Construction Safety Management

Chapter 6
Site Safety Planning and Operational Controls

Post Graduate Diploma in Civil Engineering
Construction Safety Management   •   Post Graduate

Site Safety Planning and Operational Controls

Introduction and context

Construction safety is most effective when it is designed into work before physical activity begins. A safety plan is not merely a document prepared for contractual compliance; it is a management system that translates hazard information, legal duties, project methods, resources, and worker participation into controlled operations. Site safety planning is particularly important on complex projects because work changes continuously: excavation may be followed by structural erection, temporary works may interact with permanent works, and several contractors may operate in the same area.

Operational controls are the practical arrangements that keep work within acceptable risk boundaries. They include induction, toolbox talks, inspections, permit-to-work systems, personal protective equipment (PPE), access control, housekeeping, traffic management, and safe work procedures. These controls must be coordinated with the construction programme, procurement decisions, design information, emergency arrangements, and supervision.

A useful professional principle is that safety is achieved through a hierarchy of controls rather than through PPE alone. Hazards should first be eliminated where reasonably practicable, then reduced through substitution, engineering controls, administrative controls, and finally PPE. Administrative controls such as training and procedures are necessary, but they are generally less reliable than physical design or engineered protection because they depend on human compliance.

Learning objectives

On completing this chapter, the learner should be able to:

1. Develop a project-specific construction safety plan based on risk and legal responsibilities.

2. Explain how induction, toolbox talks, inspections, and worker consultation support operational control.

3. Design a proportionate permit-to-work system for high-risk activities.

4. Evaluate PPE, access control, housekeeping, and construction traffic arrangements.

5. Prepare and review safe work procedures and method statements.

6. Analyse the effectiveness, limitations, and governance implications of site safety controls.

1. Foundations of site safety planning

1.1 Safety planning as a control cycle

A safety plan should operate as a cycle rather than as a static manual:

Plan → implement → verify → learn and improve.

Planning identifies hazards, legal requirements, resources, responsibilities, interfaces, and emergency arrangements. Implementation converts these decisions into briefings, physical controls, permits, supervision, and inspections. Verification tests whether controls are present and effective. Learning uses inspection findings, incidents, near misses, worker feedback, and changes in the project to revise the plan.

The plan should be proportionate to project risk. A small refurbishment and a deep excavation beside a live railway do not require identical documentation, although both require systematic control. Excessive paperwork can create a false sense of assurance if supervisors cannot use it in the field. Conversely, a short plan that omits interfaces, emergency arrangements, or temporary works may leave critical risks uncontrolled.

1.2 Legal and organisational responsibilities

Specific legal requirements vary by jurisdiction, but construction safety systems commonly allocate duties among the client, designer, principal or main contractor, subcontractors, supervisors, workers, and visitors. The client influences safety through project objectives, time and cost pressures, procurement, and selection of competent organisations. Designers should consider foreseeable construction, use, maintenance, and demolition risks. The principal contractor coordinates site operations and controls access. Subcontractors must provide competent labour, equipment, supervision, and task controls. Workers must follow instructions, use equipment correctly, report hazards, and exercise stop-work rights where serious uncontrolled danger exists.

A safety plan should identify:

  • project scope, location, programme, and high-risk activities;
  • statutory, contractual, client, and organisational requirements;
  • roles, competence, authority, and communication channels;
  • hazard registers and risk assessments;
  • construction methods, temporary works, plant, and materials;
  • contractor and interface arrangements;
  • site layout, access, welfare, emergency routes, and assembly points;
  • inspection, permit, incident reporting, and review processes; and
  • document control, records, and change management.

Responsibility must be matched by authority and resources. Assigning a supervisor responsibility for lifting safety without giving that person authority to stop unsafe work is ineffective governance.

1.3 Risk-based planning

Risk assessment should be activity-specific and should consider routine, non-routine, and emergency conditions. A practical sequence is:

1. Define the activity and boundaries.

2. Identify hazards and people potentially exposed.

3. Determine initiating events and possible consequences.

4. Select controls using the hierarchy of controls.

5. Assign an owner and implementation date.

6. Verify controls before and during work.

7. Review when conditions, methods, or information change.

Risk matrices may help prioritise attention, but they are not measurements of actual risk and should not replace professional judgement. Matrix scores can create artificial precision, especially where consequence is uncertain or where rare catastrophic events are given a low numerical likelihood. Critical controls should therefore be identified separately. Examples include excavation support, isolation of hazardous energy, lifting exclusion zones, fall prevention, and atmospheric testing in confined spaces.

