Cost Estimating, Budgeting and Financial ControlIntroduction and ContextCost is one of the primary constraints in construction project management, together with time, quality, scope, safety and sustainability. A technically successful project can still be regarded as unsuccessful if it exceeds its approved budget, creates unaffordable cash requirements, or fails to provide reliable financial information for decision-making. Construction cost management therefore extends beyond preparing a bill of quantities. It involves developing estimates, establishing a cost baseline, forecasting cash requirements, controlling commitments and actual expenditure, measuring performance, and taking corrective action. Construction costs are particularly difficult to manage because projects are temporary, location-specific and exposed to uncertainty. Design information develops progressively; quantities may change; labour and material productivity varies; market prices fluctuate; ground conditions may be uncertain; and contractual responsibility for risk differs between procurement systems. Sound cost management must therefore combine measurement and accounting techniques with probabilistic thinking, project controls and professional judgement. This chapter presents an integrated framework for preparing conceptual and detailed estimates, developing budgets and cash-flow forecasts, accounting for contingency and escalation, and applying cost codes and earned value management (EVM) to control performance. Learning ObjectivesAfter studying this chapter, the reader should be able to: 1. distinguish between conceptual estimates, definitive estimates, budgets, commitments and actual costs; 2. select appropriate estimating methods for different stages of project definition; 3. prepare a resource-based or quantity-based cost estimate and explain its assumptions; 4. establish a cost breakdown structure, cost codes and a time-phased cost baseline; 5. prepare and interpret project cash-flow forecasts; 6. distinguish contingency, escalation, allowance and management reserve; 7. calculate and interpret planned value, earned value, actual cost and major EVM indices; 8. forecast final cost and explain variance analysis and corrective action; 9. evaluate the limitations, governance requirements and ethical responsibilities of construction cost control. 1. The Cost Management SystemA project cost management system links four activities: - Estimating: predicting the resources and monetary value required to complete the defined scope.
- Budgeting: authorising an allocation of funds and distributing it across work packages and time.
- Financial control: comparing performance and expenditure with the approved baseline.
- Forecasting: updating the expected final cost and cash requirement using current information.
These activities are iterative. An early estimate may be based on floor area or historical cost data. As drawings, specifications, quantities, construction methods and procurement information become available, the estimate is progressively refined. The estimate should not be interpreted as equally accurate at every stage. Its reliability depends on scope definition, information quality, market conditions, productivity assumptions and identified risks. Important cost classifications include: - Direct cost: cost traceable to a work item, such as concrete, reinforcement, labour or equipment used for a particular activity.
- Indirect project cost: cost supporting the project but not conveniently traceable to one measured work item, such as site offices, supervision, temporary services and security.
- Overhead: organisational or corporate cost allocated to projects, such as head-office administration and insurance systems.
- Fixed cost: a cost that does not vary substantially with the quantity of a particular output over the relevant range, although it may vary with project duration.
- Variable cost: a cost that changes with quantity, production or resource usage.
- Committed cost: the value of contractual obligations, purchase orders or subcontracts, whether or not payment has occurred.
- Accrued cost: cost relating to work or goods received but not yet invoiced or paid.
- Actual cost: the cost recorded for work performed during a specified period.
- Sunk cost: expenditure already incurred that cannot normally be recovered and should not determine a rational future decision.
A distinction must be maintained between the client’s project budget and the contractor’s cost plan. The client budget may include construction cost, design fees, land, statutory charges, finance, client contingency, inflation and taxes. A contractor’s internal budget usually focuses on the cost of executing the contracted work and may also include site overhead, head-office overhead, risk allowances and profit. Contract price, project budget and forecast cost are therefore not interchangeable. 2. Estimating Methods and Estimate Development2.1 Conceptual estimatingConceptual estimates are prepared when scope and design information are incomplete. Their purpose is to test feasibility, compare options, establish funding requirements and support early decisions. Common methods include: - Analogous estimating: using the cost of a similar completed project, adjusted for size, location, complexity, time and market conditions.
