Cost Accounting

Chapter 13
Strategic and Contemporary Cost Management

Bachelors Program in Accounting and Finance
Cost Accounting   •   Bachelor

Strategic and Contemporary Cost Management

Introduction

Traditional cost accounting emphasizes product costing, inventory valuation and variance control. Strategic cost management extends the accountant’s role beyond recording historical expenditure. It uses cost information to influence product design, process improvement, supply-chain relationships, quality, capacity and long-term competitive position.

A strategically useful cost system asks not only, “What did the product cost?” but also:

  • What may the product cost if the required profit is to be earned?
  • Which product features create customer value?
  • When are costs committed, even if they are incurred later?
  • Where in the value chain are delays, defects and waste created?
  • Which resource constrains organizational performance?
  • How can costs be reduced without damaging quality, safety or stakeholder trust?

This chapter integrates target costing, life-cycle costing, kaizen costing, value engineering, value-chain analysis, total quality costing, lean accounting, just-in-time (JIT) systems and the theory of constraints (TOC). These methods are complementary rather than interchangeable: each addresses a different stage or dimension of strategic cost management.

Learning Objectives

After studying this chapter, students should be able to:

  1. Explain the strategic role of contemporary cost management.
  2. Calculate target costs and identify cost-reduction gaps.
  3. evaluate costs over a product’s complete life cycle.
  4. Distinguish design-stage value engineering from production-stage kaizen costing.
  5. Analyze activities across an organizational value chain.
  6. classify and evaluate quality-related costs.
  7. Explain the operational and accounting implications of lean and JIT systems.
  8. Apply throughput accounting and the theory of constraints.
  9. Integrate contemporary cost methods in managerial decisions.
  10. Assess implementation, governance, technological and ethical issues.

1. The Strategic Cost Management Perspective

Strategic cost management is the deliberate use of cost information to formulate, communicate and implement business strategy. Its focus is wider than internal cost control because costs are affected by customers, competitors, suppliers, technology, regulation and product architecture.

Three principles distinguish it from a purely traditional approach:

  1. External orientation: Prices and required functionality are often established by the market rather than by adding a profit margin to internal cost.
  2. Long-term orientation: Decisions made during research and design may determine costs incurred years later.
  3. Process orientation: Costs are managed by improving activities and workflows, not merely by reducing departmental budgets.

Strategic cost management must remain consistent with the organization’s competitive strategy. A cost-leadership strategy emphasizes efficiency, standardization and waste removal. A differentiation strategy may justify additional costs for innovation, reliability, customization or service. Cost reduction is strategically desirable only when it preserves or improves customer value.

2. Target Costing

2.1 Market-Based Cost Planning

Target costing is a market-led method used mainly during product planning and design. Rather than calculating cost and then adding a profit margin, management begins with an expected competitive selling price and deducts the required profit.

Target cost = Target selling price − Target profit

For a product with target selling price P, target profit π and target cost CT:

CT = P − π

If profit is specified as a proportion m of sales revenue:

CT = P(1 − m)

Here, m is a target return-on-sales rate. This formula must not be used when the profit percentage is defined as a markup on cost. If the desired markup on cost is k, the appropriate relationship is P = CT(1+k), so CT = P ÷ (1+k).

2.2 Worked Example: Target Cost Gap

A company expects to sell a smart meter for $500. Management requires profit equal to 18% of sales revenue.

Target profit = $500 × 18% = $90
Target cost = $500 − $90 = $410

If the current estimated cost is $438, the target cost gap is:

Target cost gap = $438 − $410 = $28 per unit

The $28 gap is not automatically resolved through arbitrary budget cuts. Cross-functional teams must redesign the product or process while maintaining required functionality, quality, safety and regulatory compliance.

