprise resource planning (ERP) implementation is not primarily an information-technology installation. It is an organisational transformation through which processes, data, controls, roles and decision rights are redesigned around an integrated information platform. In materials management, ERP affects purchasing, inventory, supplier management, receiving, inspection, warehouse operations, production supply, logistics, finance and master-data governance. A technically successful system may nevertheless fail if users reject redesigned processes, data are unreliable, controls are weak or expected benefits are not realised. ERP selection and implementation therefore require a business case, a disciplined evaluation of alternatives, process analysis, fit-gap assessment, configuration governance, data migration, testing, cutover planning, training, change management and post-implementation benefits management. The central managerial challenge is to balance standardisation with legitimate business differentiation. Excessive customisation increases cost and complexity; excessive standardisation may damage regulatory compliance, customer service or operational effectiveness. Learning ObjectivesBy the end of this chapter, the learner should be able to: - Develop and evaluate an ERP business case using strategic, financial and operational criteria.
- Compare ERP alternatives through structured requirements, weighted scoring and risk analysis.
- Map materials-management processes and conduct fit-gap analysis.
- Distinguish configuration, extension, integration and customisation decisions.
- Design effective approaches to data migration, testing, cutover and training.
- Lead change management, governance and benefits-realisation activities.
- Critically evaluate implementation risks, ethical issues and contemporary ERP developments.
1. The Strategic Role of ERP in Materials ManagementAn ERP system integrates transaction processing and information flows across functions. A purchase requisition can generate a purchase order; the goods receipt can update inventory; an invoice can be matched against the order and receipt; and the resulting liability can be posted to finance. This integration reduces duplicated data entry and improves traceability, but it also creates dependency: inaccurate material master data or an incorrectly configured planning parameter can affect purchasing, production and financial reporting simultaneously. For materials management, ERP commonly supports: - material and supplier master data;
- purchasing and contract management;
- requirements planning and replenishment;
- inventory valuation and stock movements;
- warehouse and location control;
- quality inspection and blocked stock;
- batch, serial and expiry tracking;
- supplier performance and spend analytics;
- segregation of duties and audit trails.
ERP should be viewed as a socio-technical system. Its performance depends on technology, processes, organisational structure, skills, incentives, data quality and governance. The implementation question is therefore not simply “Which software has the most features?” but “Which operating model and information architecture will best support organisational strategy at acceptable risk and total cost?” 2. Building the ERP Business CaseA business case establishes why change is necessary, what alternatives exist, how value will be created and how risk will be controlled. It should be approved before detailed solution design, while remaining sufficiently flexible to accommodate evidence discovered during analysis. 2.1 Problem definition and strategic alignmentThe problem statement should be evidence-based. Typical symptoms include excessive inventory, poor stock visibility, delayed purchase orders, duplicate suppliers, weak traceability, manual reconciliations, unreliable planning data or inability to support growth. Symptoms must be distinguished from root causes. For example, high inventory may result from poor demand data, inappropriate safety stocks, supplier unreliability or incentives that reward local availability rather than total supply-chain performance. The business case should connect ERP objectives to strategy, such as: - supporting multi-site growth;
- improving working-capital productivity;
- strengthening regulatory traceability;
- standardising procurement controls;
- enabling reliable planning and analytics;
- integrating acquisitions;
- improving resilience and supplier visibility.
