Construction & Site Management

Chapter 7
Estimating, Cost Control and Commercial Management

Advance Diploma in Interior Design Management
Construction & Site Management   •   Advance Diploma

Estimating, Cost Control and Commercial Management

Introduction

Construction and interior fit-out projects are commercial as well as technical undertakings. A design may be visually successful yet fail if its cost, procurement strategy, cash requirements or contractual obligations are not controlled. Estimating converts design information into a forecast of resource requirements and cost. Budgeting establishes an approved financial framework. Cost control compares planned, committed and actual expenditure so that corrective action can be taken before the final account becomes unacceptable. Commercial management extends this process to valuations, payment, variations, claims, risk, procurement and contractual decision-making.

For an interior design manager, commercial competence does not mean replacing a quantity surveyor or commercial manager. It means being able to interpret drawings and specifications, prepare reliable quantity information, recognise cost consequences of design decisions, challenge unsupported forecasts, and communicate financial implications to clients, contractors and consultants.

The chapter uses monetary values in generic currency units. Local tax, measurement rules, building regulations and contract forms must always be checked against the jurisdiction and project conditions.

Learning objectives

By the end of this chapter, the learner should be able to:

  1. Explain the relationship between estimating, budgeting, cost control and commercial management.
  2. Prepare a structured quantity take-off from drawings, schedules and specifications.
  3. Develop preliminary estimates, elemental budgets and detailed cost plans.
  4. Distinguish budget, forecast, commitment, actual cost, valuation and final cost.
  5. Prepare a basic cash-flow forecast and interpret cost movement.
  6. Assess variations, contingencies, allowances and commercial risks.
  7. Apply earned value indicators to monitor progress and cost performance.
  8. Support valuations, payment certification, procurement and final-account processes.
  9. Use digital tools and professional judgement without compromising verification, ethics or accountability.

1. The commercial life cycle of a project

Cost information develops progressively as design information becomes more complete. At concept stage, an estimate may rely on floor area and benchmark rates. During developed design, it can be organised by building elements or work packages. At tender stage, quantities, specifications, programme assumptions and quotations support a more detailed estimate. During construction, the focus moves to commitments, valuations, actual costs, forecast final cost and change control.

A useful hierarchy is:

StageMain commercial outputTypical information quality
ConceptOrder-of-cost estimateArea, use, quality and benchmark assumptions
Developed designElemental cost planAreas, systems, outline specifications
Technical designPre-tender estimateMeasured quantities, specifications and programme
ProcurementTender analysis and contract sumContractor prices, exclusions and qualifications
ConstructionCost report and cash-flow forecastOrders, invoices, progress and approved changes
CompletionFinal account and lessons learnedMeasured work, agreed changes and close-out records

The estimate is not a promise. It is a model based on stated assumptions. Its reliability depends on the completeness of design information, market conditions, measurement method, productivity, risk allowances and the quality of cost data.

2. Quantity take-off: from design information to measurable work

A quantity take-off identifies and measures work required to construct or fit out a project. It is the foundation of pricing, procurement and cost control. A professional take-off should be traceable: another person should be able to locate the drawing, detail, specification clause and calculation supporting each quantity.

2.1 Information required

Typical inputs include:

  • coordinated architectural, interior, structural and building-services drawings;
  • room data sheets, finish schedules and door or ironmongery schedules;
  • specifications and performance requirements;
  • surveys and existing-condition information;
  • site logistics, access and working-hour constraints;
  • design responsibility matrices and exclusions;
  • programme, phasing and procurement information; and
  • the applicable measurement standard or client measurement rules.

Drawings must be checked for revision status and coordination. Measuring an obsolete drawing can create a technically accurate but commercially invalid quantity.

2.2 Measurement principles

The measurer should establish a work breakdown structure before measuring. For interior work, this may include preliminaries, demolition, partitions, ceilings, floor finishes, wall finishes, joinery, doors, furniture, fixtures, lighting, mechanical alterations, electrical power, fire protection, testing and cleaning.

Quantities are normally recorded with a description, location, drawing reference, quantity, unit, rate and amount. Common units include:

  • m: linear metre, for skirtings, trims and services;
  • m²: square metre, for floors, ceilings, painting and wall coverings;
  • m³: cubic metre, for concrete, excavation or bulk materials;
  • kg or tonne, for some structural or material items;
  • nr or item, for doors, fittings and equipment; and
  • hour or day, where labour or plant is separately measured.