2.3 Target Costing Process

A disciplined target-costing process normally involves:

  1. Research customer needs and competitor offerings.
  2. Establish the market-based selling price.
  3. determine the required profit consistent with strategy and capital expectations.
  4. derive the allowable target cost.
  5. estimate the product’s current design cost.
  6. identify the target cost gap.
  7. use value engineering and supplier collaboration to close the gap.
  8. authorize production only when cost, quality and functionality requirements are acceptably balanced.

Target costs may be decomposed into component, subsystem or functional targets. Suppliers should be involved early because purchased components frequently represent a large proportion of total product cost.

3. Value Engineering and Functional Analysis

Value engineering is a systematic, multidisciplinary method for achieving required functions at the lowest total cost without unacceptable reductions in quality, reliability, safety or customer satisfaction. It is particularly effective before production begins, when design flexibility is greatest.

A basic value relationship is:

Value = Required functionality ÷ Life-cycle cost

This expression is a decision concept rather than a financial accounting identity. Functionality must be evaluated through measurable performance, customer preference or engineering requirements. Value rises when required functionality improves without a proportionate cost increase, or when cost falls without impairing required functionality.

A value-engineering team may ask:

  • Is the function necessary to the customer?
  • Can multiple components be combined?
  • Can a standard part replace a customized part?
  • Can assembly time or movement be reduced?
  • Would a higher-cost component reduce warranty or maintenance costs?
  • Can material use be reduced without compromising safety?

A feature with high cost but low customer importance is a strong redesign candidate. However, legal compliance and safety functions cannot be eliminated merely because customers do not explicitly value them.

4. Life-Cycle Costing

4.1 The Product Life-Cycle Perspective

Life-cycle costing accumulates and manages costs over all stages of a product’s economic life. Depending on the decision, the perspective may include:

  • research and development;
  • product and process design;
  • supplier qualification and tooling;
  • manufacturing;
  • marketing and distribution;
  • operation and customer support;
  • warranty and repair;
  • decommissioning, recycling and disposal.

The method is strategically important because a substantial proportion of manufacturing and support costs may be committed during design, even though cash expenditure occurs later. A product’s architecture influences materials, labor time, defect rates, maintenance and disposal obligations.

4.2 Undiscounted and Discounted Life-Cycle Cost

For planning purposes, an undiscounted life-cycle cost may be expressed as:

LCC = ∑t=0n Ct

where Ct is the expected cost incurred in period t, n is the final period, and all costs are measured in a consistent currency basis.

When timing is material, costs should be discounted:

PV(LCC) = C0 + ∑t=1n Ct ÷ (1+r)t

Here, r is the appropriate discount rate per period. The periods used for r must match those used for t. Nominal cash flows require a nominal discount rate incorporating consistent inflation assumptions; real cash flows require a real rate.

4.3 Worked Example: Present Value of Life-Cycle Cost

A product requires an immediate development cost of $600,000. Expected support and disposal costs are $120,000 at the end of year 1, $100,000 at the end of year 2 and $80,000 at the end of year 3. At an annual discount rate of 8%:

PV(LCC) = $600,000 + $120,000÷1.08 + $100,000÷1.082 + $80,000÷1.083
PV(LCC) = $600,000 + $111,111 + $85,734 + $63,507 = $860,352

Rounded to the nearest dollar, the present value of expected life-cycle cost is $860,352.

Life-cycle estimates are uncertain. Sensitivity analysis should therefore test changes in sales volume, warranty claims, useful life, inflation, discount rates and disposal obligations.

5. Kaizen Costing and Continuous Improvement

Kaizen means continuous, incremental improvement. Kaizen costing applies this philosophy to cost reduction during the manufacturing and delivery stage, after the principal product design has been established.