2.2 Costs, benefits and investment appraisalRelevant costs include software licences or subscriptions, implementation services, internal staff time, infrastructure, data cleansing, interfaces, testing, training, temporary productivity loss, support and future upgrades. Benefits may include reduced inventory, lower transaction cost, fewer stockouts, reduced expedited freight, improved supplier compliance, faster close and reduced audit exposure. A simple return-on-investment measure is: ROI = (PV(Benefits) − PV(Costs)) ÷ PV(Costs) × 100% Here, PV(Benefits) and PV(Costs) are the present values of expected benefits and costs over the appraisal period. The measure assumes that benefits and costs are estimated on a comparable basis and that the chosen period and discounting method are appropriate. ROI alone is insufficient because it ignores timing and risk; a project with a high nominal return may have poor cash flow or unacceptable implementation risk. Net present value is often more rigorous: NPV = ∑[t=0 to n] (CFt ÷ (1 + r)t) CFt is the net cash flow in period t, r is the discount rate per period, and n is the number of periods. Cash flows should be incremental, consistently measured and expressed in the same currency and time units. A positive NPV indicates value creation under the stated assumptions, not certainty of success. A sound business case also includes sensitivity analysis. Management should test how conclusions change if implementation cost is 20% higher, benefits are delayed, adoption is incomplete or inventory reductions are smaller than forecast. Non-financial benefits—such as auditability, worker safety, compliance and resilience—should be made explicit rather than hidden in arbitrary monetary estimates. 3. ERP Alternatives and SelectionAlternatives may include extending an existing platform, adopting a new on-premise system, using a cloud ERP, selecting a best-of-breed architecture or retaining current systems with targeted improvements. The decision should consider the organisation’s process complexity, geographic footprint, regulatory requirements, integration capability, internal skills, risk appetite and desired speed of change. 3.1 Requirements engineeringRequirements should be written as observable capabilities rather than vendor slogans. A materials requirement might state: “The system shall record batch receipt, quality status, expiry date and storage location and shall prevent issue of expired or blocked stock without authorised override.” Requirements should be classified as: - mandatory regulatory or control requirements;
- essential operational requirements;
- desirable improvement requirements;
- future or optional capabilities.
Requirements should include acceptance criteria, data needs, user roles, performance expectations, reporting needs, interfaces and audit requirements. Stakeholders should include procurement, stores, planning, quality, finance, production, IT, internal audit, suppliers and representative end users. 3.2 Evaluation criteria and weighted scoringA weighted decision matrix makes assumptions visible. For criterion i, let wi be its weight and ri the alternative’s score. If weights sum to 1, the total score is: S = ∑[i=1 to m] wi ri The method assumes criteria are sufficiently defined, scores use a consistent scale and weights reflect decision priorities. It should not disguise a “must-have” failure: an alternative that fails a mandatory legal or technical requirement should normally be eliminated, regardless of its total score. | Criterion | Illustrative weight | Evidence to examine |
|---|
| Functional fit | 25% | Demonstrated scenarios and reference sites | | Total cost of ownership | 15% | Five- to ten-year cost model | | Integration and data capability | 15% | APIs, middleware, security and data model | | Usability and adoption | 10% | Role-based demonstrations and user testing | | Vendor viability and support | 10% | Financial strength, roadmap and service levels | | Implementation risk | 15% | Delivery method, resources and dependencies | | Scalability and analytics | 10% | Sites, volumes, reporting and future growth |
Demonstrations should use the organisation’s scenarios and data, not only scripted vendor presentations. Reference checks should investigate actual implementation duration, post-go-live support, customisation burden, upgrade experience and realised benefits. 3.3 Total cost of ownership and sourcing choicesCloud ERP may reduce infrastructure responsibility and accelerate upgrades, but it introduces subscription dependence, data-residency questions, connectivity requirements and less control over upgrade timing. On-premise systems may offer greater control but require substantial infrastructure, cybersecurity and specialist support. Best-of-breed systems can provide deep functionality but increase integration and master-data complexity. No sourcing model removes governance responsibilities. 4. Process Mapping and Fit-Gap Analysis4.1 Process mappingProcess mapping documents how work is actually performed, not merely how policy says it should be performed. A useful map identifies events, activities, decisions, roles, documents, systems, controls, data objects, exceptions and performance measures. Common materials processes include procure-to-pay, plan-to-replenish, inventory adjustment, quality inspection, warehouse receipt and return-to-supplier. The analysis should begin with “as-is” processes, including workarounds and informal spreadsheets. The team should then design “to-be” processes that remove unnecessary activities and clarify accountability. Process maps may use flowcharts, swim lanes or BPMN notation. The method matters less than consistent symbols, clear ownership and validation by process participants. 4.2 Fit-gap analysisFit-gap analysis compares requirements and desired processes with standard ERP capability. Each requirement should be classified, for example, as: - Fit: standard functionality meets the requirement.
- Configuration: the requirement can be met through supported settings.
- Extension or integration: additional governed functionality is required without changing the core product.
- Customisation: source-code or core modification is required.
- Gap or rejection: the requirement cannot be justified or supported acceptably.