- Parametric estimating: applying a cost rate to a measurable parameter, such as cost per square metre of gross floor area, cost per kilometre of road, or cost per installed megawatt.
- Factor estimating: estimating a major component from a known base cost using an empirical factor.
- Expert or Delphi judgement: obtaining structured estimates from experienced specialists, preferably with documented assumptions and independent review.
- Three-point estimating: developing optimistic, most-likely and pessimistic values to expose uncertainty. A weighted average may be used only when its probability assumptions are defensible; it should not be treated as a guarantee of accuracy.
For a parametric estimate, \[ C = Qr \] where \(C\) is estimated cost, \(Q\) is the quantity of the cost-driving parameter, and \(r\) is the appropriate unit cost. The equation is valid only when the unit definition, scope, location, specification, price base and productivity conditions of \(r\) correspond to those of \(Q\). For example, a cost per square metre that includes finishes and mechanical services cannot be applied to a shell-only building. If historical cost is adjusted for location and time, a simplified relationship is: \[ C_2=C_1\left(\frac{I_2}{I_1}\right)L \] where \(C_1\) is the historical cost, \(I_1\) and \(I_2\) are appropriate cost indices at the historical and current dates, and \(L\) is a location adjustment factor. This approach assumes that the project scope and specification are sufficiently comparable and that the selected index reflects the relevant cost structure. 2.2 Preliminary and elemental estimatingAs design develops, costs may be organised by elements such as substructure, frame, envelope, internal finishes, services and external works. Elemental estimating supports option appraisal. For example, a higher initial façade cost may reduce cooling loads and maintenance expenditure. Life-cycle cost analysis is therefore preferable when alternatives have materially different operating, maintenance, replacement or disposal costs. A life-cycle cost comparison should identify the analysis period, discount convention, energy and maintenance assumptions, residual value, taxes and risk. A simple present-value relationship is: \[ PV_t=\frac{C_t}{(1+i)^t} \] where \(PV_t\) is the present value of a future cost \(C_t\), \(i\) is the discount rate per period, and \(t\) is the number of periods. The rate and period must be applied consistently. Discounting does not remove uncertainty; it only expresses future monetary amounts in a common time basis. 2.3 Detailed estimatingA detailed estimate is prepared from drawings, specifications, schedules, geotechnical information, construction methods and procurement data. It generally involves: 1. defining the scope and inclusions; 2. developing a work breakdown structure (WBS); 3. measuring quantities using a consistent method; 4. identifying labour, material, plant, subcontract and temporary-work requirements; 5. applying rates and productivity assumptions; 6. pricing preliminaries, indirect costs and overheads; 7. adding appropriate risk allowances and escalation; 8. checking arithmetic, omissions, double counting and interfaces; 9. documenting assumptions, exclusions and estimate confidence. For a measured work item, a basic direct-cost relationship is: \[ C_i=Q_i(r_{m,i}+r_{l,i}+r_{p,i}+r_{s,i}) \] where \(Q_i\) is the measured quantity of item \(i\), and the four rates represent material, labour, plant and subcontract components respectively. The equation is a pricing model, not a universal law. It assumes the rates are expressed in compatible monetary units and include the resources intended by the estimator. Waste, small tools, testing, delivery, productivity losses and taxes must be included explicitly or stated as separate items. Productivity assumptions require special scrutiny. If a crew installs 40 square metres per shift and the total quantity is 800 square metres, the theoretical requirement is 20 crew-shifts. Actual duration or cost may be higher because of access restrictions, rework, weather, learning, congestion and non-productive time. Historical productivity should therefore be adjusted to the project’s conditions rather than copied mechanically. 2.4 Estimate review and reconciliationIndependent estimate review is an important control. Useful tests include: - comparison with benchmarks and historical projects;
- reconciliation of quantities with drawings and schedules;
- review of high-value and high-risk items;
- examination of abnormally low or high rates;
- reconciliation between estimate, procurement packages and construction programme;
- checks for scope gaps at design interfaces;
- sensitivity testing of labour, material, duration and quantity assumptions.