A quantity should reflect the measurement rule. For example, whether openings are deducted from wall finishes depends on the adopted standard and threshold. Consistency is more important than informal intuition.

2.3 Basic geometric calculations

For a rectangular area:

A = L × W

where A is area in m², L is length in m and W is width in m. For a wall finish, a simplified gross area is:

Aw = P × H

where Aw is gross wall area in m², P is room perimeter in m and H is wall height in m. Net area may be calculated as:

An = Aw − ΣAo

where An is net area and ΣAo is the sum of openings deducted, subject to the relevant measurement rules.

For a rectangular volume:

V = L × W × H

All dimensions must be expressed in compatible units. These equations are geometrical relationships, not complete measurement rules; waste, laps, returns, joints, tolerances and installation requirements may require separate allowances.

Worked example: flooring and skirting

An open-plan room is 8.4 m long and 5.6 m wide. A 1.2 m × 2.1 m cupboard zone is excluded from the floor finish. The room perimeter is 28.0 m, and a 1.0 m-wide doorway interrupts 2.1 m-high skirting on one wall. Calculate the net floor and skirting quantities before waste.

Floor area:

Ag = 8.4 × 5.6 = 47.04 m²

Cupboard area:

Ac = 1.2 × 2.1 = 2.52 m²

Net floor area:

An = 47.04 − 2.52 = 44.52 m²

Skirting length:

Ls = 28.0 − 1.0 = 27.0 m

The measured quantities are therefore 44.52 m² of flooring and 27.0 m of skirting. If procurement requires 7% flooring waste, the purchase quantity is:

Qp = Qm × (1 + w)

where Qp is purchase quantity, Qm is measured quantity and w is waste expressed as a decimal. Thus, Qp = 44.52 × 1.07 = 47.6364 m², normally rounded in accordance with pack sizes and supplier requirements. Waste must not be confused with measurement of installed work or with contingency.

3. Estimating and budget formation

3.1 Preliminary estimating

A preliminary estimate is prepared when design information is incomplete. Common methods include:

  • Floor-area method: gross area multiplied by an appropriate benchmark rate.
  • Elemental method: cost distributed among elements such as partitions, finishes, services and furniture.
  • Functional-unit method: cost related to units such as bedrooms, workstations or sanitary fittings.
  • Analogy method: comparison with a genuinely comparable completed project.
  • Resource or assembly method: quantities of labour, materials, plant and subcontract work multiplied by rates.

The floor-area method is rapid but sensitive to differences in quality, location, procurement, complexity, services intensity and project scale. A benchmark must state what it includes and excludes. A rate from a high-specification hotel should not be transferred uncritically to a standard office fit-out.

A simple area estimate is:

Cb = A × r

where Cb is benchmark cost, A is relevant area and r is a cost rate per m². The formula assumes that the selected rate is comparable and that scope, price base, location and time have been adjusted appropriately.

3.2 Elemental cost planning

An elemental cost plan links design decisions to cost categories. A typical interior project plan may contain:

ElementCost driverCost-control question
PreliminariesDuration, access, supervisionIs the programme realistic?
Demolition and enabling worksExisting conditions, disposalHas intrusive survey information been obtained?
Partitions and doorsLength, height, performanceAre acoustic and fire requirements defined?
FinishesArea, specification, wastageIs the visual quality proportionate to the budget?
Joinery and furnitureNumber, complexity, materialsCan standardisation reduce cost and lead time?
Building servicesLoad, distribution, coordinationAre design changes creating hidden cost?
Testing and handoverSystems and client requirementsAre commissioning activities included?

The cost plan should identify the price base, tax treatment, design stage, inclusions, exclusions, assumptions and risk allowances. It should not hide uncertainty in an unexplained percentage.

3.3 Direct cost, indirect cost and project allowances

Direct costs can be assigned to a work item, such as plasterboard, installation labour or a joinery package. Indirect costs support the work but are not easily assigned to one item, such as site supervision, temporary facilities, insurance and general administration. Preliminaries are often treated as a separate section or distributed through rates.

A simplified estimate can be expressed as:

Ct = Cd + Ci + Cr + Ces

where Ct is total forecast cost, Cd is direct cost, Ci is indirect cost, Cr is risk or contingency allowance, and Ces is escalation allowance. The categories must be defined to avoid double counting. Tax, professional fees, client-supplied items and financing costs may be included or excluded depending on the client’s cost definition.

