Cost Accounting

Chapter 5
Job, Batch and Contract Costing

Bachelors Program in Accounting and Finance
Cost Accounting   •   Bachelor

Job, Batch and Contract Costing

Introduction

Organizations producing customized goods or undertaking identifiable projects require costing systems that trace costs to a specific cost unit. A cost unit may be one job, a batch of identical units, or a long-term contract. These environments differ from continuous, homogeneous production, where process costing averages costs across large volumes of similar output.

Job costing is used for customized assignments such as specialist machinery, audit engagements and repair work. Batch costing applies job-costing principles to a group of identical units. Contract costing is designed for large, usually site-based projects such as buildings, roads and engineering installations.

These systems support pricing, profitability analysis, operational control, customer billing and financial reporting. Their reliability depends on accurate source records, defensible overhead allocation and disciplined recognition of contract profit.

Learning Objectives

After studying this chapter, students should be able to:

  1. distinguish job, batch, contract and process costing;
  2. design and prepare job and batch cost records;
  3. calculate total job cost and customer quotations;
  4. determine an economic batch size under stated assumptions;
  5. prepare a contract account and calculate notional profit;
  6. explain work certified, retention money, escalation clauses and incomplete contracts;
  7. evaluate alternative approaches to contract profit recognition; and
  8. assess operational, ethical and technological implications of customized costing systems.

Choosing an Appropriate Costing System

The costing system should reflect how production is organized and how management needs to measure performance.

SystemCost unitProduction characteristicsTypical applications
Job costingIndividual job or orderCustomized, separately identifiable outputPrinting, consulting, repairs, specialist equipment
Batch costingBatch and units within itIdentical units produced togetherPharmaceuticals, garments, components
Contract costingIndividual contractLarge, long-duration, commonly site-basedConstruction, shipbuilding, infrastructure
Process costingProcess or departmentContinuous production of homogeneous outputChemicals, oil refining, cement, beverages

In process costing, costs are accumulated by process or department for a period and averaged over equivalent units of output. Individual units generally cannot be economically distinguished. Job costing instead traces costs to separately authorized jobs. Thus, a custom-built turbine is suited to job costing, whereas litres of continuously refined fuel are suited to process costing.

A business may combine systems. A construction contractor may use contract costing for each project, job costing for variations, and process costing in a concrete-production subsidiary.

Selection of a costing system Nature of production Identify the cost object Distinct custom orderJob costing Identical groupBatch costing Large site projectContract costing Continuous outputProcess costing Management information Pricing • cost control • profitability • billing • forecasting
Selection of a costing system according to production characteristics
Figure: Selection of a costing system according to production characteristics

Figure: Selection of a costing system according to production characteristics.

Job Costing

The job as a cost object

A job is a separately identifiable customer order, project or production assignment. Each job receives a unique number. Costs are accumulated on a job cost sheet from authorization until completion.

The general job-cost equation is:

CJ = DM + DL + DE + OHA

where:

  • CJ = total job cost, in currency;
  • DM = direct materials;
  • DL = direct labour;
  • DE = direct expenses attributable exclusively to the job; and
  • OHA = absorbed production overhead.

Direct expenses may include specialist equipment hire, design fees or royalties incurred solely for the job. Selling and administrative costs are normally added separately when preparing a quotation rather than included in production cost, unless the organization’s stated cost policy requires otherwise.

Cost records and documentation

A sound job-costing system connects operational activity to accounting records.

RecordPurpose
Job orderAuthorizes work and assigns a job number
Bill of materialsSpecifies required material quantities
Materials requisitionRecords materials issued to a job
Labour time ticketRecords employee hours by job
Direct-expense voucherIdentifies job-specific external or internal expenses
Machine-hour recordMeasures machine use for overhead absorption
Job cost sheetSummarizes all costs and compares them with revenue or budget

Materials returned to stores should be credited to the job. Abnormal waste caused by avoidable error should be separately investigated rather than concealed in ordinary job cost.

Overhead absorption

Indirect production costs cannot normally be traced economically to one job. They are assigned using a predetermined overhead absorption rate:

OAR = BOH ÷ BA

where OAR is the overhead absorption rate, BOH is budgeted production overhead in currency, and BA is budgeted activity measured in labour hours, machine hours, labour cost or another appropriate driver.

Overhead absorbed by a job is:

OHA = OAR × AJ

where AJ is the job’s actual quantity of the selected activity base. Units must be consistent: a rate in dollars per machine-hour must be multiplied by machine-hours.

A labour-hour rate is appropriate where labour effort drives overhead. A machine-hour rate is usually more representative in automated production. Activity-based costing may use several cost pools and drivers where one volume-based rate materially distorts job profitability.

