Chapter 6
Capital Budgeting and Investment Decisions
Bachelors Program in Banking Finance and Insurance
Corporate Finance
•
Bachelor
Capital Budgeting and Investment Decisions
Introduction
Capital budgeting is the process of identifying, evaluating and selecting long-term investments. Decisions about production facilities, information systems, branch networks, equipment replacement and new products can commit substantial capital for many years. Their consequences therefore extend beyond a single accounting period.
Sound capital budgeting rests on two tasks. First, analysts must estimate incremental after-tax cash flows—the cash flows that occur only because a project is accepted. Second, they must apply decision criteria consistent with shareholder wealth maximization. Net present value (NPV) is generally the primary criterion, while internal rate of return (IRR), modified internal rate of return (MIRR), payback, discounted payback and profitability index (PI) provide complementary information.
Learning Objectives
After studying this chapter, students should be able to:
Distinguish incremental cash flows from accounting profits.
estimate initial, operating and terminal project cash flows after tax.
Analyze expansion and replacement investments.
Apply NPV, IRR, MIRR, payback, discounted payback and PI.
Resolve conflicts among criteria for mutually exclusive projects.
Incorporate inflation, project risk, working capital and relevant opportunity costs.
Evaluate governance, ethical and technological issues in capital budgeting.
1. The Capital-Budgeting Framework
A project normally passes through five stages:
Strategic identification: finding investments consistent with organizational objectives.
Evaluation: applying a risk-appropriate required return and decision criteria.
Authorization and implementation: approving, financing and executing the investment.
Post-audit: comparing actual outcomes with forecasts and learning from deviations.
Capital budgeting uses cash flows rather than accounting income because cash can be reinvested or distributed to investors. Accounting income includes noncash charges, accruals and cost allocations that may not represent incremental economic consequences.
1.1 Independent and mutually exclusive projects
An independent project can be accepted without preventing the acceptance of another project. If capital is unconstrained, every independent project with a positive NPV should be accepted.
Mutually exclusive projects compete with one another: accepting one requires rejecting the others. Examples include alternative banking platforms or two machines performing the same function. The project with the greatest positive NPV should normally be selected, provided the alternatives are evaluated over economically comparable horizons.
1.2 Expansion and replacement investments
An expansion project increases capacity, introduces a product or enters a market. Its relevant cash flows are usually the new revenues, costs, taxes and working-capital requirements created by the expansion.
A replacement project substitutes a new asset for an existing one. The analysis must compare the “replace” and “continue with the old asset” alternatives. Relevant cash flows include the new asset’s cost, proceeds from selling the old asset, changes in operating costs, differences in depreciation tax shields and differences in terminal value.
2. Incremental After-Tax Cash Flows
The incremental principle asks:
What cash flows will change if, and only if, the project is accepted?
A project’s cash-flow schedule is commonly divided into initial outlay, operating cash flows and terminal cash flow.
2.1 General cash-flow representation
Let CFt denote the project’s incremental after-tax cash flow at time t, measured in currency units. The complete schedule is:
CF0, CF1, CF2, …, CFn
Here, CF0 is commonly negative, while later cash flows may be positive or negative.
2.2 Initial outlay
A general initial cash-flow expression is:
CF0 = −(P + I) − ΔNWC − OC + ATPold
where:
P = purchase price of the new asset;
I = installation, transport and commissioning costs;
ΔNWC = initial increase in net working capital;
OC = opportunity cost of resources committed to the project;
ATPold = after-tax proceeds from selling an old asset.
The signs must reflect the direction of cash movement. Purchases and additional working capital are outflows; proceeds from selling an old asset are inflows.
If an asset is sold for S, has tax book value BV and the applicable tax rate is T, its after-tax proceeds are:
ATP = S − T(S − BV)
This expression assumes gains are taxable and deductible losses can be used at rate T. If S > BV, tax is paid on the gain. If S < BV, the negative tax term represents a tax saving, subject to tax-law restrictions.
2.3 Operating cash flow
Suppose incremental revenue is ΔRt, incremental cash operating cost is ΔCt, depreciation is Dt and the tax rate is T. Earnings before interest and tax are:
EBITt = ΔRt − ΔCt − Dt
Adding back noncash depreciation gives operating cash flow:
OCFt = (ΔRt − ΔCt − Dt)(1 − T) + Dt
An equivalent tax-shield form is:
OCFt = (ΔRt − ΔCt)(1 − T) + DtT
These formulas assume interest expense is excluded. Financing costs are reflected in the required return; subtracting interest from project cash flows and also using a financing-based discount rate would double-count financing effects.