The preferred hierarchy is usually: adopt standard process; configure; use a controlled extension or integration; customise only with strong justification. Customisation may be warranted for legal obligations, genuine competitive differentiation or critical operational needs. It should not merely preserve inefficient historical practices. Each gap should have an owner, priority, cost estimate, risk rating, decision date and acceptance criterion. A “gap register” is more useful than a narrative report because it supports governance and prevents unresolved issues from disappearing into design documents. 5. Configuration, Integration and Data DesignConfiguration changes parameters within the intended ERP design—for example, organisational units, purchasing tolerances, approval rules, replenishment methods, valuation settings, calendars, units of measure, storage locations and user roles. Configuration should be documented, transported through controlled environments and approved by business owners. Integration connects ERP with systems such as product lifecycle management, warehouse management, transport management, supplier portals, e-commerce platforms, banks, tax systems and manufacturing execution systems. Interface design must specify ownership, frequency, message structure, error handling, reconciliation, security and recovery. An interface that transfers data successfully but cannot identify or correct failed transactions is not operationally complete. Security design should apply least privilege and segregation of duties. For example, the ability to create a supplier, approve a purchase order and release payment should not be concentrated in one role without compensating controls. Access should be reviewed periodically, especially after role changes and implementation waves. Master-data governanceMaster data includes materials, suppliers, customers, bills of material, locations, units of measure, lead times, pricing conditions and planning parameters. Governance should define data owners, naming standards, approval workflows, duplicate controls, validity rules and periodic quality measures. Transaction processing cannot compensate for poor master data. Useful data-quality dimensions include completeness, validity, uniqueness, consistency, timeliness and accuracy. A material record may be complete but invalid if its unit of measure is inconsistent with purchasing practice. Data owners should distinguish authoritative sources from replicated copies and define how changes are synchronised. 6. Data MigrationMigration is a business-quality activity, not a clerical upload. The typical sequence is extract, profile, cleanse, transform, validate, load, reconcile and approve. Historical data need not all be migrated. Organisations should decide which open transactions, balances, master records and selected history are necessary for legal, operational and analytical purposes. A migration strategy should specify: - source-to-target field mapping;
- transformation and conversion rules;
- treatment of duplicates and inactive records;
- opening inventory and financial-balance controls;
- batch, serial and expiry requirements;
- reconciliation totals;
- data owners and sign-offs;
- mock-load cycles and defect resolution.
For inventory, reconciliation should compare quantities and values by relevant dimensions such as material, site, location, batch and status. Differences must be investigated rather than absorbed as unexplained opening adjustments. 7. Testing and Quality AssuranceTesting should be risk-based and progressive. Unit testing verifies individual configurations or developments. System integration testing verifies end-to-end interactions. Data migration testing verifies converted data. User acceptance testing determines whether business users can perform approved processes under realistic conditions. Performance, security, disaster recovery and regulatory testing may also be necessary. A comprehensive scenario should follow a business chain, such as: demand signal → requisition → approval → purchase order → supplier confirmation → goods receipt → quality inspection → put-away → invoice match → payment and reporting. Negative and exception scenarios are essential: partial delivery, over-delivery, blocked stock, duplicate invoice, supplier change, failed interface and emergency purchase. Test management should include traceability from requirement to scenario, expected result, evidence, defect severity, retest and business approval. “Testing complete” means defined exit criteria have been met, not that every possible combination has been executed. 8. Cutover and Go-LiveCutover is the controlled transition from the old operating environment to the new one. A cutover plan should contain a sequenced schedule, named owners, dependencies, communication points, decision gates, rollback criteria, support contacts and contingency actions. Typical activities include freezing selected master-data changes, completing final transaction processing, extracting and reconciling data, loading opening balances, validating interfaces, confirming user access, checking printers and devices, communicating operating instructions and obtaining go/no-go approval. Big-bang deployment may shorten the coexistence period but concentrates risk. Phased deployment can reduce exposure and allow learning, but creates temporary interfaces, duplicated processes and possible design inconsistency. A pilot may be suitable where sites are sufficiently representative and lessons can be transferred. Go-live should be treated as the beginning of stabilisation, not the end of implementation. A hypercare period should monitor incidents, data quality, transaction backlogs, user questions, supplier impacts and operational performance. A formal rollback may be difficult after live transactions begin, so rollback decisions must be defined before go-live. 9. Training and Change ManagementTraining should be role-based, process-based and practice-oriented. A warehouse operator needs different instruction from a buyer, planner, data steward or financial controller. Training should explain not only which buttons to press but why controls and new responsibilities matter. Change management addresses awareness, willingness, capability and reinforcement. Important interventions include stakeholder analysis, leadership sponsorship, process-owner networks, communication, super users, simulations, job aids, floor support and feedback loops. Resistance is often rational: users may fear loss of autonomy, increased workload, poor system usability or performance measurement. Treating resistance as misconduct can conceal design defects and damage adoption. Readiness should be assessed using evidence such as training completion, proficiency tests, data quality, process rehearsals, access readiness, support capacity and stakeholder confidence. Adoption metrics after go-live should examine actual behaviour, including use of offline spreadsheets, bypassed approvals, manual adjustments and unresolved errors. 