Worked example: job cost and quotation

A manufacturer records the following for Job J47:

  • direct materials: $18,000;
  • 600 direct labour hours at $24 per hour;
  • specialist design fee: $2,500;
  • 300 machine-hours;
  • production overhead rate: $16 per machine-hour.

Direct labour is 600 × $24 = $14,400, while absorbed overhead is 300 × $16 = $4,800. Therefore:

CJ = $18,000 + $14,400 + $2,500 + $4,800 = $39,700

If the required profit is 20% of selling price, cost represents 80% of selling price. The quotation is:

Selling price = $39,700 ÷ (1 − 0.20) = $49,625

This differs from adding a 20% markup on cost, which would produce $47,640. Margin and markup must not be confused.

Control implications

A completed job should be compared with its estimate. Material, labour-time and overhead variances may reveal poor specifications, rework, idle time, inaccurate standards or unauthorized resource use. Managers should also examine customer changes and distinguish them from internal inefficiency.

Batch Costing

A batch is treated as one job, but the total batch cost is divided among identical units:

Cost per unit = Total batch cost ÷ Good units produced

Only acceptable output should generally be used in the denominator. Normal loss may be absorbed by good units, whereas abnormal loss should be separately reported according to organizational policy.

Worked example: batch cost

Batch B16 contains 500 good units. Its costs are:

  • direct materials: $10,000;
  • direct labour: $6,000;
  • direct expenses: $1,000;
  • setup cost: $1,500;
  • other absorbed overhead: $4,000.

Total batch cost is $22,500, giving:

Cost per unit = $22,500 ÷ 500 = $45

If only 480 good units resulted and the loss were normal, unit cost would be $22,500 ÷ 480 = $46.875, or $46.88 when rounded.

Economic Batch Size

Producing larger batches reduces the number of setups but increases average inventory. Economic batch size balances these two relevant costs.

Let:

  • D = annual demand, units per year;
  • S = setup cost per batch, currency per setup;
  • Q = batch size, units;
  • h = annual holding cost per unit, currency per unit per year.

Under the basic model, annual setup cost is DS ÷ Q. If inventory falls uniformly from Q to zero, average inventory is Q ÷ 2, so annual holding cost is hQ ÷ 2. Relevant annual cost is:

TC(Q) = DS ÷ Q + hQ ÷ 2

Differentiating and setting the derivative equal to zero gives:

dTC/dQ = −DS ÷ Q2 + h ÷ 2 = 0

Therefore:

Q^* = √(2DS ÷ h)

The formula assumes stable demand, constant setup and holding costs, no shortages, and effectively instantaneous replenishment of the batch. It excludes unit production cost when that cost is unaffected by batch size.

Numerical application

Annual demand is 12,000 units, setup cost is $150 per batch, and annual holding cost is $6 per unit:

Q^* = √[(2 × 12,000 × $150) ÷ ($6 per unit)] = √600,000 ≈ 774.60 units

A feasible batch size would be approximately 775 units. At the theoretical optimum, annual setup cost and annual holding cost are each approximately $2,323.79.

Where items are produced gradually rather than received instantaneously, the basic formula overstates average inventory. If production rate P exceeds demand rate D, the economic production quantity is:

Q^* = √{2DS ÷ [h(1 − D ÷ P)]}

Here D and P must use the same time unit, and P > D. This is a special case and should not be used when replenishment is instantaneous.

Practical batch selection must also consider shelf life, machine capacity, workforce availability, storage limits, quality risk and customer lead times. Lean production may justify smaller batches even where measured setup and holding costs suggest otherwise, particularly after setup-time reduction.

Contract Costing

Nature of contract costs

A contract is a large, individually identifiable assignment, often performed at the customer’s site over more than one accounting period. Most costs are direct to the contract, although head-office and shared equipment costs may require allocation.

Typical contract-account debits include:

  • materials delivered to the site;
  • site wages and supervision;
  • direct expenses and subcontractor charges;
  • plant charged at cost, where that accounting method is used;
  • allocated contract overhead; and
  • notional profit as the balancing figure on a profitable contract.

Typical credits include work certified, work uncertified, materials remaining at site, materials returned, and plant remaining at site where the plant was originally debited at full cost.

Care is required to avoid double counting plant. If only plant depreciation is debited, the closing plant value is not also credited as though full plant cost had been charged.

Work certified and retention money

Work certified is work approved by the contract architect, engineer or surveyor. Work completed but not yet certified is work uncertified and is normally valued at cost, subject to prudence.