An estimate should be accompanied by an estimate basis document. It records the data date, design status, measurement rules, assumptions, exclusions, allowances, escalation basis, taxes, exchange rates, risk treatment and confidence range. Without such a record, later changes may be wrongly attributed to poor performance rather than to changed scope or assumptions. 3. From Estimate to Budget and Cost BaselineThe estimate becomes a management budget only after scope, responsibility and authorisation are established. A budget should be structured so that planned expenditure can be compared with physical progress and contractual commitments. 3.1 Work and cost breakdown structuresThe WBS decomposes the project into deliverables and work packages. A cost breakdown structure (CBS) groups costs by useful control categories, such as project, phase, location, discipline, work package, resource type and responsible manager. The WBS and CBS need not be identical, but they must be cross-referenced. A practical coding structure might contain fields for: - project and contract;
- building or geographic area;
- discipline or trade;
- WBS work package;
- cost type, such as labour, material, plant, subcontract or overhead;
- funding source or change order;
- accounting period.
Cost codes should be sufficiently detailed to reveal actionable variance but not so detailed that data entry becomes unreliable. Codes should be defined in a coding dictionary and applied consistently by estimating, procurement, site supervision, accounts and commercial management. 3.2 Budget hierarchyA typical hierarchy is: \[ \text{Control accounts} \rightarrow \text{Work packages} \rightarrow \text{Activities and cost codes} \] A control account is a management point where scope, schedule, budget and responsibility are integrated. The approved, time-phased budget for in-scope work is commonly called the performance measurement baseline (PMB). The total authorised budget may additionally include a management reserve for unknown-unknowns, depending on the governance system. Management reserve is not part of the performance measurement baseline until formally allocated to authorised scope. The baseline should be frozen at an agreed control date, while approved changes are incorporated through a documented change-control process. It is poor practice to alter the baseline retrospectively merely to hide an unfavourable variance. 4. Contingency, Escalation and Uncertainty4.1 TerminologyThese terms must be distinguished: - Allowance: a provisional amount for a defined but not fully specified item, such as a provisional sum for specialist equipment.
- Contingency: an amount or quantified provision for identified uncertainty or risk within the approved scope.
- Escalation: increase in prices due to inflation, market movement, wage growth, material scarcity or exchange-rate effects.
- Management reserve: an amount controlled by authorised management for unforeseen work or unknown-unknowns; its use requires governance approval.
- Risk event: an uncertain event that may affect cost, time, quality or scope.
Applying a blanket percentage to every estimate can be convenient but is weak risk management. Contingency should reflect the risk register, estimate maturity, project complexity and chosen confidence level. 4.2 Deterministic and probabilistic approachesA deterministic approach identifies risks and assigns estimated impacts. For mutually exclusive or suitably defined risk events, a simple expected monetary value is: \[ EMV=\sum_{j=1}^{n}p_jI_j \] where \(p_j\) is the probability of risk event \(j\), and \(I_j\) is its monetary impact. Positive and negative impacts should be treated consistently. The formula assumes that probabilities are meaningful, impacts are appropriately estimated and interaction between events is either negligible or separately modelled. EMV is not a prediction of the exact outcome; it is an expected value useful for portfolio-level decisions. Probabilistic cost risk analysis uses distributions for uncertain quantities, rates, durations or risk impacts and may employ Monte Carlo simulation. Outputs can include a median estimate or a percentile such as P80, meaning that the simulated cost is not exceeded in approximately 80 percent of modelled cases, subject to model validity. Correlation matters: steel and fuel prices, for example, may move together. Ignoring correlation can materially distort results. 4.3 Escalation calculationIf a cost component is expected to grow at an annual rate \(e\) for \(t\) years, compound escalation may be represented by: \[ C_t=C_0(1+e)^t \] where \(C_0\) is the base-date cost. This assumes a constant annual rate and a clearly defined compounding period. In practice, different components may require separate indices, and escalation should be aligned with the expected timing of procurement or expenditure rather than simply the project completion date. 5. Cash-Flow Forecasting and Financial PlanningProfitability and liquidity are different. A project may be profitable on completion but experience cash stress because expenditure precedes client payment. Cash-flow forecasting estimates the timing of receipts and payments. A period cash balance can be expressed as: \[ B_t=B_{t-1}+R_t-P_t \] where \(B_t\) is closing cash balance in period \(t\), \(R_t\) is cash received, and \(P_t\) is cash paid. The opening balance is \(B_{t-1}\). The relationship is an accounting identity and requires consistent treatment of tax, retention, advance payments, financing, interest and payment timing. The cost baseline is not automatically a cash-flow forecast. Planned value may represent the budgeted value of work scheduled, whereas cash payments depend on procurement terms, valuation rules, retention, advance payment recovery, subcontract payment cycles and invoice approval. A cash-flow model should therefore include: - planned labour and material payment dates;
- subcontractor applications and certification lags;
- supplier credit terms;
- client valuations and payment periods;
- retention and release dates;
- taxes and statutory payments;
- bonds, insurance and financing costs;
- likely changes, claims and dispute delays.