A sound risk assessment distinguishes hazards from controls. “Working at height” is a hazard exposure; “edge protection installed and inspected” is a control. It should also distinguish inherent risk, before controls, from residual risk, after controls. Residual risk is acceptable only if controls are implemented, verified, and consistent with legal and organisational criteria.

2. The construction safety plan

2.1 Content and structure

A professional safety plan normally contains the following integrated elements:

Project governance. State the safety policy, objectives, consultation arrangements, roles, competency requirements, and authority to stop work.

Site establishment. Show boundaries, gates, fencing, welfare facilities, emergency access, pedestrian routes, vehicle routes, storage zones, lifting areas, hazardous-material locations, fire points, first-aid facilities, and assembly points.

Risk controls. Summarise critical risks, applicable method statements, temporary works controls, inspection requirements, and permits.

Workforce management. Define recruitment, competency verification, induction, language and literacy support, supervision, fatigue management, occupational health, and worker consultation.

Operational arrangements. Address plant, lifting, excavation, work at height, electrical systems, hot work, confined spaces, hazardous substances, traffic, housekeeping, and environmental interfaces.

Emergency preparedness. Include alarms, communication, first aid, rescue, fire, spill response, severe weather, utility strikes, structural instability, and liaison with emergency services.

Assurance and improvement. Specify inspections, audits, leading and lagging indicators, incident investigation, corrective actions, and management review.

The plan should be controlled as a live document. Revisions should identify what changed, why it changed, who approved it, and how affected people were informed.

2.2 Method statements and safe work procedures

A safe work procedure explains how a task is to be performed safely. A method statement is often a more detailed project-specific description that links sequence, resources, hazards, controls, and verification. Neither should be a generic document copied from another project.

A robust procedure usually includes:

  • task scope and exclusions;
  • required drawings, specifications, and permits;
  • competence and supervision;
  • plant, tools, materials, and inspection status;
  • step-by-step sequence;
  • hazards and critical controls at each step;
  • hold points requiring approval before continuation;
  • emergency and rescue arrangements;
  • environmental controls;
  • PPE;
  • communication and coordination requirements; and
  • review triggers.

Procedures must be usable. Long documents that workers cannot understand at the point of work should be supplemented with diagrams, photographs, translated material, demonstrations, or task cards. Consultation is essential: a procedure developed without the experience of the people performing the task may overlook practical failure modes.

3. Communication and workforce engagement

3.1 Site induction

Induction is the controlled introduction of a person to the site’s hazards, rules, facilities, and emergency arrangements. It should occur before access is granted and should be appropriate to the person’s role. A general induction commonly covers:

  • site boundaries and sign-in arrangements;
  • prohibited conduct and restricted areas;
  • emergency signals, evacuation, first aid, and reporting;
  • traffic routes and pedestrian separation;
  • mandatory PPE;
  • welfare and hygiene facilities;
  • hazard reporting and stop-work arrangements;
  • environmental and housekeeping expectations; and
  • task-specific training and permit requirements.

Induction is not proven by a signature alone. Understanding should be checked through questions, demonstration, observation, or a short assessment. Visitors require a proportionate briefing and escort arrangements. Induction should be refreshed after significant changes, extended absence, incidents, or evidence of misunderstanding.

3.2 Toolbox talks

A toolbox talk is a short, work-focused discussion conducted close to the activity. It should address the day’s conditions rather than repeat general policy. Effective talks identify the task, changed conditions, hazards, critical controls, interfaces, emergency response, and worker concerns. Attendance records are useful, but the supervisor should also confirm understanding and invite dissent or alternative viewpoints.

Topics may include weather-related lifting restrictions, excavation changes, simultaneous operations, newly delivered plant, a recent near miss, or a change in work sequence. Toolbox talks are most effective when followed by field verification. They should not be used to transfer all responsibility to workers for hazards created by poor design, inadequate equipment, or unrealistic programming.