The customer often withholds part of the certified value as retention money to protect against defects or incomplete obligations:

Cash received = Work certified − Retention money

If the retention rate is r, then, assuming no other deductions:

Cash received = Work certified × (1 − r)

Retention is not a reduction in the value of work performed. It is a delayed contractual receivable, although collectability and performance conditions must be assessed.

Notional profit

When contract-account credits exceed costs charged to date, the balancing figure is notional profit:

Notional profit = (Work certified + Work uncertified + Materials at site + Plant at site + Other contract credits) − Costs debited to date

This expression applies where plant has been debited at full cost and its closing value is therefore credited. Items returned or transferred are also credits. The precise account must follow a consistent treatment of every asset and cost.

Worked contract account

Contract C21 has the following year-end information:

ItemAmount
Materials issued$600,000
Site wages$550,000
Direct expenses$150,000
Plant charged at cost$200,000
Work certified$1,700,000
Work uncertified at cost$100,000
Materials remaining at site$50,000
Plant remaining at site$50,000

The contract account is:

DebitAmountCreditAmount
Materials issued$600,000Work certified$1,700,000
Site wages$550,000Work uncertified$100,000
Direct expenses$150,000Materials at site$50,000
Plant at cost$200,000Plant at site$50,000
Notional profit, balancing figure$400,000
Total$1,900,000Total$1,900,000

Thus:

Notional profit = $1,700,000 + $100,000 + $50,000 + $50,000 − $1,500,000 = $400,000

Notional profit appears on the debit side because the credit values exceed costs and it is the balancing figure on a profitable contract.

Profit recognition on incomplete contracts

Notional profit is not necessarily recognized in full. Some profit is retained as a reserve against future uncertainty. Traditional cost-accounting conventions often use completion bands, for example:

Recognized profit = Notional profit × 1/3 × Cash received ÷ Work certified

for a moderately progressed contract, and:

Recognized profit = Notional profit × 2/3 × Cash received ÷ Work certified

for a substantially progressed contract. These fractions are conventions, not universal accounting rules. The applicable financial-reporting framework and the entity’s consistently applied policy take precedence.

Suppose Contract C21 has a contract price of $2,400,000 and the customer pays 80% of certified work. Cash received is $1,700,000 × 80% = $1,360,000. If the entity’s policy permits the two-thirds convention for this stage:

Recognized profit = $400,000 × 2/3 × ($1,360,000 ÷ $1,700,000) = $213,333.33

The remaining notional profit of approximately $186,666.67 is held as a reserve.

For a contract nearing completion, management may estimate total contract profit:

Estimated total profit = Contract price − Estimated total contract cost

One traditional recognition convention is:

Recognized profit = Estimated total profit × Cash received ÷ Contract price

This should be used only when total outcome can be estimated reliably and when it is consistent with applicable policy. Expected contract losses should be recognized promptly rather than deferred.

Under contemporary revenue standards such as IFRS 15, revenue is recognized over time only when specified criteria are met—for example, when the customer controls the asset as it is created or the asset has no alternative use and the entity has an enforceable right to payment. Progress may be measured using input or output methods. Cost-to-cost measures must exclude costs that do not depict performance faithfully.

Escalation clauses

An escalation clause permits the contract price to be adjusted when specified input prices or indices change materially. It allocates inflation risk between contractor and customer.

A simplified index-based adjustment may be expressed as:

Adjustment = B × w × (I1 − I0) ÷ I0

where B is the eligible value of work in currency, w is the proportion governed by the index, I0 is the base index and I1 is the current index. The formula applies only when it matches the contract clause.

For eligible work of $600,000, a material weighting of 40%, and an index increase from 100 to 125:

Adjustment = $600,000 × 0.40 × (125 − 100) ÷ 100 = $60,000

The clause should specify thresholds, caps, indices, timing and documentary evidence. Unilateral or unsupported adjustments create legal and ethical risk.

Variations, claims and cost-plus contracts

A variation changes the original scope. Its costs and revenue should be separately coded to preserve accountability. Claims for delay, disruption or disputed work should not be treated as certain revenue merely because management expects recovery.

Under a cost-plus contract, the customer reimburses allowable cost plus an agreed fee or percentage. Such arrangements reduce the contractor’s cost risk but can weaken incentives for efficiency. Open-book records, allowable-cost definitions, audit rights and approval controls are therefore essential.

Illustrative Case: Apex Engineering Services

Background

Apex Engineering Services, a fictional company, manufactures customized control panels, produces standard sensor modules in batches and installs automation systems under long-term contracts.

Problem

Apex used one factory-wide overhead rate based on labour hours. Automated jobs appeared highly profitable, setup costs were hidden in general overhead, and installation managers recognized most notional profit as soon as work was certified. The company also lacked separate codes for customer variations.