A time-phased S-curve is often used to display cumulative planned cost or cash expenditure. It is a communication model, not proof of performance. Sudden procurement payments may produce a cash curve different from the physical-progress curve. 6. Earned Value ManagementEVM integrates scope, schedule and cost by comparing three values at a status date: - Planned Value (PV): budgeted cost of the work scheduled to be performed by the status date.
- Earned Value (EV): budgeted cost of the work actually performed by the status date.
- Actual Cost (AC): actual cost incurred for the work performed by the status date.
All three must use the same scope, currency, time-phasing rules and status date. EV is not the invoice value and AC is not necessarily the amount paid; definitions must be established in the project control system. The principal variances are: \[ CV=EV-AC \] \[ SV=EV-PV \] where CV is cost variance and SV is schedule variance, both expressed in monetary units. A positive CV indicates that the budgeted value of completed work exceeds its actual cost. A positive SV indicates that more budgeted work has been completed than was scheduled. Because schedule variance is measured in money, it tends toward zero when the project is complete and should not replace schedule-network analysis. Performance indices are: \[ CPI=\frac{EV}{AC}, \qquad SPI=\frac{EV}{PV} \] CPI measures cost efficiency and SPI measures progress efficiency relative to the baseline. Values above 1.00 are favourable under conventional interpretation; values below 1.00 indicate inefficiency or delay. These interpretations require reliable progress measurement and should be supplemented by physical schedule metrics. A common forecast of estimate at completion is: \[ EAC=\frac{BAC}{CPI} \] where BAC is the budget at completion. This method assumes that current cost efficiency will continue for the remaining work. Other situations justify different forecasts. If a one-time variance is not expected to recur, a simple forecast may be: \[ EAC=AC+(BAC-EV) \] If both cost efficiency and remaining work conditions are expected to influence performance, a formulation sometimes used is: \[ EAC=AC+\frac{BAC-EV}{CPI\times SPI} \] The selected formula must be justified; no EAC equation can compensate for poor data or an invalid assumption about future performance. The estimate to complete is \(ETC=EAC-AC\), and the variance at completion is \(VAC=BAC-EAC\). A negative VAC indicates an anticipated overrun against BAC. Worked Example: EVM interpretationA roadwork package has a BAC of $2,400,000. At the status date, PV is $1,200,000, EV is $1,080,000 and AC is $1,200,000. Therefore: \[ CV=1{,}080{,}000-1{,}200{,}000=-120{,}000 \] \[ SV=1{,}080{,}000-1{,}200{,}000=-120{,}000 \] \[ CPI=1{,}080{,}000/1{,}200{,}000=0.90 \] \[ SPI=1{,}080{,}000/1{,}200{,}000=0.90 \] Using the assumption that current cost efficiency continues, \[ EAC=2{,}400{,}000/0.90=2{,}666{,}667\text{ approximately} \] Thus the forecast overrun against BAC is approximately $266,667. Management should not simply report the index. It should investigate whether the cause is low productivity, rework, incorrect rates, delayed access, scope change, inaccurate EV measurement or a one-off event. 7. Variance Analysis, Forecasting and Corrective ActionEffective control asks four questions: What differs from the baseline? Why did it differ? What will happen if the trend continues? What action is justified? A useful variance-analysis hierarchy is: 1. Detection: identify material cost, commitment, productivity, quantity or schedule variance. 2. Classification: separate scope change, estimating error, price variance, quantity variance, productivity variance, timing variance and coding error. 3. Causation: examine evidence from timesheets, delivery records, measurement sheets, invoices, programme updates, inspection records and change registers. 