This differs from target costing:

DimensionTarget costingKaizen costing
Primary stagePlanning and designProduction and delivery
Main objectiveAchieve allowable product costContinuously reduce actual cost
Typical changesProduct or process redesignSmall recurring process improvements
OrientationMarket and customerOperational learning and waste removal
ParticipantsDesigners, engineers, marketers, suppliers, accountantsProduction teams, operators, supervisors, accountants

If a kaizen reduction rate q is applied to a cost base CB, the planning target is:

Planned cost reduction = CB × q

Suppose a quarterly conversion-cost base is $2,400,000 and management establishes a feasible 1.5% improvement target:

Planned reduction = $2,400,000 × 1.5% = $36,000

The new planning benchmark is $2,364,000, assuming comparable volume and operating conditions. The target should be normalized for changes in product mix, input prices and production volume; otherwise employees may be judged on factors outside their control.

Kaizen methods include setup-time reduction, standard-work improvement, preventive maintenance, mistake-proofing, workplace organization and employee suggestion systems. Continuous improvement should not mean continuous work intensification. Sustainable kaizen removes waste rather than shifting unreasonable pressure to employees or suppliers.

6. Value-Chain Analysis

A value chain is the linked set of activities through which an organization and its partners create and deliver value. A typical chain extends from research and supplier development through design, operations, distribution, customer service and end-of-life recovery.

Strategic value chain Research &design Suppliernetwork Operations Distribution &marketing Customerservice Recovery &disposal Cost, quality, time and customer information flow across organizational boundaries
Strategic value chain from research through end-of-life recovery
Figure: Strategic value chain from research through end-of-life recovery

Figure: Activities and information flows across a strategic value chain.

Value-chain analysis identifies:

  • value-creating and non-value-creating activities;
  • cost drivers and dependencies between activities;
  • supplier and customer linkages;
  • opportunities for coordination, differentiation or cost reduction;
  • environmental and social effects across organizational boundaries.

A cost reduction in one activity may increase total cost elsewhere. For example, purchasing cheaper components may reduce procurement cost but increase inspection, rework, warranty claims and reputational risk. Strategic analysis therefore evaluates total system consequences rather than isolated departmental savings.

7. Total Quality Costing

The cost of quality is the cost of preventing, detecting and correcting failures to meet requirements. It is commonly classified into four categories:

CategoryMeaningExamples
PreventionAvoiding defects before they occurTraining, process design, supplier certification
AppraisalAssessing conformityInspection, testing, quality audits
Internal failureDefects found before deliveryScrap, rework, retesting, downtime
External failureDefects found after deliveryWarranty, recalls, complaints, lost goodwill
Total quality cost = Prevention + Appraisal + Internal failure + External failure

All terms must cover the same accounting period and organizational scope. The formula is classificatory: it does not imply that every quality-related consequence is easily measurable. Lost customers, reputational damage and safety consequences may substantially exceed recorded accounting costs.

Worked Quality-Cost Report

A manufacturer reports annual prevention costs of $180,000, appraisal costs of $240,000, internal failure costs of $310,000 and external failure costs of $470,000.

Total quality cost = $180,000 + $240,000 + $310,000 + $470,000 = $1,200,000

Conformance costs are prevention plus appraisal, or $420,000. Non-conformance costs are internal plus external failure, or $780,000. The large failure component suggests that well-designed prevention investment could reduce total cost. Nevertheless, management should assess causal evidence rather than assume that every additional dollar of prevention creates an equal reduction in failure cost.

Modern quality management emphasizes designing quality into processes. Inspection alone identifies defects after resources have already been consumed; it cannot substitute for capable processes, reliable suppliers and appropriate product design.

8. Lean Systems, Just-in-Time and Lean Accounting

8.1 Lean Management

Lean management seeks to create customer value using fewer resources by improving flow and eliminating waste. Common forms of waste include overproduction, waiting, unnecessary transport, excess processing, inventory, unnecessary motion, defects and unused employee capability.

A value stream includes all activities required to deliver a product or service family. Lean improvement favors end-to-end flow over isolated departmental efficiency. Maximizing machine utilization can be counterproductive if it creates excess inventory that customers do not require.