Contingency is an allowance for identified or foreseeable uncertainty within the defined scope. It is not a source of discretionary spending. An allowance may be used where the scope exists but cannot yet be priced accurately, such as a provisional sum for specialist equipment. Escalation addresses anticipated price movement over time. These concepts should be reported separately.

4. Cost control during construction

Cost control is a cycle rather than a single report:

  1. establish an approved baseline;
  2. allocate the budget to work packages and cost codes;
  3. record commitments such as purchase orders and subcontract agreements;
  4. record actual costs from invoices, payroll and delivery records;
  5. value work completed and approved changes;
  6. forecast the cost to complete and final cost;
  7. investigate variances and risks; and
  8. implement, document and review corrective action.

The cost report should distinguish at least four values:

  • Original budget: the approved baseline before authorised changes.
  • Current budget: original budget plus approved budget changes.
  • Committed cost: contractual or purchase commitments made, whether or not invoiced.
  • Actual cost: cost recorded as incurred under the organisation’s accounting rules.

A commitment is not necessarily an actual cost, and an invoice is not necessarily evidence that the corresponding work has been properly valued. Accruals may be required for work performed but not yet invoiced.

4.1 Forecast final cost

A practical forecast is:

EAC = AC + ETC

where EAC is estimate at completion, AC is actual cost to date and ETC is estimate to complete. If a cost code has a committed but unpaid amount, the team must establish whether it is already included in AC, ETC or a separate commitment forecast. The accounting convention must be consistent.

Variance against the current budget is:

V = Bc − EAC

where V is favourable when positive, Bc is current budget and EAC is forecast final cost. A negative value indicates forecast overspend. Variance percentages should state the denominator; a common measure is Vp = (Bc − EAC) ÷ Bc × 100%, provided Bc is not zero.

4.2 Valuations and payment

A valuation assesses the value of work properly executed, materials appropriately stored where permitted, approved variations, and other contractual entitlements, less retention, previous payments, recoveries and applicable adjustments. The precise rules depend on the contract.

A simplified gross valuation is:

G = Wc + Ms + Va + Oe

where G is gross value, Wc is value of completed work, Ms is eligible stored materials, Va is approved variation value and Oe is other eligible amounts. A net payment certificate may then be represented as:

Pn = G − R − Pp − D

where Pn is net amount due, R is retention, Pp is previous payments and D represents permitted deductions such as advances, damages or recoveries. This is a simplified teaching model; contract provisions govern the actual calculation.

Valuation requires evidence: progress records, measurements, delivery notes, inspection records, photographs, approved instructions and subcontractor submissions. Certifying unverified work creates financial, legal and ethical exposure.

5. Variations, change and commercial risk

A variation is a change to the contracted scope, quantity, quality, sequence, access or method. Typical causes include client design development, statutory requirements, unforeseen existing conditions, substitutions, errors, omissions and contractor proposals.

A disciplined change process should:

  1. identify the event and contractual instruction;
  2. describe the scope and reason;
  3. determine time, cost and design consequences;
  4. obtain quotations or build-up evidence;
  5. assess alternatives and funding source;
  6. obtain the required approval before commitment where possible;
  7. update drawings, schedules, budget, programme and risk register; and
  8. track the change to agreement and final account.

A variation price may comprise labour, materials, plant, subcontractor cost, waste, overhead and profit, subject to the contract. Rates should be based on existing contract rates where applicable, analogous rates where reasonable, or fair valuation using substantiated resource build-ups. A quotation that states only a lump sum without scope, assumptions, exclusions and time impact is difficult to audit.

Risk management complements contingency. A risk register should state the event, cause, probability, impact, owner, response and residual exposure. A simple expected monetary value is:

EMV = p × I

where EMV is expected monetary value, p is probability between 0 and 1, and I is the monetary impact if the event occurs. This is a prioritisation tool, not a prediction of the exact outcome. It is unsuitable as the sole basis for risks that are highly correlated, catastrophic or inadequately understood.

6. Cash-flow forecasting

A cost forecast explains how much a project may cost; a cash-flow forecast explains when money is expected to leave or enter the project. Timing affects funding, procurement decisions, payment administration and contractor solvency.