4. Forecasting: update ETC, EAC, completion date and cash requirement. 5. Response: remove constraints, revise methods, renegotiate procurement, resequence work, approve scope change or escalate the issue. 6. Learning: record the cause and response for future estimates. A cost variance can be decomposed conceptually into quantity and rate effects. For a resource, if budgeted quantity is \(Q_B\), actual quantity is \(Q_A\), budgeted rate is \(r_B\), and actual rate is \(r_A\), then a simple total variance is: \[ V=Q_A r_A-Q_B r_B \] The decomposition into price and quantity components depends on the chosen convention. One common convention is price variance \(Q_A(r_A-r_B)\) and quantity variance \(r_B(Q_A-Q_B)\), whose sum equals total variance. The analysis is meaningful only when the units, scope and rate definitions are comparable. Corrective action should be proportionate. A minor adverse variance may require monitoring; a persistent negative CPI may require a recovery plan, revised productivity assumptions and senior review. Cost cutting that damages safety, quality, environmental compliance or long-term asset performance is not responsible control. 8. Governance, Ethics and Digital ToolsCost information affects payment, claims, taxation, lending and public accountability. Ethical responsibilities include accurate measurement, transparent assumptions, segregation of duties, protection against fraud, timely disclosure of material risks and avoidance of deliberate baseline manipulation. Conflicts of interest must be declared, and records must be auditable. Change control should define who may initiate, assess, approve and implement changes. No change should be incorporated into the baseline without a clear description of scope, cost, time, risk and funding effects. Contractual notice requirements and applicable procurement, tax, labour, environmental and public-finance regulations must be observed. Digital cost-management platforms can connect BIM quantities, schedules, procurement, accounts payable, field records and dashboards. Automated quantity extraction and anomaly detection can improve speed, but model errors, inconsistent coding and incomplete data can propagate rapidly. Artificial intelligence may assist in classifying invoices, forecasting trends and identifying unusual rates; it should not replace professional verification, contractual interpretation or accountability. Data governance should address access control, version management, cybersecurity, privacy, explainability and audit trails. 9. Illustrative Case: Municipal Hospital ExpansionBackgroundThis illustrative case concerns a 12,000-square-metre hospital expansion procured under a design-and-build contract. The initial approved construction budget was $48 million. The project included complex mechanical and medical-gas services, a constrained urban site and phased connection to an operating hospital. ProblemSix months after mobilisation, the monthly control report showed CPI = 0.93 and SPI = 0.88. The cash forecast also indicated a peak funding requirement $2.1 million higher than the client’s financing plan. Management initially suspected excessive subcontractor pricing. AnalysisThe controls team reconciled the estimate, cost codes, procurement commitments, progress records and cash forecast. The analysis found four main causes: - temporary works and infection-control measures had been underdeveloped in the original estimate;
- design revisions increased mechanical-service quantities, but several changes had not completed approval;
- EV for services was being claimed using procurement milestones rather than verified installation progress;
- long-lead equipment required early supplier payments, while client certification followed physical installation.