3.3 Consultation and psychological safety

Workers often possess the most detailed knowledge of how work actually occurs. Consultation mechanisms may include safety representatives, pre-start meetings, suggestion systems, participatory risk assessments, and stop-work protocols. A psychologically safe culture allows people to report hazards and challenge decisions without retaliation. This is both an ethical requirement and a practical source of risk information.

4. Inspections, observations, and assurance

Inspections verify the condition of plant, workplaces, access routes, temporary works, and controls. They should be planned at several levels:

  • Pre-use checks: completed by operators before using plant or equipment.
  • Routine supervisor inspections: focused on current work fronts and changing conditions.
  • Specialist inspections: conducted for scaffolds, lifting equipment, excavations, electrical installations, or temporary works by competent persons.
  • Management inspections and audits: assess system implementation and recurring weaknesses.

Inspection quality depends on competence, frequency, independence where appropriate, and closure of findings. A finding should state the condition observed, location, risk, immediate action, responsible person, due date, and verification of closure. “Housekeeping poor” is less useful than “loose formwork timber obstructing the north stair landing; remove before next shift; supervisor to verify.”

Leading indicators such as completed critical-control verifications, close-out time, worker participation, and planned inspection completion can reveal deteriorating control before injury occurs. Lagging indicators such as injuries, property damage, and lost time are important but occur after failure. Metrics can also distort behaviour: rewarding low reported incidents may suppress reporting. Balanced assurance therefore examines both outcomes and the quality of control implementation.

5. Permit-to-work systems

5.1 Purpose and principles

A permit-to-work (PTW) system is a formal communication and authorisation process for specified hazardous work. It confirms that hazards have been assessed, isolations and precautions are in place, responsible persons understand the work, and the task is authorised for a defined time and location. A permit is not a substitute for risk assessment or supervision.

Permits are commonly used for hot work, confined-space entry, electrical or mechanical isolation, excavation near services, work at height in exceptional circumstances, line breaking, radiation sources, and work in operational or restricted areas. The precise categories should be defined by the project risk assessment and legal requirements.

5.2 Permit lifecycle

A sound lifecycle includes:

1. Application: the performing team describes the task, location, equipment, duration, and hazards.

2. Review: an authorised issuer checks the risk assessment, method statement, interfaces, competence, and required controls.

3. Preparation: isolations, gas tests, barriers, fire protection, rescue equipment, and communications are established.

4. Issue: issuer and performing supervisor confirm conditions and sign or electronically authorise the permit.

5. Execution: the supervisor maintains controls and stops work if conditions change.

6. Suspension or handover: work is paused safely during breaks, alarms, weather changes, or shift changes.

7. Close-out: the area is inspected, equipment is made safe, and the permit is returned and cancelled.

Permit authority should be separated from production pressure where practicable. Electronic PTW systems can improve traceability, but a digital approval does not guarantee a physical isolation. Field verification remains essential. Simultaneous permits require interface review; for example, hot work above solvent application may be incompatible even if both permits are individually valid.

6. PPE and personal protection

PPE is the final or supplementary layer in the hierarchy of controls. It should be selected from a task-based assessment considering hazard, exposure, compatibility, fit, duration, environment, and user characteristics. Typical equipment includes safety helmets, eye and face protection, hearing protection, gloves, safety footwear, respiratory protective equipment, high-visibility clothing, fall-arrest systems, and protective clothing.

Employers or controlling organisations should provide suitable PPE, maintain it, replace defective items, provide training, and enforce its correct use. Users require instruction in inspection, fitting, limitations, cleaning, storage, and reporting defects. Compatibility matters: safety spectacles may interfere with a respirator seal; gloves may increase entanglement risk near rotating machinery; hearing protection may prevent hearing alarms.

Respiratory protective equipment requires particularly careful selection and fit testing. A filter is not automatically suitable for every contaminant, concentration, oxygen condition, or duration. Air-purifying equipment must not be used where oxygen deficiency is possible unless specifically designed and approved for that environment. Fall-arrest equipment requires anchor design, clearance calculations, rescue planning, and consideration of suspension trauma; it is not equivalent to fall prevention.

7. Access control, housekeeping, and traffic management

7.1 Access control

Access control protects workers, visitors, the public, and site assets. It may involve fencing, gates, identification, sign-in systems, escorts, segregation of delivery areas, restricted permits, and security outside working hours. Access arrangements should account for emergency egress, accessibility needs, changing work fronts, and unauthorised entry by children or members of the public.