Analysis

Automated panel jobs consumed machine support rather than labour effort, so the existing overhead base distorted job margins. Small sensor batches generated frequent setups, but setup costs were invisible to production planners. Contract profit calculations ignored materials remaining at site and did not adequately reserve against incomplete testing and retention risk.

Approach and solution

Apex introduced unique job and variation codes, electronic materials requisitions and labour time capture. Factory overhead was divided into machine-processing, setup and production-support pools. Sensor planners applied economic batch analysis but adjusted the calculated result for shelf life and storage limits.

For contracts, Apex implemented a monthly reconciliation covering work certified, uncertified work, materials and plant at site, cash received, retention and forecast cost to complete. Profit recognition required approval by both the project director and financial controller. Expected losses were reported immediately.

Outcome

Management discovered that several apparently profitable automated jobs had been undercosted, while labour-intensive jobs had been overcosted. Setup reduction allowed smaller sensor batches without materially increasing total cost. Contract forecasts became more cautious, and variation recovery improved because supporting records were available.

Learning points

Costing design affects decisions as well as reported profit. Appropriate cost drivers, accurate closing-site records, separate variation coding and independent review are necessary for reliable customized costing.

Operational, Governance and Ethical Considerations

Cost records can be manipulated by charging excess hours to cost-plus work, delaying recognition of waste, overstating uncertified work or using optimistic cost-to-complete estimates. Such practices may mislead customers, lenders and shareholders.

Effective controls include:

  • sequential job and contract authorization;
  • segregation of ordering, receipt and recording duties;
  • supervisor approval of labour and machine time;
  • physical verification of site materials and plant;
  • reconciliation of job ledgers to the general ledger;
  • independent certification and variation approval;
  • documented overhead-rate reviews; and
  • audit trails for estimate revisions.

Confidential customer designs and employee data must be protected. Cost allocation policies should be consistent, transparent and based on causal or benefit relationships rather than chosen to shift profit opportunistically.

Technology and Contemporary Practice

Enterprise resource planning systems can connect procurement, inventory, payroll, production and contract billing through a common job code. Mobile applications allow site personnel to record materials, progress and equipment use. Building information modelling can connect construction quantities with budgets and progress measures.

Artificial intelligence may identify unusual time entries, predict cost overruns or forecast completion costs. However, algorithmic results depend on data quality and may reproduce historical bias. Human review remains necessary, especially where forecasts determine revenue, bonuses or impairment decisions. Access controls, model validation and documented overrides are essential governance practices.

Limitations and Best Practices

Job and contract costing can be administratively expensive. Detailed tracing may cost more than the information is worth, while arbitrary overhead allocation can create false precision. Economic batch models simplify uncertain demand and operational constraints. Contract estimates are especially vulnerable to inflation, technical uncertainty and claims disputes.

Best practice is to balance accuracy with materiality, use drivers reflecting resource consumption, reconcile physical and accounting records, update forecasts regularly, separate normal inefficiency from abnormal loss, and disclose estimation uncertainty to decision-makers.

Chapter Summary

Job costing accumulates direct materials, direct labour, direct expenses and absorbed overhead for a distinct assignment. Batch costing applies the same logic to a group of identical units and calculates unit cost over good output. Economic batch size balances setup and holding costs, subject to restrictive assumptions and operational constraints.

Contract costing accumulates project costs and credits work certified, uncertified work and closing site assets. On a profitable contract, notional profit is the debit-side balancing figure. Retention delays cash but does not automatically reduce certified value. Profit on incomplete contracts must be recognized prudently and consistently with applicable financial-reporting requirements. Reliable systems require suitable cost drivers, physical verification, forecast discipline, ethical conduct and effective digital controls.

Key Terms

Job costing: Accumulation of costs for a separately identifiable order or assignment.

Job cost sheet: Record summarizing the materials, labour, direct expenses and overhead assigned to a job.

Direct expense: A non-material, non-labour cost traceable exclusively to a cost object.

Overhead absorption rate: Predetermined rate used to assign indirect production costs to cost objects.

Under-absorbed overhead: The excess of actual overhead over overhead absorbed.

Batch costing: Costing method that treats a group of identical units as one job.

Economic batch size: Batch quantity that minimizes relevant setup and inventory-holding costs under specified assumptions.

Setup cost: Cost incurred each time production is prepared for a batch.

Holding cost: Cost of carrying one unit of inventory for a period.

Contract costing: Cost accumulation for a large, separately identifiable contract.

Work certified: Completed work formally approved by an authorized certifier.