The first issue represented an estimate gap and risk realisation; the second involved scope change; the third was a measurement weakness; and the fourth was a liquidity-timing problem rather than necessarily a final-cost overrun. Approach and solutionThe project team established a revised CBS with separate codes for temporary works, infection control, medical services and approved changes. A joint quantity review corrected EV rules. Unapproved design changes were logged in a change register with owner, probability, cost range and decision date. The client approved justified scope changes, rejected unsupported claims and released a controlled contingency for defined risks. The cash forecast was rebuilt using supplier payment terms, retention, certification lags and the equipment procurement schedule. The contractor also introduced weekly commitment reviews and a four-week look-ahead linked to procurement constraints. Management did not reduce testing or infection-control measures merely to improve the reported CPI. OutcomeWithin two reporting periods, the apparent schedule variance reduced because EV measurement was corrected. The forecast peak cash requirement was reduced by negotiating staged supplier payments and aligning approved advance payments with guarantees. The final cost forecast remained above the original construction budget because genuine scope and risk costs had materialised, but the forecast became credible and was formally approved through change control. Learning pointsThe case demonstrates that EVM indicators are only as reliable as scope definition and progress rules. Cost overruns, cash shortages and reporting errors may coexist but require different responses. A sound control system separates baseline changes from performance variance, links risk information to contingency and integrates commercial, planning, procurement and accounting data. 10. Limitations and Best PracticesNo estimate or control system eliminates uncertainty. Benchmark data may be non-comparable; rates may conceal different productivity assumptions; inflation may be non-linear; risk events may be correlated; and EVM may provide misleading signals when scope changes or subjective progress measurement are poorly controlled. Best practice includes: - define scope, assumptions and exclusions before pricing;
- use progressive estimating with documented confidence and data dates;
- link WBS, CBS, schedule, procurement and accounting codes;
- distinguish contingency, escalation, allowance and management reserve;
- time-phase the baseline and maintain formal change control;
- forecast both final cost and cash requirement;
- measure physical progress using objective rules;
- reconcile commitments, accruals, invoices and actual costs;
- investigate causes rather than merely reporting indices;
- use independent review for material estimates and forecasts;
- preserve audit trails and protect cost data;
- integrate safety, quality, environmental and whole-life consequences into decisions.
Chapter SummaryConstruction cost management is an integrated process of estimating, budgeting, time-phasing, forecasting and control. Conceptual estimates support early decisions, while detailed estimates rely on measured quantities, resource rates, construction methods and explicit assumptions. A reliable budget is structured through WBS and CBS arrangements and becomes a time-phased performance measurement baseline after authorisation. Contingency addresses uncertainty within defined scope, escalation addresses changing prices, allowances address incompletely specified items and management reserve is controlled separately according to governance rules. Cash-flow forecasts must distinguish planned value from the timing of receipts and payments. EVM compares PV, EV and AC to calculate variances, efficiency indices and forecasts, but its results depend on valid scope, accurate actual costs and objective progress measurement. Professional control requires causal variance analysis, disciplined change management, risk-based forecasting, ethical reporting and auditable digital systems. The purpose is not merely to reduce expenditure; it is to deliver authorised scope safely, efficiently, transparently and with an informed understanding of uncertainty. Key TermsCost estimate: Prediction of resources and monetary expenditure required for defined scope. Conceptual estimate: Early estimate based on limited design information. Detailed estimate: Estimate based on developed drawings, specifications, quantities and methods. Parametric estimating: Estimating using a cost rate applied to a measurable parameter. Direct cost: Cost traceable to a specific work item. Indirect cost: Project-support cost not directly assigned to one measured item. Committed cost: Value of contractual obligations or purchase orders. Accrued cost: Cost incurred for received work or goods but not yet invoiced. Cost breakdown structure: Hierarchical organisation of project costs for control. Control account: Point integrating scope, budget, schedule and management responsibility. Performance measurement baseline: Approved, time-phased budget for planned work. Contingency: Provision for identified uncertainty within approved scope. Escalation: Increase in cost caused by inflation or market movement. Management reserve: Authorised reserve controlled for unforeseen requirements. Cash-flow forecast: Projection of future project receipts and payments. Planned Value: Budgeted value of work scheduled by a status date. Earned Value: Budgeted value of work actually performed. Actual Cost: Cost incurred for work performed. Cost Performance Index: Ratio of earned value to actual cost. Estimate at Completion: Forecast of total cost when the project is completed. Review QuestionsShort Answer Questions1. Distinguish between a project budget, a cost baseline and a cash-flow forecast. 2. Why should an estimate basis document record assumptions and exclusions? 3. Define contingency, escalation and management reserve. 4. What do PV, EV and AC represent in earned value management? 5. State two reasons why a project may be profitable overall but experience cash-flow stress. Long Answer Questions1. Explain how a construction estimate should develop from conceptual estimating to a detailed estimate. Discuss the information and controls required at each stage. 2. Describe how a WBS, CBS, cost codes and control accounts combine to create an effective cost-control system. 3. Explain deterministic and probabilistic approaches to construction cost risk and evaluate the limitations of expected monetary value. 4. Discuss the meaning, calculation and limitations of CPI, SPI, CV, SV and EAC. 5. Explain the governance and ethical requirements for maintaining a credible construction cost baseline. Analytical / Application Questions1. A package has BAC = $5,000,000, PV = $2,500,000, EV = $2,250,000 and AC = $2,000,000. Calculate CV, SV, CPI, SPI and EAC using the assumption that current cost efficiency continues. Interpret the results. 2. A contractor forecasts substantial material payments before receiving client certification. Develop a cash-flow investigation framework identifying the information required and practical actions to reduce liquidity risk. 3. A project’s CPI falls after a major design revision, while the approved budget has not changed. Explain how the team should distinguish scope change from performance variance and propose a compliant change-control response. Multiple Choice Questions with AnswersQuestion 1Which value represents the budgeted cost of work actually performed at the status date? A. Planned Value B. Earned Value C. Actual Cost D. Budget at Completion Correct Answer: B. Earned Value Question 2A project has EV = $900,000 and AC = $1,000,000. What is its CPI? A. 0.90 B. 1.11 C. $100,000 D. $1,900,000 Correct Answer: A. 0.90 Question 3Which item is most directly associated with changing market prices over time? A. Contingency B. Escalation C. Earned value D. Accrual Correct Answer: B. Escalation Question 4If PV = $700,000 and EV = $630,000, what is the schedule variance? A. $70,000 favourable B. -$70,000 C. $630,000 D. $1,330,000 Correct Answer: B. -$70,000 Question 5What is the principal purpose of a cost breakdown structure? A. To replace the project schedule B. To organise costs for measurement and control C. To calculate structural loads D. To approve building permits Correct Answer: B. To organise costs for measurement and control Question 6A BAC is $3,000,000 and CPI is 0.75. Using EAC = BAC/CPI, what is EAC? A. $2,250,000 B. $3,750,000 C. $4,000,000 D. $4,500,000 Correct Answer: C. $4,000,000 Question 7Which statement best describes committed cost? A. Only expenditure already paid B. A contractual obligation or purchase order value C. A future risk with no contract D. The value of completed physical work only Correct Answer: B. A contractual obligation or purchase order value Question 8Why may a cash-flow forecast differ from a time-phased cost baseline? A. Cash forecasts never include procurement B. Cash timing is affected by payment terms, retention and certification lags C. Baselines contain no dates D. Cash flow is unrelated to project cost Correct Answer: B. Cash timing is affected by payment terms, retention and certification lags Question 9Under conventional EVM interpretation, a CPI below 1.00 indicates that: A. Actual cost is lower than earned value B. Earned value exceeds planned value C. The project is cost-inefficient relative to the baseline D. The project is necessarily ahead of schedule Correct Answer: C. The project is cost-inefficient relative to the baseline Question 10Which practice most strengthens the credibility of a cost baseline? A. Changing the baseline after every adverse variance B. Excluding documented assumptions C. Using formal change control and preserving an audit trail D. Combining all costs into one undifferentiated code Correct Answer: C. Using formal change control and preserving an audit trail
|