8.2 Just-in-Time Systems

JIT seeks to obtain or produce goods only when needed, in the required quantity and at the required quality. A pull system authorizes production in response to downstream demand rather than forecasts alone.

Potential benefits include:

  • lower inventory holding and obsolescence costs;
  • shorter lead times;
  • earlier exposure of defects and bottlenecks;
  • reduced storage and material movement;
  • improved responsiveness.

JIT also increases sensitivity to unreliable suppliers, transport disruptions, demand volatility and geopolitical events. Resilient JIT therefore requires dependable suppliers, visible demand information, short setup times, quality at source and deliberate risk assessment. Strategic safety stocks may be justified where interruption consequences are severe.

For a simple inventory account:

Ending inventory = Beginning inventory + Additions − Inventory transferred or sold

All amounts must use the same valuation basis and period. For example, beginning inventory of $50,000 plus additions of $120,000 less $130,000 transferred or sold gives ending inventory of $40,000.

8.3 Lean Accounting

Traditional systems may reward large production batches by allocating fixed manufacturing overhead across more units and recording unsold output as inventory. Such signals can conflict with lean objectives.

Lean accounting aims to provide understandable, timely information aligned with value streams. Practices may include:

  • value-stream income statements;
  • direct assignment of costs where practical;
  • reduced reliance on complex allocations;
  • operational measures of lead time, first-pass yield and on-time delivery;
  • plain-language performance reports;
  • simplified transaction processing after controls become reliable.

A simplified value-stream profit measure is:

Value-stream profit = Value-stream revenue − Directly attributable value-stream costs

This format is useful for internal decisions but does not remove the need to comply with applicable financial reporting requirements for inventory measurement and external statements. Shared facility and corporate costs must also be considered in long-term strategic decisions, even when they are not allocated to weekly value-stream reports.

9. Theory of Constraints and Throughput Accounting

The theory of constraints views system performance as limited by at least one constraint. Improving a non-constraint may create excess work-in-process without increasing total output.

The five focusing steps are:

  1. Identify the system constraint.
  2. Exploit the constraint using existing resources effectively.
  3. Subordinate other activities to the constraint’s requirements.
  4. Elevate the constraint by adding or improving capacity when justified.
  5. Repeat the process when the constraint moves.

9.1 Throughput Measures

In short-term throughput accounting:

Throughput contribution per unit = Selling price per unit − Totally variable cost per unit

Totally variable cost usually consists principally of direct material in the short run, but its definition must reflect costs that genuinely vary with each additional unit in the decision context. It should not automatically be equated with all conventional variable costs.

Where a scarce resource constrains production:

Throughput per constraint unit = Throughput contribution per unit ÷ Constraint units required per product

Products should generally be prioritized by throughput per unit of the binding constraint, subject to demand, contractual, quality and strategic considerations.

9.2 Worked Product-Mix Example

Product A sells for $120, has totally variable cost of $45 and requires 15 bottleneck minutes. Product B sells for $155, has totally variable cost of $55 and requires 25 bottleneck minutes.

For Product A:

Throughput per unit = $120 − $45 = $75
Throughput per bottleneck minute = $75 ÷ 15 = $5.00

For Product B:

Throughput per unit = $155 − $55 = $100
Throughput per bottleneck minute = $100 ÷ 25 = $4.00

If bottleneck time is the only binding constraint and demand exists for both products, Product A should be prioritized even though Product B provides more throughput per finished unit.

At the organization level, a common short-run TOC representation is:

Net profit = Total throughput − Operating expense
Return on investment = (Total throughput − Operating expense) ÷ Investment

Investment includes funds tied up in inventory and productive assets under the adopted TOC definition. These managerial measures do not replace financial reporting profit or statutory asset measurement.