10. Benefits Realisation and Performance ControlBenefits realisation converts the business case into measurable operational outcomes. Each benefit should have a baseline, target, owner, measurement method, timing and dependency. Examples include inventory days, stockout frequency, purchase-order cycle time, invoice exception rate, supplier on-time delivery, forecast bias, data completeness and manual touches per transaction. A benefit should not be attributed to ERP merely because it occurs after go-live. External demand changes, supplier renegotiation, network redesign or staffing changes may also affect performance. Benefits reviews should therefore document assumptions and causal mechanisms. For example, inventory days of supply can be expressed as: Inventory Days = Average Inventory ÷ Cost of Goods Sold × Number of Days Average inventory and cost of goods sold must use consistent valuation and the same time period; the number of days may be 365 or the relevant accounting-period convention. This measure is useful for trend analysis but should not be minimised blindly, because insufficient inventory can increase stockouts and operational risk. Benefits governance should continue after stabilisation. Process owners should review whether controls operate, users follow standard processes, data remain accurate and further improvement is justified. Continuous improvement may use release governance, process mining, root-cause analysis and controlled experimentation. 11. Governance, Risk and Ethical ResponsibilitiesERP programmes require layered governance: executive sponsorship for strategic decisions, a steering committee for scope and risk, a programme office for delivery control, process owners for design authority, data owners for information quality and an architecture/security function for technical integrity. Major risks include scope expansion, unrealistic timelines, vendor dependency, inadequate internal capacity, poor data, weak testing, integration failure, cybersecurity incidents, uncontrolled customisation and insufficient adoption. A risk register should record probability, impact, owner, response and trigger. Risk responses may include avoidance, reduction, transfer or acceptance, but acceptance requires explicit authority. Ethical and regulatory responsibilities include privacy protection, lawful processing, retention, access control, auditability, non-discrimination in automated decisions and transparency concerning analytics. Supplier and employee data should not be exposed merely because an ERP makes aggregation convenient. Automated recommendations must be reviewed for biased data, inappropriate incentives and unexplained outcomes. AI-enabled ERP functions—such as demand sensing, anomaly detection, conversational search and supplier-risk prediction—can improve decision support, but they do not eliminate data governance or managerial accountability. Users should understand whether outputs are predictions, rules or generated explanations. Human review is especially important for sanctions, supplier exclusion, safety stock changes, quality release and financial postings. 12. Contemporary Implementation ApproachesModern ERP programmes increasingly use cloud platforms, application programming interfaces, process mining, low-code extensions and agile delivery. Agile methods can provide frequent demonstrations and early feedback, but they do not remove the need for architecture, controls, documentation or integrated testing. “Agile” is not a justification for unclear scope or permanent design instability. Process mining can discover actual event sequences from transaction logs and identify rework, bottlenecks and compliance deviations. Its conclusions depend on event-log completeness, consistent identifiers and correct interpretation of exceptional cases. Digital twins and advanced analytics may support scenario analysis, but model outputs remain dependent on assumptions and data quality. Composable architectures allow organisations to combine a core ERP with specialised applications. Their benefits include flexibility and functional depth; their risks include duplicated master data, complex integration, fragmented user experience and unclear accountability. The appropriate architecture is one that can be governed over its full lifecycle, not merely one that appears technically elegant. Illustrative Case: Northstar Components Ltd.BackgroundNorthstar Components, a fictional mid-sized manufacturer, operates four plants and seven warehouses. It uses separate purchasing, warehouse and finance applications. Buyers maintain local spreadsheets, material codes are duplicated and inventory status is not consistently visible across sites. ProblemThe company reports frequent emergency purchases, excess slow-moving stock, delayed month-end reconciliation and weak batch traceability. Senior management proposes a cloud ERP implementation with a twelve-month deadline. The initial vendor proposal recommends extensive customisation to preserve local approval practices. AnalysisA cross-functional team maps procure-to-pay, plan-to-replenish and batch-receipt processes. It finds that local approval differences are not legally required and that many “special” material codes represent the same item in different units of measure. A data profile identifies 18% duplicate supplier