Depreciation is not itself a cash flow, but it lowers taxable income and creates a depreciation tax shield of DtT, provided the firm can use the deduction.
2.4 Terminal cash flow
At the end of a project, terminal cash flow may include asset disposal, working-capital recovery and shutdown costs:
TCFn = ATPn + Recovery of NWC − Shutdown costs
The final-period total cash flow is therefore:
CFn = OCFn + TCFn
Working-capital recovery is generally not taxable because it represents the liquidation of inventories and receivables net of current liabilities. Any gains or losses on particular assets may nevertheless have tax effects.
3. Relevant and Irrelevant Cash Flows
3.1 Sunk costs
A sunk cost has already been incurred and cannot be changed by the decision. It must be excluded. A completed feasibility study is irrelevant even if it was expensive.
3.2 Opportunity costs
An opportunity cost is the value sacrificed by using an existing resource in the project. For example, land owned by a bank has a relevant market value even though no new purchase is required.
3.3 Externalities and cannibalization
A new product may reduce sales of an existing product. This cannibalization is an incremental cost. Positive spillovers, such as additional insurance sales generated by a digital-banking platform, are incremental benefits.
3.4 Allocated overhead
Allocated corporate overhead is relevant only to the extent that the project changes total cash expenditure. Merely reallocating an existing fixed cost does not create an incremental cash flow.
3.5 Inflation consistency
Nominal cash flows include expected inflation and must be discounted at a nominal required return. Real cash flows exclude inflation and must be discounted at a real return. The rates are related by:
1 + rn = (1 + rr)(1 + π)
where rn is the nominal return, rr is the real return and π is expected inflation. Mixing real cash flows with nominal discount rates understates project value.
4. Capital-Budgeting Decision Methods
4.1 Net present value
For a project lasting n periods with required return r, NPV is:
NPV = ∑t=0n CFt/(1 + r)t
The rate r must correspond to the timing, currency, inflation basis and risk of the cash flows.
Decision rules are:
accept an independent project if NPV > 0;
reject it if NPV < 0;
among mutually exclusive alternatives, select the feasible project with the greatest positive NPV.
NPV measures the estimated increase in owners’ wealth in currency units and assumes intermediate cash flows can be reinvested at the required return.
4.2 Internal rate of return
IRR is the discount rate that makes NPV equal to zero:
0 = ∑t=0n CFt/(1 + IRR)t
Accept an independent conventional project if IRR > r. A conventional project has one initial outflow followed by inflows.
IRR has important limitations. Nonconventional cash-flow sequences may produce multiple IRRs or no economically meaningful IRR. For mutually exclusive projects, IRR can conflict with NPV because of scale or timing differences. NPV should then govern.
4.3 Modified internal rate of return
MIRR assumes positive cash flows are reinvested at a specified reinvestment rate and negative cash flows are financed at a specified finance rate. For a horizon of n periods:
MIRR = (FVpositive/|PVnegative|)1/n − 1
Here, FVpositive is the terminal value of positive cash flows compounded at the reinvestment rate, while PVnegative is the present value of negative cash flows discounted at the finance rate. MIRR usually provides a unique and more economically defensible rate than IRR, although NPV remains the direct measure of wealth creation.
4.4 Payback period
The payback period is the time required for undiscounted cash inflows to recover the initial investment. If recovery occurs during year k, under the conventional assumption that cash flow arrives uniformly during that year:
Payback = (k − 1) + Unrecovered amount at start of year k / CFk
Payback is easy to communicate and highlights liquidity exposure, but it ignores the time value of money and all cash flows after recovery.
4.5 Discounted payback period
Discounted payback applies the same recovery procedure to discounted cash flows:
Discounted CFt = CFt/(1 + r)t
It recognizes the time value of money but still ignores cash flows occurring after the cutoff. A project that never recovers its investment on a discounted basis has no finite discounted payback within its life.
4.6 Profitability index
For a conventional project with one initial investment, PI is:
PI = PV of future cash inflows / Initial investment
A project has positive NPV when PI > 1. PI is useful for ranking divisible independent projects when capital is rationed. It can misrank mutually exclusive projects because it measures value per unit invested rather than total value created.