10. Integrating the Methods

The methods can be aligned across the product and process life cycle:

Strategic questionPrincipal method
What may the product cost?Target costing
How can required functions be delivered economically?Value engineering
What costs arise from conception to disposal?Life-cycle costing
How can current operations improve continuously?Kaizen costing
Where is value created across organizations?Value-chain analysis
What is the economic impact of quality?Total quality costing
How can waste and inventory be reduced?Lean and JIT
Which resource limits total performance?Theory of constraints

Integration prevents local optimization. A target-costing team should consider lifetime warranty and disposal costs. A lean team should not accelerate production beyond a constraint. A purchasing department should not select low-price suppliers without considering quality, lead time, emissions and supply continuity.

11. Illustrative Case: NovaHome Energy Controller

Background

NovaHome Ltd., a fictional electronics company, plans to launch a residential energy controller. Forecast lifetime sales are 100,000 units at $600 each. Management requires profit equal to 15% of sales revenue.

Problem

The current estimated life-cycle cost is:

Cost categoryForecast cost
Research and design$4,000,000
Production$43,000,000
Distribution$3,000,000
Warranty and support$2,500,000
Total$52,500,000

Analysis

Forecast revenue is:

100,000 × $600 = $60,000,000

Required profit is:

$60,000,000 × 15% = $9,000,000

Therefore, allowable life-cycle cost is:

$60,000,000 − $9,000,000 = $51,000,000

The target cost gap is:

$52,500,000 − $51,000,000 = $1,500,000

Approach and Solution

A value-engineering team proposes a more reliable modular component. It increases component expenditure by $300,000 but reduces assembly cost by $1,100,000 and expected warranty cost by $600,000.

Net cost reduction is:

$1,100,000 + $600,000 − $300,000 = $1,400,000

Revised production cost is $42,200,000, revised warranty cost is $1,900,000, and total expected life-cycle cost becomes $51,100,000. A remaining gap of $100,000 exists.

NovaHome then sets a first-year kaizen target equal to 0.25% of revised production cost:

$42,200,000 × 0.25% = $105,500

If achieved without reducing required functionality, total expected cost falls to $50,994,500, which is $5,500 below the allowable cost.

Outcome

The board conditionally approves the product, subject to supplier validation, safety testing and monthly tracking of quality, bottleneck utilization and kaizen savings. The company avoids a simplistic component-price reduction that could have increased failure costs.

Learning Points

  • Market requirements determine the allowable cost.
  • Value engineering evaluates system-wide cost and functionality.
  • Life-cycle costing reveals warranty effects that unit manufacturing cost may omit.
  • Kaizen closes a small remaining gap during production.
  • Savings should be validated rather than treated as guaranteed forecasts.

12. Implementation Challenges and Limitations

Contemporary cost methods face several practical limitations:

  • Forecast uncertainty: Selling prices, demand, warranty claims and disposal costs may differ from estimates.
  • Measurement difficulty: Customer value, reputation and environmental effects may resist precise monetary measurement.
  • Functional silos: Departments may optimize their own metrics rather than total value.
  • Behavioral resistance: Employees may perceive improvement programs as disguised workforce reduction.
  • Supplier power: Target-cost reductions may be infeasible or unfairly transferred to weaker suppliers.
  • Data quality: Inaccurate routings, defect records or constraint times undermine decisions.
  • Short-term bias: Throughput rankings suitable for current capacity may not support long-term product or market strategy.
  • Accounting conflict: Internal lean reports must be reconciled with external reporting and taxation rules.

Scenario analysis, pilot testing, post-implementation review and cross-functional governance help manage these limitations.

13. Ethics, Governance and Sustainability

Strategic cost management creates pressure to reduce expenditure, which can produce harmful behavior if governance is weak. Managers must not close target-cost gaps by concealing defects, weakening safety, exploiting labor, delaying necessary maintenance or transferring unsustainable demands to suppliers.