Work uncertified: Completed work not yet formally certified, normally valued cautiously at cost.

Retention money: Portion of certified value withheld until contractual conditions are satisfied.

Notional profit: Excess of contract-account credits over costs charged to date.

Escalation clause: Contract provision adjusting price for defined changes in specified costs or indices.

Variation: Authorized change to contractual scope, specification or quantity.

Cost-plus contract: Contract reimbursing allowable cost plus an agreed fee or profit component.

Process costing: Averaging of costs across homogeneous output produced continuously through processes.

Review Questions

Short Answer Questions

  1. What is the principal cost object in job costing?
  2. Distinguish direct expenses from production overhead.
  3. Why is retention money withheld on a contract?
  4. What assumptions underlie the basic economic batch-size model?
  5. Why is notional profit shown on the debit side of a profitable contract account?

Long Answer Questions

  1. Compare job costing with process costing, referring to cost accumulation, output characteristics and unit-cost measurement.
  2. Explain the documents and internal controls required for an effective job-costing system.
  3. Derive the economic batch-size formula and evaluate its practical limitations.
  4. Explain the accounting treatment of work certified, work uncertified, materials at site, plant at site and retention money.
  5. Critically discuss traditional and contemporary approaches to recognizing profit on incomplete contracts.

Analytical / Application Questions

  1. A job uses materials of $24,000, 800 labour hours at $28 per hour, direct equipment hire of $3,600 and 500 machine-hours. Overhead is absorbed at $18 per machine-hour. Calculate total job cost and a selling price that provides a 25% margin on sales.
  2. Annual demand is 20,000 units, setup cost is $240 per batch and holding cost is $8 per unit per year. Calculate economic batch size and explain two reasons management might select a different quantity.
  3. Prepare a contract account from the following data: materials issued $700,000; wages $500,000; expenses $120,000; plant charged at cost $180,000; work certified $1,600,000; work uncertified $90,000; materials at site $40,000; and plant at site $70,000. Calculate notional profit and explain how incomplete-contract risk should affect profit recognition.

Multiple Choice Questions with Answers

Question 1

A job uses direct materials of $12,000, 400 labour hours at $30 per hour and 400 machine-hours with overhead absorbed at $10 per machine-hour. There are no direct expenses. What is the total job cost?

A. $24,000

B. $28,000

C. $30,000

D. $32,000

Correct Answer: B. $28,000

Question 2

Which production environment is most suitable for process costing?

A. Custom legal assignments

B. Construction of a bridge

C. Continuous production of homogeneous chemicals

D. Manufacture of a unique machine

Correct Answer: C. Continuous production of homogeneous chemicals

Question 3

Annual demand is 10,000 units, setup cost is $200 per batch and annual holding cost is $4 per unit. What is the economic batch size under the basic model?

A. 500 units

B. 707 units

C. 1,000 units

D. 2,000 units

Correct Answer: C. 1,000 units

Question 4

A batch costs $48,000 and produces 1,200 good units. What is its cost per good unit?

A. $36

B. $40

C. $44

D. $48

Correct Answer: B. $40

Question 5

Using the chapter's Contract C21 data, what is the notional profit?

A. $350,000

B. $375,000

C. $400,000

D. $450,000

Correct Answer: C. $400,000

Question 6

What is the main purpose of retention money in a contract?

A. To convert direct cost into overhead

B. To protect the customer against defects or incomplete obligations

C. To eliminate the contractor's receivable

D. To reduce the certified value of completed work

Correct Answer: B. To protect the customer against defects or incomplete obligations

Question 7

Eligible work is $600,000, the indexed proportion is 40%, and the index rises from 100 to 125. Using the chapter's simplified escalation formula, what is the adjustment?

A. $24,000

B. $50,000

C. $60,000

D. $150,000

Correct Answer: C. $60,000

Question 8

A contract has notional profit of $400,000, cash received of $1,360,000 and work certified of $1,700,000. Under the two-thirds convention, what profit is recognized?

A. $186,667

B. $213,333

C. $266,667

D. $320,000

Correct Answer: B. $213,333

Question 9

Actual production overhead is $250,000 and absorbed overhead is $235,000. What is the result?

A. Over-absorption of $15,000

B. Under-absorption of $15,000

C. Under-absorption of $235,000

D. No absorption difference

Correct Answer: B. Under-absorption of $15,000

Question 10

Which treatment is most appropriate when a reliable forecast shows that a contract will make an overall loss?

A. Defer the loss until contract completion

B. Recognize the expected loss promptly

C. Recognize the loss only when retention is paid

D. Offset the loss against unrelated profitable jobs

Correct Answer: B. Recognize the expected loss promptly