5. Worked Application: Payback and Discounted Payback
A project costs £100,000 and generates the following year-end cash inflows:
Year
Cash flow (£000)
Discounted at 10% (£000)
Cumulative discounted (£000)
1
30
27.273
27.273
2
35
28.926
56.199
3
40
30.053
86.252
4
25
17.075
103.327
For undiscounted payback, £65,000 is recovered by the end of year 2. The unrecovered amount is £35,000:
Payback = 2 + 35/40 = 2.875 years
For discounted payback, £86.252 thousand is recovered by the end of year 3. Assuming the year-4 cash flow accrues uniformly during that year:
If cash flows occur only at year-end rather than uniformly, recovery occurs at the end of year 3 on an undiscounted basis and at the end of year 4 on a discounted basis. Analysts should state the timing convention explicitly.
6. Mutually Exclusive Projects: A Numerical Comparison
A firm must choose between Projects A and B. Both last three years, and the required return, finance rate and reinvestment rate are 10%.
Year
Project A (£000)
Project B (£000)
0
−100
−400
1
130
0
2
0
0
3
0
600
6.1 NPV
NPVA = −100 + 130/1.10 = £18.182 thousand
NPVB = −400 + 600/(1.10)3 = £50.789 thousand
Project B creates more total value and should be selected.
6.2 IRR
IRRA = 130/100 − 1 = 30.00%
IRRB = (600/400)1/3 − 1 ≈ 14.47%
IRR ranks A above B, illustrating a scale-and-timing conflict.
6.3 MIRR
Using a common three-year horizon, Project A’s £130,000 inflow is reinvested for two years:
MIRRA = [130(1.10)2/100]1/3 − 1 ≈ 16.29%
MIRRB = (600/400)1/3 − 1 ≈ 14.47%
MIRR also ranks A higher on percentage return, but it does not overturn B’s greater wealth contribution.
6.4 Payback, discounted payback and PI
Using the conventional within-year interpolation assumption:
Method
Project A
Project B
Preferred by method
NPV (£000)
18.182
50.789
B
IRR
30.00%
14.47%
A
MIRR
16.29%
14.47%
A
Payback
0.769 years
2.667 years
A
Discounted payback
0.846 years
2.887 years
A
PI
1.182
1.127
A
For example:
PIB = [600/(1.10)3]/400 = 1.127
The conflict demonstrates why NPV is preferred for mutually exclusive investments: it measures total value rather than speed of recovery or percentage return. If the cash flows are strictly year-end, the paybacks are one year for A and three years for B rather than the interpolated figures.
7. Illustrative Replacement Case: Meridian Bank Processing Equipment
Background
This is an illustrative case. Meridian Bank is considering replacing an existing document-processing machine with automated equipment. The new equipment costs £300,000, installation costs £20,000 and additional net working capital of £20,000 is required.
The old machine can be sold immediately for £70,000. Its tax book value is £100,000. The corporate tax rate is 30%. Both alternatives have four remaining years. The new machine will reduce annual cash operating costs by £110,000. It is depreciated straight-line to zero over four years. The old machine would have generated annual tax depreciation of £25,000. The new machine can be sold for £40,000 at year 4; the old machine would then have no value. The required return is 12%.
Initial cash flow
Selling the old machine creates a deductible tax loss of £30,000:
ATPold = 70 − 0.30(70 − 100) = £79 thousand
Therefore:
CF0 = −300 − 20 − 20 + 79 = −£261 thousand
Annual operating cash flow
New annual depreciation is £80,000, so incremental depreciation is:
ΔD = 80 − 25 = £55 thousand
The annual operating cash flow from cost savings is:
OCF = 110(1 − 0.30) + 55(0.30) = £93.5 thousand
Terminal cash flow
The new machine’s £40,000 sale price is fully taxable because its book value is zero:
ATP4 = 40 − 0.30(40 − 0) = £28 thousand
Working capital of £20,000 is recovered. Thus the additional terminal cash flow is £48,000, and total year-4 cash flow is £141,500.
Replacement project cash-flow timeline with initial outflow below time zero and later inflows above the timeline
Figure: Replacement project cash-flow timeline with initial outflow below time zero and later inflows above the timeline
Figure: The time-0 outlay is shown as a downward arrow connected to time 0; subsequent inflows are shown above their respective dates.
Evaluation and outcome
The project’s NPV is:
NPV = −261 + 93.5[1 − (1.12)−4]/0.12 + 48/(1.12)4
NPV ≈ −261 + 283.992 + 30.505 = £53.497 thousand
Other indicators are approximately:
Measure
Result
NPV at 12%
£53.50 thousand
IRR
20.8%
MIRR at 12%
17.3%
Payback
2.79 years
Discounted payback
3.41 years
PI
1.205
The replacement should be accepted because it has a positive NPV. The analysis depends on the firm’s ability to use depreciation deductions and the tax loss on disposal.