Responsible governance should include:

  • independent safety and quality approval;
  • transparent assumptions and sensitivity analysis;
  • supplier labor and environmental standards;
  • traceable authorization of design changes;
  • protection for employees reporting quality concerns;
  • separation of verified savings from speculative savings;
  • life-cycle consideration of emissions, repairability and disposal.

Environmental life-cycle costing may include carbon charges, waste treatment, take-back obligations and remediation. Such costs should be included where relevant, measurable and consistent with the decision horizon.

14. Technology and Contemporary Developments

Enterprise systems, sensors, digital twins and process-mining tools can provide timely data on material flow, machine downtime, quality and constraint utilization. Artificial intelligence can support demand forecasting, predictive maintenance, defect detection and design alternatives.

These tools do not eliminate managerial judgment. Algorithms may optimize an incomplete objective, rely on biased data or recommend cost reductions that conflict with safety and resilience. Effective governance requires data validation, explainability appropriate to the decision, cybersecurity controls, human review and clear accountability.

Contemporary practice increasingly combines cost, resilience and sustainability. Firms are reconsidering extremely fragile JIT networks, designing products for repair and reuse, and extending value-chain analysis to carbon emissions and human-rights risks.

15. Best-Practice Principles

Effective strategic cost management should:

  1. begin with customer value and organizational strategy;
  2. manage costs before they become committed;
  3. use cross-functional teams and early supplier involvement;
  4. evaluate total life-cycle and value-chain consequences;
  5. combine financial and operational measures;
  6. focus improvement on the system constraint;
  7. distinguish genuine waste removal from cost shifting;
  8. validate savings against quality, safety and service outcomes;
  9. use scenario and sensitivity analysis for uncertain estimates;
  10. maintain ethical accountability and reliable data governance.

Chapter Summary

Strategic cost management connects cost analysis with market position, product design, operations and long-term value creation. Target costing derives an allowable cost from market price and required profit, while value engineering redesigns functions and processes to close the target cost gap. Life-cycle costing broadens analysis to costs from research through disposal, including the time value of money when material.

Kaizen costing supports incremental cost reduction during production. Value-chain analysis examines relationships among activities, suppliers and customers, helping management avoid local optimization. Total quality costing classifies prevention, appraisal and failure costs and highlights the economic significance of defects.

Lean systems seek customer value, flow and waste elimination, while JIT reduces inventory through synchronized pull-based operations. Lean accounting provides timely value-stream information but must remain compatible with external reporting. The theory of constraints directs attention to the resource limiting total performance and prioritizes products using throughput per constraint unit. Successful integration requires sound data, cross-functional collaboration, ethical governance, resilience and protection of quality and safety.

Key Terms

Appraisal cost: Expenditure incurred to assess whether products or processes meet requirements.

Constraint: A resource or condition that limits achievement of a system’s objective.

External failure cost: Cost caused by defects discovered after delivery to the customer.

Internal failure cost: Cost caused by defects discovered before delivery.

Just-in-time: A system that obtains or produces items only when they are needed.

Kaizen costing: Continuous, incremental cost improvement during production and delivery.

Lean accounting: Accounting practices designed to support lean operations and value streams.

Lean management: Management philosophy focused on customer value, flow and waste elimination.

Life-cycle costing: Accumulation and management of costs across a product’s complete economic life.

Prevention cost: Cost incurred to prevent defects from occurring.

Pull system: Production system in which downstream demand authorizes upstream activity.

Target cost: Maximum allowable cost consistent with a market price and required profit.

Theory of constraints: Management approach that focuses improvement on the system’s limiting factor.

Throughput contribution: Sales revenue less costs that vary directly with each additional unit, as defined for the decision.

Total quality cost: Sum of prevention, appraisal, internal failure and external failure costs.

Value engineering: Systematic analysis of how required functions can be achieved at the lowest life-cycle cost.

Value chain: Linked activities through which organizations create and deliver value.

Value stream: End-to-end activities required to deliver a product or service family.