A basic period cash balance is:

CBt = OBt + It − Ot

where CBt is closing cash balance in period t, OBt is opening balance, It is cash inflow and Ot is cash outflow. For a project funded by client payments, inflows may lag certified work because of assessment, certification and payment periods.

A cash-flow forecast should consider mobilisation, deposits, long-lead procurement, labour loading, subcontractor payment terms, retention, tax, approved variations, seasonal productivity and final retention release. A forecast can be prepared monthly by allocating the expected cost-to-complete across the programme. The allocation should be based on a work-package programme, not an arbitrary smooth curve.

Cash flow is not the same as cost. Purchasing materials early can produce high cash outflow before installation, while retention can reduce cash received despite work being complete. Commercial decisions must therefore consider both forecast cost and liquidity.

7. Earned value indicators

Earned value management compares planned progress, achieved progress and actual cost. It is most useful when the work breakdown structure, budget and progress measurement rules are stable.

The principal measures are:

  • Planned Value (PV): authorised budget for work scheduled by the status date.
  • Earned Value (EV): authorised budget for work actually completed by the status date.
  • Actual Cost (AC): actual cost incurred for completed work by the status date.

Two variances are:

SV = EV − PV
CV = EV − AC

SV is schedule variance in monetary terms and CV is cost variance. Positive SV indicates more budgeted work has been achieved than planned; positive CV indicates that achieved work cost less than its budgeted value.

Two indices are:

SPI = EV ÷ PV
CPI = EV ÷ AC

SPI is schedule performance index and CPI is cost performance index. Values above 1.00 generally indicate favourable performance against the selected baseline; values below 1.00 indicate unfavourable performance. These indicators are not substitutes for programme logic, quality inspection or professional judgement.

A simple estimate at completion, assuming current cost efficiency continues, is:

EAC = BAC ÷ CPI

where BAC is the budget at completion. This formula assumes that the current cost performance is representative of the remaining work and that the original budget remains the relevant baseline. If a known, one-off variance will not recur, a different forecast is more appropriate.

Worked earned-value example

At the reporting date, a work package has PV = 80,000, EV = 72,000 and AC = 90,000. Therefore:

SV = 72,000 − 80,000 = −8,000

CV = 72,000 − 90,000 = −18,000

SPI = 72,000 ÷ 80,000 = 0.90

CPI = 72,000 ÷ 90,000 = 0.80

The package has achieved 90% of the planned progress and generated 80 units of budgeted value for every 100 units of actual cost. If BAC = 200,000 and the current cost efficiency continues:

EAC = 200,000 ÷ 0.80 = 250,000

The result signals a need to investigate productivity, scope change, incorrect progress measurement, rework, procurement prices and cost coding. It does not by itself prove contractor underperformance.

8. Commercial governance and professional ethics

Commercial information influences decisions about design, procurement and payment, so its integrity is essential. Good governance includes clear authority limits, segregation of duties, revision control, audit trails, documented approvals and timely reporting.

Ethical practice requires the professional to:

  • report adverse cost information rather than conceal it;
  • distinguish fact, assumption, estimate and opinion;
  • avoid manipulating progress percentages to improve apparent performance;
  • declare conflicts of interest and gifts;
  • protect confidential tender and client information;
  • ensure that value engineering does not compromise safety, accessibility, durability or statutory compliance; and
  • maintain accurate records capable of independent review.

Regulatory requirements may include procurement law, tax rules, payment legislation, health and safety duties, environmental obligations, accessibility standards, anti-bribery legislation and data-protection requirements. The applicable contract and jurisdiction must be consulted; no generic chapter can replace legal or professional advice.

9. Digital tools and artificial intelligence

Cost databases, spreadsheets, quantity-take-off software, BIM models, common data environments and enterprise resource-planning systems can improve speed and traceability. Model-based quantity extraction is valuable when object classification, units, revisions and model ownership are controlled. A model quantity is not automatically a contract quantity: gaps, duplicates, unmodelled work and incorrect parameters must be checked.

Artificial intelligence may assist with document classification, anomaly detection, historical benchmarking and draft cost-code mapping. It should not independently approve a valuation, invent missing scope or replace professional responsibility. AI outputs require source verification, confidentiality controls, bias review and an audit trail. Sensitive tender prices and personal data should not be entered into unapproved systems.

10. Illustrative case: office fit-out under design development

Background

A client approves a 1,200 m² office fit-out with an initial construction budget of 1,800,000. The concept includes open work areas, meeting rooms, a reception feature wall, tea points and upgraded lighting. The target cost is therefore 1,500 per m².