Learning points
Replacement analysis uses differences between the new and old alternatives.
Selling the old asset affects both initial cash proceeds and taxes.
Foregone old-asset depreciation must be included when calculating incremental depreciation.
Working-capital recovery and after-tax disposal value belong in terminal cash flow.
8. Risk, Uncertainty and Managerial Judgment
A single NPV estimate can create false precision. Managers should examine the assumptions underlying revenues, operating costs, project life, tax treatment and disposal values.
Sensitivity analysis changes one variable at a time to identify value drivers. Scenario analysis changes several related assumptions simultaneously to represent optimistic, base and adverse conditions. Simulation assigns probability distributions to uncertain inputs and generates a distribution of project outcomes.
The discount rate should reflect project risk rather than merely the firm’s average risk. Applying the company-wide weighted average cost of capital to every project can lead to accepting overly risky investments and rejecting safe ones.
Projects can also contain real options, including options to delay, expand, contract or abandon. A static NPV model may undervalue managerial flexibility. However, option values should be supported by realistic operational rights and assumptions, not added merely to justify an unattractive proposal.
9. Capital Rationing and Unequal Lives
Under capital rationing, a firm cannot undertake every positive-NPV project. PI can assist when projects are divisible and only one period’s investment budget is constrained. With indivisible projects, multiple-period constraints or dependencies, optimization techniques such as integer programming may be required.
Alternatives with unequal lives should not automatically be compared using one-cycle NPVs. If projects can be repeated under similar conditions, analysts may use equivalent annual value:
EAV = NPV × r/[1 − (1 + r)−n]
Here, EAV is the constant annual value equivalent to the project’s NPV. The repeatability assumption must be credible; otherwise, analysts should use a common planning horizon with explicit replacement assumptions.
10. Governance, Ethics and Technology
Capital-budget forecasts are vulnerable to optimism bias, strategic understatement of costs and exaggerated terminal values. Strong governance requires documented assumptions, independent review, approval limits, conflict-of-interest controls and post-investment audits. Project sponsors should not be rewarded solely for obtaining approval.
Regulatory and environmental obligations may generate mandatory cash flows even when they do not produce direct revenues. Analysts must include compliance costs, decommissioning obligations, data-protection requirements and environmental liabilities where relevant.
Modern planning systems integrate operational, tax and treasury data into cash-flow models. Artificial intelligence can help identify forecast patterns, classify expenses and generate scenarios. It cannot determine strategic relevance or ethical acceptability without human oversight. Models should therefore be validated, access-controlled, explainable and monitored for poor-quality or biased data.
11. Professional Best Practices
A defensible capital-budgeting analysis should:
model incremental after-tax cash flows rather than accounting earnings;
separate operating assumptions from financing decisions;
document tax, inflation and timing conventions;
use a discount rate appropriate to project risk;
reconcile all cash flows to supporting operational assumptions;
test adverse scenarios and key sensitivities;
use NPV as the principal decision criterion;
explain conflicts between NPV and percentage-return measures;
conduct a post-audit after implementation.
Chapter Summary
Capital budgeting evaluates long-term investments through their incremental after-tax cash flows. Relevant cash flows include initial acquisition and installation costs, working capital, opportunity costs, operating cash flows, tax effects and terminal proceeds. Sunk costs and nonincremental overhead allocations are excluded.
NPV directly measures expected wealth creation and is the preferred criterion for independent and mutually exclusive decisions. IRR and MIRR express performance as rates of return but can produce rankings inconsistent with NPV. Payback and discounted payback provide liquidity and exposure information, while PI measures value per unit invested and can assist under capital rationing. Reliable decisions also require consistent inflation treatment, project-specific risk assessment, scenario analysis, governance controls and transparent assumptions.
Key Terms
Capital budgeting: The process of evaluating and selecting long-term investments.
Incremental cash flow: A cash flow that changes because a project is accepted.
Initial outlay: The project’s net cash flow at time zero.
Operating cash flow: After-tax cash generated by project operations.
Terminal cash flow: End-of-project cash flow from disposal, working-capital recovery and closure effects.
Net working capital: Current operating assets minus current operating liabilities.
Sunk cost: A past cost unaffected by the current decision.
Opportunity cost: The benefit sacrificed by using a resource in a project.
Cannibalization: Reduction in existing cash flows caused by a new project.
Depreciation tax shield: Tax saving arising from deductible depreciation.
Net present value: Present value of all project cash flows, including the initial outlay.