records and 11% of material records lacking reliable lead times. The business case shows that the strongest benefits depend on master-data cleansing and common purchasing policies, not software alone. The selection team defines mandatory requirements for batch traceability, quality status, multi-site stock visibility, approval segregation and integration with production scheduling. Vendors demonstrate Northstar scenarios using sample data. The preferred solution meets most requirements through standard configuration; two interfaces and one controlled extension are approved. Custom approval screens are rejected because they preserve unnecessary variation. Approach and solutionNorthstar establishes data owners, a common material-naming convention and a supplier-creation workflow. It migrates active materials, open purchase orders, on-hand balances and legally required history after two mock conversions. Testing includes partial receipts, blocked batches, inter-site transfers, returns and invoice exceptions. A pilot begins at one representative plant, supported by trained super users. The cutover plan freezes selected master-data changes, reconciles inventory by site and batch, validates user roles and provides a weekend command centre. Benefits are assigned to the procurement, inventory and finance process owners. Baselines are recorded before go-live. OutcomeAfter stabilisation, Northstar reports improved stock visibility, fewer duplicate suppliers and faster invoice exception resolution. However, the first benefits review finds that planners continue using spreadsheets because lead times and replenishment parameters were not maintained. The programme therefore adds a data-governance routine and monthly parameter review rather than treating the issue as a software defect. Learning pointsThe case demonstrates that ERP value depends on process ownership, data discipline and behavioural adoption. Standardisation should challenge unjustified variation, while genuine operational and regulatory needs should remain visible. Benefits management must continue after technical go-live. Challenges and LimitationsERP implementation methods cannot remove uncertainty. Benefits estimates may be optimistic; process maps may reflect politically acceptable rather than actual practice; weighted scoring may embed managerial bias; reference sites may not be comparable; and standard processes may not fit unusual regulatory or manufacturing contexts. Cloud releases can alter functionality faster than governance cycles. Measurement may also create dysfunctional behaviour—for example, reducing inventory without protecting service levels. Accordingly, implementation should use explicit assumptions, independent challenge, staged investment, traceable decisions and post-implementation review. The goal is not a perfect forecast but a controlled learning process in which risks are visible and decisions are reversible where possible. Chapter SummaryERP selection and implementation in materials management are strategic transformation activities. A robust business case links operational problems to strategic objectives, evaluates costs and benefits, and tests uncertainty. Selection should use clear requirements, realistic demonstrations, total-cost analysis and structured risk assessment. Process mapping and fit-gap analysis distinguish standard capability from configuration, extension, integration and unjustified customisation. Successful implementation depends on governed configuration, reliable master data, controlled migration, end-to-end testing, disciplined cutover, role-based training and active change management. Post-go-live benefits must be measured against baselines and assigned to accountable process owners. Security, privacy, segregation of duties, auditability and responsible use of AI are essential. The enduring lesson is that ERP creates value only when technology, processes, data and human behaviour are managed as one system. Key TermsERP: An integrated system supporting cross-functional organisational processes and data. Business case: A structured justification for investment, including costs, benefits, risks and alternatives. Total cost of ownership: The full lifecycle cost of acquiring, implementing, operating, supporting and upgrading a solution. Requirements engineering: The systematic identification, analysis, documentation and validation of business and technical needs. Weighted decision matrix: A method that combines criterion weights and alternative scores to support structured comparison. Process mapping: Visual or textual representation of activities, decisions, roles, information and controls in a process. Fit-gap analysis: Comparison of required capability with standard system capability to identify fit and unresolved needs. Configuration: Adjustment of supported system settings without changing core source code. Extension: Additional functionality designed to complement the core ERP while preserving upgradeability. Customisation: Modification of core software beyond standard supported configuration. Master data: Relatively stable data objects such as materials, suppliers, locations and planning parameters. Data migration: Extraction, transformation, validation and loading of data into a new system. System integration testing: Testing of interactions among system components and connected applications. User acceptance testing: Business-user assessment of whether the solution supports approved requirements and processes. Cutover: Controlled transition from the legacy operating environment to the new ERP. Hypercare: Intensive support and monitoring immediately after go-live. Change management: Structured activity to prepare, equip and reinforce people during organisational change. Benefits realisation: Governance of expected outcomes from investment through measurement and improvement. Segregation of duties: Control that prevents incompatible responsibilities from being concentrated in one person or role. Process mining: Analysis of event logs to discover and evaluate actual process execution. Review QuestionsShort Answer Questions- Why is ERP implementation considered a socio-technical transformation?