Problem

During developed design, the client requests higher acoustic performance, additional meeting rooms, bespoke joinery and a revised mechanical layout. The design manager believes the changes are affordable because the original area has not increased. The commercial team identifies that the cost drivers are specification intensity and services complexity, not merely floor area.

Analysis

The elemental cost plan shows the following movement:

ElementOriginal budgetRevised forecast
Partitions and doors240,000315,000
Finishes300,000342,000
Joinery and furniture270,000390,000
Building services510,000600,000
Preliminaries and other costs480,000480,000
Total1,800,0002,127,000

The forecast increase is 327,000, or approximately 18.2% of the original budget. The revised unit cost is 2,127,000 ÷ 1,200 = 1,772.50 per m². The team also identifies a 90,000 risk allowance for incomplete existing-services information. This is not yet an approved variation and should be reported separately from committed cost.

Approach and solution

The team establishes a change log and asks the client to rank requirements. Three options are developed:

  1. retain all acoustic and bespoke requirements;
  2. retain acoustic performance but standardise joinery and reduce decorative features; or
  3. retain the visual concept but phase selected furniture and feature elements.

A value-management workshop reviews life-cycle performance, not just initial price. Standard door types reduce procurement complexity; modular joinery maintains the design language at lower fabrication risk; lighting controls are retained because they support energy performance and commissioning requirements. The approved design is re-costed, and each change receives a scope description, cost, programme impact and approval reference.

Outcome

The client selects a revised package forecast at 1,965,000, with 65,000 of identified risk allowance retained and a clearly documented list of deferred items. The project team updates the budget, procurement schedule, cash-flow forecast and design responsibility matrix. During construction, a services coordination issue is recorded as a potential variation rather than hidden within general contingency.

Learning points

The case demonstrates that area rates are screening tools, not permanent budgets. Design quality, services intensity, fabrication complexity and programme constraints can move cost substantially. Early, transparent change control allows the client to choose consciously rather than discover overspend through late invoices.

11. Limitations and best practice

Estimates remain uncertain because construction is exposed to incomplete information, volatile material prices, labour availability, hidden conditions, design development and productivity variation. A precise-looking spreadsheet can create false confidence. Sensitivity analysis is useful: vary key assumptions such as labour rate, programme duration, material price and quantity, then identify which assumptions most affect the forecast.

Best practice includes:

  • define the cost boundary and price base;
  • use a controlled work breakdown structure and cost-code system;
  • reconcile drawings, schedules, specifications and model data;
  • record assumptions, exclusions and measurement rules;
  • separate approved changes from pending changes and risk allowances;
  • reconcile commitments, accruals, invoices and valuations;
  • forecast cost and cash flow at regular reporting intervals;
  • investigate trends rather than merely reporting historic variance;
  • link commercial records to programme and design revisions; and
  • communicate concise decisions, owners and deadlines.

Chapter Summary

Estimating converts design and construction information into a forecast of resources and cost. Quantity take-offs must be measurable, traceable and based on coordinated information. Preliminary estimates may use area or benchmark rates, while elemental and detailed estimates provide stronger control as design information develops.

Cost control compares the approved baseline with commitments, actual costs, valuations and forecast final cost. Contingency, allowances and escalation represent different forms of uncertainty and should not be combined without explanation. Variations require documented scope, pricing evidence, authority and updates to budget and programme. Cash-flow forecasting addresses timing and liquidity, which differ from accounting cost. Earned value indicators—PV, EV, AC, SV, CV, SPI and CPI—provide structured signals but require reliable baselines and informed interpretation.

Commercial management also depends on governance, ethical reporting, contract awareness, digital traceability and professional judgement. The interior design manager contributes by identifying cost consequences early, supporting coordinated decisions and ensuring that design ambition remains aligned with available resources.

Key Terms

Actual cost: Cost recorded as incurred under the project’s accounting rules.

Allowance: A provisional amount included where scope exists but cannot yet be priced precisely.

Budget: Approved financial limit or baseline for defined scope.

Cash flow: Timing of project cash inflows and outflows.

Commitment: Contractual or purchase obligation made for future payment.

Contingency: Allowance for identified or foreseeable uncertainty within defined scope.

Cost plan: Structured forecast distributing cost among elements or work packages.