Internal rate of return: Discount rate at which project NPV equals zero.
Modified internal rate of return: Return calculated using specified finance and reinvestment rates.
Payback period: Time required to recover the initial investment from undiscounted cash flows.
Discounted payback: Time required to recover the initial investment from discounted cash flows.
Profitability index: Present value of future inflows divided by initial investment.
Mutually exclusive projects: Alternatives for which accepting one prevents acceptance of another.
Equivalent annual value: Constant annual value economically equivalent to a project’s NPV.
Capital rationing: A constraint that prevents financing every acceptable project.
Real option: Managerial flexibility to alter a project after uncertainty is resolved.
Review Questions
Short Answer Questions
Why are incremental cash flows used instead of accounting profit?
How does depreciation affect project operating cash flow?
Distinguish a sunk cost from an opportunity cost.
Why can IRR produce multiple solutions?
What information does discounted payback add to ordinary payback?
Long Answer Questions
Explain how initial, operating and terminal cash flows are estimated for an expansion project.
Discuss the strengths and limitations of NPV, IRR, MIRR, payback and PI.
Explain why NPV should normally govern conflicts among mutually exclusive projects.
Describe the construction of incremental cash flows for an asset-replacement decision.
Evaluate how inflation, risk, governance and post-investment audits affect capital-budgeting quality.
Analytical / Application Questions
A machine costs £240,000, requires £15,000 of working capital and produces annual after-tax operating cash flows of £80,000 for four years. Working capital is recovered at the end. Calculate NPV at 11% and recommend a decision.
A project costs £150,000 and generates £50,000, £60,000 and £75,000 over three years. Calculate payback, discounted payback at 9% and PI.
Construct the initial cash flow for replacing an asset sold for £45,000 when its book value is £60,000, the tax rate is 25%, the new installed cost is £200,000 and additional working capital is £10,000.
Multiple Choice Questions with Answers
Question 1
Which cash flow should be excluded from a project evaluation?
A. A recoverable working-capital investment
B. A feasibility-study cost already paid
C. The opportunity cost of owned land
D. After-tax asset disposal proceeds
Correct Answer: B. A feasibility-study cost already paid
Question 2
Incremental revenue is £200,000, cash operating cost is £120,000, depreciation is £30,000 and the tax rate is 25%. What is annual operating cash flow?
A. £57,500
B. £60,000
C. £67,500
D. £80,000
Correct Answer: C. £67,500
Question 3
An asset is sold for £70,000, has a tax book value of £100,000 and the applicable tax rate is 30%. Assuming the tax loss is immediately usable, what are the after-tax proceeds?
A. £61,000
B. £70,000
C. £79,000
D. £91,000
Correct Answer: C. £79,000
Question 4
A £100,000 project generates £30,000, £35,000, £40,000 and £25,000 in successive years. Assuming uniform cash flow during each year, what is its payback period?
A. 2.50 years
B. 2.875 years
C. 3.20 years
D. 3.805 years
Correct Answer: B. 2.875 years
Question 5
Which criterion directly measures the estimated addition to owners’ wealth in currency units?
A. Payback period
B. Internal rate of return
C. Profitability index
D. Net present value
Correct Answer: D. Net present value
Question 6
A project costs £100,000 and produces £130,000 one year later. What is its NPV at 10%?
A. £13,000
B. £18,182
C. £30,000
D. £118,182
Correct Answer: B. £18,182
Question 7
A two-year project costs £100,000 and generates £60,000 at the end of each year. If the reinvestment and finance rates are 10%, what is its MIRR?
A. 10.00%
B. 12.25%
C. 14.47%
D. 20.00%
Correct Answer: B. 12.25%
Question 8
For mutually exclusive projects, Project A has NPV of £18,182 and IRR of 30%, while Project B has NPV of £50,789 and IRR of 14.47%. Which project should normally be selected?
A. Project A, because it has the higher IRR
B. Project A, because it requires less capital
C. Project B, because it has the higher NPV
D. Neither, because the rankings conflict
Correct Answer: C. Project B, because it has the higher NPV
Question 9
A conventional project has a present value of future inflows of £240,000 and an initial investment of £200,000. What is its profitability index?
A. 0.20
B. 0.83
C. 1.20
D. 1.40
Correct Answer: C. 1.20
Question 10
Why is interest expense normally excluded from project operating cash flows?
A. Interest is never tax deductible
B. Interest is included in depreciation
C. Financing effects are reflected in the required return
D. Interest is always a sunk cost
Correct Answer: C. Financing effects are reflected in the required return