Review Questions

Short Answer Questions

  1. Define strategic cost management.
  2. Distinguish a target profit based on sales from a markup based on cost.
  3. What is the difference between target costing and kaizen costing?
  4. Name the four categories of quality cost.
  5. What is a constraint in the theory of constraints?

Long Answer Questions

  1. Explain the target-costing process and the role of cross-functional teams.
  2. Discuss how life-cycle costing can improve product design decisions.
  3. Evaluate the benefits and risks of just-in-time inventory systems.
  4. Explain how lean accounting differs from traditional departmental cost reporting.
  5. Discuss the ethical and governance risks associated with aggressive cost-reduction programs.

Analytical / Application Questions

  1. A product’s market price is $800 and required profit is 22% of sales. Calculate its target cost and identify the cost gap if estimated cost is $650.
  2. Compare two products using throughput per bottleneck hour and explain why throughput per finished unit may give a different ranking.
  3. Design an integrated cost-management plan for a manufacturer experiencing high warranty costs, excess inventory and a production bottleneck.

Multiple Choice Questions with Answers

Question 1

A product has a target selling price of $500 and required profit equal to 20% of sales. What is its target cost?

A. $400

B. $480

C. $600

D. $625

Correct Answer: A. $400

Question 2

Beginning inventory is $50,000, additions are $120,000 and inventory transferred or sold is $130,000. What is ending inventory?

A. $40,000

B. $50,000

C. $60,000

D. $300,000

Correct Answer: A. $40,000

Question 3

Which cost is most clearly included in a comprehensive product life-cycle cost but may occur after production has ended?

A. Past-period corporate tax

B. Product disposal obligation

C. Unrelated head-office renovation

D. Dividend distribution

Correct Answer: B. Product disposal obligation

Question 4

Which activity creates a prevention cost?

A. Reworking defective units

B. Paying customer warranty claims

C. Training employees in quality procedures

D. Inspecting completed units

Correct Answer: C. Training employees in quality procedures

Question 5

Which statement best distinguishes kaizen costing from target costing?

A. Kaizen costing emphasizes incremental improvements during production.

B. Kaizen costing establishes the market selling price.

C. Target costing is used only after a product is discontinued.

D. Target costing ignores required profit.

Correct Answer: A. Kaizen costing emphasizes incremental improvements during production.

Question 6

A design change increases component cost by $30,000, reduces assembly cost by $90,000 and reduces expected warranty cost by $20,000. What is the net life-cycle cost reduction?

A. $40,000

B. $60,000

C. $80,000

D. $140,000

Correct Answer: C. $80,000

Question 7

What is a principal operational risk of an extremely low-inventory JIT system?

A. It necessarily increases product variety.

B. Supply disruptions can stop production quickly.

C. It eliminates the need for supplier quality controls.

D. It guarantees excess safety stock.

Correct Answer: B. Supply disruptions can stop production quickly.

Question 8

Product X has throughput contribution of $84 and requires 12 bottleneck minutes. Product Y has throughput contribution of $96 and requires 16 bottleneck minutes. Which product has the higher throughput per bottleneck minute?

A. Product X at $7 per minute

B. Product X at $8 per minute

C. Product Y at $7 per minute

D. Product Y at $8 per minute

Correct Answer: A. Product X at $7 per minute

Question 9

A value stream reports revenue of $800,000, directly attributable material cost of $300,000, conversion cost of $240,000 and support cost of $60,000. What is value-stream profit?

A. $140,000

B. $200,000

C. $260,000

D. $500,000

Correct Answer: B. $200,000

Question 10

Under the theory of constraints, what should management normally do immediately after identifying the binding constraint?

A. Maximize production at every non-constraint resource

B. Discontinue all products using the constraint

C. Exploit the constraint using existing resources effectively

D. Allocate more fixed overhead to the constraint

Correct Answer: C. Exploit the constraint using existing resources effectively

Cost Accounting
Chapter 13 of 15