Earned value: Budgeted value of work actually completed.

Elemental estimate: Estimate organised by building or fit-out elements.

Estimate at completion: Forecast total cost when the project or work package is complete.

Escalation: Allowance for expected price movement over time.

Final account: Agreed financial statement of the completed contractual work and changes.

Preliminaries: Indirect project costs supporting construction operations.

Quantity take-off: Process of identifying and measuring required work.

Risk register: Record of risks, causes, impacts, owners and responses.

Schedule performance index: Earned value divided by planned value.

Variation: Contractual change to scope, quantity, quality, sequence or method.

Valuation: Assessment of the value of work and other eligible amounts for payment.

Review Questions

5 Short Answer Questions

  1. What is the difference between a commitment and an actual cost?
  2. Why must assumptions and exclusions accompany a preliminary estimate?
  3. Define contingency, allowance and escalation.
  4. What information is required to support a construction valuation?
  5. What does a CPI below 1.00 generally indicate?

5 Long Answer Questions

  1. Explain how a quantity take-off develops into an elemental cost plan and then a construction cost report.
  2. Discuss the advantages and limitations of floor-area, elemental and resource-based estimating methods.
  3. Explain the change-control process for a client-requested variation, including cost, programme and approval implications.
  4. Describe how a project team should prepare and maintain a cash-flow forecast.
  5. Evaluate the role of governance and ethics in commercial management of interior fit-out projects.

3 Analytical / Application Questions

  1. A 900 m² fit-out has a benchmark rate of 1,350 per m². A design change adds 120,000 to services, while procurement savings reduce furniture cost by 45,000. Prepare the revised benchmark estimate and explain which assumptions should be tested before approval.
  2. A package has PV = 150,000, EV = 135,000 and AC = 120,000. Calculate schedule variance, cost variance, SPI and CPI, then recommend two investigations before concluding that performance is satisfactory.
  3. A contractor submits a lump-sum variation for additional joinery after a revised room schedule. Identify the evidence and commercial questions required before the variation is valued and approved.

Multiple Choice Questions with Answers

Question 1

Which item is normally a commitment rather than an actual cost?

A. An approved purchase order not yet invoiced

B. A paid supplier invoice

C. Recorded labour payroll

D. An accrued cost for work completed

Correct Answer: A. An approved purchase order not yet invoiced

Question 2

A room measures 6 m by 4 m. What is its floor area?

A. 10 m²

B. 20 m²

C. 24 m²

D. 48 m²

Correct Answer: C. 24 m²

Question 3

Which allowance primarily addresses expected price movement over time?

A. Retention

B. Escalation

C. Preliminaries

D. Earned value

Correct Answer: B. Escalation

Question 4

If PV is 80,000 and EV is 72,000, what is the schedule performance index?

A. 0.80

B. 0.90

C. 1.11

D. 8,000

Correct Answer: B. 0.90

Question 5

If EV is 90,000 and AC is 100,000, what is the cost variance?

A. 10,000 favourable

B. 10,000 unfavourable

C. 90,000 unfavourable

D. 190,000 favourable

Correct Answer: B. 10,000 unfavourable

Question 6

Which document most directly records the cause, owner and response for a commercial uncertainty?

A. Risk register

B. Door schedule

C. Tender return form

D. Room data sheet

Correct Answer: A. Risk register

Question 7

What is the principal purpose of a valuation?

A. To establish the value of eligible work and amounts due

B. To replace the construction programme

C. To set the architectural concept

D. To calculate only material waste

Correct Answer: A. To establish the value of eligible work and amounts due

Question 8

If a current budget is 500,000 and the forecast final cost is 530,000, the forecast variance is:

A. 30,000 favourable

B. 30,000 unfavourable

C. 530,000 favourable

D. 1,030,000 unfavourable

Correct Answer: B. 30,000 unfavourable

Question 9

Which statement about earned value is correct?

A. EV is the actual cash paid to date

B. EV is the budgeted value of work actually completed

C. EV is always equal to the original budget

D. EV is the forecast cost to complete

Correct Answer: B. EV is the budgeted value of work actually completed

Question 10

Why should a variation quotation state assumptions and exclusions?

A. To make the scope and price auditable

B. To avoid recording the variation

C. To eliminate all project risk

D. To convert actual cost into planned value

Correct Answer: A. To make the scope and price auditable

Construction & Site Management
Chapter 7 of 15