A site map should identify controlled zones such as lifting areas, excavation edges, live electrical rooms, confined spaces, and demolition zones. Physical barriers are preferable to warning signs alone. Access permissions should be reviewed when a person’s role, competence, or task changes.

7.2 Housekeeping

Housekeeping is an engineering and operational control, not merely an appearance standard. It reduces slips, trips, fire load, falling objects, blocked exits, manual-handling hazards, and uncontrolled waste. Controls include designated storage, waste segregation, planned removal routes, cable management, protection of openings, secure stacking, spill response, and end-of-shift checks.

The “clean as you go” principle is useful, but it must be supported by adequate labour, skips, storage capacity, and programme planning. Repeated housekeeping failures may indicate poor logistics rather than worker negligence.

7.3 Traffic management

Construction traffic plans should be based on a site-specific assessment of vehicle types, delivery frequency, turning movements, gradients, visibility, pedestrian demand, and neighbouring public roads. The preferred arrangement is physical separation of vehicles and pedestrians. Where interaction is unavoidable, controls may include barriers, designated crossings, one-way systems, speed management, trained bankspeople, reversing restrictions, lighting, mirrors, cameras, alarms, and delivery booking.

Bankspeople should not be treated as the sole control for reversing where layout or physical segregation can eliminate the manoeuvre. Drivers need clear routes, adequate visibility, and information about overhead, underground, and edge hazards. Traffic plans should be reviewed as the site layout changes.

8. Emergency readiness and change management

Emergency arrangements should be credible for the hazards present. A confined-space rescue plan, for example, must specify equipment, trained rescuers, retrieval method, atmospheric monitoring, communication, and emergency-service interface; merely posting an emergency telephone number is inadequate. Drills should test realistic scenarios and identify recovery actions.

Change management is essential because construction risk is dynamic. A change in design, sequence, subcontractor, material, plant, weather, access, or neighbouring operation should trigger review. The review should ask: what new hazards arise, which existing controls become invalid, who must be consulted, and what authorisation is required? Temporary works and interfaces deserve particular attention because their failure can affect many activities simultaneously.

9. Applied case: illustrative high-rise project

Background

A fictional 18-storey mixed-use project is entering the façade and services phase. Three subcontractors share a constrained site. Deliveries use one gate, pedestrians cross the loading area, and hot work is planned near stored insulation. Earlier inspections recorded blocked access routes and incomplete permit close-outs.

Problem

The project team has a detailed safety manual, but field controls are inconsistent. A near miss occurs when a reversing delivery vehicle approaches a pedestrian crossing while a hot-work crew begins cutting without a current fire watch. The events reveal failures of coordination rather than a single careless action.

Analysis

The project manager maps the interfaces and identifies four critical controls: physical pedestrian–vehicle separation, delivery scheduling, a functioning hot-work permit with fire watch, and daily verification of access routes. The team also finds that subcontractor supervisors interpret the permit boundary differently and that induction does not explain temporary route changes.

Approach and solution

The principal contractor introduces a revised traffic plan with barriers, a controlled crossing, a trained marshal at peak delivery times, and booked delivery slots. The hot-work procedure is revised to require removal or protection of combustibles, suitable extinguishers, a named fire watch during work and after completion for the period specified by the project’s fire-risk assessment, and close-out inspection. A short daily coordination meeting reviews simultaneous operations. Updated route maps are displayed at access points, and toolbox talks use photographs of the actual work areas. Supervisors conduct documented critical-control checks rather than relying solely on general inspections.

Outcome

In this illustrative case, subsequent inspections show improved route clearance and permit close-out. More importantly, workers begin reporting conflicts before work starts. The project does not assume that the absence of an injury proves success; it reviews whether barriers remain in place, whether delivery slots are followed, and whether hot-work controls are physically verified.

Learning points

The case demonstrates that a safety plan must manage interfaces, not just individual tasks. Permits, induction, traffic controls, and housekeeping are interdependent. A written rule is ineffective unless responsibilities, resources, field verification, and feedback are established.

10. Technology, ethics, and contemporary practice

Digital inspection platforms, wearable location systems, drones, computer vision, and sensor-based monitoring can support safety management. They may identify people entering exclusion zones, record inspection trends, or provide evidence of changing conditions. Artificial intelligence can assist in classifying observations and detecting recurring patterns, but it should not be treated as an autonomous safety decision-maker. False alarms, blind spots, poor data quality, and algorithmic bias must be evaluated.