- Distinguish configuration, extension and customisation.
- What is the purpose of fit-gap analysis?
- Identify four important data-quality dimensions.
- Why should benefits be assigned to process owners?
Long Answer Questions- Explain how an organisation should construct and evaluate an ERP business case.
- Discuss the advantages and limitations of weighted scoring in ERP selection.
- Describe a complete approach to master-data migration for materials management.
- Explain how testing, cutover and hypercare should be integrated into a go-live strategy.
- Critically evaluate the relationship between standardisation and customisation in ERP design.
Analytical / Application Questions- An organisation has a high-scoring ERP alternative that fails a mandatory batch-traceability requirement. Recommend a decision approach and justify it.
- A company achieves technical go-live, but planners continue using spreadsheets and inventory accuracy declines. Diagnose possible causes and propose a benefits-realisation response.
- Design a fit-gap and governance approach for a multi-site manufacturer deciding whether to retain local purchasing approvals or adopt a common process.
Multiple Choice Questions with AnswersQuestion 1Which statement best describes the strategic nature of ERP implementation in materials management? A. It is primarily the installation of servers and software. B. It integrates technology, processes, data, controls and organisational behaviour. C. It is limited to automating purchase-order creation. D. It replaces the need for process ownership. Correct Answer: B. It integrates technology, processes, data, controls and organisational behaviour. Question 2In a weighted decision matrix, what does the weight assigned to a criterion represent? A. The vendor’s implementation duration B. The number of users requiring access C. The relative importance of that criterion in the decision D. The probability that the criterion will fail Correct Answer: C. The relative importance of that criterion in the decision Question 3Which requirement is most likely to be met through configuration rather than customisation? A. Changing a supported approval threshold B. Rewriting the ERP database engine C. Replacing the core inventory valuation algorithm with an unrelated design D. Creating an external application that bypasses all controls Correct Answer: A. Changing a supported approval threshold Question 4What is the preferred general hierarchy when addressing an ERP process gap? A. Customise first, then consider standardisation B. Reject every requirement that is not already available C. Adopt standard process where appropriate, then configure or use governed extensions D. Maintain the legacy spreadsheet as the primary system Correct Answer: C. Adopt standard process where appropriate, then configure or use governed extensions Question 5Which activity is central to a controlled data-migration process? A. Loading data without reconciliation to save time B. Extracting, cleansing, transforming, validating and reconciling data C. Migrating every historical record regardless of purpose D. Allowing each user to define independent material codes Correct Answer: B. Extracting, cleansing, transforming, validating and reconciling data Question 6Which test most directly evaluates whether business users can perform approved end-to-end processes? A. Unit testing B. User acceptance testing C. Compilation testing D. Network cabling inspection Correct Answer: B. User acceptance testing Question 7What is the primary purpose of a cutover plan? A. To define the organisation’s long-term marketing strategy B. To sequence and control the transition to the new operating environment C. To eliminate the need for data validation D. To replace post-go-live support Correct Answer: B. To sequence and control the transition to the new operating environment Question 8Which practice best supports effective ERP change management? A. Training all employees with identical generic content B. Treating resistance as evidence of employee misconduct C. Using role-based training, super users, communication and feedback D. Restricting users from testing the system before go-live Correct Answer: C. Using role-based training, super users, communication and feedback Question 9If average inventory is 2,000,000 currency units, annual cost of goods sold is 12,000,000 currency units and a 365-day convention is used, what are inventory days? A. 30.4 days B. 60.8 days C. 182.5 days D. 2,190 days Correct Answer: B. 60.8 days Question 10Which control most directly supports segregation of duties in procure-to-pay? A. Allowing one employee to create suppliers, approve orders and release payment B. Separating supplier creation, purchase approval and payment responsibilities C. Removing audit logs to protect confidentiality D. Permitting shared user accounts for faster processing Correct Answer: B. Separating supplier creation, purchase approval and payment responsibilities
|