Technology also raises governance questions. Worker location and video data may affect privacy, dignity, and trust. Organisations should define purpose, access, retention, consent or lawful basis where applicable, and processes for correcting errors. Surveillance must not replace consultation or be used to blame individuals for system failures.

Ethically, safety decisions should respect human life, equity, competence, and the right to refuse or stop seriously unsafe work. Production incentives must not encourage permit bypassing, under-reporting, or inadequate supervision. Regulatory compliance is a minimum standard; professional responsibility requires anticipating foreseeable harm and learning from weak signals.

Challenges and limitations

Site safety planning faces persistent limitations. Construction conditions change faster than documents can be revised. Multiple employers create fragmented authority. Schedule pressure can encourage shortcuts. Risk matrices may obscure catastrophic low-frequency events. Training can be ineffective where language, literacy, fatigue, or high turnover is ignored. Audits may measure paperwork rather than control quality. PPE can create discomfort, heat stress, communication barriers, and false confidence.

These limitations are addressed through clear critical controls, competent supervision, worker participation, practical procedures, physical design solutions, dynamic review, and verification at the workface. Safety performance should be judged by the reliability of controls and the quality of learning, not by incident counts alone.

Best-practice checklist

Before work begins, the responsible team should be able to answer yes to the following questions:

  • Are hazards and interfaces understood by the people doing the work?
  • Are elimination and engineering controls considered before administrative controls and PPE?
  • Are roles, authority, competence, and stop-work arrangements clear?
  • Are access, traffic, housekeeping, welfare, and emergency routes physically established?
  • Are permits used only where necessary and verified in the field?
  • Are inspections focused on critical controls and followed by corrective action?
  • Are workers consulted and able to report concerns without retaliation?
  • Has the plan been reviewed after changes, incidents, near misses, or new information?
  • Are records reliable without allowing documentation to replace observation?

Chapter Summary

Site safety planning converts project hazards, legal duties, construction methods, and organisational responsibilities into coordinated controls. An effective plan is a live management cycle of planning, implementation, verification, and learning. It includes risk assessment, safe work procedures, competence, consultation, emergency arrangements, contractor coordination, and change management.

Inductions establish site expectations, while toolbox talks address immediate task conditions. Inspections and assurance verify the presence and effectiveness of critical controls. Permit-to-work systems formalise authorisation for defined high-risk activities but do not replace risk assessment or supervision. PPE is essential but should remain the final layer after elimination, substitution, engineering, and administrative controls.

Access control, housekeeping, and traffic management require physical planning and adequate resources. Digital tools and AI can improve visibility and analysis, but they require human oversight, privacy governance, and realistic evaluation. Ultimately, safety performance depends on reliable controls at the point of work, worker participation, competent leadership, and the willingness to learn and adapt.

Key Terms

Risk assessment: Systematic identification and evaluation of hazards and selection of controls.

Hierarchy of controls: Ordered preference for eliminating or reducing hazards, from elimination to PPE.

Residual risk: Risk remaining after selected controls have been implemented.

Critical control: A control essential to preventing a serious or fatal event.

Safety plan: Project-specific system defining safety responsibilities, hazards, controls, and assurance.

Method statement: Description of how a task will be performed, including sequence and controls.

Safe work procedure: Practical instruction for carrying out work safely.

Induction: Initial site-specific orientation and competence confirmation for persons entering a site.

Toolbox talk: Short, task-focused safety discussion conducted near the work activity.

Inspection: Planned examination of workplace conditions, equipment, or controls.

Audit: Systematic evaluation of management-system implementation and effectiveness.

Permit-to-work: Formal authorisation and communication system for specified hazardous work.

Isolation: Separation of energy or hazardous substances from people and equipment.

PPE: Equipment or clothing worn to protect a person from residual hazards.

Access control: Measures regulating entry to a site or restricted area.

Housekeeping: Planned management of storage, waste, cleanliness, and unobstructed routes.

Traffic management plan: Arrangement controlling vehicle and pedestrian movement.

Hold point: Required approval or verification before work proceeds.

Change management: Controlled review of hazards and controls when conditions or methods change.

Leading indicator: Forward-looking measure of control activity or system health.

Review Questions

Short Answer Questions

1. What is the purpose of a construction safety plan?

2. Distinguish a hazard from a control.

3. Why is a permit-to-work system not a substitute for risk assessment?

4. State two limitations of relying on PPE as the main safety control.

5. What information should be recorded when an inspection finding is raised?

Long Answer Questions

1. Explain how the hierarchy of controls should influence preparation of a safe work procedure.

2. Describe the complete lifecycle of a permit-to-work system and discuss the responsibilities of the issuer and performing supervisor.

3. Discuss how induction, toolbox talks, consultation, and supervision interact to influence worker behaviour and control reliability.

4. Develop a framework for managing construction traffic on a constrained urban site.

5. Critically evaluate the use of leading and lagging indicators in construction safety management.

Analytical / Application Questions

1. A project has repeated blocked exits, incomplete permits, and frequent changes in delivery routes. Analyse the likely system causes and propose a prioritised improvement plan.

2. Design a control strategy for hot work near combustible materials in an occupied building, including permits, isolation, fire protection, monitoring, and close-out.

3. A contractor proposes replacing physical pedestrian barriers with a trained banksman and warning signs. Evaluate the proposal using the hierarchy of controls and recommend conditions under which it might be acceptable.

Multiple Choice Questions with Answers

Question 1

Which control is generally preferred over an administrative instruction to avoid a construction hazard?

A. A physical engineering control

B. A longer toolbox talk

C. A warning poster

D. Additional PPE only

Correct Answer: A. A physical engineering control

Question 2

What is the primary purpose of a permit-to-work system?

A. To replace all risk assessments

B. To formally authorise and communicate controls for specified hazardous work

C. To record worker attendance

D. To eliminate the need for supervision

Correct Answer: B. To formally authorise and communicate controls for specified hazardous work

Question 3

Which activity is most appropriately managed through a task-focused toolbox talk?

A. Explaining the company’s full insurance policy

B. Discussing changed delivery routes and vehicle–pedestrian conflicts for the day

C. Approving the project budget

D. Issuing a building permit

Correct Answer: B. Discussing changed delivery routes and vehicle–pedestrian conflicts for the day

Question 4

Which statement best describes residual risk?

A. Risk before any controls are selected

B. Risk remaining after controls are implemented

C. Risk that has no possible consequence

D. Risk recorded only after an incident

Correct Answer: B. Risk remaining after controls are implemented

Question 5

Why should a permit be suspended when site conditions change significantly?

A. The original assumptions and controls may no longer be valid

B. Suspension automatically cancels the construction contract

C. All permits must end at midday

D. A suspension removes the need for a close-out inspection

Correct Answer: A. The original assumptions and controls may no longer be valid

Question 6

Which arrangement best supports construction traffic safety?

A. Relying only on vehicle horns

B. Physical separation of pedestrian and vehicle routes where practicable

C. Allowing pedestrians to choose any route

D. Removing all delivery schedules

Correct Answer: B. Physical separation of pedestrian and vehicle routes where practicable

Question 7

What is a limitation of using injury frequency alone as a safety-performance measure?

A. It is a leading indicator of critical-control reliability

B. It may encourage under-reporting and does not show whether controls are working

C. It measures every near miss accurately

D. It eliminates the need for inspections

Correct Answer: B. It may encourage under-reporting and does not show whether controls are working

Question 8

Which statement about PPE is correct?

A. PPE should normally be considered before elimination

B. PPE is the final or supplementary layer in the hierarchy of controls

C. PPE removes the need for emergency planning

D. One glove type is suitable for every task

Correct Answer: B. PPE is the final or supplementary layer in the hierarchy of controls

Question 9

What is the main purpose of a hold point in a method statement?

A. To permit work to continue without inspection

B. To require verification or approval before the next stage proceeds

C. To replace worker consultation

D. To record payroll information

Correct Answer: B. To require verification or approval before the next stage proceeds

Question 10

Which response best demonstrates effective change management?

A. Ignoring a changed excavation sequence because the plan was already approved

B. Reviewing new hazards, affected controls, responsibilities, and required authorisation

C. Deleting the original risk assessment

D. Allowing only the client to notice changes

Correct Answer: B. Reviewing new hazards, affected controls, responsibilities, and required authorisation

Construction Safety Management
Chapter 6 of 15